You are on page 1of 251

IRR-DAW

Chapter - I

Standard Data
Index- code IRR-DAW
IRR-DAW-1 IRR-DAW-1-1

DAM AND ALLIED WORKS


EXCAVATION & FOUNDATION TREATMENT WORKS: Excavation for foundation in all kinds of soil including boulders upto 0.30 m diameter for dam, spillway, intake structure and other appurtenant works and placing the excavated soil neatly in dump area or disposing off the same as directed etc., complete with initial lead upto 1 km and all lifts.

DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 Particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 2 3 Description Unit Quantity 8.00 8.00 48.00 48.00 8.00 8.00 Rs: Rate in Rs. Amount in Rs Unit Quantity 0.00 0.00 Rs: UNIT 880 cum Rate Amount in Rs. in Rs

Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Dumpers 5 cum capacity 6 Nos Hour Fuel / Energy charges Hour Tipper 5 cum capacity 1 No Hour Fuel / Energy charges Hour Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3 4 5 Description Crew for Shovel Crew for Dumper Crew for Tipper work inspector mazdoor Unit Quantity 8.00 48.00 8.00 1.00 16.00 Rs: 0.00 Rs. Rs: Rs: Rate in Rs. Amount in Rs

Hour Hour Hour Day Day Total cost of Labour D Add for contractor's profit and 0% overheads on A+B+C Total cost for 880.00 Rate per/ Cu.mt.=(A+B+C+D) /880

cum

IRR-DAW-1-2

DATA:

Excavation for foundation in ordinary rock without blasting including boulders above 0.3 m upto 0.6 m dia for dam, spillway, intake structure and other appurtenant works and placing the excavated material neatly in dump area or disposing off the same as directed etc., complete with initial lead upto 1 km and all lifts. Capacity of shovel bucket DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 Particulars NIL Total cost of Materials B. MACHINERY: Sl No Description Unit Quantity Unit Quantity

0.85 cum

UNIT : 520 cum Rate in Rs. Rs: Amount in Rs.

0.00

Rate in Rs.

Amount in Rs

IRR-DAW

1 2 3

Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Dumpers 5 cum capacity( 4 Nos) Hour Fuel / Energy charges Hour Tipper 5 cum capacity( 1 No) Hour Fuel / Energy charges Hour Total hire charges of Machinery

8.00 8.00 32.00 32.00 8.00 8.00 Rs:

C. LABOUR: Sl No 1 2 3 4 5 6 Description Crew for Shovel Crew for Dumper Crew for Tipper work inspector Crowbarman mazdoor Unit Hour Hour Hour Day Day Day Total cost of Labour 0% 520 cum Rate per/ Cu.mt.=(A+B+C+D) /520 cum Quantity 8.00 32.00 8.00 1.00 2.50 10.00 Rs. Rs. Rs: Rs: Rate in Rs. Amount in Rs

D Add for contractor's profit and overheads on A+B+C

IRR-DAW-1-3

Excavation for foundation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. for dam, spillway, intake structure and other appurtenant works and placing the excavated material neatly in dump area or disposing off the same as directed etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Description Unit Quantity 216.00 26.00 104.00 154.00 320.00 5.00 Rs. UNIT : 520 CU.MTS Rate in Rs. Amount in Rs

Use rate of 1.5 m drill rod Rm Reconditioning charges @ 10% Use rate of air hose 4 Nos. Hour Explosive small dia kg Electric detonators Nos Fuse coil Rm Sundries LS Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5 Description Unit Quantity 8.00 8.00 32.00 32.00 8.00 8.00 13.00 13.00 26.00 26.00 Rs: Rate in Rs. Amount in Rs

Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Dumpers 5 cum capacity 4 Nos. Hour Fuel / Energy charges Hour Tipper 5 cum capacity 1 No Hour Fuel / Energy charges Hour Air compressor 8.5 cmm ( ele ) 2 Nos our H Fuel / Energy charges Hour Jack hammers 4 Nos. Hour Fuel / Energy charges Hour Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11 Description Crew for Shovel Crew for Dumper Crew for Tipper Crew for Air compressor Crew for Jack hammer work inspector Blaster Helper blaster Crowbarman Stone breaker mazdoor Unit Quantity 8.00 32.00 8.00 13.00 26.00 1.00 1.00 1.00 2.50 1.00 10.00 Rs. Rs. Rs: Rs. Rate in Rs. Amount in Rs

D Add for contractor's profit and overheads on A+B+C

Hour Hour Hour Hour Hour Day Day Day Day Day Day Total cost of Labour 0% Rate per/ Cu.mt.=(A+B+C+D) /520

IRR-DAW

IRR-DAW-1-4 (a)

Excavation for foundation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for dam, spillway, intake structure and other appurtenant works and placing the excavated rock neatly in dump area or stack yard including levelling as directed etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 7 Use rate of drill rod 1.5 m long Reconditioning charges @ Use rate of air hose 4 Nos. Explosive small dia Ordinary detonators Electric detonators Fuse coil Sundries Rm 10% Hour kg Nos Nos Rm LS 48.00 95.00 10.00 333.00 450.00 5.00 310.00

UNIT 320.00 cum Rate Amount in Rs. in Rs

Rs: B. MACHINERY: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 8.00 8.00 24.00 24.00 4.00 4.00 1.00 1.00 24.00 24.00 48.00 48.00

Rate in Rs.

Amount in Rs

Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Dumpers 5 cum capacity 3 Nos. Hour Fuel / Energy charges Hour Tipper 5 cum capacity 1 No Hour Fuel / Energy charges Hour Angle dozer 90 hp Hour Fuel / Energy charges Hour Air compressor 8.5 cmm (ele) 2 Nos.Hour Fuel / Energy charges Hour Jack hammers 4 Nos. Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rs.

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11 12

Description Crew for Shovel Crew for Dumper Crew for Tipper Crew for Dozer Crew for Air compressor Crew for Jack hammer work inspector Blaster Helper blaster Crowbarman Stone breaker mazdoor

Unit Hour Hour Hour Hour Hour Hour Day Day Day Day Day Day Total cost of Labour

Quantity 8.00 24.00 4.00 1.00 24.00 48.00 1.00 1.00 1.00 1.00 2.00 6.00

Rate in Rs.

Amount in Rs

Rs.

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D Add for contractor's profit and overheads on A+B+C 0% Rate per Cu.mt.=(A+B+C+D) /320

Rs: Rs: Rs: Rs: Rs. Rs: Rs:

0.00 0.00 0.00 0.00

IRR-DAW

IRR-DAW-1-5 (b)

Excavation for foundation in hard rock of all toughness including boulders above 1.2 m dia. by controlled blasting method and controlling fly-rock by muffling arrangements for dam, spillway, intake structure and other appurtenant structures etc., including placing and levelling the excavated rock neatly in dump area or other place as directed etc., complete with lead upto upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 9 Particulars Unit Quantity 464.00 70.00 715.00 580.00 149.00 23.00 500.00 700.00 10.00 Rs: UNIT : 480.00 cum Rate Amount in Rs. in Rs

Use rate of drill rod 1.5 m length Rm Reconditioning charges @ 10% Use rate of 50 m air hose 4 Nos. Hour Use rate of chain link wire mesh sqm Use rate of sand bag Nos Explosive small dia. kg Ordinary detonators Nos Electric delay detonators Nos Fuse coil Rm Sundries LS Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5 6

Particulars

Unit

Quantity 12.00 12.00 2.00 2.00 36.00 36.00 4.00 4.00 35.00 35.00 70.00 70.00

Rate in Rs.

Amount in Rs

Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Angle dozer 90 hp Hour Fuel / Energy charges Hour Dumpers 5 cum capacity 3 Nos. Hour Fuel / Energy charges Hour Tipper 5 cum capacity 1 No Hour Fuel / Energy charges Hour Air compressor 8.5 cmm ( ele ) 2 Nos our H Fuel / Energy charges Hour Jack hammers 4 Nos. Hour Fuel / Energy charges Hour Total hire charges of Machinery Description Crew for Shovel Crew for Angle dozer Crew for Dumper Crew for Tipper Crew for Air compressor Crew for Jack hammer work inspector Blaster Helper blaster Crowbarman Stone breaker mazdoor ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Rate per/ Cu.mt.=(A+B+C+D) /480 Unit Quantity

Rs: Rate in Rs. 12.00 2.00 36.00 4.00 35.00 70.00 4.50 1.50 3.00 2.50 2.50 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs. Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11 13

Hour Hour Hour Hour Hour Hour Day Day Day Day Day Day Total cost of Labour

Rs: 0.00 Rs: 0.00 Rs: 0.00

0%

Rs. Rs:

IRR-DAW

IRR-DAW-1-6 ( c)

Note :

Excavation for foundation in hard rock of all toughness including boulders above 1.2 m dia. by line drilling and smooth blasting and controlling fly-rock by muffling arrangements for dam, spillway, intake structure and other appurtenant structures etc., including dressing sides and bed to required level / profile, placing and levelling the excavated rock neatly in dump area or other place as directed etc., complete with lead upto 1 km and all lifts. i ) 1 m width of excavation along the face to be dressed shall be treated as excavation by line drilling and smooth blasting. ii ) The rate under this item shall be paid only on ascertaining that the surface requiring dressing has come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for inspection and are spaced at specified interval. iii ) In case, where the above criteria is not fulfilled payment shall be restricted to the rate provided for excavation by normal or controlled blasting as the case may be.. UNIT : A. MATERIALS: Sl No 1 2 3 4 5 6 7 Particulars Unit Quantity 138.00 22.00 10.50 2.00 76.00 140.00 2.00 Rs. 40.00 cum Rate Amount in Rs. in Rs

Use rate of drill rod 1.5 m length Rm Reconditioning charges @ 10% Use rate of 50 m air hose 4 Nos. Hour Explosive small dia. kg Ordinary detonators Nos Electric delay detonators Nos Fuse coil Rm Sundries LS Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5

Description

Unit

Quantity 1.00 1.00 0.25 0.25 3.00 3.00 11.00 11.00 22.00 22.00

Rate in Rs.

Amount in Rs

Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Angle dozer 90 hp Hour Fuel / Energy charges Hour Dumpers 5 cum capacity 3 Nos. Hour Fuel / Energy charges Hour Air compressor 8.5 cmm ( ele ) 2 Nos our H Fuel / Energy charges Hour Jack hammers 4 Nos. Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rs:

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11

Description Crew for Shovel Crew for Angle dozer Crew for Dumper Crew for Air compressor Crew for Jack hammer work inspector Blaster Helper blaster Crowbarman Stone breaker mazdoor

Unit Hour Hour Hour Hour Hour Day Day Day Day Day Day Total cost of Labour

Quantity 1.00 0.25 3.00 11.00 22.00 0.50 0.50 0.50 0.50 0.50 2.00

Rate in Rs.

Amount in Rs

Rs.

Add for contractor's profit and overheads on A+B+C Rate per/ Cu.mt.=(A+B+C+D) /40

0%

Rs. Rs:

IRR-DAW

IRR-DAW-1-7

DATA:

Preparing foundation bed for masonry or concrete by benching, stepping, removing all loose material by wedging / chiselling and disposing off the same as directed and cleaning the surface with air and water jet etc. ,complete with initial lead upto 50 m and all lifts. 1 Crowbarman, 1 stone breaker and 1 mazdoor prepare 50 sqm per day. 0.5 mazdoor for air water jet cleaning for 100 sqm area.

DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 NIL Total cost of Materials B. MACHINERY: Sl No 1 2 Particulars Unit Quantity

UNIT: 100.00 sqm Rate Amount in Rs. in Rs

Description

Unit

Quantity 1.00 1.00 1.00 1.00

Rate in Rs.

Amount in Rs

Air compressor 8.5 cmm ( ele ) Hour Fuel / Energy charges Hour Pump 5 hp ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rs. 0.00

C. LABOUR: Sl No 1 2 3 4 5

Description Crew for Air compressor Crew for Pump Stone breaker mazdoor Crowbar man

Unit Hour Hour Day Day Day Total cost of Labour

Quantity 1.00 1.00 2.00 2.50 2.00

Rate in Rs.

Amount in Rs

Rs:

Add for contractor's profit and overheads on A+B+C

0%

Rs. Rs:

Rate per/ Square.mt.=(A+B+C+D) /100 IRR-DAW-1-8 Preparing foundation bed for cut-off trench filling in rock portion by removing all loose materials by wedging / chiselling and disposing off the same as directed etc., complete with initial lead upto 50 m and all lifts. 1 crowbar man, 1 stone breaker and 1 mazdoor prepare 50 sqm per day. DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 NIL

DATA:

Particulars

UNIT: 100.00 sqm Unit Quantity Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 Total cost of Materials Rs. 0.00

B. MACHINERY: Sl No 1 NIL

Description

Unit

Quantity 0.00 0.00

Rate in Rs.

Total cost of Machinery C. LABOUR: Sl No 1 2 3

Amount in Rs 0.00 0.00 0.00 0.00 Rs. 0.00

Description Crowbar man Stone breaker mazdoor

Unit

Quantity 2.00 2.00 2.00

Day Day Day Total cost of Labour Add for contractor's profit and overheads on A+B+C

Rate in Rs. 0.00 0.00 0.00 Rs: Rs. Rs:

Amount in Rs 0.00 0.00 0.00 0.00

0%

Rate per/ Square.mt.=(A+B+C+D) /100

IRR-DAW

IRR-DAW-1-9

NOTE: DATA:

Drilling 45 to 50 mm dia holes vertical or inclined upto 10 degrees to vertical in rock /masonry/ concrete by percussion drilling using waggon drill or any other suitable equipment including cost of all materials, machinery, labour, redrilling through partially set grout wherever required etc., complete. for drilling upto 6 m depth from surface. The item rate for drilling through rock / masonry / concrete includes redrilling through partially set grout, if any, in the portion of hole already grouted. Generally rate of drilling by waggon drill in rock or masonry or concrete in open area including shifting from hole to hole will be about 12 m per hour. As normally 6 m stage is considered for grouting, 16 holes of 6 m each considered for rate analysis with one 8.5 cmm capacity air compressor and one waggon drill per day. For drilling in hard rock beyond 6 m from surface increase the basic rate per Rm of previous stage by 10 percent for next stage of 6 m beyond previous stage towards redrilling in partially set grout / additional extension rods / reduction in progress etc. DATA & RATE ANALYSIS UNIT: A. MATERIALS: Sl No 1 2 3 Particulars Unit Quantity 96.00 8.00 96.00 96.00 Rm Rate Amount in Rs. in Rs

Use rate of cross bit 50 mm dia Rm Use rate of 50 mm dia air hose 50 mHour Use rate of extension rod 4.5 m Rm Total cost of Materials

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 8.00 8.00 2.00

Rate in Rs.

Amount in Rs

Waggon drill Hour Fuel / Energy charges Hour Air compressor 8.5 cmm ( ele ) Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3

Description Crew for Waggon drill Crew for Air compressor mazdoor

Unit Hour Hour Day Total cost of Labour

Quantity 8.00 8.00 2.00

Rate in Rs.

Amount in Rs

Add for contractor's profit and overheads on A+B+C Rate per/ R.Mt.=(A+B+C+D) /96

0%

Rs. Rs:

Beyond 6 m upto 12 m from surface : Upto 6 m from surface Rate per Add for redrilling through partially set grout / additional extension rods / reduction in rate of drilling etc @ Beyond 6 m upto 12 m from surface Beyond 12 m upto 18 m from surface : For 6 m to 12 m from surface Rate per Add for redrilling through partially set grout / additional extension rods / reduction in rate of drilling etc @ Beyond 12 m upto 18 m from surface Beyond 18 m upto 24 m from surface For 12 m to 18 m from surface Rate per Add for redrilling through partially set grout / additional extension rods / reduction in rate of drilling etc @ Beyond 18 m upto 24 m from surface Beyond 24 m upto 30 m from surface For 18 m to 24 m from surface

Rm 10% Rate / Rm

Rs: Rs: Rs:

Rm 10% Rate / Rm Rm

Rs: Rs: Rs: : Rs:

10% Rate / Rm

Rs: Rs: : Rs:

Rate per

Rm

Add for redrilling through partially set grout / additional extension rods / reduction in rate of drilling etc @ : Beyond 24 m upto 30 m from surface Beyond 30 m upto 36 m from surface For 24 m to 30 m from surface Rate per Add for redrilling through partially set grout / additional extension rods / reduction in rate of drilling etc @ Beyond 30 m upto 36 m from surface Beyond 36 m upto 42 m from surface For 30 m to 36 m from surface Rate per Add for redrilling through partially set grout / additional extension rods / reduction in rate of drilling etc @ Beyond 36 m upto 42 m from surface Beyond 42 m upto 48 m from surface

10% Rate / Rm Rm 10% Rate / Rm Rm 10% Rate / Rm

Rs Rs: : Rs: Rs: Rs: : Rs: Rs: Rs:

IRR-DAW

For 36 m to 42 m from surface Rate per Add for redrilling through partially set grout / additional extension rods / reduction in rate of drilling etc @ Beyond 42 m upto 48 m from surface

Rm 10% Rate / Rm

Rs: Rs: Rs:

IRR-DAW-1-10 Flushing grout holes of all sizes with water and air jets alternatively for an average period of 30 minutes including water intake observations after flushing, cost of all materials, machinery, labour etc., complete. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 Use rate of air hose 2 Nos x 8 hrs Hour Use rate of water hose 2 Nos x 8 hrs Hour Sundries LS Total cost of Materials 16.00 16.00 2.00

UNIT : 192.00 Rm. Rate Amount in Rs. in Rs

Rs:

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 8.00 8.00 2.00

Rate in Rs.

Amount in Rs

Air compressor 8.5 cmm ( ele ) Hour Fuel / Energy charges Hour Pump 5 hp ( ele ) Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery

Rs: 0.00

C. LABOUR: Sl No

Description

Unit Hour Hour Day Total cost of Labour

Quantity 8.00 8.00 4.00

Rate in Rs.

Amount in Rs

1 Crew for Air compressor 2 Crew for Pump 3 mazdoor

Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 Rs. Rs:

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C 0%

Rate per/ Running .Metre.=(A+B+C+D) /192

IRR-DAW-1-11 Consolidation grouting with neat cement grout mix of suitable (a) consistency under specified pressure as directed in drilled holes by stage grouting method including cost of all materials, machinery, labour, redrilling if necessary etc.,complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit Quantity 1.05 8.00 3.00 UNIT : 1.05 Ton Rate Amount in Rs. in Rs

Cement tonne Use rate of 50 m pressure hose Hour Sundries ( packer assembly etc ) LS Total cost of Materials

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 2.00 2.00 2.00 Rs:

Grouting equipment Fuel / Energy charges Pump 5 hp ( ele ) Fuel / Energy charges Sundries

Hour Hour Hour Hour LS Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3

Description

Unit

Quantity 8.00 2.00 2.00

Rate in Rs.

Amount in Rs

Crew for Grout pump Hour Crew for Pump Hour mazdoor ( cement handling) Day Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

0%

Rs.

Rate per/ Ton.=(A+B+C+D) /1.05

Rs:

IRR-DAW

IRR-DAW-1-12 Curtain grouting with neat cement grout mix of suitable consistency (b) under specified pressure as directed in drilled holes by stage grouting method including cost of all materials, machinery, labour, redrilling if necessary etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 Cement tonne Use rate of 100 m pressure hose Hour Use rate of 400 m GI pipe Hour Sundries ( packer assembly etc ) LS Total cost of Materials 1.05 8.00 8.00 3.00

UNIT : 1.05 Ton Rate Amount in Rs. in Rs

Rs:

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 2.00 2.00 2.00

Rate in Rs.

Amount in Rs

Grouting equipment Fuel / Energy charges Pump 5 hp ( ele ) Fuel / Energy charges Sundries

Hour Hour Hour Hour LS Total hire charges of Machinery

Rs: 0.00

C. LABOUR: Sl No 1 2 3 4

Description Crew for Grout pump Crew for Pump Pipe fitter mazdoor ( cement handling ) Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Hour Hour Day Day

Unit

Quantity 8.00 2.00 1.00 3.00

Rate in Rs.

Amount in Rs

Rs: Rs: Rs: Rs: 0% Rs.

D.Add for contractor's profit and overheads on A+B+C

Rate per/ Ton.=(A+B+C+D) /1.05 IRR-DAW-1-13 Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowel bars with one end driven into 45 to 50 mm diameter 1.50 m deep hole drilled in bed rock and other end provided with L-bend for embedding in concrete / masonry of over flow / non-over flow blocks and other appertenant works including cost of drilling and cleaning hole, filling hole with cement mortar 1 : 1 proportion, driving anchor rod, cost of all materials, machinery, labour etc., complete with initial lead upto 1 km and all lifts. Consider 25 anchor rods for analysis. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity Use rate of drill bit 50 mm dia Rm Use rate of air hose 50 m Hour Anchor rod 25 mm dia kg Cement kg Sand ( screened ) cum Total cost of Materials B. MACHINERY: Sl No Description Unit 1 2 1 2 3 4 5 37.50 4.00 303.20 75.00 0.05

Rs:

UNIT: 25 Nos. Rate Amount in Rs. in Rs

Quantity 4.00 4.00 4.00 4.00

Air compressor 8.5 cmm ( ele ) Hour Fuel / Energy charges Hour Waggon drill Hour Fuel / Energy charges Hour Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3 4 5

Description Crew for Air compressor Crew for Waggon drill Bar bender Mason Cl- II mazdoor

Unit Hour Hour Day Day Day Total cost of Labour

Quantity 4.00 4.00 0.50 0.50 1.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C 0%

Rs: Rs: Rs: Rs.

Rate per/ Each.=(A+B+C+D) /25

Rs:

IRR-DAW

IRR-DAW-1-14 Providing and fixing 25 mm dia. 2.75 m long ribbed steel anchor rods with one end split and driven firmly using steel wedge into 1.25 m deep 45 to 50 mm dia. hole drilled in bed rock and other end provided with L- bend for embedding in concrete / masonry for spillway and appurtenant works including drilling and cleaning hole, filling hole with thick cement slurry, driving anchor rod, cost of all materials, machinery, labour, steel wedge etc., complete with initial lead upto 1 km and all lifts. Consider 25 anchor rods for analysis. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity Use rate of 50 mm dia drill bit Rm Use rate of air hose 50 m 1 Nos. Hour Anchor rod 25 mm dia kg Cement kg Gas for splitting anchor rods LS Steel wedges LS Total cost of Materials B. MACHINERY: Sl No Description Unit 1 2 1 2 3 4 5 6 31.50 3.00 277.92 62.50 5.00 10.00

UNIT: 25.00 Nos. Rate Amount in Rs. in Rs

Rs: 0.00 Quantity 3.00 3.00 3.00 3.00 Rs: 0.00 Rate in Rs. Amount in Rs Rate in Rs. Amount in Rs

Air compressor 8.5 cmm ( ele ) Hour Fuel / Energy charges Hour Waggon drill Hour Fuel / Energy charges Hour Total hire charges of Machinery Description Crew for Air compressor Crew for Waggon drill Bar bender Mason Cl- II Gas cutter mazdoor Unit Hour Hour Day Day Day Day Total cost of Labour

C. LABOUR: Sl No 1 2 3 4 5 6

Quantity 3.00 3.00 0.50 0.50 1.00 2.00

Rs: Rs: Rs: Rs: 0% Rs.

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

Rate per/ Each.=(A+B+C+D) /25 IRR-DAW-2 REINFORCEMENT & CEMENT CONCRETE WORKS :

Rs:

IRR-DAW-2-1A Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods overlaps and wastages wherever required, tying with 1.25 mm diameter soft annealed steel wire, including cost of all materials, machinery, labour etc., complete with initial lead upto 1 km and all lifts. overlaps and wastage as per NHAI-data Lap jointing considered for bars upto 36 mm diameter. Quantity of binding wire per tonne overlapping and wastage Wastage of steel RATE ANALYSIS A. MATERIALS: Sl No 1 2 UNIT : 1.00 tonne Rate Amount in Rs. in Rs : 9.00 kg 5.00 percent

Particulars

Unit tonne kg

Quantity 1.05 9.00

Rein.Steel with 5 % wastage Binding wire 1.25 mm dia

Total cost of Materials B. MACHINERY: Sl No

Rs: 0.00

Description

Unit

Quantity

Rate in Rs. Rs:

Amount in Rs

Total hire charges of Machinery C. LABOUR: Sl No 3 4 Bar bender mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 2.00 6.84

Rate in Rs.

Amount in Rs

A.MATERIAL B.LABOURs C. MACHINERY D.Add for contractor's profit and overheads on A+B+C

0%

Rs.

10

IRR-DAW

Rate per/ TON.=(A+B+C+D) / I IRR-DAW-2-1B Providing, fabricating and placing in position reinforcement steel for RCC above 36 dia with welding and wastage at 2.5%, tying with 1.25 mm diameter soft annealed steel wire, including cost of all materials, machinery, labour etc., complete with initial lead upto 1 km and all lifts. overlaps and wastage as per NHAI-data welding joints considered for bars above 36 mm diameter. DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 3 Particulars Unit tonne Quantity 1.03 70.00 Rs: 0.00

Rs:

Rein.Steel with 2.5 % wastage

UNIT : 1.00 tonne Rate Amount in Rs. in Rs 0.00

Welding electrodes 5 per jointand One 14 joints per ton Total cost of Materials

B. MACHINERY: Sl No 1

Description hour

Unit

Quantity 10.00 10.00

Rate in Rs. 49.00

Amount in Rs

welding machine fuel charges

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3 welder Bar bender mazdoor

Rs: 0.00

Description

Unit day Day Day Total cost of Labour

Quantity 2.50 2.00 6.84

Rate in Rs.

Amount in Rs

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Rate per/ TON.=(A+B+C+D) / I IRR-DAW-2-2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for plain concrete works with initial lead upto 1 km and all lifts. ( Cement content : 210 kg /cum with use of super plasticiser , CA : 0.98 cum, Blending Ratio of CA -- 40:30:20:10, FA : 0.35 cum )

0%

DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 Particulars Unit Quantity

UNIT: 240.00 cum Rate Amount in Rs. in Rs

3 4 5

Cement for mix kg 50400.00 Cement for incidentals @ 3 kg / cumkg 720.00 Coarse aggregate 80-40 mm cum 94.08 Coarse aggregate 40-20 mm cum 70.56 Coarse aggregate 20-10 mm cum 47.04 Coarse aggregate 10 mm below cum 23.52 Fine aggregate ( screened ) cum 84.00 Super Plasticizer or AEA kg 201.60 Use rate of shuttering sqm 120.00 Add seigniorage charges on CA @ (Included in material rates) Add seigniorage charges on FA @ (Included in material rates) Total cost of Materials

Rs:

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour

Unit

Quantity 8.00 8.00 8.00 8.00 32.00 32.00 16.00 16.00 40.00 40.00 8.00 8.00 16.00 16.00

Rate in Rs.

