SCHEDULE - E Rough Cost Estimate per Square Foot Serial Item of Work

Amount in Rupees per sq. ft.

HIG Units
1)

Foundation work (Civil)


Cost of providing R.C.C. Pile , Pile Cap, Tie Beam,Brick soling, P.C.C. excavation Filling etc.including reinforcements,shuttering as per IS CODE and all complete

160.00

Cost of providing R.C.C. Columns, Floor Beams & Slabs, Lintel, Chajja etc. all complete. including reinforcements,shuttering,concreting as per IS CODE , with curing , and all complete. (ii) Cost of 200 mm & 125/75 mm brickwork in cement - sand mortar with 1st.Class bricks all complete. (iii) Cost of Plastering Interior,Exterior Walls & Ceiling with cement - sand mortar all complete. (iv) Cost of providing RCC underground and over head water reservoirs including necessary water proofing , plastering etc and all complete. (v) Cost of providing Masonry Septic Tanks as per reqd. capacity with RCC slabs , including plastering, etc. and all complete. 3)

2) (i)

Superstructure work (Civil)

550.00

Flooring
Cost of providing and fixing Marble Slabs to all Floors Ceramic Tiles to Dado in Toilet and Kitchen, with Granite Kitchen counter counter top etc. all complete.

130.00

4)

Plaster of Paris
Cost of providing Plaster of Paris punning to Interior Walls & Ceiling .

20.00

5)

Painting
Cost of Painting Exterior Walls with Acrylic Emulsion paint (weather coat) of different shades of colour with necessary cement based primer , surface preparation etc. with curing and all complete

15.00

6) (i)

Doors and Windows


Cost of providing sliding type Aluminium windows with clear glass window shutters. Number of tracks as reqd. ( aluminium to be natural annodised) with all accesories and all complete. Cost of providing solid type Flush Door with wooden Door Frame,with synthetic enamel paint , with necessary hardware and all complete. Cost of providing wooden door Frame with solid core flush door shutter with both sides teak veneer with necessary hardware including door lock to entrance door. and all complete.

130.00

(ii)

(iii)

SCHEDULE - E Rough Cost Estimate per Square Foot Serial Item of Work 7) Grill and Railing (i) Cost of providing M.S. Grill (12 to16kg / m2) to window. As per design. with synthetic enamel painting on necessary coats of red lead primer etc. and all complete. (ii) Cost of providing M.S. Railing to Stair & Verandah on 450 high brick work. With painting and all complete. 8)

Amount in Rupees per sq. ft. 35.00

Electrical Work
Providing Electrical points in walls and ceiling , including piano switches on backelite boards and MS boxes , concealed wiring of al.wires in pvc conduits with necessary earthing , distribution boards , panels changeovers, saftey devices , etc and other works as per IS CODE and all complete.

35.00

9)

Plumbing & Sanitary Work


Cost of providing and fixing medium coloured sanitaryware in toilets including CP fittings with GI(medium)pipes for concealed water lines , PVC soil, waste,rain water pipes , stoneware sewer lines including yard gullys,masonry inspection pits, and GI water supply and distribution system with gun metal valves , adequate capacity pumps, etc and all complete.

50.00

10)

Lift
Cost of providing lift( size and number as per drawing ) in all buildings of normal speed and telescopic door with necessary interiors,facia nad all complete.

50.00

11)

Roof Treatment
Cost of providing waterproofing course to top roof surface with a layer of screed concrete over it and finishing and all complete.

10.00

12)

Miscellaneous Works TOTAL COST PER SQ. FT.

15.00 1,200.00

SCHEDULE - E Rough Cost Estimate per Square Foot Serial Item of Work

Amount in Rupees per sq. ft.

MIG Units
1)

Foundation work (Civil)


Cost of providing R.C.C. Pile , Pile Cap, Tie Beam,Brick soling, P.C.C. excavation Filling etc.including reinforcements,shuttering as per IS CODE and all complete

160.00

Cost of providing R.C.C. Columns, Floor Beams & Slabs, Lintel, Chajja etc. all complete. including reinforcements,shuttering,concreting as per IS CODE , with curing , and all complete. (ii) Cost of 200 mm & 125/75 mm brickwork in cement - sand mortar with 1st.Class bricks all complete. (iii) Cost of Plastering Interior,Exterior Walls & Ceiling with cement - sand mortar all complete. (iv) Cost of providing RCC underground and over head water reservoirs including necessary water proofing , plastering etc and all complete. (v) Cost of providing Masonry Septic Tanks as per reqd. capacity with RCC slabs , including plastering, etc. and all complete. 3)

2) (i)

Superstructure work (Civil)

550.00

Flooring
Cost of providing and fixing Ceramic tiles(1'x1') to all Floors Ceramic Tiles to Dado in Toilet and Kitchen, with Marble Kitchen counter counter top etc. all complete. Staircase flooring to be done in cast in situ mosaic with multi coloured chips ,glass strips etc.

