You are on page 1of 4

Chapter 6: Project Time Management Includes processes required to accomplish timely completion of the project. 1.

Activity Definition Identifying and documenting the work that is planned to be performed Activity Definition Inputs (previously discussed) Activity Definition Tools and Techniques: a) Decomposition Involves subdividing the project work packages into smaller, more manageable components b) Rolling Wave Planning Form of progressive elaboration planning c) Planning Component Schedule activities may be summary activities that are not enough to support detailed estimating, scheduling, executing, monitoring or controlling of the project work Control Account used as basis for planning when associated work packages have not yet been planned Planning Package component used for planning known work content that does not have detailed schedule activities Activity Definition Tools and Techniques Outputs: a) Activity List Comprehensive list including all schedule activities that are planned to be performed on the project. b) Activity Attribute Characteristics of each activity. Includes the activity identifier, activity codes, activity description, predecessor activities, successor activities, logical relationships, etc. c) Milestone List List of schedule milestone (highlight) and indicates whether the milestone is mandatory (required by the contract) or optional (based upon project requirements or historical information) Activity Sequencing Involves identifying and documenting the logical relationships among schedule activities. Activity Sequencing Inputs (previously discussed) Activity Sequencing Tools and Techniques: a) Precedence Diagramming Method Method of constructing a project schedule that uses boxes or rectangles, referred to as nodes to represent activities and connects them with arrows that show dependencies. b) Arrow Diagramming Method Method of constructing project schedule that uses arrows to represent activities and connects them at nodes to show their dependencies. c) Schedule Network Templates d) Dependency Determination Define the sequence among the activities. Mandatory Dependencies - required, compulsory Discretionary Dependencies optional, unrestricted External Dependencies those that involve a relationship between project activities and nonproject activities e) Applying Leads and Lags lead - allows acceleration of the successor activity

2.

lag directs a delay in the successor activity Activity Sequencing Outputs: a) Project Schedule Network Diagrams Schematic (graphic) displays of the projects schedule activities and the logical relationships among them, also referred to as dependencies 3. Activity Resource Estimating Determining what resources (persons, equipment, or material) and what quantities of each resource will be used, and when each resource will be available to perform project activities. Activity Resource Estimating Inputs: a) Resource Availability Information on which resources are potentially available is used for estimating the resource types Activity Resource Estimating Tools and Techniques: a) Published Estimating Data Several companies routinely publish updated production rates and unit costs of resources for an extensive array of labor trades, materiel, and equipment b) Bottom Up Estimating When a schedule activity cannot be estimated with reasonable degree of confidence, the work within the schedule activity is decomposed into more detail The resource needs of each lower, more detailed piece of work are estimated, and these estimates are then aggregated into a total quantity. Activity Resource Estimating Tools and Techniques: a) Activity Resource Estimating Identification and description of the types and quantities of resources required for each schedule activity in a work package b) Resource Breakdown structure (RBS) Hierarchical structure of the identified resources by resource category and resource type Activity Duration Estimating Estimating schedule activity duration (period/length) Activity Duration Inputs: a) Resource Calendar Includes the availability, capabilities, and skills of human resources The type, quantity, availability and capability of both materiel and resources Activity Duration Tools and Techniques: a) Analogous Estimating Using the actual duration of a previous similar schedule activity as the basis for estimating the duration of future schedule activity b) Parametric Estimating Multiplying the quantity of work to be performed by the productivity rate c) Three-Point Estimates Considering the amount of risk in the original estimate Most Likely (most possible) - the duration of the schedule activity, given the resources likely to eb assigned, their productivity, realistic expectations of availability for the schedule activity, dependencies on other participants, and interruptions Optimistic based on best-case scenario of what is described in the most likely estimate Pessimistic based worst-case scenario of what is described in the most likely estimate

4.

d) Reserve Analysis Additonal time referred to as contingency reserves; can be percentage of the estimated activity duration or a fixed number of work periods. Activity Duration Estimates Outputs: a) Activity Duration Estimates Quantitative assessments of the likely number of work periods that will be requires to complete a schedule activity 5. Schedule Development iterative process that determines the planned start and finish dates for project activities Schedule Development Inputs (previously discussed) Schedule Development Tools and Techniques: a) Schedule Network Analysis Technique that generates the project schedule. It employs a schedule model and various analytical techniques b) Critical Path Method Calculates the theoretical early start and finish dates, and late start and finish dates for all schedule activities c) Schedule Compression Shortens the project schedule without changing the project scope Crashing cost and schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression Fast Tracking schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel d) What-If Scenario Analysis Analysis of the question What if the situation represented by scenario X happens? e) Resource Levelling To keep selected resource usage at a constant level during specific time periods of the project work. f) Critical Chain Method Schedule network analysis technique that modifies the project schedule to account for limited resources g) Applying Calendars Project calendars and resource calendars identify periods when work is allowed. h) Adjusting Leads and Lags Develop a viable (possible) project schedule i) Schedule Model Used in conjunction with other schedule tools to generate the project schedule Schedule Development: Outputs a) Project Schedule A planned start and planned finished date for each schedule activity. Can be presented in summary form, sometimes referred to as the master schedule or milestone schedule, or presented in detail Presented in tabular/ graphically using the following formats: Project Schedule Network Diagrams with activity date information, usually show both the project logic Bar Charts bars representing activities, show activity start and end dates as well as expected durations Milestone Charts only identify the scheduled start or completion of major deliverables

b) Schedule Baseline Baseline start dates and baseline finish dates 6. Schedule Control Concerned with: Determining the current status of the project schedule Influencing the factors that create schedule changes Determining that the project schedule has changed Managing the actual changes as they occur Schedule Control Inputs: a) Schedule Management Plan Establishes how the project schedule will be managed and controlled b) Schedule Baseline Approved project schedule, basis for measuring and reporting schedule performance as part of the performance measurement baseline c) Performance Reports Provide information on schedule performance such as which planned dates have been met and which have not. Schedule Control Tools and Techniques: a) Progress Reporting Includes information such as actual finish dates and the remaining durations for unfinished schedule activities b) Schedule Change Control System Defines the procedures by which the project schedule can be changed. It includes paper works, tracking systems, and approval levels necessary for authorizing changes. c) Performance Measurement Uses to assess the magnitude (size/level, etc) of any project schedule variations that occur. d) Variance Analysis Comparing targets schedule dates with the actual/forecast start and finish dates provides information for the detection of deviations, and for the implementation of corrective actions in case of delays. e) Schedule Comparison Bar Charts Displays two bars for each schedule activity. One bar shows the current actual status and the other shows the status of the approved project schedule baseline. This shows graphically where the schedule has progressed as planned or where slippage has occurred. Schedule Control Outputs: a) Performance Measurements Work packages and control accounts are documented and communicated to stakeholders b) Recommended Corrective Actions Anything done to bring expected future project schedule performance in line with the approved project schedule baseline

You might also like