Amount in Rs

Batching plant Fuel / Energy charges Air compressor 7 cmm ( ele ) Fuel / Energy charges Tipper Fuel / Energy charges Tower crane 5 t Fuel / Energy charges Concrete bucket Fuel / Energy charges 10 hp pump ( ele ) Fuel / Energy charges Needle vibrator 60 mm dia ( ele ) Fuel / Energy charges

11

IRR-DAW

Sundries

LS Total hire charges of Machinery

10.00 Rs:

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description

Unit

Quantity 8.00 8.00 32.00 16.00 8.00 16.00 4.00 2.00 2.00 2.00 2.00 6.00 2.00 120.00

Rate in Rs.

Amount in Rs

10

Crew for Batching plant Hour Crew for Air compressor Hour Crew for Tipper ( 4 ) Hour Crew for Tower crane ( 2 ) Hour Crew for Pump Hour Crew for Needle vibrator ( 2 ) Hour Mason Class-I Day Foreman Day mazdoor for silo ( cement handling ) Day for batching plant Day for conveyor system Day for laying & vibrating Day for cleaning / washing / curing Day Labour cost for shuttering sqm Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

Rs: Rs: 0.00 Rs: 0.00 Rs: 0.00 0% Rs. Rs:

Rate per/ CU.MTS=(A+B+C+D) /240 IRR-DAW-2-3 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for plain concrete works with initial lead upto 1 km and all lifts. ( Cement content : 190 kg /cum with use of super plasticiser, CA: 0.98 cum, Blending Ratio of CA --40:30:20:10, FA: 0.37 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 Particulars Unit Quantity 45600 720.00 94.08 70.56 47.04 23.52 88.8 182.40 120.00

UNIT: 240.00 cum Rate Amount in Rs. in Rs

3 4 5

Cement for mix kg Cement for incidentals @ 3 kg / cumkg Coarse aggregate 80-40 mm cum Coarse aggregate 40-20 mm cum Coarse aggregate 20-10 mm cum Coarse aggregate 10 mm below cum Fine aggregate ( screened ) cum Super Plasticizer or AEA kg Use rate of shuttering sqm

B. MACHINERY: Sl No 1 2 3 4 5 6 7 8 C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description

Unit

Quantity 8.00 8.00 8.00 8.00 32.00 32.00 16.00 16.00 40.00 40.00 8.00 8.00 16.00 16.00 10.00

Batching plant 2 x 1.5 cum Hour Fuel / Energy charges Hour Air compressor 7 cmm ( ele ) Hour Fuel / Energy charges Hour Tipper Hour Fuel / Energy charges Hour Tower crane 5 t Hour Fuel / Energy charges Hour Concrete bucket Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Needle vibrator 60 mm dia ( ele ) Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery Description Crew for Batching plant Crew for Air compressor Crew for Tipper ( 4 ) Crew for Tower crane ( 2 ) Crew for Pump Crew for Needle vibrator ( 2 ) Mason Class-I Foreman mazdoor for silo ( cement handling ) for batching plant Hour Hour Hour Hour Hour Hour Day Day Day Day Unit

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Quantity 8.00 8.00 32.00 16.00 8.00 16.00 4.00 2.00 2.00 2.00

0.00 0.00 0.00 0.00

12

IRR-DAW

10

for conveyor system Day for laying & vibrating Day for cleaning / washing / curing Day Labour cost for shuttering sqm Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

2.00 6.00 2.00 120.00

0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00

Rs: 0.00 Rs: 0.00 Rs: 0.00 0% Rs. Rs:

Rate per/ CU.MTS=(A+B+C+D) /240

IRR-DAW-2-4

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating structures, training walls, piers, abutments and such other locations with initial lead upto 1 km and all lifts. ( Cement content : 270 kg / cum with use of super plasticiser, CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg Cement for incidentals @ 3 kg / cumkg Coarse aggregate 40-20 mm cum Coarse aggregate 20-10 mm cum Coarse aggregate 10 mm below cum Fine aggregate ( screened ) cum Super Plasticizer or AEA kg Use rate of shuttering sqm Scaffolding of shuttering @ 64800 720.00 108 64.8 43.2 96 259.20 360.00 15%

3 4 5 6

UNIT: 240.00 cum Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 8.00 8.00 8.00 8.00 32.00 32.00 16.00 16.00 40.00 40.00 8.00 8.00 16.00 16.00 10.00

Batching plant 2 x 1.5 cum Hour Fuel / Energy charges Hour Air compressor 7 cmm ( ele ) Hour Fuel / Energy charges Hour Tipper Hour Fuel / Energy charges Hour Tower crane 5 t Hour Fuel / Energy charges Hour Concrete bucket Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Needle vibrator 60 mm dia ( ele ) Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description

Unit

Quantity

10 11

Crew for Batching plant Hour 8.00 Crew for Air compressor Hour 8.00 Crew for Tipper ( 4 ) Hour 32.00 Crew for Tower crane ( 2 ) Hour 16.00 Crew for Pump Hour 8.00 Crew for Needle vibrator ( 2 ) Hour 16.00 Mason Class-I Day 4.00 Foreman Day 2.00 mazdoor for silo ( cement handling ) Day 2.00 for batching plant Day 2.00 for conveyor system Day 2.00 for laying & vibrating Day 6.00 for cleaning / washing / curing Day 2.00 Labour cost for shuttering sqm 360.00 Labour cost for scaffolding @ 15% Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C 0% Rate per/ CU.MTS=(A+B+C+D) /240

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs:

Amount in Rs

Rs. Rs:

IRR-DAW-2-5

Providing and laying insitu vibrated M-15 ( 28 days cube compressive

13

IRR-DAW

strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for plain concrete works with initial lead upto 1 km and all lifts. ( Cement content : 210 kg / cum with use of super plasticiser, CA : 0.90 cum, Blending Ratio of CA -- 50:30:20, FA : 0.40 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix Cement for incidentals @ 3 kg Coarse aggregate 40-20 mm Coarse aggregate 20-10 mm Coarse aggregate 10 mm below Fine aggregate ( screened ) Super plasticizer Use rate of shuttering Use rate of scaffolding @ kg kg cum cum cum cum kg sqm 15% 3570 51.00 6.75 4.05 1.35 6 14.28 17.00

UNIT : 17 cum Rate Amount in Rs. in Rs

3 4 5 6

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.0 8.0 1.0 1.0 8.0 8.0

Rate in Rs.

Amount in Rs

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Needle vibrator 40 mm dia ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rs:

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 8.00 1.00 8.00 1.00 2.00 9.00 4.00 3.00 17.00 1.00 17.00

Rate in Rs.

Amount in Rs

6 7

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Needle vibrator Hour Mason Class-I Day mazdoor for batching cement ( cement handling Day for batching other materials Day for loading mortar pans Day for laying Day for conveying concrete Day for cleaning / washing / curing Day Labour cost of shuttering sqm Labour cost of scaffolding @ 15% Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Rate per/ CU.MTS=(A+B+C+D) /17

Rs:

Rs: Rs: Rs: 0% Rs. Rs:

IRR-DAW-2-6

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravity type structures including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete with initial lead upto 1 km and all lifts. ( Cement content : 204 kg / cum of concrete with use of plums and super plasticiser, CA : 0.77 cum, Blending Ratio of CA : 50:30:20, FA : 0.34 cum, plums of size 150 to 80 mm : 0.25 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg Cement for incidentals @ 3 kg / cumkg Coarse aggregate 40-20 mm cum Coarse aggregate 20-10 mm cum Coarse aggregate 10 mm below cum Plums of size 150 to 80 mm cum Fine aggregate ( screened ) cum Super Plasticizer kg Use rate of shuttering for 40 uses sqm Scaffolding of shuttering @ 4284 63.00 8.03 4.82 3.21 5.25 7.14 17.14 21.00 15%

UNIT: 21 cum Rate Amount in Rs. in Rs

3 4 5 6 7

B. MACHINERY:

14

IRR-DAW

Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 1.00 1.00 8.00 8.00

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Needle vibrator 60 mm dia ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 8.00 1.00 8.00 1.00 1.00 2.00 9.00 4.00 1.00 4.00 17.00 3.00 1.00 21.00

Rate in Rs.

Amount in Rs

7 8

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Needle vibrator Hour Mason Class-I Day work inspector Day mazdoor for batching cement ( cement handling Day for batching other materials Day for loading mortar pans Day for loading plums Day for laying concrete and plums Day for conveying concrete Day for conveying plums Day for cleaning / washing / curing Day Labour for shuttering sqm Labour for scaffolding @ 15% Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

0%

Rate per/ CU.MTS=(A+B+C+D) /21 IRR-DAW-2-7 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for plain concrete works with initial lead upto 1 km and all lifts. ( Cement content 190 kg / cum with use of super plasticiser, CA : 0.90 cum, Blending Ratio of CA : 65:35, FA : 0.40 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg 3610.00 Cement for incidentals @ 3 kg/ cum kg 57.00 Coarse aggregate 40-20 mm cum 7.20 Coarse aggregate 20-10 mm cum 4.32 Coarse aggregate 10 mm below cum 2.88 Fine aggregate ( screened ) cum 7.63 Super plasticizer kg 14.44 Use rate of shuttering sqm 19.00 Use rate of scaffolding @ 15% Add seigniorage charges on CA @ (Included in material rates) Add seigniorage charges on FA @ (Included in material rates) Total cost of Materials

UNIT: 19.00 cum Rate Amount in Rs. in Rs

3 4 5 6

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 1.00 1.00 8.00 8.00

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Needle vibrator 40 mm dia ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5

Description Crew for Concrete mixer Hour Crew for Pump Hour Crew for Needle vibrator Hour Mason Class-I Day mazdoor for batching cement ( cement handling Day for batching other materials Day for loading mortar pans Day for laying Day

Unit

Quantity 8.00 1.00 8.00 1.00 2.00 9.00 4.00 3.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

15

IRR-DAW

6 7

for conveying concrete Day for cleaning / washing / curing Day Labour cost of shuttering sqm Labour cost of scaffolding @ 15% Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

19.00 1.00 19.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00

0%

Rs.

Rate per/ CU.MTS=(A+B+C+D) /19 IRR-DAW-2-8 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for plain concrete works with initial lead upto 1 km and all lifts. ( Cement content : 240 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending Ratio of CA -- 65:35, FA : 0.44 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement for mix kg 3600 Cement for incidentals @ 3 kg/ cum kg 45.00 Coarse aggregate 20-10 mm cum 7.8 Coarse aggregate 10 mm below cum 4.2 Fine aggregate ( screened ) cum 6.6 Super plasticiser kg 14.40 Use rate of shuttering sqm 15.00 Use rate of scaffolding @ 15% Add seigniorage charges on CA @ (Included in material rates) Add seigniorage charges on FA @ (Included in material rates) Total cost of Materials

Rs:

UNIT: 15.00 cum Rate Amount in Rs. in Rs

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 1.00 1.00 8.00 8.00

Rate in Rs.

Amount in Rs

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Needle vibrator 40 mm dia ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 8.00 1.00 8.00 1.00 2.00 9.00 4.00 3.00 15.00 1.00 15.00

Rate in Rs.

Amount in Rs

6 7

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Needle vibrator Hour Mason Class-I Day mazdoor for batching cement ( cement handling Day for batching other materials Day for loading mortar pans Day for laying Day for conveying concrete Day for cleaning / washing / curing Day Labour cost of shuttering sqm Labour cost of scaffolding @ 15% Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

0%

Rs.

Rate per/ CU.MTS=(A+B+C+D) /15 IRR-DAW-2-9 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC works of spillway bridge, blockouts and such other similar structures with conjested reinforcement with initial lead upto 1 km and all lifts. ( Cement content : 300 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending Ratio of CA -- 65:35, FA : 0.44 cum)

Rs:

16

IRR-DAW

DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Particulars Unit Quantity

Cement for mix kg 4200 Cement for incidentals @ 3 kg/ cum kg 42.00 Coarse aggregate 20-10 mm cum 7.28 Coarse aggregate 10 mm below cum 3.92 Fine aggregate ( screened ) cum 6.16 Super plasticiser ltr 16.80 Use rate of shuttering sqm 35.00 Scaffolding of shuttering @ On 5 100% Add seigniorage charges on CA @ (Included in material rates) Add seigniorage charges on FA @ (Included in material rates) Total cost of Materials

UNIT: 14.00 cum Rate Amount in Rs. 0.00

Rs: Rs: Rs:

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 1.00 1.00 8.00 8.00

Concrete mixer 300 / 200 ltr ( ele Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Needle vibrator 40 mm dia ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 8.00 1.00 8.00 1.00 2.00 9.00 4.00 3.00 14.00 1.00 35.00

6 7

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Needle vibrator Hour Mason Class-I Day mazdoor for batching cement ( cement handling ) Day for batching other materials Day for loading mortar pans Day for laying Day for conveying concrete Day for cleaning/ washing/ curing Day Labour cost of shuttering sqm Labour cost of scaffolding @ 100% Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Amount in Rs 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00

0%

Rs.

Rate per/ CU.MTS=(A+B+C+D) /14 IRR-DAW-2-10 Providing and forming porous concrete body drain of size 68.5 x 68.5 cm with 23 cm diameter central hole using cement and 20 mm down approved, clean, hard, graded coarse aggregates in 1 : 3.50 proportion by volume including cost of all materials, machinery, labour, formwork, curing etc., complete with initial lead upto 1 km and all lifts. (M15 Cement content : 408kg/cum, CA : 1cum, Blending Ratio of CA -- 65:35) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 Cement kg 3492.48 Coarse aggregate 20-10 mm cum 5.564 Coarse aggregate 10-4.75 mm cum 2.996 Use rate of shuttering sqm 76.00 Add seigniorage charges on CA @ (Included in material rates) Add seigniorage charges on FA @ (Included in material rates) Total cost of Materials

Rs:

UNIT: 20.00 Rate in Rs. 0.00 0.00 0.00 0.00 Rs: Rs: Rs:

Rm Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1 2

Description

Unit

Quantity 8.00 8.00 0.50 0.50

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3

Description Crew for Concrete mixer Crew for Pump Mason Class-I Hour Hour Day

Unit

Quantity 8.00 0.50 1.00

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00

17

IRR-DAW

mazdoor for batching cement ( cement handling Day for batching other materials Day for loading mortar pans Day for laying & packing concrete Day for conveying concrete Day Fitter shuttering Day Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

2.00 6.00 2.00 2.00 9.00 3.00

0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00

Rs: 0.00 Rs: 0.00 Rs: 0.00 0% Rs.

Rate per/ Running Metre=(A+B+C+D) /20 IRR-DAW-2-11 Providing and laying insitu vibrated M-20 ( 28 days cube compressive (a) strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC solid parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m pillars spaced approximately at 3.35 m c / c, 12.5 cm thick wall 80 cm height with 12.5 cm thick and 35 cm wide coping slab for wall and 12 .5 cm thick 40 cm x 40 cm coping for pillars with top edges of kerb and coping chamferred / rounded as directed etc., complete ( excluding cost of providing and placing reinforcement steel and gate ) with initial lead upto 1 km and all lifts. ( Cement content 300 kg / cum with use of super plasticiser( 0.4% by wt. of cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 7 Cement mix Cenent for incidentals @ 5 kg / cum Coarse aggregate 20-10 mm Coarse aggregate 10-4.75 mm Fine aggregate ( screened ) Super plasticiser Use rate of shuttering Scaffolding of shuttering @ Sundries kg kg cum cum cum kg sqm 15% LS 2.00 2601 180.00 4.5 2.42 3.81 10.40 95.00

Rs:

UNIT: 36.00 Rm Rate Amount in Rs. in Rs

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 8.00 8.00 0.50 0.50

Rate in Rs.

Amount in Rs

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour Needle vibrator 40 mm ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 8.00 0.50 8.00 2.00 1.00 2.00 9.00 4.00 2.00 9.00 2.00 95.00 Rs: Rs: Rs: Rs: 0% Rs.

7 8

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Vibrator Hour Mason Class-I Day work inspector Day mazdoor for batching cement ( cement handling ) Day for batching other materials Day for loading mortar pans Day for laying & packing concrete Day for conveying concrete Day for curing & miscellaneous Day Labour for shuttering sqm Labour for scaffolding @ 15% Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

Rate per/ Running Metre=(A+B+C+D) /36 IRR-DAW-2-12 Providing and laying insitu vibrated M-20 ( 28 days cube compressive (b) strength not less than 20 N / sq mm ) grade cement concrete using 20 mm

Rs:

18

IRR-DAW

down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC ornamental parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m pillars spaced approximately at 3.5 m apart, 20 cm x 15 cm posts 80 cm height approximately 30 cm c / c with 12.5 cm thick and 35 cm wide coping slab for posts and pillars with top edges of kerb and coping chamferred or rounded as directed etc., complete ( excluding cost of providing and placing reinforcement steel and gate ) with initial lead upto 1 km and all lifts. ( Cement content : 300 kg / cum with use of super plasticiser(0.4% by wt. of cement, CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 7 Cement mix Cenent for incidentals @ 5 kg / cum Coarse aggregate 20-10 mm Coarse aggregate 10-4.75 mm Fine aggregate ( screened ) Super plasticiser Use rate of shuttering Scaffolding of shuttering @ Sundries kg kg cum cum cum kg sqm 15% LS 2.00 2100 35.00 3.64 1.96 3.08 8.40 115.00

UNIT: 36.00 Rm Rate Amount in Rs. in Rs

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 8.00 8.00 0.50 0.50

Concrete mixer 300 / 200 ltr ( ele Hour Fuel / Energy charges Hour Needle vibrator 40 mm ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 8.00 0.50 8.00 2.00 1.00 2.00 9.00 4.00 2.00 7.00 2.00 115.00

7 8

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Vibrator Hour Mason Class-I Day work inspector Day mazdoor for batching cement ( cement handling ) Day for batching other materials Day for loading mortar pans Day for laying & packing concrete Day for conveying concrete Day for curing & miscellaneous Day Labour for shuttering sqm Labour for scaffolding @ 15% Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs:

Amount in Rs

0%

Rs.

Rate per/ Running Meter =(A+B+C+D) /36 IRR-DAW-2-13 Providing and laying insitu M- 25 ( 28 days cube compressive strength not less than 25 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for wearing coat including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting, finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 1 km and all lifts. ( Cement content : 300 kg / cum with use of super plasticiser(0.4% by wt. of cement, CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 Cement for mix kg Cement for incidentals @ 5 kg / cumkg Coarse aggregate 20-10 mm cum Coarse aggregate 10 mm below cum Fine aggregate ( screened ) cum Super Plasticizer kg Use rate of shuttering sqm 4200 70.00 7.28 3.92 6.3 16.80 7.00

Rs:

UNIT: 14.00 cum Rate Amount in Rs. in Rs 0.00

19

IRR-DAW

Sundries ( asphalt mortar etc ) LS 5.00 Add seigniorage charges on CA @ (Included in material rates) Add seigniorage charges on FA @ (Included in material rates) Total cost of Materials

20

IRR-DAW

B. MACHINERY: Sl No 1 2

Description

Unit

Quantity 8.00 8.00 0.50 0.50

Rate in Rs.

Amount in Rs

Concrete mixer 300/200 ltr ( diesel ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rs:

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 8.00 0.50 3.00 1.00 2.00 9.00 4.00 5.00 14.00 1.00 7.00

Rate in Rs.

Amount in Rs

Crew for Concrete mixer Hour Crew for Pump Hour Mason Class-I Day work inspector Day mazdoor for batching cement ( cement handling ) Day for batching materials Day for loading mortar pans Day for laying & compacting Day for conveying concrete Day for cleaning/ washing/ curing Day Labour cost for shuttering sqm Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

Rs: Rs: Rs: 0% Rs. Rs:

Rate per/ Cubic .MetreTS=(A+B+C+D) /14 IRR-DAW-2-14 Pre-cooling to control placement temperature of cement concrete in the range of 18 to 21 C at the concrete placement point by inundation of coarse aggregates and adding flaked ice as part of mixing water including cost of all materials, machinery, labour etc., complete with all leads and lifts. DATA: Consider M-15 grade concrete using 80 mm down CA and 30-50 mm slump. DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT: 500 Rate in Rs. 0.00 0.00 Rs:

Particulars LS

Unit

Quantity 3.00 0.00

Sundries ( amonia gas etc)

Total cost of Materials B. MACHINERY: Sl No 1

cum Amount in Rs 0.00 0.00 0.00

Description

Unit

Quantity 24.00

Ice maker unit consisting of: Hour Compressor 125 hp - 1 No Condenser with 30 hp motor - 1 No. Ice makers 10 t / day each - 3 Nos. Pump 2 hp for ice cutting - 3 Nos. Pump 2 hp for pumping water-3 Nos. Screw conveyor with 15 hp motor -1 Ice elevator with 5 hp motor - 1 No. Fuel / Energy charges for system Hour Total hire charges of Machinery

Rate Amount in Rs. in Rs 0.00 0.00

24.00

0.00 0.00 Rs: 0.00

C. LABOUR: Sl No 1 2

Description

Unit

Quantity 24.00 6.00 3.00

Crew for Ice maker unit Hour mazdoor for Ice chamber ( 2 x 3 ) Day for miscellaneous works ( 1 x 3 ) Day Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for contractor's profit and overheads on A+B+C Rate per/ Cu.mt.=(A+B+C+D) /500

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00

0%

Rs. Rs:

21

IRR-DAW

IRR-DAW-2-15 Conveying and fixing elastomeric bearing for spillway bridge including cleaning and preparing surface, mixing and applying adhesive, fixing bearing in correct position etc., including cost of all materials except bearings, machinery, labour etc., complete with all leads and lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 UNIT: 6.00 Rate in Rs. 0.00 0.00 Rs: Nos. Amount in Rs 0.00 0.00 0.00

Particulars

Unit

Quantity 0.60 2.00

Synthetic adhesive ( Resin + Hardener ) kg Sundries LS Total cost of Materials

B. MACHINERY: Sl No 1 Nil

Description

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00

Description Marker / Erector work inspector mazdoor

Unit Day Day Day Total cost of Labour

Quantity 1.00 1.00 2.00

Rate in Rs. 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ Each=(A+B+C+D) /6 0%

Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs. Rs:

IRR-DAW-2-16 Providing and constructing 150 mm dia hume pipe weep holes for concrete / masonry walls including providing 20 x 20 x 20 cm size porous concrete block made of cement and 20 mm down coarse aggregate in 1 : 4 proportion including 10 cm thick sand backing at the junction of wall and soil back fill, cost of all materials, machinery, labour etc., complete with lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 150 mm dia hume pipe Rm Cement kg 20 - 10 mm coarse aggregate cum Sand ( unscreened ) cum Add seigniorage charges on CA @ (Included in material rates) Add seigniorage charges on FA @ (Included in material rates) Total cost of Materials 2.90 3.00 0.01 0.02

3.00 Rm Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: Rs: Rs:

B. MACHINERY: Sl No 1 Nil

Description

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs

Description Mason Class-II mazdoor

Unit Day Day Total cost of Labour

Quantity 0.25 0.25

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C 0%

Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs. Rs:

Rate per/ Running Meter.=(A+B+C+D) /3

22

IRR-DAW

IRR-DAW-2-17 Providing and forming expansion joint for spillway bridge consisting of 75 x 75 x 6 mm angles 2 numbers provided with 25 cm long 12 mm dia. anchors fixed to both flanges at 15 cm c /c and 140 x 6 mm plate welded on top of one of the angle including cost of all materials, machinery, labour, providing and fixing 38 mm thick joint filler board matching the thickness of wearing coat, painting etc., complete with lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Structural steel plate kg Structural steel angle kg 12 dia steel anchors kg Welding electrodes Nos Joint filler board 19 mm thick sqm Sundries ( cutting gas / paint etc ) LS Total cost of Materials 50.70 104.50 27.40 70.00 1.00 1.50

UNIT: 7.50 Rm Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

B. MACHINERY: Sl No 1 2

Description

Unit

Quantity 8.00 8.00 2.00

Welding set Hour Fuel / Energy charges Hour Sundries (cutting torch/ welding gunsLS etc) Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 Rs:

Amount in Rs

C. LABOUR: Sl No 1 2 3

Description Marker / Fabricator / Erector Gas cutter / Welder mazdoor ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour C. Cost of Labour

Unit

Quantity 1.50 1.50 2.00

Day Day Day Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 Rs:

Amount in Rs

Rs: Rs: Rs: Rs: 0.00 0% Rs. Rs:

D. Add for contractor's profit and overheads on A+B+C

Rate per/ Running Meter.=(A+B+C+D) /7.5

IRR-DAW-3 IRR-DAW-3-1

MASONRY & GUNITING WORKS : Providing and constructing un-coursed rubble stone masonry using approved stones in cement mortar 1 : 3 proportion including cost of all materials, machinery, labour, scaffolding, cleaning, packing mortar, wedging stone chips, curing etc., complete with initial lead upto 1 km and all lifts. ( Cement content : 190 kg/cum of masonry, rubble stones : 0.85 cum, stone chips : 0.15 cum/cum, FA : 0.4 cum) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 Cement for mortar kg 4750 Rubble stones cum 21.25 Stone chips cum 3.75 Sand ( screened ) cum 10 Add seigniorage charges for sand (included in material cost) Add seigniorage charges for Stone (included in material cost) Total cost of Materials

UNIT: 25.00 Rate in Rs.

cum Amount in Rs

Rs: Rs: Rs:

B. MACHINERY: Sl No 1 2

Description

Unit

Quantity 8.00 8.00 1.00 1.00

Rate in Rs.

Amount in Rs

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rs: 0.00

C. LABOUR: Sl No 1 2 3 4

Description Crew for Concrete mixer Crew for Pump work inspector Mason Class-I Hour Hour Day Day

Unit

Quantity 8.00 1.00 1.00 2.50

Rate in Rs.

Amount in Rs

23

IRR-DAW

5 6 7

Mason Class-II Day Chavali Day mazdoor for batching cement ( cement handling ) Day for batching sand Day for loading mortar pans Day for laying & packing mortar Day for loading chips Day for washing rubble / finishing / curing Day for conveying mortar / chips Day Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C

4.00 16.00 2.00 6.00 4.00 10.00 1.00 4.00 12.00 Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00 0% Rs.