100.00

4)

Plaster of Paris
Cost of providing Plaster of Paris punning to Interior Walls & Ceiling .

15.00

5)

Painting
Cost of Painting Exterior Walls with Acrylic Emulsion paint (weather coat) of different shades of colour with necessary cement based primer , surface preparation etc. with curing and all complete

15.00

6) (i)

Doors and Windows


Cost of providing sliding type Aluminium windows with clear glass window shutters. Number of tracks as reqd. ( aluminium to be natural annodised) with all accesories and all complete. Cost of providing solid type Flush Door with wooden Door Frame,commercial ply,with synthetic enamel paint , with necessary hardware and all complete.

110.00

(ii)

SCHEDULE - E Rough Cost Estimate per Square Foot Serial Item of Work 7) Grill and Railing (i) Cost of providing M.S. Grill to window. As per design. with synthetic enamel painting on necessary coats of red lead primer etc. and all complete. (ii) Cost of providing M.S. Railing to Stair & Verandah on 450 high brick work. With painting and all complete. 8)

Amount in Rupees per sq. ft. 30.00

Electrical Work
Providing Electrical points in walls and ceiling , including piano switches on backelite boards and MS boxes , concealed wiring of al.wires in pvc conduits with necessary earthing , distribution boards , panels changeovers, saftey devices , etc and other works as per IS CODE and all complete.

30.00

9)

Plumbing & Sanitary Work


Cost of providing and fixing white sanitaryware in toilets including cp fittings with GI(medium)pipes for concealed water lines , PVC soil, waste,rain water pipes , stoneware sewer lines including yard gullys,masonry inspection pits, and GI water supply and distribution system with gun metal valves , adequate capacity pumps, etc and all complete.

40.00

10)

Lift
Cost of providing lift( size and number as per drawing ) in all buildings of normal speed and telescopic door with necessary interiors,facia nad all complete.

30.00

11)

Roof Treatment
Cost of providing waterproofing course to top roof surface with a layer of screed concrete over it and finishing and all complete.

10.00

12)

Miscellaneous Works TOTAL COST PER SQ. FT.

10.00 1100.00

SCHEDULE - E Rough Cost Estimate per Square Foot Serial Item of Work

Amount in Rupees per sq. ft.

Service Apartments
1)

Foundation work (Civil)


Cost of providing R.C.C. Pile , Pile Cap, Tie Beam,Brick soling, P.C.C. excavation Filling etc.including reinforcements,shuttering as per IS CODE and all complete

160.00

Cost of providing R.C.C. Columns, Floor Beams & Slabs, Lintel, Chajja etc. all complete. including reinforcements,shuttering,concreting as per IS CODE , with curing , and all complete. (ii) Cost of 200 mm & 125/75 mm brickwork in cement - sand mortar with 1st.Class bricks all complete. (iii) Cost of Plastering Interior,Exterior Walls & Ceiling with cement - sand mortar all complete. (iv) Cost of providing RCC underground and over head water reservoirs including necessary water proofing , plastering etc and all complete. (v) Cost of providing Masonry Septic Tanks as per reqd. capacity with RCC slabs , including plastering, etc. and all complete. 3)

2) (i)

Superstructure work (Civil)

550.00

Flooring
Cost of providing and fixing Ceramic tiles(1'x1') to all Floors Ceramic Tiles to Dado in Toilet and Kitchen, with Marble Kitchen counter counter top etc. all complete. Staircase flooring to be done in cast in situ mosaic with multi coloured chips ,glass strips etc.

130.00

4)

Plaster of Paris
Cost of providing Plaster of Paris punning to Interior Walls & Ceiling .

25.00

5)

Painting
Cost of Painting Exterior Walls with Acrylic Emulsion paint (weather coat) of different shades of colour with necessary cement based primer , surface preparation etc. with curing and all complete

15.00

6) (i)

Doors and Windows


Cost of providing sliding type Aluminium windows with clear glass window shutters. Number of tracks as reqd. ( aluminium to be natural annodised) with all accesories and all complete. Cost of providing solid type Flush Door with wooden Door Frame,commercial ply,with synthetic enamel paint , with necessary hardware and all complete.

