Scheduling/Leveling Report - 14-Sep-12 04:29 PM - PM.

exe
========================================================
Default Project..................................................2887
Projects:
2887............................................................
Refineria Cajamarquilla
Scheduling/Leveling Settings:
----------------------------General
------Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retaine
d Logic
Calculate start-to-start lag from ...............................Early S
tart
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish
Float
Calendar for scheduling Relationship Lag ........................Predece
ssor Activity Calendar
Advanced
-------Calculate multiple float paths...................................No
Statistics:
----------# Projects.......................................................1
# Activities.....................................................28
# Not Started....................................................24
# In Progress....................................................4
# Completed......................................................0
# Relationships..................................................56
# Activities with Constraint.....................................2
Project:
2887
Activity:
81EST 1000
Montaje
Estructura Plataforma
Project:
2887
Activity:
SU1000 Adquisicion de T
uberias
Errors:
------Warnings:
--------Activities without predecessors..................................1
Project:
2887
Activity:
HT1000 Inicio del Proye
cto
Activities without successors....................................1
Project:
2887
Activity:
HT1050 Fin del proyecto

Out-of-sequence activities.......................................4
Project:
2887
Activity:
81EQP 1000
Montaje
de Horno de Fusin #3
Project:
2887
Activity:
81EST 1000
Montaje
Estructura Plataforma
Project:
2887
Activity:
81EST 1010
Montaje
de plataforma de inspeccion
Project:
2887
Activity:
81EST 1020
Montaje
de vigas porta riel
Activities with Actual
Project:
de Horno de Fusin #3
Project:
Estructura Plataforma
Project:
de plataforma de inspeccion
Project:
de vigas porta riel

Dates > Data Date.........................4


2887
Activity:
81EQP 1000
Montaje
2887

Activity:

81EST 1000

Montaje

2887

Activity:

81EST 1010

Montaje

2887

Activity:

81EST 1020

Montaje

Milestone Activities with invalid relationships..................3


Project:
2887
Activity:
HT1010 Entrega de Area
Project:
2887
Activity:
HT1020 LLegada de Estru
cturas
Project:

2887

Activity:

HT1030 Suministro de Eq

uipos
Scheduling/Leveling Results:
---------------------------# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................28
# Relationships with other projects..............................0
Data Date........................................................13-Sep12 07:00 AM
Earliest Early Start Date........................................13-Sep12 07:00 AM
Latest Early Finish Date.........................................01-Jun13 01:00 PM
Exceptions:
----------Critical Activities..............................................13
Project:
2887
Activity:
00GE1000
Moviliza
cion
Project:
2887
Activity:
00GE1010
Desmovil
izacion
Project:
2887
Activity:
81EQP 1000
Montaje
de Horno de Fusin #3
Project:
2887
Activity:
81EQP 1030
Montaje
de Lnea de Moldeo de Barras
Project:
2887
Activity:
81PIP1000
Montaje
de Lnea de Instrumentos
Project:
2887
Activity:
81PIP1010
Montaje
de Lnea de Agua de Enfriamiento
Project:
2887
Activity:
81PIP1020
Montaje
de Lnea de Gas Propano
Project:
2887
Activity:
G1020 Elaboracin del In
forme Final
Project:
2887
Activity:
HT1000 Inicio del Proye
cto
Project:
2887
Activity:
HT1010 Entrega de Area

Project:

2887

Activity:

HT1040 Mechanical compl

Project:
Project:

2887
2887

Activity:
Activity:

HT1050 Fin del proyecto


SU1000 Adquisicion de T

etion
uberias
Activities with unsatisfied constraints..........................0
Activities with unsatisfied relationships........................0
Activities with external dates...................................0