Rate per/ cu.metre.=(A+B+C+D) /25

Rs:

IRR-DAW-3-2

Providing and constructing un-coursed rubble stone masonry using approved stones in cement mortar 1 : 4 proportion including cost of all materials, machinery, labour, scaffolding, cleaning, packing mortar, wedging stone chips, curing etc., complete with initial lead upto 1 km and all lifts. ( Cement content : 143 kg/cum of masonry, rubble stones : 0.85 cum, stone chips : 0.15 cum/cum, FA : 0.4 cum) For 1 cum masonry :DATA & RATE ANALYSIS A. MATERIALS: 25.00 Sl No Particulars Unit Quantity Rate in Rs. 1 Cement for mortar kg 3575 0.00 2 Rubble stones cum 21.25 0.00 3 Stone chips cum 3.75 0.00 4 Sand ( screened ) cum 10 0.00 Add seigniorage charges for sand (included in material cost) Rs: Add seigniorage charges for Stone (included in material cost) Rs: Total cost of Materials Rs: B. MACHINERY: Sl No 1 2

cum Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit

Quantity 8.00 8.00 1.00 1.00

Concrete mixer 300 / 200 ltr Hour Fuel / Energy charges Hour 10 hp pump Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description

Unit

Quantity 8.00 1.00 1.00 2.50 4.00 16.00 2.00 6.00 4.00 10.00 1.00 4.00 12.00 0.00 0 0.00 0.00

Crew for Concrete mixer Hour Crew for Pump Hour work inspector Day Mason Class-I Day Mason Class-II Day Chavali Day mazdoor for batching cement ( cement handling ) Day for batching sand Day for loading mortar pans Day for laying & packing mortar Day for loading chips Day for washing rubble / finishing / curing Day for conveying mortar / chips Day Total cost of Labour labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Rs: 0.00 Rs: 0.00 Rs: 0.00 0% Rs. Rs:

Rate per/ cu.metre.=(A+B+C+D) /25

24

IRR-DAW

IRR-DAW-3-3

Providing and constructing coursed rubble face stone masonry using approved rubble stones in cement mortar 1 : 3 proportion including cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone chips, curing etc., with initial lead upto 1 km and all lifts. ( Cement content : 178 kg/cum of masonry, rubble stones : 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.375 cum, CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement for mortar kg Coursed rubble stone 30 x 30 x 45 cmos N Coursed rubble stone 30 x 30 x 60 cmos N Rubble stones cum Stone chips cum Sand ( screened ) cum Add seigniorage charges for sand (included in material cost) Add seigniorage charges for Stone (included in material cost) Total cost of Materials 4450 244 82 8.75 3.75 9.375

UNIT: 25.00 Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs:

cum Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1 2

Description

Unit

Quantity 8.00 8.00 1.00 1.00

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery Description Unit

Rate in Rs. 0.00 0.00 0.00 0.00 Rs: Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Quantity 8.00 1.00 1.00 7.00 2.50 4.00 16.00 2.00 6.00 4.00 10.00 1.00 4.00 12.00

Crew for Concrete mixer Hour Crew for Pump Hour work inspector Day Stone chiseller Cl -II Day Mason Class-I Day Mason Class-II Day Chavali Day mazdoor for batching cement ( cement handling ) Day for batching sand Day for loading mortar pans Day for laying & packing mortar Day for loading chips Day for washing rubble / finishing / curing Day for conveying mortar / chips Day Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C

Rs: 0.00 Rs: 0.00 Rs: 0.00 0% Rs.

Rate per/ cu.metre.=(A+B+C+D) /25

Rs:

25

IRR-DAW

IRR-DAW-3-4

DATA:

Providing and constructing coursed rubble face stone masonry using approved rubble stones in cement mortar 1 : 4 proportion including cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone chips, curing etc., with initial lead upto 1 km and all lifts. ( Cement content : 134 kg/cum of masonry, rubble stones : 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.375 cum, CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No) Thickness of CR face stone masonry assumed For 1 cum masonry CR stones 30 x 30 x 45 cm. CR stones 30 x 30 x 60 cm. Rubble stones : Sand Cement Average output of 300 / 200 ltr mixer Daily output of masonry for 10 cum mortar with 37.50 % mortar content However, as face stone masonry is comparatively slower 25 cum / day considered. Labour requirement: Stone Chiseller Cl II : Other category same as in item 32 DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6

: : : : : :

75.00 9.75 3.25 0.35 0.38 134.00 10.00 26.65

cm Nos. Nos. cum cum. kg cum / day cum

7.00 Nos.

Particulars

Unit

Quantity

Cement for mortar kg 3350 Coursed rubble stone 30 x 30 x 45 cmos N 244 Coursed rubble stone 30 x 30 x 60 cmos N 82 Rubble stones cum 8.75 Stone chips cum 3.75 Sand ( screened ) cum 9.5 Add seigniorage charges for sand (included in material cost) Add seigniorage charges for Stone (included in material cost) Total cost of Materials

UNIT: 25.00 Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs:

cum Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1 2

Description

Unit

Quantity 8.00 8.00 1.00 1.00

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 8.00 1.00 1.00 7.00 2.50 4.00 16.00 2.00 6.00 4.00 10.00 1.00 4.00 12.00

Crew for Concrete mixer Hour Crew for Pump Hour work inspector Day Stone chiseller Cl -II Day Mason Class-I Day Mason Class-II Day Chavali Day mazdoor for batching cement ( cement handling ) Day for batching sand Day for loading mortar pans Day for laying & packing mortar Day for loading chips Day for washing rubble / finishing / curing Day for conveying mortar / chips Day Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Rs: 0.00 Rs: 0.00 Rs: 0.00

Rate per/ cu.metre.=(A+B+C+D) /25

IRR-DAW-3-5

Providing and constructing chisel drafted and hammer dressed face stone masonry with approved stones in cement mortar 1 : 3 proportion including cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km and all lifts. ( Cement content : 167 kg/cum of masonry, rubble stones : 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45 cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No) DATA & RATE ANALYSIS UNIT: A. MATERIALS: 25.00 cum Sl No Particulars Unit Quantity Rate Amount in Rs. in Rs 1 Cement for mortar kg 4175 0.00 0.00

26

IRR-DAW

2 3 4 5 6

Coursed rubble stone 30 x 30 x 45 cmos N 250 Coursed rubble stone 30 x 30 x 60 cmos N 85 Rubble stones cum 8.75 Stone chips cum 3.75 Sand ( screened ) cum 8.75 Add seigniorage charges for sand (included in material cost) Add seigniorage charges for Stone (included in material cost) Total cost of Materials

0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1 2

Description

Unit

Quantity 8.00 8.00 1.00 1.00

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description

Unit

Quantity 8.00 1.00 1.00 14.00 7.00 2.50 4.00 16.00 2.00 6.00 4.00 10.00 1.00 4.00 12.00

Crew for Concrete mixer Hour Crew for Pump Hour work inspector Day Stone chiseller Cl -I Day Stone chiseller Cl -II Day Mason Class-I Day Mason Class-II Day Chavali Day mazdoor for batching cement ( cement handling ) Day for batching sand Day for loading mortar pans Day for laying & packing mortar Day for loading chips Day for washing rubble / finishing / curing Day for conveying mortar / chips Day Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Rs: 0.00 Rs: 0.00 Rs: 0.00

Rate per/ cu.metre.=(A+B+C+D) /25 IRR-DAW-3-6 Providing and constructing chisel drafted and hammer dressed face stone masonry with approved stones in cement mortar 1 : 4 proportion including cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km and all lifts. ( Cement content : 125 kg/cum of masonry, rubble stones : 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45 cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No) DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 UNIT: 25.00 Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: cum Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Particulars

Unit

Quantity 3125 250 85 8.75 3.75 8.75

Cement for mortar kg Coursed rubble stone 30 x 30 x 45 cmos N Coursed rubble stone 30 x 30 x 60 cmos N Rubble stones cum Stone chips cum Sand ( screened ) cum Add seigniorage charges for sand (included in material cost) Add seigniorage charges for Stone (included in material cost) Total cost of Materials

B. MACHINERY: Sl No 1 2

Description

Unit

Quantity 8.00 8.00 1.00 1.00

Concrete mixer 300 / 200 ltr ( ele ) Hour Fuel / Energy charges Hour 10 hp pump ( ele ) Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5

Description Crew for Concrete mixer Crew for Pump work inspector Stone chiseller Cl -I Stone chiseller Cl -II Hour Hour Day Day Day

Unit

Quantity 8.00 1.00 1.00 14.00 7.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00

Amount in Rs 0.00 0.00 0.00 0.00 0.00

27

IRR-DAW

6 7 8 9

Mason Class-I Day Mason Class-II Day Chavali Day mazdoor for batching cement ( cement handling Day for batching sand Day for loading mortar pans Day for laying & packing mortar Day for loading chips Day for washing rubble / finishing / curing Day for conveying mortar / chips Day Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour

2.50 4.00 16.00 2.00 6.00 4.00 10.00 1.00 4.00 12.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Rs: 0.00 Rs: 0.00 Rs: 0.00

D. Add for contractor's profit and overheads on A+B+C Rate per/ cu.metre.=(A+B+C+D) /25

IRR-DAW-3-7

DATA:

Providing cement mortar pointing to coursed rubble face stone masonry 50 mm deep in CM 1 : 2 proportion by volume including raking and cleaning joints, pressing mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with initial lead upto 1 km and all lifts. Consider 100 sqm area for analysis. Considering 15 to 20 mm wide and 50 mm deep joints the quantity of cement mortar required will be about 0.70 cum for 100 sqm of pointing. Quantity of mortar with 5 to 10 % wastage : 0.75 cum For 0.75 cum mortar : Cement : 455.446 kg Sand : 0.735 cum DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 UNIT: 100.00 Rate in Rs. 0.00 0.00 Rs: Rs: sqm Amount in Rs 0.00 0.00 0.00 0.00

Particulars

Unit

Quantity

Cement kg 455.446 Sand ( screened ) cum 0.735 Add seigniorage charges for sand (included in material cost) Total cost of Materials

B. MACHINERY: Sl No

Description

Unit

Quantity 0.00 0.00

1 NIL (Manual mixing ) Total hire charges of Machinery C. LABOUR: Sl No 1 2 Mason Cl- I mazdoor Description Unit Day Day Total cost of Labour

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00 Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00

Quantity 10.00 10.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ Sq metre.=(A+B+C+D) /100 IRR-DAW-3-8 Providing cement mortar pointing to coursed rubble face stone masonry 50 mm deep in CM 1 : 3 proportion by volume including raking and cleaning joints, pressing mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with initial lead upto 1 km and all lifts. Consider 100 sqm area for analysis. Considering 15 to 20 mm wide and 50 mm deep joints the quantity of cement mortar required will be about 0.70 cum for 100 sqm of pointing. Quantity of mortar with 5 to 10 % wastage : 0.75 cum Cement : 321.8 kg Sand : 0.735 cum DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2

DATA:

Particulars

Unit

Quantity

Cement kg 321.80 Sand ( screened ) cum 0.74 Add seigniorage charges for sand (included in material cost) Total cost of Materials

UNIT: 100.00 Rate in Rs. 0.00 0.00 Rs: Rs:

sqm Amount in Rs 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit

Quantity 0.00 0.00

NIL Manual mixing )

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00

28

IRR-DAW

Total hire charges of Machinery C. LABOUR: Sl No 1 2 Mason Cl- I mazdoor

Rs: 0.00

Description

Unit Day Day Total cost of Labour

Quantity 10.00 10.00

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ Sq..metre.=(A+B+C+D) /100

29

IRR-DAW

IRR-DAW-4 IRR-DAW-4-1

CONTRACTION JOINT WORKS: Providing 25 mm thick guniting to rock or masonry surface in cement mortar 1 : 3 proportion by weight including cost of all materials, machinery, labour, raking-out and cleaning joints, scaffolding wherever required and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement kg 609.90 Sand ( screened ) cum 1.09 Use rate of grout hose 25 m Hour 8.00 Use rate of water hose 25 m Hour 8.00 Use rate of guniting nozzle Hour 8.00 Sundries LS 2.00 Add seigniorage charges for sand (included in material cost) Total cost of Materials

UNIT : 36.00 sqm Rate Amount in Rs. in Rs

B. MACHINERY: Sl No 1 2 3 4

Description

Unit

Quantity 8.00 8.00 8.00 8.00 1.00 1.00 2.00

Rate in Rs.

Amount in Rs

Guniting equipment Hour Fuel / Energy charges Hour Air compressor 8.5 cmm ( ele ) Hour Fuel / Energy charges Hour Pump 10 hp ( ele ) Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 8.00 8.00 1.00 1.00 2.00 2.00 2.00

Rate in Rs.

Amount in Rs

Crew for Guniting equipment Hour Crew for Air compressor Hour Crew for pump Hour Mason Cl II Day mazdoor for cement handling Day for sand Day mazdoor for other works Day Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour Add for scaffolding D. Add for contractor's profit and overheads on A+B+C 0%

Total Total

Rs: Rs: Rs: Rs: Rs:

Rate per/ Sq..metre.=(A+B+C+D) /36 IRR-DAW-4-2 Providing and constructing contraction joints by fixing 16 SWG 60 cm wide annealed copper sheets in two lines with 8 mm dia steel dowel rods on either side at one metre interval, forming 125 x 125 mm size groove in between copper strips for filling asphalt including fixing 15 mm dia two legged G.I pipe with U - bend at bottom for circulation of steam at intervals and forming 150 mm dia formed drain behind water seals including cost of all materials, machinery, labour, filling asphalt, circulation of steam through pipes etc., complete with all leads and lifts. consider 12 m height of contraction joint for analysis. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Copper sheet 16 SWG kg Reinforcement steel 8 mm dia kg GI pipe 15 mm dia Rm Asphalt kg Elbows / Nipple / Plugs etc., LS Soldering materials LS Total cost of Materials 215.00 30.00 24.00 192.00 5.00 40.00

UNIT: 12.00 Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Rm Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No

Description

Unit

Quantity 8.00 10.00

1 Steam circulation arrangement LS Fuel charges ( gas for heating ) LS Total hire charges of Machinery C. LABOUR: Sl No 1 Welder

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00

Description Day

Unit

Quantity 1.00

Rate Amount in Rs. in Rs 0.00 0.00

30

IRR-DAW

2 3 4 5 6

Tinsmith Bar bender Pipe fitter Mason Class-I mazdoor

Day Day Day Day Day Total cost of Labour

1.00 0.50 0.50 0.50 1.00

0 0 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/Running metre.=(A+B+C+D) /12

Rs: 0.00 Rs: 0.00 Rs: 0.00 0.00 0 0.00

IRR-DAW-4-3

Providing and constructing contraction joints by fixing 310 mm wide central bulb type approved quality PVC water stop in two lines with 8 mm diameter steel dowel rods on either side at 1m interval, forming 125 x 125 mm size groove in between two water stops, providing & fixing 15 mm dia two legged G.I pipe with U-bend at bottom for circulation steam at interval, forming 150 mm diameter formed drain behind water seals including filling groove with asphalt, circulation of steam at intervals, cost of all materials, machinery, labour etc., complete with all leads andlifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Particulars Unit Quantity 24.50 30.00 24.00 192.00 5.00 25.00 UNIT: 12.00 Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

PVC water stops 310 mm wide Rm Reinforcement steel 8 mm dia kg GI pipe 15 mm dia Rm Asphalt kg Elbows / Nipple / Plugs etc., LS Vulcanizing materials LS Total cost of Materials

Rm. Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit

Quantity 8.00 10.00

Steam circulation arrangement LS Fuel charges ( gas for heating ) LS Total hire charges of Machinery

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00

C. LABOUR: Sl No 1 2 3 4 5

Description Welder Bar bender Pipe fitter Mason Class-I mazdoor

Unit Day Day Day Day Day Total cost of Labour

Quantity 0.50 0.50 0.50 0.50 1.00

Rate in Rs. 0.00 0 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ Running .metre.=(A+B+C+D) /12

Rs: 0.00 Rs: 0.00 Rs: 0.00 0.00 0 0.00

IRR-DAW-4-4

Providing and constructing contraction joints by fixing 16 SWG 60 cm wide annealed copper sheets in single line with 8 mm dia steel dowel rods on either side at 1 metre interval including cost of all materials, machinery, labour etc., complete with all leads and lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 Copper sheet 16 SWG kg Reinforcement steel 8 mm dia kg Soldering materials LS Total cost of Materials 77.00 15.00 10.00

UNIT: 8.7 Rate in Rs. 0.00 0.00 0.00 Rs:

Rm Amount in Rs 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit

Quantity 3.00 5.00

Sundries such as soldering gun etc., LS Fuel charges ( gas ) LS Total hire charges of Machinery

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00

C. LABOUR: Sl No

Description

Unit

Quantity

Rate in Rs.

Amount in Rs

31

IRR-DAW

1 2 3 4 5

Welder Tinsmith Bar bender Mason Class-I mazdoor

Day Day Day Day Day Total cost of Labour

0.5 0.5 0.5 0.5 0.5

0.00 0 0 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/Running metre.=(A+B+C+D) /8.7

Rs: 0.00 Rs: 0.00 Rs: 0.00 0.00 0 0.00

IRR-DAW-4-5

DATA:

Providing and constructing contraction joints by fixing 23 cm wide central bulb type PVC water stop in single line supported by 10 mm dia steel dowel rods on either side at 1 metre interval including cost of all materials, machinery, labour, valcunising joints etc., complete with all leads and lifts. Consider 1.5 x 2.1 m size gallery contraction joint for analysis. Length of contraction joint at water seal location 8.70 m. Materials required: PVC water seal 23 cm wide 9.00 m. 10 mm torsteel rods 10.00 kg DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 UNIT: 8.70 Rate in Rs. 0.00 0.00 0.00 Rs: Rm Amount in Rs 0.00 0.00 0.00 0.00

Particulars

Unit

Quantity 9.00 10.00 2.00

PVC water seal 23 cm wide Rm Reinforcement steel 10 mm dia kg Vulcanising materials LS Total cost of Materials

B. MACHINERY: Sl No 1

Description

Unit

Quantity 0.50 0.50

Sundries such as heater etc., LS Fuel charges for heating LS Total hire charges of Machinery

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4

Description Welder Bar bender Mason Class-I mazdoor

Unit Day Day Day Day Total cost of Labour

Quantity 0.50 0.50 0.50 0.50

Rate in Rs. 0.00 0 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/metre=(A+B+C+D) /8.7 IRR-DAW-5 IRR-DAW-5-1 EARTH / ROCKFILL EMBANKMENT WORKS : Providing hearting embankment using selected impervious soil from approved borrow areas in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transportation, spreading soil in layer of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent or as stipulated using sheep / pad foot roller etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 NIL Add seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 Particulars Unit

Rs: 0.00 Rs: 0.00 Rs: 0.00 0% Rs. Rs:

Quantity 0.00 0.00

UNIT 825.00 Rate in Rs. 0.00 0.00 Rs: Rs:

cum Amount in Rs 0.00 0.00 0.00 0.00

Description Hour Hour Hour

Unit

Quantity 5.50 5.50 8.00

Angle dozer 90 hp Fuel / Energy charges Shovel 0.85 cum capacity

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00

32

IRR-DAW

3 4 5 6 7

Fuel / Energy charges Hour Tippers 5.00 cum capacity 5 Nos. Hour Fuel / Energy charges Hour Pump 5 hp ( ele ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Vibratory pad foot roller 8 tonne Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery

8.00 40.00 40.00 4.00 4.00 8.00 8.00 6.50 6.50 2.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor

Unit

Quantity 5.50 8.00 40.00 4.00 8.00 6.50 2.00 4.00 0.00 0 0.00 0.00

Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Add for contractor's profit and overheads on D. A+B+C 0%

Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00

Rate per/ cubic metre=(A+B+C+D) /825

IRR-DAW-5-2

Providing cut-off trench filling using selected impervious soil from approved borrow areas in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transportation, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent using sheep foot / pad foot roller as stipulated etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 NIL Add seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No Description 1 2 3 4 5 6 7 0.00 0.00

825.00 Rate in Rs. 0.00 0.00 Rs: Rs:

cum Amount in Rs 0.00 0.00 0.00 0.00

Unit

Quantity 5.50 5.50 8.00 8.00 48.00 48.00 4.00 4.00 8.00 8.00 6.50 6.50 2.00

Angle dozer 90 hp Hour Fuel / Energy charges Hour Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Tippers 5.00 cum capacity 6 Nos. Hour Fuel / Energy charges Hour Pump 5 hp ( ele ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Vibratory pad foot roller 8 tonne Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No Description 1 2 3 4 5 6 7 8 Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor

Unit Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour

Quantity 5.50 8.00 48.00 4.00 8.00 6.50 2.00 4.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery

33

IRR-DAW

C. Cost of Labour Add for contractor's profit and overheads on D. A+B+C Rate per/ cubic metre=(A+B+C+D) /825

Rs: 0%

0.00 Rs. Rs:

IRR-DAW-5-3

Providing casing embankment using semi-pervious soil from approved borrow areas in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all other operations such as excavation, sorting out, transportation, spreading soil in layers of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent using sheep foot / pad foot roller as stipulated etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 NIL Add seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 0.00 0.00

UNIT : 630 Rate in Rs. 0.00 0.00 Rs: Rs:

cum Amount in Rs 0.00 0.00 0.00 0.00

Description

Unit

Quantity 4.00 4.00 8.00 8.00 32.00 32.00 3.00 3.00 5.00 5.00 5.00 5.00 5.00

Angle dozer 90 hp Hour Fuel / Energy charges Hour Shovel 0.85 cum Hour Fuel / Energy charges Hour Tipper 5 cum Hour Fuel / Energy charges Hour Pump 5 hp ( ele ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Vibratory pad foot roller 8 tonne Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor

Unit

Quantity 4.00 8.00 32.00 3.00 5.00 5.00 2.00 4.00

Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour Total Add for contractor's profit and overheads on D. A+B+C Rate per/ cubic metre=(A+B+C+D) / 630 0%

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 Rs. Rs:

IRR-DAW-5-4

Providing casing embankment using semi-pervious soil available from excavation in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all other operations such as re-excavation, sorting out, transportation, spreading in layers of specified thickness, breaking clods, sectioning, watering, compacting to specified density control of not less than 95 percent using sheep foot / pad foot roller as stipulated etc.,complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 NIL Add seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 0.00 0.00

UNIT : 970.00 cum Rate Amount in Rs. in Rs

Description Hour Hour Hour

Unit

Quantity 4.60 4.60 8.00

Angle dozer 90 hp Fuel / Energy charges Shovel 0.85 cum

34

IRR-DAW

3 4 5 6 7

Fuel / Energy charges Tipper 5 cum Fuel / Energy charges Pump 5 hp ( ele ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

8.00 48.00 48.00 4.00 4.00 8.00 8.00 7.00 7.00 5.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor

Unit Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour

Quantity 4.60 8.00 48.00 4.00 8.00 7.00 2.00 4.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 970 0% Rs. Rs:

IRR-DAW-5-5

Providing homogeneous embankment using soil from approved borrow area in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transportation, spreading soil in layer of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent or as stipulated using sheep / pad foot roller etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit Quantity 1 NIL Add seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 0.00 0.00

UNIT : 807.00 Rate in Rs. 0.00 0.00 Rs: Rs:

cum Amount in Rs 0.00 0.00 0.00 0.00

Description

Unit

Quantity 5.40 5.40 8.00 8.00 40.00 40.00 4.00 4.00 8.00 8.00 6.40 6.40 2.00

Rate in Rs.