135.00

(ii)

SCHEDULE - E Rough Cost Estimate per Square Foot Serial Item of Work 7) Grill and Railing (i) Cost of providing M.S. Grill to window. As per design. with synthetic enamel painting on necessary coats of red lead primer etc. and all complete. (ii) Cost of providing M.S. Railing to Stair & Verandah on 450 high brick work. With painting and all complete. 8)

Amount in Rupees per sq. ft. 35.00

Electrical Work
Providing Electrical points in walls and ceiling , including piano switches on backelite boards and MS boxes , concealed wiring of al.wires in pvc conduits with necessary earthing , distribution boards , panels changeovers, saftey devices , etc and other works as per IS CODE and all complete.

35.00

9)

Plumbing & Sanitary Work


Cost of providing and fixing white sanitaryware in toilets including cp fittings with GI(medium)pipes for concealed water lines , PVC soil, waste,rain water pipes , stoneware sewer lines including yard gullys,masonry inspection pits, and GI water supply and distribution system with gun metal valves , adequate capacity pumps, etc and all complete.

50.00

10)

Lift
Cost of providing lift( size and number as per drawing ) in all buildings of normal speed and telescopic door with necessary interiors,facia nad all complete.

40.00

11)

Roof Treatment
Cost of providing waterproofing course to top roof surface with a layer of screed concrete over it and finishing and all complete.

10.00

12)

Miscellaneous Works TOTAL COST PER SQ. FT.

15.00 1200.00

SCHEDULE - E Rough Cost Estimate per Square Foot Serial Item of Work

Amount in Rupees per sq. ft.

Commercial
1)

Foundation work (Civil)


Cost of providing R.C.C. Pile , Pile Cap, Tie Beam,Brick soling, P.C.C. excavation Filling etc.including reinforcements,shuttering as per IS CODE and all complete

160.00

Cost of providing R.C.C. Columns, Floor Beams & Slabs, Lintel, Chajja etc. all complete. including reinforcements,shuttering,concreting as per IS CODE , with curing , and all complete. (ii) Cost of 200 mm & 125/75 mm brickwork in cement - sand mortar with 1st.Class bricks all complete. (iii) Cost of Plastering Interior,Exterior Walls & Ceiling with cement - sand mortar all complete. (iv) Cost of providing RCC underground and over head water reservoirs including necessary water proofing , plastering etc and all complete. (v) Cost of providing Masonry Septic Tanks as per reqd. capacity with RCC slabs , including plastering, etc. and all complete. 3)

2) (i)

Superstructure work (Civil)

550.00

Flooring
Cost of providing and fixing Ceramic tiles(1'x1') to all Floors Ceramic Tiles to Dado in Toilet and all complete. Staircase flooring to be done in cast in situ mosaic with multi coloured chips ,glass strips etc.

130.00

4)

Plaster of Paris
Cost of providing Plaster of Paris punning to Interior Walls & Ceiling .

15.00

5)

Painting
Cost of Painting Exterior Walls with Acrylic Emulsion paint (weather coat) of different shades of colour with necessary cement based primer , surface preparation etc. with curing and all complete

15.00

6) (i)

Doors and Windows


Cost of providing sliding type Aluminium windows with clear glass window shutters. Number of tracks as reqd. ( aluminium to be natural annodised) with all accesories and all complete. Cost of providing solid type Flush Door with wooden Door Frame,commercial ply,with synthetic enamel paint , with necessary hardware and all complete.

100.00

(ii)

SCHEDULE - E Rough Cost Estimate per Square Foot Serial Item of Work 7) Grill and Railing (i) Cost of providing M.S. Grill to window. As per design. with synthetic enamel painting on necessary coats of red lead primer etc. and all complete. (ii) Cost of providing M.S. Railing to Stair & Verandah on 450 high brick work. With painting and all complete. (iii) Cost of providing MS Rolling shutters. As shown in drg. with synthetic enamel painting over a coat of primer and all complete with locking arrangements. 8)

Amount in Rupees per sq. ft. 70.00

Electrical Work
Providing Electrical points in walls and ceiling , including piano switches on backelite boards and MS boxes , concealed wiring of al.wires in pvc conduits with necessary earthing , distribution boards , panels changeovers, saftey devices , etc and other works as per IS CODE and all complete.

30.00

9)

Plumbing & Sanitary Work


Cost of providing and fixing white sanitaryware in toilets including cp fittings with GI(medium)pipes for concealed water lines , PVC soil, waste,rain water pipes , stoneware sewer lines including yard gullys,masonry inspection pits, and GI water supply and distribution system with gun metal valves , adequate capacity pumps, etc and all complete.

20.00

12)

Miscellaneous Works TOTAL COST PER SQ. FT.

10.00 1100.00