Amount in Rs

Angle dozer 90 hp Hour Fuel / Energy charges Hour Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Tippers 5.00 cum capacity 5 Nos. Hour Fuel / Energy charges Hour Pump 5 hp ( ele ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Vibratory pad foot roller 8 tonne Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor

Unit

Quantity 5.40 8.00 40.00 4.00 8.00 6.40 2.00 4.00

Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery

35

IRR-DAW

C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 807 0%

IRR-DAW-5-6

Providing embankment adjacent to masonry / concrete structures and filling trial pits using impervious soil from approved borrow areas in layers of 10 to 15 cm and compacting each layer to density control of not less than 95 percent using pneumatic tampers or by vibratory earth rammers including cost of all materials, machinery, labour, picking previous layer, spreading soil in layer, breaking clods, watering etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS UNIT : 81 cum A. MATERIALS: Sl No Particulars Unit Quantity Rate Amount in Rs. in Rs 1 Use rate of air hose Hour 16.00 0.00 Add seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No Description 1 2 3 4 5 6 7 8

Unit

Quantity 0.15 0.15 0.80 0.80 3.00 3.00 8.00 8.00 0.40 0.40 0.80 0.80 16.00 16.00 1.00

Angle dozer 90 hp Hour Fuel / Energy charges Hour Shovel 0.85 cum Hour Fuel / Energy charges Hour Tipper 5 cum Hour Fuel / Energy charges Hour Air compressor 8.5 cmm ( ele ) Hour Fuel / Energy charges Hour Pump 5 hp ( ele ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Pneumatic tampers 2 Nos. Hour Fuel / Energy charges Hour Sundries LS Total hire charges of Machinery

C. LABOUR: Sl No Description 1 2 3 4 5 6 7 8 9

Unit

Quantity 0.15 0.80 3.00 8.00 0.40 0.80 16.00 1.00 5.00

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Air compressor Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Pneumatic tamper Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) /81

Rs: Rs: Rs: 0%

0.00 0.00 0.00 Rs. Rs:

IRR-DAW-5-7

Providing and constructing rockfill embankment with 300 mm down graded stones and quarry spalls from approved source including cost of all materials, machinery, labour, spreading stones and spalls in layers, hand packing, wedging, finishing the surface to required slopes etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars 1 2 3 4 5 6 7 Unit Quantity 387.00 60.00 118.00 159.00 8.00 200.00 10.00 18.00 400 Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: cum Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Use rate of drill rod 2.5 m long Rm Reconditioning charges @ 10% Use rate of air hose 6 Nos. Hour Explosive small dia kg Electric detonators Nos Detonator ordinary Nos Fuse coil Rm Sundries ( waste tyres etc ) LS Add seigniorage charges on Stones per cum Total cost of Materials

36

IRR-DAW

B. MACHINERY: Sl No Description 1 2 3 4 5

Unit

Quantity 30.00 30.00 60.00 60.00 4.00 4.00 8.00 8.00 24.00 24.00

Air compressor 8.5 cmm ( diesel ) 3 Nos Hour Fuel / Energy charges Hour Jack hammer 6 Nos Hour Fuel / Energy charges Hour Angle dozer 90 hp Hour Fuel / Energy charges Hour Shovel 0.85 cum Hour Fuel / Energy charges Hour Tipper 5 cum Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No Description 1 2 3 4 5 6 7 8 9 10 Crew for Air compressor Crew for Jack hammer Crew for Shovel Crew for Tipper Crew for Dozer Blaster licensed Helper blaster work inspector Mason Class-II mazdoor

Unit Hour Hour Hour Hour Hour Day Day Day Day Day Total cost of Labour

Quantity 30.00 60.00 8.00 24.00 4.00 1.00 1.00 2.00 2.00 10.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs:

Amount in Rs

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour Total D. Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 400 0%

IRR-DAW-5-8

Providing and constructing dry rubble rock-toe using rubble and stone chips from approved source including cost of all materials, machinery, labour, hand packing rubble and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS UNIT : 100 cum A. MATERIALS: Sl No Particulars 1 2 3 4 5 6 7

Unit

Quantity 97.00 15.00 30.00 40.00 2.00 50.00 2.00 18.00

Use rate of drill rod 1.5 m long Rm Reconditionong charges @ 10% Use rate of air hose Hour Explosive small dia kg Electric detonator Nos Detonator ordinary Nos Fuse coil Rm Sundries LS Add seigniorage charges on Stones per cum Total cost of Materials

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No Description 1 2 3 4

Unit

Quantity 7.50 7.50 15.00 15.00 2.00 2.00 6.00 6.00

Air compressor 8.5 cmm ( diesel ) Hour Fuel / Energy charges Hour Jack hammer Hour Fuel / Energy charges Hour Shovel 0.85 cum Hour Fuel / Energy charges Hour Tipper 5 cum Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No Description 1 2 3 4 5 6 7 8 9 Crew for Air compressor Crew for Jack hammer Crew for Shovel Crew for Tipper Blaster licensed Helper blaster work inspector Mason Class-II mazdoor

Unit Hour Hour Hour Hour Day Day Day Day Day Total cost of Labour

Quantity 7.50 15.00 2.00 6.00 0.50 1.00 1.00 7.00 19.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

37

IRR-DAW

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 100 0%

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-DAW-5-9

Note:

Providing and constructing dry rubble rock-toe with rubble and stone chips from dump yard including cost of all materials, machinery, labour, hand packing rubble and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto 1 km and all lifts. Useful rubble and stone chips will be issued at dump yard at the issue rate for usefull rubble / stone chips. Sorting out and breaking charges included in rate analysis. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars 1 2 Unit UNIT : Quantity 100.00 15.00 100 cum Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: 0.00

Useful rubble ( at dump yard ) cum Useful stone chips ( at dump yard ) cum Add seigniorage charges on Stones Total cost of Materials

B. MACHINERY: Sl No Description 1 2 Shovel 0.85 cum Fuel / Energy charges Tipper 5 cum Fuel / Energy charges

Unit

Quantity 2.00 2.00 6.00 6.00

Hour Hour Hour Hour Total hire charges of Machinery

Rate in Rs. 0.00 0.00 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No Description 1 2 3 4 6 7 Crew for Shovel Crew for Tipper Mason Class-II work inspector Stone breaker mazdoor

Unit Hour Hour Day Day Day Day Total cost of Labour

Quantity 2.00 6.00 7.00 1.00 2.00 21.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 100 0%

IRR-DAW-5-10 Providing and laying 30 cm diameter open jointed hume pipes with collars in rock-toe for drainage including cost of all materials, machinery, labour etc., complete with lead upto 1 km and all lifts. DATA & RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars 1 Hume pipe 300 mm dia.with collar Rm Unit Quantity 100.00 0.00 100 Rm Rate in Rs. 0.00 0.00 Rs: Amount in Rs 0.00 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No Description 1 NIL Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 Mason Cl- II mazdoor

Unit

Quantity 0.00 0.00

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00

Unit Day Day Total cost of Labour

Quantity 2 6

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

38

IRR-DAW

D. Add for contractor's profit and overheads on A+B+C Rate per/ Running metre=(A+B+C+D) / 100 IRR-DAW-6 IRR-DAW-6-1 FILTER & PITCHING WORKS :

0%

Providing and constructing 1.20 m internal diameter and average 3 m height RCC manhole with 60 cm dia. top cover in M-15 grade cement concrete using 20 mm down graded, clean, hard coarse aggregate, 20 cm thick for bed / sides / top slab / 1.5 m long cut-off wall and 7.5 cm thick for cover including providing 12 mm dia reinforcement bars at 30 cm c / c bothways for bed / sides / cut-off wall / top slab / rungs and 8 mm dia bars at 15 cm c / c bothways for cover, excavation for foundation, providing 30 cm dia hume pipe outlet, cost of all materials, machinery, labour, formwork, scaffolding, batching, mixing, laying, vibrating, finishing, curing etc., complete with lead upto 1 km and all lifts. ( Cement content : 300 kg/cum , CA : 0.80 cum, Blending Ratioof CA -- 65:35, FA : 0.44 cum, superplasticizer (0.4% by wt. of cement) DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars 1 2 3 4 5 6 7 8 9 10 Unit UNIT Quantity Rate in Rs. 1 Each Amount in Rs

Cement kg 1331.70 Cement for incidentals @ 3 kg / cumkg 13.32 Coarse aggregate 20 to 10 mm cum 2.31 Coarse aggregate 10 to 4.75 mm cum 1.24 Fine aggregate ( screened ) cum 1.95 Super plasticiser kg 23.65 Reinforcement steel with 5 % wastage kg 163.70 Binding wire kg 4.00 Hume pipe 300 mm dia Rm 1.00 Use rate of shuttering sqm 36.00 Scaffolding of shuttering @ 5% Sundries LS 2.00 Add seigniorage charges on CA @ ( Included in material rate) Add seigniorage charges on Sand @ ( Included in material rate) Total cost of Materials

B. MACHINERY: Sl No Description 1 2 3 4

Unit

Quantity 4.00 4.00 4.00 4.00 0.50 0.50 1.00

Concrete mixer 300 / 200 ( ele ) Fuel / Energy charges Needle vibrator 40 mm dia ( ele ) Fuel / Energy charges Pump 5 hp ( ele ) Fuel / Energy charges Sundries Total hire charges of Machinery

C. LABOUR: Sl No Description 1 2 3 4

Unit

Quantity 1.00 1.00 1.00 2.00 1.00 5.00 2.00 4.00 1.00 36.00 Rs: Rs: Rs: Rs: 0% 0.00 0.00 0.00 0.00

Mason Cl- II Day Bar bender Day work inspector Day mazdoor for excavation for foundation Day for bar bending Day for concreting Day for excavation for foundation Day for concreting Day for curing Day Labour for shuttering sqm Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ each=(A+B+C+D) /1

IRR-DAW-6-2

Providing and constructing longitudinal and cross graded filter drains using sand and 80-20 mm and 20 mm down graded aggregates satisfying specified filter creteria in layers as per specifications including cost of all materials, machinery, labour, laying to required slopes, compaction etc. complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars 1 2 Sand ( unscreened ) Coarse aggregate 80-40 mm cum cum Unit Quantity 47.50 17.865 Rate in Rs. 100 cum Amount in Rs

39

IRR-DAW

3 4 5

Coarse aggregate 40-20 mm cum 1.99 Coarse aggregate 20-10 mm cum 24.49 Coarse aggregate 10 mm down cum 8.16 Add seigniorage charges on CA @ ( Included in material rate) Add seigniorage charges on Sand @ ( Included in material rate) Total cost of Materials

B. MACHINERY: Sl No Description 1 NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 work inspector mazdoor

Unit

Quantity 1.00 38.00

Day Day Total cost of Labour labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 100

Rs: Rs: Rs:

0%

40

IRR-DAW

IRR-DAW-6-3

Providing and constructing 1.40 m thick vertical or inclined graded filter media consisting of 20 cm thick sand layers, 25 cm thick 20 mm down coarse aggregate layers and 50 cm thick 80-20 mm coarse aggregate layer using approved materials satisfying specified filter creteria as per specifications including cost of all materials, machinery, labour, laying to required slope, compaction etc., complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS UNIT : 100 cum A. MATERIALS: Sl No Particulars Unit Quantity Rate Amount in Rs. in Rs 1 Sand ( unscreened ) cum 28.60 0.00 0.00 2 Coarse aggregate 80-40 mm cum 32.13 0.00 0.00 3 Coarse aggregate 40-20 mm cum 3.57 0.00 0.00 4 Coarse aggregate 20-10 mm cum 28.13 0.00 0.00 5 Coarse aggregate 10 mm down cum 8.93 0.00 0.00 Add seigniorage charges on CA @ ( Included in material rate) Rs: 0.00 Add seigniorage charges on Sand @ ( Included in material rate) Rs: 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No Description 1 NIL Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 work inspector mazdoor

Unit

Quantity 0.00 0.00

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00

Unit Day Day Total cost of Labour

Quantity 1.00 38.00

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 100

0%

IRR-DAW-6-4

Providing and constructing graded filter media below and behind rock-toe consisting of 20 cm thick sand, 25 cm thick 20 - 4.75 mm and 40 cm thick 80 - 20 mm size graded coarse aggregates satisfying filter creteria as per specifications including cost of all materials, labour, machinery, laying to required slope, compaction etc., complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS UNIT 100 cum A. MATERIALS: Sl No Particulars Unit Quantity Rate Amount in Rs. in Rs 1 Sand ( unscreened ) cum 23.55 0.00 0.00 2 Coarse aggregate 80-40 mm cum 42.39 0.00 0.00 3 Coarse aggregate 40-20 mm cum 4.71 0.00 0.00 4 Coarse aggregate 20-10 mm cum 22.05 0.00 0.00 5 Coarse aggregate 10 mm down cum 7.35 0.00 0.00 Add seigniorage charges on CA @ ( Included in material rate) Rs: 0.00 Add seigniorage charges on Sand @ ( Included in material rate) Rs: 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No Description 1 NIL Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 work inspector mazdoor

Unit

Quantity 0.00 0.00

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00

Unit Day Day Total cost of Labour

Quantity 1.00 34.00

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 100 0%

41

IRR-DAW

IRR-DAW-6-5

DATA:

Providing and laying filter media consisting of 2 layers of 250 gsm poly-propeline non-woven filter fabric and 400 mm thick 20 mm down graded coarse aggregate for vertical / inclined and horizontal filter blanket for embankment including cost of all materials, machinery, labour etc., complete with lead upto 50 m for aggregate and all leads for fabric and all lifts. Consider 100 sqm filter blanket laying. Filter fabric with 10 % for lapping and wastage ( 2 x 100 x 1.10 ) 220.00 sqm. 20 mm down aggregate ( 100 x 0.4 ) 40.00 cum. DATA & RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars 1 2 Unit Quantity 100 sqm Rate in Rs. 0.00 0.00 0.00 Rs: Amount in Rs 0.00 0.00 0.00 0.00

PP filter fabric 250 gsm sqm 220.00 20 - 10 mm CA @ 75 % cum 30.00 10 mm down CA @ 25 % cum 10.00 Add seigniorage charges on CA @ ( Included in material rate) Total cost of Materials

B. MACHINERY: Sl No Description 1 NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00

Unit Day Day Total cost of Labour

Quantity 1.00 14.00

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ sq metre=(A+B+C+D) / 100 0%

IRR-DAW-6-6

Providing and constructing 45 cm thick chimney filter using clean approved sand satisfying filter creteria including cost of all materials, machinery, labour, compacting etc., complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS UNIT : 100 cum A. MATERIALS: Sl No Particulars Unit Quantity Rate Amount in Rs. in Rs 1 Sand ( unscreened) cum 105.00 0.00 0.00 0.00 0.00 0.00 Add seigniorage charges on sand @ ( Included in material rate) Rs: 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No Description 1 NIL Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 work inspector mazdoor

Unit

Quantity 0.00 0.00

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00

Unit Day Day Total cost of Labour

Quantity 1.00 30.00

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 100

Rs: Rs: Rs: 0%

0.00 0.00 0.00

IRR-DAW-6-7

Providing and constructing 90 cm thick transition cum filter media behind rockfill using approved sand and 80-20 mm and 20 mm down graded aggregates satisfying the filter creteria in layers of 30 cm thickness each as per specifications including cost of all materials,

42

IRR-DAW

machinery, labour, laying each layer to required slope, compaction etc., complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars 1 2 3 4 5 UNIT : Quantity 100 cum. Amount in Rs

Unit

Rate in Rs.

Sand ( unscreened ) cum 34.00 Coarse aggregate 80-40 mm cum 30.60 Coarse aggregate 40-20 mm cum 3.40 Coarse aggregate 20-10 mm cum 25.50 Coarse aggregate 10 mm down cum 8.50 Add seigniorage charges on Sand @ (Included in material rate) Add seigniorage charges on CA @ ( Included in material rates ) Total cost of Materials

B. MACHINERY: Sl No Description 1 NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs

Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 work inspector mazdoor

Unit Day Day Total cost of Labour

Quantity 1.00 40.00

Rate in Rs.

Amount in Rs

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/ cubic metre=(A+B+C+D) / 100

Rs: Rs: Rs: 0%

0.00 0.00 0.00

IRR-DAW-6-8

Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to 75 cm long through stones at 1.50 m c / c over a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 15 cm thick each including cost of all materials, machinery, labour, laying to required slopes, wedging with chips, finishing etc. complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars 1 2 3 4 5 6 UNIT : Quantity 100 sqm Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00

Unit

Sand ( unscreened ) cum 15.30 Coarse aggregate 10 mm down cum 15.30 Coarse aggregate 40-20 mm cum 15.30 Stone chips cum 9.00 Rough stones ( rubble ) 30 to 45 cm cum long 57.60 Through stones 65 to 75 cm long Nos 44.00 Add seigniorage charges on Sand @ ( Included in material rate) Add seigniorage charges on CA @ ( Included in material rate) Add seigniorage charges on Stone @ (Included in material rate) Total cost of Materials

B. MACHINERY: Sl No Description 1 NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 3 work inspector Mason Class-II mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs 0.00 0.00 0.00

Unit Day Day Day Total cost of Labour

Quantity 1.00 10.00 33.00

Rate in Rs. 0.00 0.00 0.00 Rs: Rs: Rs: Rs:

Amount in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/Square metre=(A+B+C+D) / 100

0%

43

IRR-DAW

IRR-DAW-6-9

Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to 75 cm long through stones at 1.50 m c / c over a backing of 60 cm thick graded filter media consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 20 cm thick each including cost of all materials, machinery, labour, laying to required slopes, wedging with chips, finishing etc. complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars 1 2 3 4 5 6 Unit

100 sqm Quantity Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00 Rs: 0.00

Sand ( unscreened ) cum 20.40 Coarse aggregate 10 mm down cum 20.40 Coarse aggregate 40-20 mm cum 20.40 Stone chips cum 9.00 Rough stones ( rubble ) 30 to 45 cm cum long 57.60 Through stones 65 to 75 cm long Nos 44.00 Add seigniorage charges on Sand @ ( Included in material rate) Add seigniorage charges on CA @ ( Included in material rate) Add seigniorage charges on Stone @ (Included in material rate) Total cost of Materials

B. MACHINERY: Sl No Description 1 NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 3 work inspector Mason Class-II mazdoor

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00

Unit Day Day Day Total cost of Labour

Quantity 1.00 10.00 39.00

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: Rs: Rs: 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/Square metre=(A+B+C+D) / 100 0%

IRR-DAW-6-10 Providing and constructing 60 cm thick hand packed rough stone riprap over a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved aggregates laid in layers of 15 cm thick each including cost of all materials, machinery, labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars 1 2 3 4 5 UNIT : Quantity 100 sqm. Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs:

Unit

Sand ( unscreened ) cum 15.30 Coarse aggregate 10 mm down cum 15.30 Coarse aggregate 40-20 mm cum 15.30 Stone chips cum 9.00 Rough stones ( rubble ) cum 60.00 Add seigniorage charges on Sand @ ( Included in material rate) Add seigniorage charges on CA @ ( Included in material rate) Add seigniorage charges on Stone @ (Included in material rate) Total cost of Materials

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No Description 1 NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No Description

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00

Unit

Quantity

Rate in Rs.

Amount in Rs

44

IRR-DAW

1 2 3

work inspector Mason Class-II mazdoor

Day Day Day Total cost of Labour

1.00 5.00 28.00

0.00 0.00 0.00 Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/Square metre=(A+B+C+D) / 100

0%

IRR-DAW-6-11 Providing and constructing 75 cm thick hand packed rough stone riprap over a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved aggregates laid in layers of 15 cm thick each including cost of all materials, machinery, labour, laying to required slopes, wedging with stone chips, etc., complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars 1 2 3 4 5 UNIT : Quantity 100 sqm Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs:

Unit

Sand ( unscreened ) cum 15.30 Coarse aggregate 10 mm down cum 15.30 Coarse aggregate 40-20 mm cum 15.30 Stone chips cum 11.00 Rough stones ( rubble ) cum 75.00 Add seigniorage charges on Sand @ ( Included in material rate) Add seigniorage charges on CA @ ( Included in material rate) Add seigniorage charges on Stone @ (Included in material rate) Total cost of Materials

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No Description 1 NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 3 work inspector Mason Class-II mazdoor

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00

Unit Day Day Day Total cost of Labour

Quantity 1.00 6.00 30.00

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: Rs: Rs: 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/Square metre=(A+B+C+D) / 100

0%

IRR-DAW-6-12 Providing and constructing 90 cm thick hand packed rough stone riprap over a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved aggregates laid in layers of 15 cm thick each including cost of all materials, machinery, labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto 50 m and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars 1 2 3 4 5 UNIT : Quantity 100 sqm Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs:

Unit

Sand ( unscreened ) cum 15.30 Coarse aggregate 10 mm down cum 15.30 Coarse aggregate 40-20 mm cum 15.30 Stone chips cum 13.50 Rough stones ( rubble ) cum 90.00 Add seigniorage charges on Sand @ ( Included in material rate) Add seigniorage charges on CA @ ( Included in material rate) Add seigniorage charges on Stone @ (Included in material rate) Total cost of Materials

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No Description 1 NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00

45

IRR-DAW

C. LABOUR: Sl No Description 1 2 3 work inspector Mason Class-II mazdoor

Unit Day Day Day Total cost of Labour

Quantity 1.00 8.00 34.00

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: Rs: Rs: 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/Square metre=(A+B+C+D) / 100

0%

IRR-DAW-6-13 Providing and laying Hariyala or other approved quality turfing sods for the slopes of earthen embankments over 20 mm thick sand backing including cost of all materials, machinery, labour including preparing surface, spreading sand, watering for 15 days etc., complete with initial lead upto 1 km and all lifts. DATA & RATE ANALYSIS A. MATERIALS: Sl No Particulars 1 2 UNIT : Quantity 100 sqm. Rate Amount in Rs. in Rs 0.00 0.00 Rs: Rs:

Unit

Sand ( unscreened ) cum 2.00 Hariyala turfing sods sqm 100.00 Add seigniorage charges on Sand @ ( Included in material rate ) Total cost of Materials

0.00 0.00 0.00 0.00

B. MACHINERY: Sl No Description 1 NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No Description 1 2

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00

Unit

Quantity 2.00 15.00

Cartman with double bullock cart Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour D. Add for contractor's profit and overheads on A+B+C Rate per/Square metre=(A+B+C+D) / 100

Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 Rs: 0.00 Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00

Total 0%

46

IRR-TAW

CHAPTER-II

Standard Data
Index- code IRR-TAW
IRR-TAW-1 IRR-TAW-1-1

TUNNEL AND ALLIED WORKS


EXCAVATION :
Excavation for adit by tunnelling methods in all types of rock including cost of all materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and hauling the excavated muck outside adit upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1km and all lifts.

DATA:

DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 Perticulars Unit kg Nos Nos Rm Rm 10% Hour Hour LS

UNIT : Quantity 40.00 54.00 5.00 50.00 119.00 20.00 20.00 2.00

38.50 cum Rate in Rs. Amount in Rs.

Small dia explosive Delay detonators Electric detonators Detonating fuse coil Use rate of drill rod 2.5 m long Reconditioning charges @ Use rate of air hose Use rate of water hose Sundries( paint / template etc ) Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1 2 3 4 5 6

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 5.00 5.00 20.00 20.00 20.00 20.00 6.50 6.50 6.50

Rate in Rs.

Amount in Rs.

Drilling jumbo Fuel / Energy charges Air compressor 15 cmm ( ele ) Fuel / Energy charges Jack hammer ( 4 x 5 hrs ) Fuel / Energy charges Pusher leg Fuel / Energy charges Convey mucker Fuel / Energy charges Dumper ( 1 x 6.5 hrs )

50

IRR-TAW

7 8 9

Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Ventilation fans 20 hp Fuel / Energy charges Sundries(explosive van / magazine ) Total hire charges of Machinery

Hour Hour Hour Hour Hour LS

6.50 5.00 5.00 1.00 1.00 2.00 Rs: 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Description Crew for Drilling jumbo Crew for Air compressor Crew for Jack hammer Crew for Convey mucker Crew for Dumper Crew for Pump Crew for ventilation fans Surveyor Foreman Fitter / Mechanic Blaster ( Licensed ) Helper blasting Hammerman work inspector 1 in each shift Khalasi for mucking shift 4 Nos mazdoor for mucking shift 4 Nos for other 2 shifts 1 No each shift for cleaning & miscellaneous Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per cum= (A+B+C+D) /38.50

Unit Hour Hour Hour Hour Hour Hour Hour Day Day Day Day Day Day Day Day Day Day Day

Quantity 8.00 5.00 20.00 6.50 6.50 5.00 1.00 0.50 1.00 2.00 1.00 2.00 2.00 3.00 4.00 4.00 2.00 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% cum

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-1-2

Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of all materials, machinery, labour, shoring, strutting, scaling excavated surface, ventilation, lighting, drainage, removing and hauling excavated muck outside shaft upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. Size of shaft assumed : Shape of shaft assumed for excavation : Depth of shaft assumed : Pay-line margin assumed : Diameter of shaft upto pay line for excavation : Distance of dump yard from face :within Average lift involved for excavation of shaft upto tunnel level : DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Perticulars Unit kg Nos Rm Rm 10% Hour 5.00 Circular 75 0.2 5.4 500 40 UNIT : Quantity 32.00 65.00 50.00 95.00 18.00 m dia m m m m m 30.00 cum Rate in Rs. Amount in Rs.

DATA:

Small dia explosive Electric detonator Detonating fuse coil Use rate of drill rod 1.6 m long Reconditioning charges @ Use rate of air hose

51

IRR-TAW

7 8 9 10

Use rate of water hose Use rate of rail track Use rate of mucking bucket Sundries( paint / template etc ) Total cost of Materials

Hour Shift Hour LS

16.00 3.00 24.00 2.00 Rs: 0.00

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 4.50 4.50 16.00 16.00 4.00 4.00 2.00 2.00 28.00 28.00 24.00 24.00 2.00

Rate in Rs.

Amount in Rs.

Air compressor 15 cmm ( ele ) Fuel / Energy charges Jack hammer ( 4 x 4 hrs ) Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Pump 20 hp electric Fuel / Energy charges Winch 35 hp electric Fuel / Energy charges Tipping tub 1.5 cum Fuel / Energy charges Sundries(explosive van / magazine ) Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Description Crew for Air compressor Crew for Jack hammer Crew for Pump 10 hp Crew for Pump 20 hp Crew for Winch Surveyor Foreman Fitter / Mechanic Blaster ( Licensed ) Helper blasting Hammerman 1 No. in each shift work inspector 1 in each shift Khalasi for mucking 2 Nos in each shift mazdoor for mucking 8 Nos in each shift for other 2 shifts 1 No / shift for cleaning & miscellaneous Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per cum= (A+B+C+D) /30

Unit Hour Hour Hour Hour Hour Day Day Day Day Day Day Day Day Day Day Day

Quantity 4.50 16.00 4.00 2.00 28.00 0.50 4.00 2.00 1.00 2.00 3.00 4.00 6.00 24.00 2.00 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-1-3

Excavation for tunnel by tunnelling methods in rock not requiring supports including cost of all materials,machinery, labour, scaling excavated surface, removing under-cuts, ventilation, lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. Size of tunnel assumed ( finished section ) Shape of tunnel assumed for excavation Height of tunnel assumed ( finished section ) : : : 4.50 m dia D - shape 4.50 m

DATA:

52

IRR-TAW

Length of tunnel assumed Thickness of CC lining Pay-line margin assumed Diameter of tunnel upto pay line for excavation Distance of dump yard from face Haulage of excavated muck

: : : : :within :

1000 m 0.30 m 0.20 m 5.50 m 500 m By dumpers

DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 Perticulars Unit kg Nos Nos Rm Rm 10% Hour Hour LS

UNIT : Quantity 54.00 68.00 10.00 50.00 150.00 24.00 24.00 2.00

48.60 cum Rate in Rs. Amount in Rs.

Small dia explosive Delay detonators Electric detonators Detonating fuse coil Use rate of drill rod 2.5 m long Reconditioning charges @ Use rate of air hose Use rate of water hose Sundries( paint / template etc ) Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1 2 3 4 5 6 7 8 9

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 10.00 10.00 6.50 6.50 26.00 26.00 26.00 26.00 6.00 6.00 12.00 12.00 6.50 6.50 2.00 2.00 2.00

Rate in Rs.

Amount in Rs.

Drilling jumbo Fuel / Energy charges Air compressor 15 cmm ( ele ) Fuel / Energy charges Jack hammer ( 4 x 6.5 hrs ) Fuel / Energy charges Pusher leg Fuel / Energy charges Convey mucker Fuel / Energy charges Dumper ( 2 x 6 hrs ) Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Ventilation fans 20 hp Fuel / Energy charges Sundries(explosive van / magazine ) Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11 12

Description Crew for Drilling jumbo Crew for Air compressor Crew for Jack hammer Crew for Convey mucker Crew for Dumper Crew for Pump Crew for ventilation fans Surveyor Foreman Fitter / Mechanic Blaster ( Licensed ) Helper blasting

Unit Hour Hour Hour Hour Hour Hour Hour Day Day Day Day Day

Quantity 10.00 6.50 26.00 6.00 12.00 6.50 2.00 0.50 1.00 2.00 1.00 2.00

Rate in Rs.

Amount in Rs.

53

IRR-TAW

13 14 15 16

Hammerman work inspector 1 in each shift Khalasi for mucking shift 4 Nos mazdoor for mucking shift 8 Nos for other 2 shifts 1 No each shift for cleaning & miscellaneous Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per cum= (A+B+C+D) /48.60

Day Day Day Day Day Day

2.00 3.00 4.00 8.00 2.00 2.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-1-4

Excavation for tunnel by tunnelling methods including excavation for supports in all types of soil / rock strata requiring supports ( excluding cost of providing supports ) including cost of all other materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. Size of tunnel assumed ( finished section ) Shape of tunnel assumed for excavation Height of tunnel assumed ( finished section ) Length of tunnel assumed Thickness of CC lining Extra excavation for supports Pay-line margin assumed Diameter of tunnel upto pay line for excavation Distance of dump yard from face Haulage of excavated muck DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 Perticulars Unit kg Nos Nos Rm Rm 10% Hour Hour LS : : 4.50 m dia D - shape

DATA:

UNIT : Quantity 41.00 77.00 10.00 50.00 144.00 24.00 24.00 2.00

46.00 cum Rate in Rs. Amount in Rs.

Small dia explosive Delay detonators Electric detonators Detonating fuse coil Use rate of drill rod 2.5 m long Reconditioning charges @ Use rate of air hose Use rate of water hose Sundries( paint / template etc ) Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1 2 3 4 5 6

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 11.00 11.00 6.00 6.00 24.00 24.00 24.00 24.00 6.00 6.00 12.00

Rate in Rs.

Amount in Rs.

Drilling jumbo Fuel / Energy charges Air compressor 15 cmm ( ele ) Fuel / Energy charges Jack hammer ( 4 x 6 hrs ) Fuel / Energy charges Pusher leg Fuel / Energy charges Convey mucker Fuel / Energy charges Dumper ( 2 x 6 hrs )

54

IRR-TAW

7 8 9

Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Ventilation fans 20 hp Fuel / Energy charges Sundries(explosive van / magazine ) Total hire charges of Machinery

Hour Hour Hour Hour Hour LS

12.00 6.00 6.00 2.00 2.00 2.00 Rs: 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Description Crew for Drilling jumbo Crew for Air compressor Crew for Jack hammer Crew for Convey mucker Crew for Dumper Crew for Pump Crew for ventilation fans Surveyor Foreman Fitter / Mechanic Blaster ( Licensed ) Helper blasting Hammerman 2 Nos work inspector 1 in each shift Khalasi for mucking shift 4 Nos mazdoor for mucking shift 8 Nos for other 2 shifts 1 No each shift for cleaning & miscellaneous Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per cum= (A+B+C+D) /46

Unit Hour Hour Hour Hour Hour Hour Hour Day Day Day Day Day Day Day Day Day Day Day

Quantity 11.00 6.00 24.00 6.00 12.00 6.00 2.00 0.50 1.00 2.00 1.00 2.00 2.00 3.00 4.00 8.00 2.00 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-1-5

Excavation for tunnel by heading and benching tunnelling methods including excavation for supports in all types of soil / rock strata requiring supports ( excluding cost of providing supports ) for roof before benching including cost of all other materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage removing and hauling excavated muck outside tunnel upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. Size of tunnel assumed ( finished section ) Shape of tunnel assumed for excavation Height of tunnel assumed ( finished section ) Length of tunnel assumed Thickness of CC lining Extra excavation for supports Pay-line margin assumed Diameter of tunnel upto pay line for excavation Distance of dump yard from face Haulage of excavated muck : : : : : : : : :within : 4.50 m dia D - shape 4.50 m 1000 m 0.30 m 0.25 m 0.20 m 6.00 m 500 m By dumpers

DATA:

55

IRR-TAW

DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 Perticulars Unit kg Nos Nos Rm Rm 10% Hour Hour LS

UNIT : Quantity 44.00 84.00 10.00 50.00 157.00 26.00 26.00 2.00

50.00 cum Rate in Rs. Amount in Rs.

Small dia explosive Delay detonators Electric detonator Detonating fuse coil Use rate of drill rod 2.5 m long Reconditioning charges @ Use rate of air hose Use rate of water hose Sundries( paint / template etc ) Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1 2 3 4 5 6 7 8 9

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 12.00 12.00 6.50 6.50 26.00 26.00 26.00 26.00 6.50 6.50 13.00 13.00 6.50 6.50 3.00 3.00 2.00

Rate in Rs.

Amount in Rs.

Drilling jumbo Fuel / Energy charges Air compressor 15 cmm ( ele ) Fuel / Energy charges Jack hammer ( 4 x 6.5 hrs ) Fuel / Energy charges Pusher leg Fuel / Energy charges Convey mucker Fuel / Energy charges Dumper ( 2 x 6.5 hrs ) Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Ventilation fans 20 hp Fuel / Energy charges Sundries(explosive van / magazine ) Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Description Crew for Drilling jumbo Crew for Air compressor Crew for Jack hammer Crew for Convey mucker Crew for Dumper Crew for Pump Crew for Ventilation fan Surveyor Foreman Fitter / Mechanic Blaster ( Licensed ) Helper blasting Hammerman 2 Nos work inspector 1 in each shift Khalasi for pushing muck in heading portion for mucking shift 4 Nos mazdoor for mucking shift 8 Nos for other 2 shifts 1 No each shift for cleaning &miscellaneous Total cost of Labour ABSTRACT: A. Cost of Materials

Unit Hour Hour Hour Hour Hour Hour Hour Day Day Day Day Day Day Day Day Day Day Day Day

Quantity 12.00 6.50 26.00 6.50 13.00 6.50 3.00 0.50 1.00 2.00 2.00 4.00 2.00 3.00 4.00 4.00 8.00 2.00 2.00

Rate in Rs.

Amount in Rs.

16

Rs: Rs: 0.00

0.00

56

IRR-TAW

B. Hire charges of Machinery C. Cost of Labour Total Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per cum= (A+B+C+D) /50 NOTE: 0.00% 0.00% 0.00% 0.00% Total

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

Where mucking is to be carried out through shaft using winch and mucking tub system increase the basic rates for items 3, 4 & 5 by 8 percent.

IRR-TAW-1-6

Removing and hauling muck overfallen due to natural causes such as geological faults etc., out of tunnel including breaking large fragments by blasting if necessary and disposing off the same in specified dump area or as directed including cost of all materials, machinery, labour, ventilation, drainage, lighting and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. Quantity of overfallen muck considered for analysis Length of tunnel assumed DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 Perticulars Unit Rm 10% kg Nos. Rm Hour Hour LS : : 100 cum 1000 m UNIT : Quantity 15.00 8.00 30.00 20.00 4.00 4.00 1.00 Rs: 0.00 100.00 cum Rate in Rs. Amount in Rs.

DATA:

Use rate of drill rod Reconditioning charges @ Explosive small dia. Detonator ( ele ) Detonating fuse coil Use rate of air hose Use rate of water hose Sundries Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5 6

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 1.00 1.00 4.00 4.00 1.00 1.00 6.00 6.00 12.00 12.00 1.00

Rate in Rs.

Amount in Rs.

Air compressor 15 cmm ( ele ) Fuel / Energy charges Jack hammer Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Convey mucker Fuel / Energy charges Dumper 4.5 cum Fuel / Energy charges Sundries Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Air compressor Crew for Jack hammer Crew for Pump Crew for Convey mucker Crew for Dumper Blaster ( Licensed ) Helper blasting mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials

Unit Hour Hour Hour Hour Hour Day Day Day

Quantity 1.00 4.00 1.00 6.00 12.00 0.50 0.50 8.00

Rate in Rs.

Amount in Rs.

Rs: Rs: 0.00

0.00

57

IRR-TAW

B. Hire charges of Machinery C. Cost of Labour Total Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per cum= (A+B+C+D) /100 IRR-TAW-2 IRR-TAW-2-1 DEWATERING & GUNITING WORKS : 0.00% 0.00% 0.00% 0.00% Total

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

Dewatering tunnel by pumping out water collected by natural drainage inside tunnel including providing sump wherever necessary, cost of all materials, machinery, labour, drainage, lighting, ventilation and all other ancillary operations etc., complete. Consider 20 hp electric pump installed near junction of adit / channel with tunnel. 100 mm dia B Class G.I. Delivery pipe 250 m length. Daily average 8 hours pumping. Energy consumption per hour running of pump ( 20 x 0.746 ) : 14.92 Miscellaneous such as indicator lamps etc : 0.08 Total / hour: 15.00 Use rate of delivery pipe: Cost of 100 mm dia pipe 250 m @ Rs: 395.00 / Rm Rs: 98750.00 Add for fixtures @ 5% Rs: 4937.50 Total Rs: 103687.50 Less salvage value @ 10% Rs: 10368.75 Total Rs: 93318.75 Life of G.I. pipe : 20000 Use rate of delivery pipe per hour: ( cost / life ) Rs: 4.67 RATE ANALYSIS A. MATERIALS: Sl No 1 2 Perticulars Unit Hour LS UNIT : Quantity 1.00 0.10 Rs: 0.00

DATA:

kwhr kwhr kwhr

hrs

15.00 Kwhr Rate in Rs. Amount in Rs.

Use rate of G.I.pipe 100 mm dia Sundries Total cost of Materials

B. MACHINERY: Sl No 1 2 3

Description

Unit Hour Hour LS

Quantity 1.00 1.00 0.10

Rate in Rs.

Amount in Rs.

Electric pump 20 hp Fuel / Energy charges Sundries(Starter/Switches ete) Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description Crew charges for Pump Laying & dismantling pipe mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above

Unit Hour LS Day

Quantity 1.00 0.05 0.10

Rate in Rs. 0.00 0.00 0.00 Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Amount in Rs. 0.00 0.00 0.00 0.00

Total 0.00% 0.00% 0.00% 0.00% Total

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0%

Rs:

0.00

58

IRR-TAW

Total cost for Rate per Kwhr= (A+B+C+D) /15

Kwhr Kwhr

Rs: Rs:

0.00 0.00

IRR-TAW-2-2

Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar 1 : 3 proportion by weight including cost of all materials, machinery, labour, ventilation, lighting, drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.

DATA: DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Perticulars Unit UNIT : Quantity 36.00 sqm Rate in Rs. Amount in Rs.

Cement kg 600.00 Sand ( screened ) cum 1.10 Use rate of grout hose 20 m Hour 8.00 Use rate of water hose 20 m Hour 8.00 Use rate of guniting nozzle Hour 8.00 Sundries LS 2.00 Add for seiniorage charges on sand (Included in material cost) Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1 2 3 4 5

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 8.00 8.00 8.00 1.00 1.00 4.00 4.00 2.00

Rate in Rs.

Amount in Rs.

Guniting equipment Fuel / Energy charges Air compressor 8.5 cmm ( ele ) Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Drilling jumbo Fuel / Energy charges Sundries Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Guniting equipment Crew for Air compressor Crew for pump Crew for Drilling jumbo Mason Cl I mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per sqm= (A+B+C+D) /36

Unit Hour Hour Hour Hour Day Day

Quantity 8.00 8.00 1.00 4.00 1.00 6.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% sqm sqm

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-3 IRR-TAW-3-1

TEMPORARY & PERMANENT SUPPORTS : Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type anchorage including drilling 35 mm dia holes, providing 15 cm long 20 mm thick steel tapered wedge, 10 mm thick plate washers and nuts, tightening bolt by torque wrench, cost of all materials, machinery, labour, ventilation, lighting, drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.

59

IRR-TAW

DATA: DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 Perticulars Unit kg kg kg kg Rm 10% Hour Hour LS UNIT : Quantity 86.91 65.94 6.18 4.00 20.00 6.00 6.00 5.00 Rs: 0.00 20.00 Rm Rate in Rs. Amount in Rs.

Rein.Steel with 5 % wastage Steel plate for washers Steel plate for wedges M S Nuts for bolts Use rate of drill rod Reconditioning charges @ Use rate of air hose 4 Nos Use rate of water hose 4 Nos Sundries ( gas for cutting / heating etc ) Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5 6

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 1.50 1.50 1.00 1.00 6.00 6.00 6.00 6.00 4.00 4.00 5.00

Rate in Rs.

Amount in Rs.

Air compressor 15 cmm ( ele ) Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Jack hammer Fuel / Energy charges Pusher leg Fuel / Energy charges Drilling jumbo Fuel / Energy charges Sundries ( lathe, blower etc ) Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day

Quantity 1.50 1.00 6.00 4.00 0.50 1.00 1.00 1.00 1.00 0.50 2.00

Rate in Rs.

Amount in Rs.

Crew for Air compressor Crew for pump Crew for Jack hammer Crew for Drilling jumbo Fitter Gas cutter Turner Blacksmith Khalasi ( 2 x 0.5 ) 10 Hammerman 11 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per Rm= (A+B+C+D) /20

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% Rm Rm

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-3-2

Providing and fixing 25 mm diameter steel rock bolts with resin bond cement capsule anchorage including drilling 35 mm dia holes, inserting grout capsule, driving bolt,fixing 10 mm thick plate washers and nuts and tightening the same by torque wrench after hardening of cement grout, cost of all materials, machinery, labour, ventilation, lighting, drainage and other ancillary operations etc., complete with lead upto 1 km and all lifts.

60

IRR-TAW

DATA: Length of rock bolt including threaded portion

: :

mm 2.15 m

DATA & RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 Perticulars Unit kg kg Nos. kg Rm 10% Hour Hour LS

UNIT : Quantity 86.91 65.94 2.00 4.00 20.00 6.00 6.00 3.00

20.00 Rm Rate in Rs. Amount in Rs.

Rein.Steel with 5 % wastage Steel plate for washers Resin bond cement grout capsule M S Nuts for bolts Use rate of drill rod Reconditioning charges @ Use rate of air hose 4 Nos Use rate of water hose 4 Nos Sundries(gas for cutting etc) Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1 2 3 4 5 6

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 1.50 1.50 1.00 1.00 6.00 6.00 6.00 6.00 4.00 4.00 3.00

Rate in Rs.

Amount in Rs.

Air compressor 15 cmm ( ele ) Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Jack hammer Fuel / Energy charges Pusher leg Fuel / Energy charges Drilling jumbo Fuel / Energy charges Sundries ( lathe, etc ) Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description

Unit Hour Hour Hour Hour Day Day Day Day Day Day

Quantity 1.50 1.00 6.00 4.00 0.50 1.00 1.00 1.00 0.50 2.00

Rate in Rs.

Amount in Rs.

Crew for Air compressor Crew for pump Crew for Jack hammer Crew for Drilling jumbo Fitter Gas cutter Turner Khalasi ( 2 x 0.5 ) Hammerman 10 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for 20 Rm Rate per Rm= (A+B+C+D) /20

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% Rm

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-3-3

Providing, fabricating and fixing in position permanent structural steel supports as per details including cost of all materials, machinery, labour, cutting, bending, welding, grinding, lighting, ventilation, drainage and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts.

61

IRR-TAW

DATA:

Clear diameter of tunnel : 4.50 m Assuming 30 cm thick concrete lining and about 25 cm extra excavation for fixing permanent structural steel supports and further 20 cm pay line margin the over all width of tunnel for excavation will be 6.00 m. Permanent steel supports are generally provided in the form of quarter / half / full rib depending on the condition of rock and mode of excavation and size of sections. For the purpose of rate analysis quarter arch rib fabrication is considered.

Generally, the depth of rib will be considered at 25 mm per metre width of tunnel and the spacing of ribs depends on the condition of strata to be supported. Average spacing of 5 times the depth of rib ( generally 2 ribs per blast ) is considered for analysis. For 6 m wide tunnel the depth of rib required will be 150 mm.

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 Perticulars Unit kg kg kg cum cum Nos. kg LS

UNIT : Quantity 760.00 115.00 150.00 2.40 0.80 125.00 50.00 5.00

1.00 tonne Rate in Rs. Amount in Rs.

5 6 7

Structural steel beams Structural steel plates Steel bars for tie rods & anchors For cutting sections: Oxygen gas @ 2.4 cum / t Acetylene gas @ 0.8 cum / t For welding sections: Electrodes 4 x 300 mm @ 125 Nos / t For field connections: M.S.Bolts / Nuts & Washers Sundries Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1 2 3 4

Description

Unit Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 8.00 16.00 16.00 12.00 12.00 30.00

Rate in Rs.

Amount in Rs.

Bending machine Fuel / Energy charges Welding set Fuel / Energy charges Drilling Jumbo Fuel / Energy charges Sundries ( lathe / drilling / grinder ) Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description Crew for Drilling Jumbo Crew fir Bending machine For cutting & preparing sections: Structural steel Marker Gas cutter Fitter Turner / Driller Khalasi Helper fabrication For welding sections: Welder Helper fabrication Khalasi

Unit Hour Hour Day Day Day Day Day Day Day Day Day

Quantity 12.00 8.00 1.00 2.00 2.00 3.00 2.00 4.00 2.00 2.00 2.00

Rate in Rs.

Amount in Rs.

62

IRR-TAW

For erection of supports: Foreman Structural steel Erector Helper erector Khalasi Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per Tonne= (A+B+C+D) /1.00

Day Day Day Day

1.00 2.00 2.00 4.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% tonne tonne

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-3-4

Providing, fabricating and fixing in position temporary structural steel supports as per details and dismantling the same before concreting including cost of all materials, machinery, labour, cutting, bending, welding, grinding, ventilation, lighting, drainage and all other ancillary operations etc.,complete with initial lead upto 1 km and all lifts. As the temperary supports are dismantled before concreting and reused else where the cost of materials including fabrication will be per use of supports. As per the data under Item-11 consider 1 tonne suppots for analysis.

DATA:

RATE ANALYSIS A. MATERIALS (for 20 uses): Sl No Perticulars 1 2 3 4 Structural steel beams Structural steel plates Tie rods & anchors For cutting sections: Oxygen gas @ 2.40 cum / t Acetylene @ 0.8 cum / t 5 For welding sections: Electrodes @ 125 Nos / t 6 For field connections: M.S.Bolts / Nuts / Washers 7 Sundries Total cost of Materials for 20 uses of supports Cost per use considering B. MACHINERY (for fabrication): Sl No Description 1 2 3 Bending machine Fuel / Energy charges Welding set Fuel / Energy charges Sundries Total hire charges of Machinery Cost per use considering Unit kg kg kg cum cum Nos. kg LS 20 uses

UNIT : Quantity 760.00 115.00 150.00 2.40 0.80 125.00 50.00 20.00

1.00 tonne Rate in Rs. Amount in Rs.

Rs: Rs:

0.00 0.00

Unit Hour Hour Hour Hour LS

Quantity 8.00 8.00 16.00 16.00 30.00 20 uses

Rate in Rs.

Amount in Rs.

Rs: Rs:

0.00 0.00

B. MACHINERY (for erection and dismantling): Sl No Description 1 2 Drilling Jumbo Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour LS

Quantity 18.00 18.00 10.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR ( for fabrication ):

63

IRR-TAW

Sl No 1 2

Description Crew for Bending machine For cutting & preparing sections: Structural steel Marker Gas cutter Fitter Turner / Driller Khalasi Helper fabrication For welding sections: Welder Helper fabrication Khalasi Total cost of Labour Cost per use considering

Unit Hour Day Day Day Day Day Day Day Day Day

Quantity 8.00 1.00 2.00 2.00 3.00 2.00 4.00 2.00 2.00 2.00 20 uses

Rate in Rs.

Amount in Rs.

Rs: Rs:

0.00 0.00

C. LABOUR ( for erection ): Sl No Description 1 2 Crew for Drilling jumbo For erection of supports: Foreman Structural steel Erector Helper erector Khalasi For dismantling of supports: Foreman Structural steel Erector Helper erector Khalasi Total cost of Labour

Unit Hour Day Day Day Day Day Day Day Day

Quantity 8.00 1.00 2.00 2.00 4.00 0.50 1.00 1.00 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery for fabrication C. Hire charges of Machinery for erection and dismantling D. Cost of Labour for fabrication E. Cost of Labour for erection and dismantling Total Add for Air and Water line @ 0.00% Add for Ventilation @ 0.00% Add for Lighting @ 0.00% Add for Ele sub-station / Demand charges @ 0.00% Total F.Add for contractor's profit and overheads on A+B+C+D+E+percentages above 0% Total cost for one tonne Rate per Tonne= (A+B+C+D+E+F) /1.00 tonne

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-3-5

Providing and fixing hard variety cut jungle wood for lagging / blocking locations in tunnel wherever required including cost of all materials, machinery, labour, fixing in position, lighting, ventilation, drainage etc complete with all leads and lifts.

DATA: 1 carpenter Cl II and 2 mazdoors are considered for cutting and fixing / cum. RATE ANALYSIS A. MATERIALS: Sl No 1 2 Perticulars Unit cum LS Total cost of Materials B. MACHINERY: Sl No UNIT : Quantity 1.05 2.00 Rs: 0.00 1.00 cum Rate in Rs. Amount in Rs.

Cut jungle wood Sundries

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

64

IRR-TAW

Drilling jumbo Fuel / Energy charges Total hire charges of Machinery

Hour Hour

2.00 2.00 Rs: 0.00

C. LABOUR: Sl No 1 2 3

Description Crew for Drilling jumbo Carpenter Cl II mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Hour Day Day

Quantity 2.00 1.00 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

Total Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per/ Cum= (A+B+C+D) /1.00 IRR-TAW-4 IRR-TAW-4-1 MASONRY WORKS : 0.00% 0.00% 0.00% 0.00% Total

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

DATA:

Providing and constructing un-coursed rubble stone masonry with approved stones from tunnel excavated muck in cement mortar 1 : 6 proportion for backfilling over cuts / slips on tunnel sides due to geological faults etc., including cost of all materials, machinery, labour, cleaning,scaffolding, packing mortar, wedging stone chips, curing, ventilation, lighting, drainage complete with lead upto 1 km and all lifts. (cement content : 95 kg/cum of masonry, Rubble stones : 0.83 cum, Stone chips : 0.13 cum, FA : 0.40 cum) For 1 cum masonry :Rubble stones : 0.83 cum Stone chips : 0.13 cum. Sand : 0.40 cum. Cement : 95 kg. Cement mortar preparation : Manual Output of 1 Mason : 5.00 cum per day

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 Perticulars Unit kg cum cum cum

UNIT : Quantity

10.00 cum Rate in Rs. Amount in Rs.

Cement Rubble stones Stone chips Sand ( screened )

950.00 830.00 1.25 4.00 TOTAL Add for scaffolding @ 2.5% Add seiniorage charges on Rubble @ Rs: (Included in material rate) Add seiniorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs: Rs: Rs:

0.00

B. MACHINERY: Sl No 1

Description

Unit Hour Hour

Quantity 1.00 1.00

Rate in Rs.

Amount in Rs.

10 hp pump ( ele ) Fuel / energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 Crew for Pump work inspector Mason Class-I Mason Class-II

Description

Unit Hour Day Day Day

Quantity 1.00 1.00 1.00 2.00

Rate in Rs.

Amount in Rs.

65

IRR-TAW

mazdoor for sorting out rubble in dump yard for conveying rubble for preparing mortar for loading mortar pans for laying & packing mortar for washing rubble / finishing / curing for conveying mortar / chips

Day Day Day Day Day Day Day

Add for labour for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seiniorage charges B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for 10 Rate per cum= (A+B+C+D) /10 IRR-TAW-5 IRR-TAW-5-1 REINFORCEMENT & CONCRETE WORKS : 0.00% 0.00% 0.00% 0.00%

1.00 2.00 2.00 1.00 4.00 1.00 3.00 TOTAL 0.0%

Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00

Total

Total

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

Providing, fabricating and placing in position reinforcement steel for tunnel RCC works including cleaning, straightening, cutting, bending, hooking, lapping / welding joints wherever required, tying with 1.25 mm dia.soft annealed steel wire, including cost of all materials, labour, machinery, ventilation, lighting, drainage etc.,complete with initial lead upto 1 km and all lifts. No welding of reinforcement bars is considered since the diameter of bars for tunnel RCC works will be generally less than 32 mm. As concrete will be placed by pneumatic placer, the reinforcement bars have to be held regidly in place to prevent displacement due to shooting effect of concrete. This requires about 50 percent more binding wire compared to locations where concrete placement is by manual labour. Labour requirement per tonne: Cleaning and straightening : 2 Bar benders & 2 mazdoors Marking, bending and stacking : 3 Bar benders & 6 mazdoors Placing in position and tying : 3 Bar benders & 6 mazdoors Checking, correcting & : misc. works 1 Bar benders & 1 mazdoors

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Perticulars Unit tonne kg LS

UNIT : Quantity 1.06 13.50 5.00

1.00 tonne Rate in Rs. 0.00 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00 0.00

Rein.Steel with 5 % wastage Binding wire 1.25 mm dia Sundries ( chairs / spacers etc ) Total cost of Materials

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 Bar bender mazdoor

Description

Unit Day Day

Quantity 9.00 15.00

Total cost of Labour ABSTRACT: A. Cost of Materials Rs:

Rate in Rs. 0.00 0.00 Rs: 0.00

Amount in Rs. 0.00 0.00 0.00

66

IRR-TAW

B. Hire charges of Machinery C. Cost of Labour Total Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for one Rate per Mtonne.= (A+B+C+D) /1.00 0.00% 0.00% 0.00% 0.00% Total

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% tonne tonne

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-5-2

DATA:

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates crushed from tunnel excavated muck for filling and levelling over-cuts in bed due to geological faults etc., including cost of all materials, machinery, labour, cleaning bed, batching, mixing, conveying and laying, levelling, compacting, finishing, curing, lighting, ventilation, drainage etc., complete with initial lead upto 1 km and all lifts. ( Cement content : 190 kg / cum, CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum, Superplasticizer 0.4% by wt. of cement) For 1 cum CC :Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum Cement content : 190 kg Super plasticizer : 0.76 kg RATE ANALYSIS A. MATERIALS: Sl No 1 2 Perticulars Unit UNIT : Quantity 28.00 cum Rate in Rs. Amount in Rs.

3 4 5

Cement for mix kg 5320.00 Coarse aggregate 40-20 mm cum 12.60 Coarse aggregate 20-10 mm cum 7.56 Coarse aggregate 10 mm below cum 5.04 Fine aggregate ( screened ) cum 11.20 Super Plasticizer kg 21.28 Sundries LS 2.00 Add seiniorage charges on CA @ Rs:( Included in material rate ) Add seiniorage charges on FA @ Rs:( Included in material rate ) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4 5

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 8.00 16.00 16.00 8.00 8.00 8.00 8.00 2.00

Rate in Rs.

Amount in Rs.

Batching plant 2 x 1 cum Fuel / Energy charges Agitator car 2 cum Fuel / Energy charges 10 hp pump ( ele ) Fuel / Energy charges Needle vibrator 40 mm dia Fuel / Energy charges Sundries Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Batching plant Crew for Agitator car Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for cleaning bed for loading material bin ( Cement ) for miscellaneous works at BP for laying concrete for conveying laying concrete for cleaning bed

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day Day

Quantity 8.00 16.00 8.00 8.00 1.00 1.00 2.00 3.00 2.00 7.00 14.00 2.00

Rate in Rs.

Amount in Rs.

67

IRR-TAW

for washing CA / curing Day Total cost of Labour ABSTRACT: A. Cost of Materials including seiniorage charges B. Hire charges of Machinery C. Cost of Labour Total Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for 28 Rate per/ cum= (A+B+C+D) /28 0.00% 0.00% 0.00% 0.00% Total

2.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-5-3

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard, graded aggregates crushed from tunnel muck for kerb and bed lining including cost of all materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting, drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts. ( Cement content 270 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Erection & dismantling shuttering : 2 Fitters, 1 Carpentor Cl-II and 5 mazdoors erect 50 sqm shuttering / day. Concrete mix details for 50-70 mm slump: For 1 cum CC :Coarse aggregates : 0.90 cum(1300 kg) Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum ( 700 kg ) Cement : 270 kg Super plasticizer : 1.08 kg Requirement of materials per cum of CC: RATE ANALYSIS UNIT : 28.00 cum A. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount in Rs. in Rs. 1 Cement 43 Gr kg 7560.00 Cement for incidentals @ 1 kg / cum kg 28.00 2 Fine aggregate ( screened ) cum 11.20 3 Coarse aggregate 40-20 mm cum 12.60 Coarse aggregate 20-10 mm cum 7.56 Coarse aggregate 10-4.75 mm cum 5.04 4 Super plasticiser kg 30.24 5 Use rate of shuttering for kerb / bed sqm 28.00 6 Sundries LS 2.00 Add seiniorage charges on CA @ Rs:( Included in material rate ) Rs: 0.00 Add seiniorage charges on FA @ Rs:( Included in material rate ) Rs: 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No 1 2 3 4 5

DATA:

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 8.00 16.00 16.00 8.00 8.00 8.00 8.00 5.00

Rate in Rs.

Amount in Rs.

Batching plant 2 x 1.00 cum Fuel / Energy charges Agitator car 2 cum ( 2 Nos ) Fuel / Energy charges Needle Vibrator Fuel / Energy charges Pump 10 hp ( Ele ) Fuel / Energy charges Sundries Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1

Description Crew for Batching plant

Unit Hour

Quantity 8.00

Rate in Rs.

Amount in Rs.

68

IRR-TAW

2 3 4 5

6 7 8 9

Crew for Agitator car Hour Crew for vibrator Hour Crew for pump Hour For scaling & cleaning bed Hammerman Day mazdoor Day For loading cement to BP bin mazdoor Day For miscellaneous work at BP mazdoor Day For wetting C.A & curing mazdoor Day Laying concrete for kerb/ invert Mason Cl I Day Mason Cl II Day mazdoor Day work inspector Day 10 Labour charges for shuttering sqm Total cost of Labour ABSTRACT: A. Cost of Materials including seiniorage charges B. Hire charges of Machinery C. Cost of Labour Total Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per/ cum= (A+B+C+D) /28 0.00% 0.00% 0.00% 0.00% Total

16.00 8.00 8.00 2.00 6.00 3.00 2.00 2.00 2.00 2.00 21.00 1.00 28.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-5-4

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard, graded aggregates crushed from tunnel muck for sides and arch lining including cost of all materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting, drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts. ( Cement content 270 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Perticulars Unit kg kg cum cum cum cum kg sqm sqm

UNIT : Quantity 12960.00 48.00 19.20 21.60 12.96 8.64 51.84 6.00 100.00

48.00 cum Rate in Rs. Amount in Rs.

4 5 6

Cement 43 Gr Cement for incidentals @ 1 kg / cum Fine aggregate ( screened ) Coarse aggregate 40-20 mm Coarse aggregate 20-10 mm Coarse aggregate 10-4.75 mm Super plasticiser Use rate of end shuttering Use rate of steel gantry

69

IRR-TAW

Sundries ( placer pipe etc ) LS 5.00 Add seiniorage charges on CA @ Rs:( Included in material rate ) Add seiniorage charges on FA @ Rs:( Included in material rate ) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 16.00 12.00 12.00 12.00 32.00 32.00 16.00 16.00 8.00 8.00 8.00 8.00 5.00

Rate in Rs.

Amount in Rs.

Air compressor ( Ele ) 8.5 cmm Fuel / Energy charges @ 75 % load Batching plant 2 x 1.00 cum Fuel / Energy charges Agitator car 2 cum ( 2 Nos ) Fuel / Energy charges Concrete placer pump Fuel / Energy charges Needle Vibrator / Shutter vibrator Fuel / Energy charges Pump 10 hp ( Ele ) Fuel / Energy charges Sundries Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description

Unit

Quantity 16.00 16.00 32.00 16.00 8.00 8.00 0.50 1.00 0.50 0.50 1.00 3.00 1.00 0.50 0.50 0.50 1.00 3.00 1.00 5.00 2.00 6.00 3.00 9.00 3.00 3.00

Rate in Rs.

Amount in Rs.

10 11 12 13

14

Crew charges for Air compressor Hour Crew charges for Batching plant Hour Crew charges for Agitator car Hour Crew charges for placer pump Hour Crew charges for vibrator Hour Crew charges for Pump Hour For scaling & cleaning Stone chiseller Cl II Day mazdoor Day For dismantling / Laying track Surveyer Day Fitter shuttering Day Helper shuttering 2 x 0.5 Day Khalasi 6 x 0.5 Day mazdoor 2 x 0.5 Day For Moving / Positioning gantry Surveyer Day Foreman Day Fitter shuttering Day Helper shuttering 2 x 0.5 Day Khalasi 6 x 0.5 Day mazdoor 2 x 0.5 Day For loading cement to BP bin mazdoor Day For miscellaneous works of BP mazdoor Day For Erection/Dismantling bulk head sqm For Laying concrete by placer Masom Cl I Day mazdoor Day work inspector Day For wetting C.A / Curing etc mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seiniorage charges B. Hire charges of Machinery C. Cost of Labour Total Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ 0.00% 0.00% 0.00% 0.00% Total

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

70

IRR-TAW

D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for 48 Rate per/ cum= (A+B+C+D) /48 IRR-TAW-6 IRR-TAW-6-1 DRILLING & GROUTING WORKS :

0% cum cum

Rs: Rs: Rs:

0.00 0.00 0.00

Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling using jack hammer or stooper drills as directed to specified depth for consolidation / contact grouting including cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainage and all other ancillary operations etc., complete.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 Perticulars Unit Rm 10% Hour Hour LS 32.00 32.00 3.00 Rs: 0.00 UNIT : Quantity 100.00 100.00 Rm Rate in Rs. Amount in Rs.

Use rate of drill rod Reconditioning charges @ Use rate of air hose 4 Nos Use rate of water hose 4 Nos Sundries Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5 6

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 8.00 4.00 4.00 32.00 32.00 32.00 32.00 8.00 8.00 5.00

Rate in Rs.

Amount in Rs.

Air compressor 15 cmm ( ele ) Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Jack hammer Fuel / Energy charges Pusher leg Fuel / Energy charges Drilling jumbo Fuel / Energy charges Sundries Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5

Description Crew charges for Air compressor Crew charges for Pump Crew charges for Jack Hammer Crew charges for Drilling Jumbo mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per/ Rmt.= (A+B+C+D) /100

Unit Hour Hour Hour Hour Day

Quantity 8.00 4.00 32.00 8.00 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% Rm Rm

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-6-2

Grouting cement slurry in grout holes under specified pressure for consolidation / contact grouting including cost of all materials, machinery, labour, redrilling wherever necessary, ventilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1 km and all lifts.

71

IRR-TAW

DATA:

In contact zones, perticularly in crown portion, the grout intake will be heavy due to inadequate packing of concrete during placement of concrete by placer pump. The average grout intake in the contact zone is considered at 75 kg per metre. Beyond contact zone the grout intake may vary from 25 kg per metre to 50 kg per metre depending on the extent of opening of joints in rock during / after excavation. The average grout intake for consilidation /contact grouting is considered at 50 kg per metre. The average progress of grouting per shift is considered at 1500 kg.

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 Perticulars Unit tonne Hour Hour LS

UNIT : Quantity 1.50 8.00 8.00 2.00

1.50 tonne Rate in Rs. Amount in Rs.

Cement Use rate of grouting hose 50 m Use rate of water hose 50 m Sundries Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1 2 3 4

Description

Unit Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 8.00 2.00 2.00 2.00 2.00 2.00

Rate in Rs.

Amount in Rs.

Grouting machine Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Drilling jumbo Fuel / Energy charges Sundries Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4

Description Crew for Grout pump Crew for pump Crew for Drilling jumbo mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per/ Mtonne..= (A+B+C+D) /1.50

Unit Hour Hour Hour Day

Quantity 8.00 2.00 2.00 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

Total 0.00% 0.00% 0.00% 0.00% Total

0% tonne tonne

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-TAW-6-3

Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete in tunnel by percussion drilling using waggon drill or other suitable drilling equipment including cost of all materials, machinery, labour, ventilation, lighting, drainage etc., complete. Generally rate of drilling in rock or concrete inside tunnel will be less compared to drilling in open area. RATE ANALYSIS UNIT : 120.00 Rm A. MATERIALS: Sl No Perticulars Unit Quantity Rate Amount in Rs. in Rs. 1 Use rate of cross bit 75 mm dia Rm 120.00 2 Use rate of air hose 20 m Hour 16.00 3 Use rate of water hose 20 m Hour 16.00

DATA:

72

IRR-TAW

Use rate of extension rods Total cost of Materials

Rm

120.00 Rs: 0.00

B. MACHINERY: Sl No 1 2 3 4

Description

Unit Hour Hour Hour Hour Hour Hour LS

Quantity 16.00 16.00 8.00 8.00 6.00 6.00 2.00

Rate in Rs.

Amount in Rs.

Waggon drill Fuel / Energy charges Air compressor 15 cmm ( ele ) Fuel / Energy charges Pump 10 hp ( ele ) Fuel / Energy charges Sundries Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4

Description Crew for Waggon drill Crew for Air compressor Crew for Pump mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for Air and Water line @ Add for Ventilation @ Add for Lighting @ Add for Ele sub-station / Demand charges @ D.Add for contractor's profit and overheads on A+B+C+percentages Total cost for

Unit Hour Hour Hour Day

Quantity 16.00 8.00 6.00 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

Total 0.00% 0.00% 0.00% 0.00% Total 0% Rm

Rate per/ R.Mt.= (A+B+C+D) /120.00

Rm

Rs:

0.00

73

IRR-CAW

Chapter III Standard data


Index- code

IRR-CAW

CANAL AND ALLIED WORKS

IRR-CAW-1 IRR-CAW-1-1

EXCAVATION WORKS : Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of embankment, filter drains / catch water drains etc., including dressing bed and sides to required level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in dump area or for the formation of service road / embankment as directed etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 2 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 925.00 cum Rate in Rs. Amount in Rs.

Description Shovel 0.85 cum capacity Fuel / Energy charges Tippers 5 cum capacity 6 Nos Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour

Quantity 8.00 8.00 48.00 48.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4

Description Crew for Shovel Crew for Tipper work inspector mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Rate per cum=(A+B+C+D) /925

Unit Hour Hour Day Day

Quantity 8.00 48.00 1.00 30.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total

IRR-CAW-1-2

Excavation in all kinds of soil including boulders upto 0.30 m dia for field channels, seating of embankment for field channels etc., including dressing of bed and sides to required profile, cost of all materials, machinery, labour, placing the excavated stuff for formation of service road / embankment as directed etc., complete with lead upto 10 m and lift upto 3 m. Average output of 2 mazdoors assumed at 5 cum / day for trimming

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit

UNIT : Quantity 0.00 0.00

440.00 cum Rate in Rs. Amount in Rs.

Rs:

0.00

Description Shovel 0.50 cum capacity

Unit Hour

Quantity 8.00

Rate in Rs.

Amount in Rs.

74

IRR-CAW

Fuel / Energy charges Total hire charges of Machinery C. LABOUR: Sl No 1 2 3

Hour

8.00 Rs: 0.00

Description Crew for Shovel work inspector mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /440

Unit Hour Day Day

Quantity 8.00 1.00 17.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 440.00 cum

IRR-CAW-1-3

Excavation in ordinary rock without blasting including boulders above 0.30 m upto 0.6 m dia. for canals, seating of embankment, filter drain / catch water drains etc., including dressing of bed and sides to required level and profile, cost of all materials, machinery, labour, placing the excavated soft rock neatly in dump area or for formation of service road as directed etc., complete with lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 2 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 630.00 cum Rate in Rs. Amount in Rs.

Description Shovel 0.85 cum capacity Fuel / Energy charges Tippers 5 cum capacity 5 Nos Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour

Quantity 8.00 8.00 40.00 40.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5

Description Crew for Shovel Crew for Tipper work inspector Crowbarman mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /630

Unit Hour Hour Day Day Day

Quantity 8.00 40.00 1.00 11.00 22.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 630.00 cum

IRR-CAW-1-4

Excavation in ordinary rock without blasting including boulders above 0.3 m upto 0.60 m dia. for field channels, seating of embankment for field channels etc., including dressing of bed and sides to required profile, cost of all materials, machinery, labour, placing the excavated stuff for formation of service road as directed etc.,complete with lead upto 10 m and lift upto 3 m.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Unit UNIT : Quantity 0.00 265.00 cum Rate in Rs. Amount in Rs.

75

IRR-CAW

0.00 Total cost of Materials B. MACHINERY: Sl No 1 Rs: 0.00

Description Shovel 0.50 cum capacity Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour

Quantity 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4

Description Crew for Shovel work inspector Crowbarman mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /265

Unit Hour Day Day Day

Quantity 8.00 1.00 5.00 11.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 265.00 cum

IRR-CAW-1-5

Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. for canals, seating of embankment, filter drain / catch water drains etc., including dressing bed and sides to required level and profile, cost of all materials, machinery, labour, placing the excavated rock in dump area or for formation of service road as directed etc., complete with lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 particulars Use rate of drill rod 1.5 m length Reconditioning charges @ Use rate of 50 m air hose 2 Nos Explosive small dia ( Kelvex-220 ) Ordinary detonators Electric detonators Fuse coil Sundries Total cost of Materials Unit Rm 10% Hour kg Nos Nos Rm LS UNIT : Quantity 316.00 24.00 161.00 12.00 215.00 520.00 5.00 Rs: 0.00 805.00 cum Rate in Rs. Amount in Rs.

B. MACHINERY: Sl No 1 2 3 4

Description Shovel 0.85 cum capacity Fuel / Energy charges Tippers 5 cum capacity 5 Nos. Fuel / Energy charges Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Jack hammers 3 Nos. Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 40.00 40.00 12.00 12.00 39.00 39.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10

Description Crew for Shovel Crew for Tipper Crew for Air compressor Crew for Jack hammer work inspector Blaster Helper blaster Crowbarman Stone breaker mazdoor

Unit Hour Hour Hour Hour Day Day Day Day Day Day

Quantity 8.00 40.00 12.00 39.00 1.00 1.00 1.00 16.00 16.00 32.00

Rate in Rs.

Amount in Rs.

76

IRR-CAW

Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /805 0% 805.00 cum

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

IRR-CAW-1-6 (a)

Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for canals, seating of embankment, filter drain / catch water drains etc., including levelling the bed by removing all projections by hammering / chiselling, cost of all materials, machinery, labour, placing the excavated rock neatly in approved dump area and levelling the same as directed etc., complete with initial lead upto 1 km and all lifts. i ) The rate under this item shall be adopted for canals designed for carrying capacity of less than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m. ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever required. Assume 10.40 m width of canal at the bench level and 1.25 m average depth of cutting. Assume side slopes of 0.5 horizontal to 1 vertical. Consider average 1.0 m wide excavation on either side under line drilling and smooth blasting to obtain neat excavated slopes. Rate analysis prepared separately for smooth blasting quantity.

Note:

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Use rate of drill rod 1.5 m length Reconditioning charges @ Unit Rm 10%

UNIT : Quantity 85.00

68.00 cum Rate in Rs. Amount in Rs.

77

IRR-CAW

2 3 4 5 6

Use rate of 50 m air hose 2 Nos. Explosive small dia. (Kelvex-220 ) Ordinary detonators Electric detonators Fuse coil 7 Sundries Total cost of Materials

Hour kg Nos Nos Rm LS

13.00 21.20 4.00 59.00 90.00 2.00 Rs: 0.00

B. MACHINERY: Sl No 1 2 3 4 5

Description

Unit

Quantity 1.10 1.10 0.25 0.25 4.40 4.40 6.50 6.50 13.00 13.00

Rate in Rs.

Amount in Rs.

Shovel 0.85 cum capacity Hour Fuel / energy charges Hour Angle dozer 90 hp Hour Fuel / Energy charges Hour Tippers 5 cum capacity 4 Nos. Hour Fuel / Energy charges Hour Air compressor 8.5 cmm ( diesel ) 1 Nos Hour Fuel / Energy charges Hour Jack hammers 2 Nos. Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11

Description Crew for Shovel Crew for Dozer Crew for Tipper Crew for Air compressor Crew for Jack hammer work inspector Blaster Helper blaster Crowbarman Stone breaker mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /68

Unit Hour Hour Hour Hour Hour Day Day Day Day Day Day

Quantity 1.10 0.25 4.40 6.50 13.00 0.50 1.00 1.00 0.50 0.50 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 68.00 cum

IRR-CAW-1-7 (b)

Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved controlled blasting methods for canals, cut-off trench of embankment, filter / catch-water drains etc., including controlling fly-rock by muffling arrangements such as placing 50 x 50 mm opening chain link mesh or waste tyres and sand bags, monitoring ground vibrations at specified locations, costof all materials, machinery, labour, placing excavated rock neatly in approved dump area or other place as directed etc., complete with lead upto 1 km and all lifts. i ) The rate under this item shall be adopted for canals designed for carrying capacity of less than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m. ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations is required. Work requires: - use of delay detonators to reduce ground vibrations. - monitoring and recording ground vibrations.. - conducting trial studies for drilling and blasting method to be adopted to avoid damages to near-by structures. - covering blasting area with chain link mesh or waste conveyor belts or waste tyres and sand bags to prevent flying of rock fragments during blasting. Assume 10.40 m width of canal at the bench level and 1.25 m average depth of cutting. Assume side slopes of 0.5 horizontal to 1 vertical. Consider average 1.0 m wide excavation on either side under line drilling and smooth blasting to obtain neat excavated slopes. Rate analysis prepared separately for smooth blasting quantity.

Note:

DATA:

78

IRR-CAW

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 9 particulars Unit

UNIT : Quantity

68.00 cum Rate in Rs. Amount in Rs.

Use rate of drill rod 1.5 m length Rm 85.00 Reconditioning charges @ 10% Use rate of 50 m air hose 2 Nos. Hour 13.00 Use rate of wire mesh sqm 94.00 Use rate of sand bag Nos 98.00 Explosive small dia. (Kelvex-220 ) kg 21.20 Ordinary detonators Nos 4.00 Electric delay detonators Nos 59.00 Fuse coil Rm 90.00 Sundries LS 2.00 Seignorage charges for Sand(included in the material cost) Total cost of Materials

Rs:

0.00 0.00

B. MACHINERY: Sl No 1 2 3 4 5

Description

Unit

Quantity 1.10 1.10 0.25 0.25 4.40 4.40 6.50 6.50 13.00 13.00

Rate in Rs.

Amount in Rs.

Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Angle dozer 90 hp Hour Fuel / Energy charges Hour Tippers 5 cum capacity 3 Nos. Hour Fuel / Energy charges Hour Air compressor 8.5 cmm ( diesel ) 1 No Hour Fuel / Energy charges Hour Jack hammers 2 Nos. Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No

Description

Unit

Quantity

Rate

Amount

79

IRR-CAW

in Rs. 1 2 3 4 5 6 7 8 9 10 11 Crew for Shovel Hour Crew for Angle dozer Hour Crew for Tipper Hour Crew for Air compressor Hour Crew for Jack hammer Hour work inspector Day Blaster Day Helper blaster Day Stone chiseller Cl - II Day Stone breaker Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour 1.10 0.25 4.40 6.50 13.00 0.50 0.50 0.50 0.50 0.50 3.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs:

in Rs.

0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Add for blasting studies & monitoring vibrations etc 0.00% Total D.Add for contractor's profit and overheads on A+B+C+percentage above Total cost for Rate per cum=(A+B+C+D) /68

0% 68.00 cum

Rs: Rs: Rs:

0 0.00 0.00

IRR-CAW-1-8 ( c)

Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing canal sides neatly on either side to required profile by line drilling and smooth blasting including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in dump area or other place as directed, cost of all materials, machinery, labour etc., complete with lead upto 1 km and all lifts. i) For excavation of canal below free board level combination of normal / controlled blasting and line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose of payment 1 m width of excavation on either side shall be treated as excavation by line drilling and smooth blasting and remaining portion shall be treated as excavation by normal / controlled blasting as the case may be. ii ) The rate under this item shall be adopted for canals designed for carrying capacity of less than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m. iii ) The rate includes controlling fly-rock wherever required. iv ) The rate under this item shall be paid only on ascertaining that the excavated face has come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for inspection and are spaced at specified interval. v ) In case, where the above criteria is not fulfilled payment shall be restricted to rate provided for excavation by normal blasting or controlled blasting as the case may be. Work requires: - drilling holes at closer interval along the final excavation lines on either side of canal with light blasting to achieve neat side slopes.

Note:

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Use rate of drill rod 1.5 m length Reconditioning charges @ Use rate of 50 m air hose 2 Nos. Explosive small dia. (Kelvex-220 ) Unit Rm 10% Hour kg

UNIT : Quantity 63.00 10.00 3.50

17.50 cum Rate in Rs. Amount in Rs.

80

IRR-CAW

4 5 6

Electric delay detonators Fuse coil Sundries Total cost of Materials

Nos Rm LS

22.00 20.00 1.00 Rs: 0.00

B. MACHINERY: Sl No 1 2 3 4

Description

Unit

Quantity 0.28 0.28 1.12 1.12 5.00 5.00 10.00 10.00

Rate in Rs.

Amount in Rs.

Shovel 0.85 cum capacity Hour Fuel / Energy charges Hour Tippers 5 cum capacity 4 Nos. Hour Fuel / Energy charges Hour Air compressor 8.5 cmm ( diesel ) 1 Nos Hour Fuel / Energy charges Hour Jack hammers 2 Nos. Hour Fuel / Energy charges Hour Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10

Description Crew for Shovel Crew for Tipper Crew for Air compressor Crew for Jack hammer work inspector Blaster Helper blaster Stone breaker Stone chiseller Cl - II mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Day Day Day Day Day Day

Quantity 0.50 1.12 5.00 10.00 0.50 0.50 0.50 0.50 0.50 1.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Add for blasting studies & monitoring vibrations etc 0.00% Total D.Add for contractor's profit and overheads on A+B+C+percentage above Total cost for Rate per cum=(A+B+C+D) /17.50

0% 17.50 cum

Rs: Rs: Rs:

0 0.00 0.00

IRR-CAW-1-9 (a)

Excavation in hard rock by blasting including boulders above 1.2 m dia. for canals, seating embankment etc., including levelling bed by removing all projections by hammering / chiselling, cost of all materials, machinery, labour, placing the excavated rock neatly in approved dump area and levelling the same as directed etc.,complete with initial lead upto 1 km and all lifts. i ) The rate under this item shall be adopted for canals designed for carrying capacity of more than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m. ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever required.

Note:

DATA

81

IRR-CAW

The rate analysis is for excavation excluding smooth blasting area. RATE ANALYSIS UNIT : 386.00 cum A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 9 particulars Unit Quantity 104.00 104.00 12.00 10.50 1.00 38.00 155.00 35.00 4.00 20.00 145.00 20.00 5.00 Rs: 0.00 Rate in Rs. Amount in Rs.

Use rate of T.C bit 100 mm dia Rm Use rate of Extension rod with coupling sleeve Rm Use rate of Jack hammer drill rod 1.5 Rm m reconditioning charges @ 10% Use rate of 50 m air hose for waggonHour drill Use rate of 25 m air hose for JH 2 Nos Hour High strength ANFO booster kg ANFO kg Diesel oil ltr Explosive small dia ( Kelvex-220 ) kg Ordinary detonators Nos 10 D-cord Rm 11 Detonating fuse coil Rm 12 Sundries LS Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5 6

Description Tippers 5 cum capacity Fuel / Energy charges Shovel 0.85 cum capacity Fuel / Energy charges Angle dozer Fuel / Energy charges Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Waggon drill Fuel / Energy charges Jack hammer Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 24.84 24.84 6.21 6.21 2.00 2.00 11.50 11.50 10.50 10.50 2.00 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Tipper Crew for Shovel Crew for Dozer Crew for Air compressor Crew for Waggon drill Crew for Jack hammer work inspector Blaster Helper blaster 10 Stone chiseller Cl - II

Unit Hour Hour Hour Hour Hour Hour Day Day Day Day

Quantity 24.84 6.21 2.00 11.50 10.50 2.00 2.00 1.00 1.00 1.00

Rate in Rs.

Amount in Rs.

82

IRR-CAW

11 Stone breaker 12 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /386

Day Day

1.00 3.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 386.00 cum

IRR-CAW-1-10 (b)

Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved controlled blasting methods for canals, cut-off trench of embankment etc., including controlling fly-rock by muffling arrangements such as placing 50 x 50 mm opening chain link mesh or waste tyres and sand bags, monitoring ground vibrations at specified locations, cost of all materials, machinery, labour, placing excavated rock neatly in approved dump area or other place as directed etc., complete with lead upto 1 km and all lifts. i ) The rate under this item shall be adopted for canals designed for carrying capacity of more than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m. ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations is required. Work requires: - covering blasting area with chain link mesh or conveyor belts or waste tyres and sand bags to prevent flying of rock fragments during blasting. - use of shock tube detonators / trunk line delays to reduce ground vibrations. - monitoring and recording ground vibrations. - conducting trial studies for drilling and blasting method to be adopted to avoid damages to near-by structures.

Note:

DATA

83

IRR-CAW

The rate analysis is for excavation excluding smooth blasting area. RATE ANALYSIS UNIT : A. MATERIALS: Sl No particulars Unit Quantity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Use rate of T.C bit 100 mm dia Rm Use rate of Extension rod with coupling sleeve Rm Use rate of Jack hammer drill rod 1.6 Rm m reconditioning charges @ 10% Use rate of 50 m air hose 50 mm 1 No. Hour Use rate of 25 mm air hose 2 Nos Hour High strength ANFO booster kg ANFO kg Diesel oil ltr Explosive small dia ( Kelvex-220 ) kg Ordinary detonators Nos Shock tube detonators Rm Noiseless trunk line delays Nos Detonating fuse coil Rm Use rate of chain link wire mesh sqm Use rate of sand bag Nos Sundries LS Total cost of Materials 104.00 104.00 12.00 10.50 2.00 38.00 155.00 35.00 4.00 20.00 120.00 12.00 20.00 132.00 110.00 20.00

386.00 cum Rate in Rs. Amount in Rs.

Rs:

0.00

B. MACHINERY: Sl No 1 2 3 4 5 6

Description Tippers 5 cum capacity Fuel / Energy charges Shovel 0.85 cum capacity Fuel / Energy charges Angle dozer Fuel / Energy charges Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Waggon drill Fuel / Energy charges Jack hammer Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 30.00 30.00 10.00 10.00 2.00 2.00 12.50 12.50 11.50 11.50 2.00 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Tipper Crew for Shovel Crew for Dozer Crew for Air compressor Crew for Waggon drill Crew for Jack hammer work inspector Blaster Helper blaster 10 Stone chiseller Cl - II 11 Stone breaker 12 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Hour Hour Day Day Day Day Day Day

Quantity 30.00 10.00 2.00 12.50 11.50 2.00 1.50 0.50 0.50 1.00 1.00 5.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Add for blasting studies & monitoring vibrations etc 0.00% Total D.Add for contractor's profit and overheads on A+B+C+percentage above Total cost for Rate per cum=(A+B+C+D) /386

0% 386.00 cum

Rs: Rs: Rs:

0 0.00 0.00

84

IRR-CAW

IRR-CAW-1-11 ( c)

Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing canal sides neatly on either side to required profile by line drilling and smooth blasting including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in dump area or other place as directed, cost of all materials, machinery, labour etc., complete with lead upto 1 km and all lifts. i ) For excavation of canal below free board level combination of normal / controlled blasting and line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose of payment 1 m width of excavation on either side shall be treated as excavation by line drilling and smooth blasting and remaining portion shall be treated as excavation by normal / controlled blasting as the case may be. ii ) The rate under this item shall be adopted for canals designed for carrying capacity of more than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m. iii ) The rate includes controlling fly-rock wherever required. iv ) The rate under this item shall be paid only on ascertaining that the excavated face has come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for inspection and are spaced at specified interval. v ) In case, where the above criteria is not fulfilled payment shall be restricted to rate provided for excavation by normal blasting or controlled blasting as the case may be. Work requires: - drilling holes at closer interval near final excavation lines on either side of canal and light blasting to achieve fairly neat side slopes.

Note:

DATA

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 9 10 11 12 13 particulars Unit

UNIT : Quantity 121.00 121.00 3.00 12.00 0.50 5.00 19.00 4.50 1.00 5.00 70.00 4.00 10.00 2.00

97.00 cum Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Use rate of T.C bit 100 mm dia Rm Use rate of Extension rod with coupling sleeve Rm Use rate of Jack hammer drill rod 1.6 Rm m reconditioning charges @ 10% Use rate of 50 m air hose 50 mm 1 No. Hour Use rate of 25 mm air hose 2 Nos Hour High strength ANFO booster kg ANFO kg Diesel oil ltr Explosive small dia ( Kelvex-220 ) kg Ordinary detonators Nos Detonating shock tube Rm Noiseless trunk line delays Nos Fuse coil Rm Sundries LS Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5 6

Description Tippers 5 cum capacity Fuel / Energy charges Shovel 0.85 cum capacity Fuel / Energy charges Angle dozer Fuel / Energy charges Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Waggon drill Fuel / Energy charges Jack hammer

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 6.24 6.24 1.56 1.56 0.50 0.50 13.45 13.45 13.20 13.20 0.50

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

85

IRR-CAW

Fuel / Energy charges Total hire charges of Machinery C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Hour

0.50

0.00 Rs:

0.00 0.00

Description Crew for Tipper Crew for Shovel Crew for Dozer Crew for Air compressor Crew for Waggon drill Crew for Jack hammer work inspector Blaster Helper blaster 10 Stone breaker 11 Stone chiseller Cl- II 12 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Hour Hour Day Day Day Day Day Day

Quantity 5.24 1.56 0.50 13.45 13.45 0.50 0.50 0.50 0.50 1.00 1.00 2.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Add for blasting studies & monitoring vibrations etc 0.00% Total D.Add for contractor's profit and overheads on A+B+C+percentage above Total cost for Rate per cum=(A+B+C+D) /97 IRR-CAW-2 IRR-CAW-2-1

0% 97.00 cum

Rs: Rs: Rs:

0 0.00 0.00

EMBANKMENT WORKS USING BORROW AREA SOIL : Providing impervious hearting embankment with selected soil from approved borrow areas in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by sheep / pad foot roller etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill Seioniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs. Rs: 0.00 0.00 412.80 cum Rate in Rs. Amount in Rs.

Description Angle dozer Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 4 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3.40 3.40 8.00 8.00 32.00 32.00 2.00 2.00 4.00 4.00 5.10 5.10 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4

Description Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump

Unit Hour Hour Hour Hour

Quantity 3.40 8.00 32.00 2.00

Rate in Rs.

Amount in Rs.

86

IRR-CAW

5 6 7 8

Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /412.80

4.00 5.10 2.00 4.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 412.80 cum

IRR-CAW-2-2

Providing impervious hearting embankment with selected soil from approved borrow areas in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 95 percent or as stipulated by sheep / pad foot roller etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 0.00 412.80 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.5 cum Fuel / Energy charges Tippers 5 cum Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3.40 3.40 8.00 8.00 32.00 32.00 2.00 2.00 4.00 4.00 4.18 4.18 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 3.40 8.00 32.00 2.00 4.00 4.18 2.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /412.80

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 412.80 cum

IRR-CAW-2-3

Providing semi-pervious / pervious casing embankment using soil from approved borrow area

87

IRR-CAW

in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sortingout, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 98 percent or as stipulated by sheep's / pad foot roller etc., complete with initial lead upto 1 km and all lifts. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 0.00 412.80 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 3 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3.40 3.40 8.00 8.00 32.00 32.00 2.00 2.00 4.00 4.00 5.10 5.10 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 3.40 8.00 32.00 2.00 4.00 5.10 2.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /412.80

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 412.80 cum

IRR-CAW-2-4

Providing semi-pervious / pervious casing embankment using soil from approved borrow area in layers of 25cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sortingout, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent or as stipulated by sheep's / pad foot roller etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 0.00 412.80 cum Rate in Rs. Amount in Rs.

88

IRR-CAW

Sl No 1 2 3 4 5 6 7

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.5 cum Fuel / Energy charges Tippers 5 cum Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3.40 3.40 8.00 8.00 32.00 32.00 2.00 2.00 4.00 4.00 4.17 4.17 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 3.40 8.00 32.00 2.00 4.00 4.00 4.17 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /412.80

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 412.80 cum

IRR-CAW-2-5

Providing semi-pervious / pervious casing embankment using soil from approved borrow area in layers of 25cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sortingout, transporting, spreading in layer of specified thickness, breaking clods, sectioning, compacting each layer without watering to density control of not less than 95 percent or as stipulated by sheep's foot / pad foot roller etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 0.00 412.80 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 3 Nos. Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3.40 3.40 8.00 8.00 32.00 32.00 4.17 4.17 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description Crew for Dozer Crew for Shovel

Unit Hour Hour

Quantity 3.40 8.00

Rate in Rs.

Amount in Rs.

89

IRR-CAW

3 4 5 6

Crew for Tipper Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /412.80

32.00 4.17 2.00 4.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 412.80 cum

IRR-CAW-2-6

Providing hearting / casing embankment with homogeneous soil from approved borrow areas in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by sheep / pad foot roller etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 677.28 cum Rate in Rs. Amount in Rs.

Description Angle dozer Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 6 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 6.06 6.06 8.00 8.00 48.00 48.00 3.00 3.00 6.00 6.00 7.53 7.53 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 6.06 8.00 48.00 3.00 6.00 7.53 2.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /677.28

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 677.28 cum

IRR-CAW-2-7

Providing hearting / casing embankment with homogeneous soil from approved borrow areas in layers of 25 cm before compaction including cost of all materials, machinery,

90

IRR-CAW

labour, all operations such as excavation, sorting out, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 95 percent or as stipulated by sheep / pad foot roller etc., complete with initial lead upto 1 km and all lifts. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 0.00 : 677.28 cum Rate in Rs. Amount in Rs. 677.28

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.5 cum Fuel / Energy charges Tippers 5 cum 3 Nos Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 6.06 6.06 8.00 8.00 48.00 48.00 3.00 3.00 6.00 6.00 6.16 6.16 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 6.06 8.00 48.00 3.00 6.00 6.16 2.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /677.28

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 677.28 cum

IRR-CAW-3 IRR-CAW-3-1

EMBANKMENT WORKS USING DUMP AREA SOIL : Providing casing embankment using homogeneous soil from approved borrow area in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sortingout, transporting, spreading in layer of specified thickness, breaking clods, sectioning, compacting each layer without watering to density control of not less than 95 percent or as stipulated by sheep's foot / pad foot roller etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 0.00 677.28 cum Rate in Rs. Amount in Rs.

91

IRR-CAW

Sl No 1 2 3 4 5

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 4 Nos. Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 6.06 6.06 8.00 8.00 48.00 48.00 6.16 6.16 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 6.06 8.00 48.00 6.16 2.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /677.28

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 677.28 cum

IRR-CAW-3-2

Providing impervious hearting embankment with soil from approved dump areas in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as re-excavation, sorting out, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting each layer to achieve density control of not less than 98 percent or as stipulated by sheep's / pad foot roller etc.,complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 735.36 cum Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00 0.00

Description Angle dozer Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 6 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 4.04 4.04 8.00 8.00 48.00 48.00 3.00 3.00 6.00 6.00 7.50 7.50 2.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4

Description Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump

Unit Hour Hour Hour Hour

Quantity 3.58 8.00 48.00 3.00

Rate in Rs. 0.00 0.00 0.00 0.00

Amount in Rs. 0.00 0.00 0.00 0.00

92

IRR-CAW

5 6 7 8

Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /735.36

6.00 7.50 2.00 6.00

0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 735.36 cum

IRR-CAW-3-3

Providing impervious hearting embankment with soil from approved dump areas in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as re-excavation, sorting out, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting each layer to achieve density control of not less than 95 percent or as stipulated by sheep's / pad foot roller etc.,complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 0.00 735.36 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.5 cum Fuel / Energy charges Tippers 5 cum Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 4.04 4.04 8.00 8.00 48.00 48.00 3.00 3.00 6.00 6.00 6.13 6.13 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 4.04 8.00 48.00 3.00 6.00 6.13 2.00 6.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /735.36

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 735.36 cum

93

IRR-CAW

IRR-CAW-3-4

Providing semi-pervious / pervious casing embankment using soil from approved dump area in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as re-excavation, sorting out, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by sheep's foot / pad foot roller etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 0.00 768.00 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 6 Nos Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 4.22 4.22 8.00 8.00 48.00 48.00 3.00 3.00 6.00 6.00 7.82 7.82 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 4.22 8.00 48.00 3.00 6.00 7.82 2.00 6.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /768

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 768.00 cum

IRR-CAW-3-5

Providing semi-pervious / pervious casing embankment using soil from approved dump area in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as re-excavation, sorting out, transporting, spreading in layer of specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 95 percent or as stipulated by sheep's foot / pad foot roller etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 0.00 768.00 cum Rate in Rs. Amount in Rs.

94

IRR-CAW

Sl No 1 2 3 4 5 6 7

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.5 cum Fuel / Energy charges Tippers 5 cum of 6 Nos Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 4.22 4.22 8.00 8.00 48.00 48.00 3.00 3.00 6.00 6.00 6.40 6.40 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 4.22 8.00 48.00 3.00 6.00 6.40 2.00 6.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Shovel Hour Crew for Tipper Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /768

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 768.00 cum

IRR-CAW-4 IRR-CAW-4-1

EMBANKMENT WORKS USING EXCAVATED SOIL : Providing semi-pervious / pervious casing embankment using soil from approved dump area in layers of 25 cm before compaction including cost of all materials, machinery, labour, all operations such as re-excavation, sorting out, transporting, spreading in layer of specified thickness, breaking clods, sectioning, compacting each layer without watering to density control of not less than 95 percent or as stipulated by sheep's foot / pad foot roller etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 0.00 768.00 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 6 Nos. Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 4.22 4.22 8.00 8.00 48.00 48.00 6.40 6.40 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1

Description Crew for Dozer

Unit Hour

Quantity 4.22

Rate in Rs.

Amount in Rs.

95

IRR-CAW

2 3 4 5 6

Crew for Shovel Hour Crew for Tipper Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /768

8.00 48.00 6.40 2.00 6.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 768.00 cum

IRR-CAW-4-2

Providing impervious hearting embankment with soil collected in embankment area in heaps as part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all operations such as sortingout, spreading in layer of 25 cm before compaction, breaking clods,sectioning, watering and compacting each layer to density control of not less than 98 percent or as stipulated by sheep's foot / pad foot roller etc., complete with lead upto 1 km for water.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 0.00 600.00 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3.60 3.60 3.00 3.00 5.00 5.00 7.30 7.30 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 3.60 3.00 5.00 7.30 1.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /600

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 600.00 cum

IRR-CAW-4-3

Providing impervious hearting embankment with soil collected in embankment area in heaps as part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all operations such as sortingout, spreading in layer of 25 cm before compaction, breaking clods,sectioning, watering and compacting each layer to density control of not less than 95 percent or as stipulated by sheep's foot/ pad foot roller etc., complete with lead upto 1 km for water.

96

IRR-CAW

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 0.00 600.00 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3.60 3.60 3.00 3.00 5.00 5.00 6.06 6.06 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 3.60 3.00 5.00 6.06 2.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /600

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 600.00 cum

IRR-CAW-4-4

Providing semi-pervious / pervious casing hearting embankment using soil collected in heaps in embankment area as part of disposal of excavated soil from canal including cost of all materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25 cm before compaction, breaking clods, sectioning, watering and compacting each layer to density control of not less than 98 percent or as stipulated by sheep's foot / pad foot roller etc., complete with lead upto 1 km for water.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 0.00 600.00 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3.60 3.60 3.00 3.00 5.00 5.00 7.30 7.30 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

97

IRR-CAW

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 3.60 3.00 5.00 7.30 1.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /600

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 600.00 cum

IRR-CAW-4-5

Providing semi-pervious / pervious casing embankment using soil collected in heaps in embankment area as part of disposal of excavated soil from canal including cost of all materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25 cm before compaction, breaking clods, sectioning, watering and compacting each layer to density control of not less than 95 percent or as stipulated by sheep's foot / pad foot roller etc., complete with lead upto 1 km for water.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 0.00 600.00 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3.60 3.60 3.00 3.00 5.00 5.00 6.1 6.1 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 3.60 3.00 5.00 6.1 2.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /600

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 600.00 cum

IRR-CAW-4-6

Providing semi-pervious / pervious casing embankment using soil collected in heaps in embankment area as part of disposal of excavated soil from canal including cost of all

98

IRR-CAW

materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25 cm before compaction, breaking clods, sectioning and compacting each layer without watering to density control of not less than 95 percent or as stipulated by sheep's foot / pad foot roller etc., complete. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No 1 2 3 Unit UNIT : Quantity 0.00 Rs: Rs: Rs: 0.00 0.00 0.00 600.00 cum Rate in Rs. Amount in Rs.

Description Angle dozer 90 hp Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour LS

Quantity 3.60 3.60 6.06 6.06 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4

Description

Unit

Quantity 3.60 6.06 1.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Hour Crew for Roller Hour work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.D.Add for contractor's profit and overheads on A+B+C on A+B+C Total cost for Rate per cum=(A+B+C+D) /600

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

Total

0% 600.00 cum

Rs: Rs: Rs:

0 0.00 0.00

IRR-CAW-5 IRR-CAW-5-1

FOUNDATION FILLING WORKS : Providing compacted embankment for field irrigation channels with gravely soil from approved borrow area including sorting out, spreading in layers of 15 cm thickness, breaking clods, watering, compacting, dressing sides to required slopes etc.,complete with lead upto 50 m and all lifts. Output of 1 Crowbarman assumed at 10 cum per day for loosening gravely soil. Output of 2 mazdoors assumed at 5 cum per day for excavation of gravely soil and loading the same to transport vehicle at borrow area. Output of 1 mazdoor assumed at 10 cum loose soil for spreading and levelling. RATE ANALYSIS UNIT : 25.00 cum A. MATERIALS: Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Nill 0.00 0.00 seigniorage charges for soil Rs: 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No 1

DATA:

Description 5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour

Quantity 1.00 1.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1

Description Crew for pump

Unit Hour

Quantity 1.00

Rate in Rs.

Amount in Rs.

99

IRR-CAW

2 3 4

5 6

work inspector Day Crowbarman for loosening soil Day mazdoor For excavation at borrow area Day For spreading / levelling / sectioning Day for loading soil Day Cartman with Bullock cart for water Day Bullock drawn roller for rolling Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /25

1.00 2.50 5.00 2.50 5.00 1.00 1.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 25.00 cum

IRR-CAW-5-2

Providing rubble and sand filling in layers of 22.5 to 30 cm including cost of all materials, machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts. Consider 10 cum rubble and sand filling. Quantity of rubble Quantity of sand 4 mazdoors for rubble filling & for packing with sand & watering. RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit UNIT : Quantity

DATA:

10.00 cum 4.00 cum

10.00 cum Rate in Rs. Amount in Rs.

Rubble stones at quarry cum 10.00 Sand ( unscreened ) at quarry cum 4.00 Seionorage charges for sand (included in the material rates) Seionorage charges for stone (included in the material rates) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 mazdoor

Description

Unit

Quantity 4.00

Rate in Rs. Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10

Total 0% 10.00 cum

IRR-CAW-5-3

Providing rubble and Murum filling in layers of 22.5 to 30 cm including cost of all materials, machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts. Consider 10 cum rubble and murum filling. Quantity of rubble Quantity of murum 4 mazdoors for rubble filling & packing with murum RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit UNIT : Quantity

DATA:

10.00 cum 4.00 cum

10.00 cum Rate in Rs. Amount in Rs.

Rubble stones at quarry cum 10.00 Murum cum 4.00 Seionorage charges for Murum(included in the material rates)

Rs:

0.00

100

IRR-CAW

Seionorage charges for stone(included in the material rates) Total cost of Materials B. MACHINERY: Sl No 1

Rs: Rs:

0.00 0.00

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 mazdoor

Description

Unit

Quantity 4.00

Rate in Rs. Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10

Total 0% 10.00 cum

IRR-CAW-5-4

Providing and laying 25 cm thick sand blanket below embankment including cost of all materials, machinery, labour, spreading to specified thickness etc., complete with initial lead upto 50 m and all lifts. Consider 100 sqm sand blanket laying. Quantity of sand ( unscreened ) Requirement of labour for spreading collected sand. 2 mazdoors @ 10 cum / day. RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Sand ( unscreened ) Unit cum UNIT : Quantity

DATA:

25.00 cum

100.00 sqm Rate in Rs. Amount in Rs.

25.00 0.00 Seionorage charges for sand (included in the material rates) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 mazdoor

Description

Unit

Quantity 5.00

Rate in Rs. Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

Total 0% 100.00 sqm

IRR-CAW-5-5

Providing and constructing dry rubble rock-toe using rubble and stone chips from approved source including cost of all materials, machinery, labour, hand packing rubble and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto 50 m and all lifts. Top width Side slope upstream side Side slope down stream side Height : : : : NIL 1 (V) : 1 (H) 1 (V) : 1.5 (H) 1.00 m

DATA:

101

IRR-CAW

Cross sectional area ( 0.00 + 2.50 ) x 1 / 2 Consider 100 cum rock toe: RATE ANALYSIS A. MATERIALS: Sl No particulars 1 2 3

: UNIT : Unit Quantity

1.25 sqm 100.00 cum Rate in Rs. Amount in Rs.

Rubble cum 100.00 Stone chips cum 15.00 Sundries LS 2.00 Seionorage charges for stone chips (included in the material rates) Seionorage charges for stone(included in the material rates) Total cost of Materials Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit

Quantity 1.00 7.00 19.00

Rate in Rs.

Amount in Rs.

work inspector Day Mason Class-II Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /100

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100.00 cum

IRR-CAW-5-6

Providing and constructing longitudinal and cross graded filter drains using sand and 20 mm down graded aggregates satisfying specified filter creteria in layers as per specifications including cost of all materials, machinery, labour, laying to required slopes, compaction etc., complete with initial lead upto 50 m and all lifts. Bottom width Side slopes : Depth Top width RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Unit 0.50 1( V ):1(H) 0.50 1.50 UNIT : 100.00 Quantity Rate in Rs. m m m cum Amount in Rs.

DATA:

Sand ( unscreened ) cum 76.80 Coarse aggregate 20-10 mm 75 % cum 17.40 Coarse aggregate 10 mm down 25 %cum 5.80 Add for seignorage charges for sand(included in the material cost) Rs: Add for seignorage charges for CA(included in the material cost) Rs: Total cost of Materials Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description

Unit

Quantity 1.00 36.00

Rate in Rs.

Amount in Rs.

work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

Total

102

IRR-CAW

D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /100

0% 100.00 cum

Rs: Rs: Rs:

0 0.00 0.00

IRR-CAW-5-7

Laying Longitudinal Drains and Transverse drains of Size 600 x600 x750 mm in Bed and filling with 12 mm to 40 mm HG machine Crushed metal and sand in bed including Excavation of drains and Cost of procuring of all materials including 50 m lead and for all lifts.

DATA: A. MATERIALS: Unit: 100 sqm Sl.No Particulars Unit Qty Rate in Rs Amount in Rs. 1 12 mm to 40 mm metal Cum 13.5 2 Sand cum 36 Add seignorage charges on CA @ Rs. (included in material rate) 0 Add seignorage charges on FA @ Rs. (included in material rate) 0 Total cost of Materials Rs. 0 B. MACHINERY Sl.No Description Unit 1 Excavation of drain with Excavator Cum Total hire charges of Machinery C. LABOUR Sl.No

Quantity 45

Rate in Rs. Amount in Rs. Total Rs. 0

Particulars Unit Qty 1 Labour for Sand laying Cum 2 Labour for Metal laying Cum Total cost of Materials ABSTRACT A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

Rate in Rs 31.5 36 Rs. Rs. Rs. Rs. Total 0%

Amount in Rs.

0 0 0 0 0.00 0 0.00 0

Rs: Rs: Rs:

100.00 sqm

IRR-CAW-5-8

Laying and fixing of 100 mm Dia 300 mm long precast porus CC plugs in bed and sides using 1.181 Kgs of cement per each using 20 mm HG metal and placing in local filters of size 600x600x750 mm in size including Excavation of drains and Cost of procuring of all materials including 50 m lead and for all lifts. Rate Analysis A. MATERIALS: Sl.No Particulars Unit Qty Rate in Rs 1 Coarse aggregate Cum 0.08 2 Sand cum 0.203 3 Cement Kg 1.181 Add seignorage charges on CA @ Rs. (included in material rate) Add seignorage charges on FA @ Rs. (included in material rate) Total cost of Materials Rs. Amount in Rs. Unit 1 Plug

DATA:

0.00 0.00 0.00

B. MACHINERY Sl.No Description Unit Quantity 0.27 0.003 Total Rs. 0.00 Rate in Rs. Amount in Rs.

1 Excavation of drain with Excavator Cum 2 Machine mixing Charges Cum Total hire charges of Machinery C. LABOUR Sl.No

Particulars Unit Qty 1 Man Mazdoor Day 30.00 Total cost of Materials ABSTRACT A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C

Rate in Rs Rs. Rs. Rs. Rs. Total

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0

Rs: Rs:

0%

103

IRR-CAW

Total for one plug Rate per one plug=(A+B+C+D) /1

Rs.

0.00 0.00

IRR-CAW-5-9

Providing and constructing 0.50 m thick vertical or inclined graded filter media consisting of 15 cm thick sand layers and 20 cm thick 20 mm down coarse aggregate layer using approved materials satisfying specified filter creteria as per specifications including cost of all materials, machinery, labour, laying to required slope, compaction etc., complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Sand ( unscreened ) Coarse aggregate 20-10 mm 75 % Unit cum cum UNIT : Quantity 60.00 30.00 10.00 0.00 0.00 0.00 100.00 cum Rate in Rs. Amount in Rs.

Coarse aggregate 10 mm down 25 %cum

Add for seignorage charges for sand(included in the material cost) Rs: Add for seignorage charges for CA(included in the material cost) Total cost of Materials B. MACHINERY: Sl No 1 Rs: Rs:

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description

Unit

Quantity 1.00 36.00

Rate in Rs.

Amount in Rs.

work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /100

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100.00 cum

IRR-CAW-5-10

Providing and constructing graded filter media below and behind rock-toe consisting of 20 cm thick sand, 15 cm thick 20 mm down and 15 cm thick 40 mm down size graded coarse aggregates satisfying filter creteria behind rock-toe and 15 cm thick sand, 20 cm thick 20 mm down coarse aggregate and 65 cm thick 40 mm down size coarse aggregate satisfying filter creiteria below rock-toe as per specifications including cost of all materials, machinery, labour, laying to required slope, compaction etc., complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 particulars Unit UNIT : Quantity 176.00 cum Rate in Rs. Amount in Rs.

Sand ( unscreened ) cum 58.77 Coarse aggregate 40-20 mm cum 52.70 Coarse aggregate 20-10 mm cum 50.70 Coarse aggregate 10 mm down cum 13.80 Add for seignorage charges for sand(included in the material cost) Rs: Add for seignorage charges for CA(included in the material cost) Rs: Total cost of Materials Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR:

104

IRR-CAW

Sl No 1 2

Description

Unit

Quantity 1.00 60.00

Rate in Rs.

Amount in Rs.

work inspector Day mazdoors Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /176

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 176.00 cum

IRR-CAW-5-11 (a)

Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m a. for aggregate and all leads for fabric and all lifts. Using 200 gsm filter fabric.

DATA:

Requirement of labour for laying aggregate and filter fabric: 2 mazdoors @ 6 cum / day. RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit UNIT : Quantity 100.00 sqm Rate in Rs. Amount in Rs.

PP filter fabric 200 gsm sqm 210.00 20 - 10 mm CA @ 75 % cum 15.00 10 mm down CA @ 25 % cum 5.00 Add for seignorage charges for CA(included in the material cost) Total Cost of materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description

Unit

Quantity 1.00 7.00

Rate in Rs.

Amount in Rs.

work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100.00 sqm

IRR-CAW-5-12 (b)

Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m for aggregate and all leads for fabric and all lifts.

105

IRR-CAW

b. Using 250 gsm filter fabric. DATA: Consider 100 sqm filter media laying. RATE ANALYSIS A. MATERIALS: Sl No particulars 1 2

UNIT : Unit Quantity

100.00 sqm Rate in Rs. Amount in Rs.

PP filter fabric 250 gsm sqm 210.00 20 - 10 mm CA @ 75 % cum 15.00 10 mm down CA @ 25 % cum 5.00 Add for seignorage charges for CA(included in the material cost) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description

Unit

Quantity 1.00 7.00

Rate in Rs.

Amount in Rs.

work inspector Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100.00 sqm

IRR-CAW-6 IRR-CAW-6-1

ROCK FILL WORKS : Providing and constructing rockfill casing to canal embankment with graded stones and spalls from approved quarry including cost of all materials, machinery, labour, spreading stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc., complete with initial lead upto 50 m and all lifts. Consider 100 cum rockfill casing to canal embankment. RATE ANALYSIS A. MATERIALS: Sl No particulars Unit 1 2

DATA:

UNIT : Quantity

100.00 cum Rate in Rs. Amount in Rs.

Rubble stones ( at quarry ) cum 100.00 Stone chips / spalls ( at quarry ) 15.00 Add for seignorage charges for rubble/spalls(included in the materialRs: cost) Total cost of Materials Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description Mason Cl- II mazdoor

Unit Day Day

Quantity 6.00 8.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /100 0% 100.00 cum Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

106

IRR-CAW

IRR-CAW-6-2

Providing and constructing rockfill casing to canal embankment with graded stones and spalls available in dump yard including cost of all materials, machinery, labour, spreading stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc., complete with initial lead upto 50 m and all lifts. Stones and spalls available in dump yard shall be issued at specified issue rate.

Note: DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit

UNIT : Quantity

100.00 cum Rate in Rs. Amount in Rs.

Rubble stones at dump yard cum 100.00 Stone chips ( spalls ) at dump yard 15.00 Add for seignorage charges for rubble/spalls(included in the materialRs: cost) Total cost of Materials Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit

Quantity 6.00 2.00 10.00

Rate in Rs.

Amount in Rs.

Mason Cl- II Day Crowbarman Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /100

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100.00 cum

IRR-CAW-7 IRR-CAW-7-1

CANAL LINING WORKS : Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow area including spreading soil in layers of thickness not more than 15 cm, breaking clods, watering, compacting to density control of not less than 98 percent or as stipulated, dressing to required profile etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nil Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 394.00 cum Rate in Rs. Amount in Rs.

Description Shovel 0.5 cum Fuel / Energy charges Angle dozer 90 hp Fuel / Energy charges Tipper 5 cum Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Diesel road roller 8-10 tonne Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 8.00 3.00 3.00 24.00 24.00 4.00 4.00 4.00 4.00 11.50 11.50 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

107

IRR-CAW

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Shovel Crew for Dozer Crew for Tipper Crew for Pump Crew for Water tanker Crew for Road roller work inspector mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /394

Unit Hour Hour Hour Hour Hour Hour Day Day

Quantity 8.00 3.00 24.00 4.00 4.00 11.50 2.00 38.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 394.00 cum

IRR-CAW-7-2

Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow area including spreading soil in layers of thickness not more than 15 cm, breaking clods, watering, compacting to density control of not less than 95 percent or as stipulated, dressing to required profile etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nil Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 394.00 cum Rate in Rs. Amount in Rs.

Description Shovel 0.5 cum Fuel / Energy charges

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 8.00 3.00 3.00 24.00 24.00 4.00 4.00 4.00 4.00 10.00 10.00 5.00

Rate in Rs.

Amount in Rs.

Angle dozer 90 hp Fuel / Energy charges

Tippers 5 cum Fuel / Energy charges

Pump 5 hp ( diesel ) Fuel / Energy charges

Water tanker 8000 ltr Fuel / Energy charges

Diesel road roller 8-10 tonnes Fuel / Energy charges

Sundries Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Shovel Crew for Dozer Crew for Tipper Crew for Pump Crew for Water tanker Crew for Road roller work inspector mazdoor Total cost of Labour

Unit Hour Hour Hour Hour Hour Hour Day Day

Quantity 8.00 3.00 24.00 4.00 4.00 10.00 2.00 38.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

108

IRR-CAW

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /394 0% 394.00 cum Rs.

Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0 0.00 0.00

IRR-CAW-7-3

Providing cohesive non-swelling ( CNS ) soil lining to canal using soil collected in heaps along the edge of canal requiring CNS soil lining as part of the disposal of excavated soil from canal excavation in CNS soil reach including spreading in layers of thickness not more than 15 cm, breaking clods, watering, compacting to density control of not less than 95 percent or as stipulated, dressing to required profile etc., complete with lead upto upto 50 m and all lifts. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nil Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 394.00 cum Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

Description Angle Dozer 90 hp Fuel / Energy charges

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 1.50 1.50 5.00 5.00 5.00 5.00 13.00 13.00 5.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Pump 5 hp ( diesel ) Fuel / Energy charges

Water tanker 8000 ltr Fuel / Energy charges

Diesel road roller 8-10 tonne Fuel / Energy charges

Sundries Total hire charges of Machinery

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Dozer Crew for Pump Crew for Water tanker Crew for Road roller work inspector mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Day Day

Quantity 1.50 5.00 5.00 13.00 2.00 38.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /394 0% 394.00 cum

IRR-CAW-7-4

Providing and fixing 20 x 20 x 75 cm size top surface neatly dressed canal bed level stones including cost of all materials, labour, excavation, fixing in position to correct level etc., complete with lead upto 50 m and all lifts. Assuming 0.5 hour for excavation and fixing each stone. Consider 1 work inspector & 2 mazdoors for fixing 32 stones / day Consider 2 Stone chiseller Cl- I for top surface dressing of 32 stones.

DATA:

109

IRR-CAW

RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Rough stone 20x20x75 cm Unit Each

UNIT : Quantity Rate in Rs.

32 Nos. Amount in Rs.

32.00 0.00 Add for seignorage charges for rubble/spalls(included in the materialRs: cost) Total cost of Materials Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit

Quantity 1.00 2.00 2.00

Rate in Rs.

Amount in Rs.

work inspector Day Stone chiseller Cl- I Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per No=(A+B+C+D) /32

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 32 Nos

IRR-CAW-7-5

Providing, fabricating and placing in position reinforcement steel bars for RCC works including cleaning, straightening, cutting, bending, hooking, lapping, tying with 1.25 mm dia. soft annealed steel wire, welding wherever required including cost of all materials, machinery, labour etc., complete with initial lead upto 50 and all lifts. Lap jointing considered assuming all reinforcement below 36 mm dia. Quantity of binding wire per tonne : Wastage of steel : Cleaning and straightening : 1 Bar benders & 2 mazdoors Marking, cutting, bending & stacking : 2 Bar benders & 4 mazdoors Fixing & tying with binding wire : 2 Bar benders & 4 mazdoors Checking / correcting & misc. : 1 Bar benders & 1 mazdoors RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Rein.Steel with 5 % wastage Binding wire 1.25 mm dia Sundries ( chairs / spacers etc ) Total cost of Materials Unit kg kg LS UNIT : Quantity 1050.00 8.00 10.00 Rs: 0.00

DATA:

8 kg 5 percent

1000.00 kg Rate in Rs. Amount in Rs.

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description Bar bender mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Day Day

Quantity 6.00 11.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0

Total D.Add for contractor's profit and overheads on A+B+C 0%

110

IRR-CAW

Total cost for Rate per Kg=(A+B+C+D) /1000

1000.00 kg

Rs. Rs:

0.00 0.00

IRR-CAW-7-6

Providing and laying 75 mm thick in-situ M-15 ( 28 days cube compressive strength not less than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard, graded aggregates for canal lining using vibrating cylinder type mechanical paver including cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position, finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts. ( 43 Gr Cement content: 19.2 kg / sqm for use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS A. MATERIALS: Sl No particulars 1 2 3 4 5 7 8 UNIT : Unit Quantity 960 sqm Rate in Rs. Amount in Rs.

Cement 43 Gr kg 19008.00 Coarse aggregate 20-10 mm cum 41.18 Coarse aggregate 10-4.75 mm cum 22.18 Fine aggregate ( screened ) cum 35.64 Super plasticiser kg 76.03 PVC sealing strip Rm 640.00 Use rate of paving cylinder sqm 960.00 Sundries LS 5.00 Add Seignorage charges on CA @ Rs: ( Included in material rate ) Rs: Add Seignorage charges on FA @ Rs: ( Included in material rate ) Rs: Total cost of Materials Rs:

0 0 0.00

B. MACHINERY: Sl No Description 1 2 3 4 5 6

Unit

Quantity 8.00 8.00 24.00 24.00 8.00 8.00 8.00 8.00 8.00 8.00 2.00 2.00 8.00 8.00 8.00 8.00 5.00 Rs:

Rate in Rs.

Amount in Rs.

Batching plant Hour Lubricants etc @ 5 % Hour Transit mixer 3 Nos Hour Fuel / Energy charges Hour Mechanical paver Hour Lubricants etc @ 5 % Hour DG set for batching plant 50 KVA Hour Fuel / Energy charges Hour DG set for paver 30 KVA Hour Fuel / Energy charges Hour Shovel 0.5 cum / Loader Hour Fuel / Energy charges Hour 7 Water tanker Hour Fuel / Energy charges Hour 8 Pump 5 hp(diesel) 2 Nos. 4 hrs eachHour Fuel / Energy charges Hour 9 Sundries ( power line etc ) LS Total hire charges of Machinery

0.00

C. LABOUR: Sl No Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Unit

Quantity 8.00 24.00 8.00 16.00 2.00 8.00 16 2 1 1 1 2 5 10

Rate in Rs.

Amount in Rs.

Crew for Batching plant Hour Crew for Transit mixer Hour Crew for Concrete paver Hour Crew for DG set Hour Crew for Shovel Hour Crew for Water tanker Hour Crew for Pump Hour Mason Class I Day Mechanic Day Fitter Day Electrician Day work inspector Day mazdoor ( BP site ) Day mazdoor ( Paver site ) Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Add for shifting & re-erection of BP @ 0%

Rs: Rs: Rs: Rs: Total Rs:

0.00 0.00 0.00 0 0 0

Rs:

111

IRR-CAW

Add for LH / RH shifting & erection of Paver @ 0% Add for ledge cutting / erection of tracks etc @ 0% D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per sqm=(A+B+C+D) /960

Rs: Rs: Total

Rs:

0 0 0.00

0% 960 sqm Rs. Rs:

Rs:

0 0.00 0

IRR-CAW-7-7

Providing and laying 80 mm thick in-situ M-15 ( 28 days cube compressive strength not less than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard, graded aggregates for canal lining using vibrating cylinder type mechanical paver including cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position, finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts. ( 43 Gr Cement content: 19.2 kg / sqm for use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS A. MATERIALS: Sl No particulars 1 2 3 4 5 7 8 UNIT : Unit Quantity 960 sqm Rate in Rs. Amount in Rs.

Cement 43 Gr kg 20275.20 Coarse aggregate 20-10 mm cum 43.93 Coarse aggregate 10-4.75 mm cum 23.65 Fine aggregate ( screened ) cum 38.02 Super plasticiser kg 81.10 PVC sealing strip Rm 640.00 Use rate of paving cylinder sqm 960.00 Sundries LS 5.00 Add Seignorage charges on CA @ Rs: ( Included in material rate ) Rs: Add Seignorage charges on FA @ Rs: ( Included in material rate ) Rs: Total cost of Materials Rs:

0 0 0.00

B. MACHINERY: Sl No Description 1 2 3 4 5 6

Unit

Quantity 8.00 8.00 24.00 24.00 8.00 8.00 8.00 8.00 8.00 8.00 2.00 2.00 8.00 8.00 8.00 8.00 5.00 Rs:

Rate in Rs.

Amount in Rs.

Batching plant Hour Lubricants etc @ 5 % Hour Transit mixer 3 Nos Hour Fuel / Energy charges Hour Mechanical paver Hour Lubricants etc @ 5 % Hour DG set for batching plant 50 KVA Hour Fuel / Energy charges Hour DG set for paver 30 KVA Hour Fuel / Energy charges Hour Shovel 0.5 cum / Loader Hour Fuel / Energy charges Hour 7 Water tanker Hour Fuel / Energy charges Hour 8 Pump 5 hp(diesel) 2 Nos. 4 hrs eachHour Fuel / Energy charges Hour 9 Sundries ( power line etc ) LS Total hire charges of Machinery

0.00

C. LABOUR: Sl No Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Crew for Batching plant Crew for Transit mixer Crew for Concrete paver Crew for DG set Crew for Shovel Crew for Water tanker Crew for Pump Mason Class I Mechanic Fitter Electrician work inspector mazdoor ( BP site ) mazdoor ( Paver site ) Total cost of Labour

Unit Hour Hour Hour Hour Hour Hour Hour Day Day Day Day Day Day Day

Quantity 8.00 24.00 8.00 16.00 2.00 8.00 16 2 1 1 1 2 5 10

Rate in Rs.

Amount in Rs.

Rs:

0.00

112

IRR-CAW

ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Add for shifting & re-erection of BP @ 0% Add for LH / RH shifting & erection of Paver @ 0% Add for ledge cutting / erection of tracks etc @ 0% D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per sqm=(A+B+C+D) /960

Rs: Rs: Rs: Total Rs: Rs: Rs: Total

Rs:

Rs:

0.00 0.00 0 0 0 0 0 0.00

0% 960 sqm Rs. Rs:

Rs:

0 0.00 0

IRR-CAW-7-8

Providing and laying 100 mm thick in situ M-15 (28 days cube compressive strength not less than 15 N /Sqmm ) grade cement concrete with 20 mm down size approved, clean, hard, graded aggregates for canal lining using, vibrating, cylinder type mechanical paver including cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position, finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to othere side of canal etc., complete with initial lead upto 1 Km and all lifts. ( 43 Gr Cement content: 24 kg / sqm for use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 800 Sqm A. MATERIALS: Sl.No Particulars Unit Qty Rate in Rs. Amount 1 Cement 43 Gr Kg 21120 2 Coarse aggregate 20-10 mm cum 45.76 Coarse aggregate 10-4.75 mm cum 24.64 3 Fine aggregate (Screened) cum 39.6 4 Super plasticiser ltr 84.48 5 PVC sealing strip Rm 533 6 Use rate of paving cylinder sqm 800 Add seignorage charges on CA & Rs. (includedd in material rate) Add seignorage charges on FA & Rs. (included in material rate) Total cost of Materials Rs. B. MACHINERY: Sl.No Particulars Unit 1 Batching plant Hour 2 Transit mixer 3 Nos Hour Fuel / Energy charges Hour 3 Mechanical paver Hour lubricants etc @ 5% Hour 4 DG set for batching plant 50 KVAHour Fuel / Energy charges Hour 5 DG set for paver 30 KVA Hour Fuel / Energy charges Hour 6 Water tanker Hour Fuel / Energy charges Hour 7 Pump 5 hp (diesel) 2 Nos. 4 hrs each Hour Fuel / Energy charges Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Crew for Batching plant Crew for Transit mixer Crew for Concrete paver Crew for DG set Crew for Shovel Crew for Water tanker Crew for Pump Mason Class I Mechanic Fitter Electrician work inspector mazdoor ( BP site ) mazdoor ( Paver site ) Total cost of Labour

0 0 0

Qty 8 24 24 8 8 8 8 8 8 8 8 8 8

Rate in Rs. Amount

Rs.

Unit Hour Hour Hour Hour Hour Hour Hour Day Day Day Day Day Day Day

Quantity 8.00 24.00 8.00 16.00 2.00 8 8 2 1 1 1 2 5 10

Rate in Rs.

Amount in Rs.

Rs:

0.00

113

IRR-CAW

ABSTRACT A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Add for shifting & re-erection of BP @ Add for LH / RH shifting & erection of Paver @ Add for ledge cutting / erection of tracks etc @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per sqm=(A+B+C+D) /800

Rs. Rs. Rs. TOTAL Rs. 0% Rs. 0% Rs. 0% Rs. Total Rs:

0 0 0.00 0 0 0 0 0.00

0% 800 sqm Rs. Rs.

Rs:

0 0.00 0

IRR-CAW-7-9

Dismantling, shifting and re-erecting mechanical concrete paver and DG set with all accessories across canal CD work or other locations wherever shifting and re-erecting is necessary including aligning paver correctly for continuing canal lining work, cost of all materials, machinery, labour etc., complete with all leads and lifts. Local shifting and re-erection of paver for LH and RH side lining included in concrete lining rates under items 51 and 52 and saperate rate for shifting shall not be allowed. Dismantling, shifting and re-erecting mechanical concrete paver is necessary at each CD work location. As CD works will not be at any fixed interval separate rate is proposed for dismantling, shifting and re-erection of paver. As per the information collected from equipment suppliers 1 day time is required for dismantling, shifting and re-erection of paver and DG set including aligning. Deploy paver crew for 1 day. Deploy mazdoors 6 Nos for 1 day to assist paver crew. Deploy tipper for 4 hours with fuel charges for 1 hour for shifting.

Note:

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 NIL Total cost of Materials B. MACHINERY: Sl No 1 2 particulars Unit

UNIT : Quantity 0.00

1.00 Shifting Rate in Rs. Amount in Rs.

Rs:

0.00

Description

Unit Hour Hour LS

Quantity 4.00 1.00 1.00

Rate in Rs.

Amount in Rs.

Tipper Fuel / Energy charges Sundries (ropes / rails etc) Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description Crew for Tipper Crew for Paver mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per shifting=(A+B+C+D) /1

Unit Hour Hour Day

Quantity 4.00 8.00 6.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

Total

0% 1.00 Shifting Rs.

Rs: Rs:

0 0.00 0.00

IRR-CAW-7-10

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for bed and side lining of canal(150mm thick) including finishing the junction of bed and sides to required curveture, cost of all materials, machinery, labour, formwork including supports, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 190 kg / cum )

114

IRR-CAW

( 43 Gr Cement content: 190 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

For small canals consider locally fabricated manually operated paver for in-situ concrete lining. By operating the screw jack the side shuttering can be positioned in place. Consider laying of concrete in panels of 3 m length. Assume 1.5 m bed width and 1.2 m depth of flow. Assume side slopes of 1.5 horizontal to 1 vertical. Considering 0.3 m free board the size of shuttering for 3 m length panal will be 9.60 sqm on either side including curved portions and over laps. As the paver will be released soon after completing concreting upto top level of lining and moved to next portion to be lined 200 uses can be considered as life of paver. Further it is assumed that the shuttering of paver will be oiled after every 4 uses of the paver. Considering this the quantity of shutter oil is assumed at 0.05 ltr / sqm. Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum Cement content : 190 kg Super plasticizer : 0.76 kg RATE ANALYSIS UNIT : 36.00 cum A. MATERIALS: Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Cement for mix kg 6080 Cement for incidentals @ 5 kg / cum kg 160.00 2 Coarse aggregate 40-20 mm cum 14.4 Coarse aggregate 20-10 mm cum 8.64 Coarse aggregate 10 mm below cum 5.76 3 Fine aggregate cum 12.8 4 Super Plasticizer kg 0.76 6 Use rate of manual paver sqm 234.00 7 Sundries LS 2.00 Add seignorage charges on CA & Rs. (includedd in material rate) Rs: 0.00 Add seignorage charges on FA & Rs. (includedd in material rate) Rs: 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No 1 2 3 4

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 16.00 16.00 0.50 0.50 1.00 1.00 16.00 16.00

Rate in Rs.

Amount in Rs.

Concrete mixer 600/400 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Needle vibrator work inspector Mason Class-I Fitter mazdoor for batching materials for loading mortar pans for laying and moving paver for conveying concrete

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day

Quantity 16.00 0.50 1.00 16.00 1.00 2.00 1.00 22.00 8.00 6.00 32.00

Rate in Rs.

Amount in Rs.

115

IRR-CAW

for cleaning/ washing/ curing Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per cum=(A+B+C+D) /36

2.00 Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00

Total

0% 36.00 cum Rs.

Rs: Rs:

0 0.00 0.00

IRR-CAW-7-11

Providing and laying insitu vibrated M-10 (28 days cube compressive strength not less than 10 N/sqm) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregade for bed and side lining of canal(100 mm thick) including, finishing the junction of bed and sides to required curvature, cost of all materials, machinery, labour, formwork including supports cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead up to 50 m and all lifts (Cement content: 190 kg/cum) ( 43 Gr Cement content: 190 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: For 1 cum CC:- Coarse aggregates: 0.90 cum Blinding ratio :50:30:20 Fine aggregate: 0.40cum Cement Content : 190 Kg Super Plasticizer: 0.76 kg average output of 600/400 ltr mixer.25cum/day. RATE ANALYSIS UNIT: A. MATERIALS: Sl.No Particulars Unit 1 Cement for mix kg Cement for incidentals @0. 5 Kg / cum kg 2 Coarse aggregate 40mm cum Coarse aggregate 20 mm . cum Coarse aggregate 10 mm . cum 3 Fine aggregate cum 4 Super Plasticizer kg 5 Use rate of manual paver sqm

37 cum

Qty Rate in Rs. 7030.00 18.50 16.65 9.99 6.66 14.80 28.12 378.00 Total Rs. Add seigniorage charges on CA & Rs. (includedd in material rate) Add seigniorage charges on FA & Rs. (includedd in material rate) Total cost of Materials Rs.

Amount

0.00 0.00 0.00 0.00

B. MACHINERY: Sl.No Particulars Unit 1 Concrete mixer 600/400 ltr (diesel) Hour Fuel / Energy charges Hour 2 5 hp pump (diesl) Hour Fuel / Energy charges Hour 3 Water tanker 8000 ltr Hour Fuel / Energy charges Hour 4 Needle vibrator 40 mm die (petrol) Hour Fuel / Energy charges Hour Total hire charges of Machinery C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Qty Rate in Rs. 16.00 16.00 0.50 0.50 1.00 1.00 4.00 4.00 Rs.

Amount

0.00

Description

Unit

Quantity 16.00 0.50 1.00 16.00 1.00 2.00 1.00 22.00 8.00 6.00 32.00 2.00

Rate in Rs.

Amount in Rs.

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Needle vibrator Hour work inspector Day Mason Class-I Day Fitter Day mazdoor for batching materials Day for loading mortar pans Day for laying and moving paver Day for conveying concrete Day for cleaning/ washing/ curing Day Total cost of Labour ABSTRACT A. Cost of Materials including royalty charges B. Hire charges of Machinery

Rs: Rs. Rs.

0.00 0.00 0.00

116

IRR-CAW

C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per cum=(A+B+C+D) /37

Rs. Total Rs.

0.00 0.00

0% 37 cum Rs. Rs.

0.00 0.00 0.00

IRR-CAW-7-12

Providing and laying100mm thick insitu vibrated M-10 (28 days cube compressive strength-not less than 10.00 N / sq mm) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver including cost of all materials mechinery labour batching mixing placing in position forming contraction joints fixing pvc joint seiling strips shifting of paver from one side of canal to other side etc.complete with 1 km lead & all lifts. (Cement content: 190 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSIS UNIT : 800 Sqm A. MATERIALS: Sl.No Particulars Unit Qty Rate in Rs. Amount 1 Cement 43 Gr Kg 16720.00 2 Coarse aggregate 40 mm cum 39.60 Coarse aggregate 20 mm cum 23.76 Coarse aggregate 10 mm cum 15.84 3 Fine aggregate (Screened) cum 35.20 4 Super plasticiser kg 66.88 5 PVC sealing strip Rm 533.00 6 Use rate of paving cylinder sqm 800.00 Add seignorage charges on CA &(includedd in material rate) Rs. 0.00 Add seignorage charges on FA &(includedd in material rate) Rs. 0.00 Total cost of Materials Rs. 0.00 B. MACHINERY: Sl.No Particulars Unit 1 Batching plant Hour 2 Transit mixer 3 Nos Hour Fuel / Energy charges Hour 3 Mechanical paver Hour lubricants etc @ 5% Hour 4 DG set for batching plant 50 KVAHour Fuel / Energy charges Hour 5 DG set for paver 30 KVA Hour Fuel / Energy charges Hour 6 Water tanker Hour Fuel / Energy charges Hour 7 Pump 5 hp (diesel) 2 Nos. 4 hrs each Hour Fuel / Energy charges Hour Total hire charges of Machinery

Qty Rate in Rs. 8.00 24.00 24.00 5.00 5.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 Rs.

Amount

0.00

C. LABOUR: Sl No Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Unit

Quantity 8.00 24.00 8.00 16.00 2.00 8 8 2 1 1 1 2 5 10

Rate in Rs.

Amount in Rs.

Crew for Batching plant Hour Crew for Transit mixer Hour Crew for Concrete paver Hour Crew for DG set Hour Crew for Shovel Hour Crew for Water tanker Hour Crew for Pump Hour Mason Class I Day Mechanic Day Fitter Day Electrician Day work inspector Day mazdoor ( BP site ) Day mazdoor ( Paver site ) Day Total cost of Labour ABSTRACT A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Add for shifting & re-erection of BP @

Rs: Rs. Rs. Rs. TOTAL Rs. 0% Rs.

0.00 0.00 0.00 0.00 0.00 0

117

IRR-CAW

Add for LH / RH shifting & erection of Paver @ Add for ledge cutting / erection of tracks etc @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per sqm=(A+B+C+D) /800

0.0% Rs. 0% Rs. Total

Rs:

0 0 0.00

0% 800.00 Sqm Rs. Rs.

Rs:

0 0.00 0.00

IRR-CAW-7-13

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for bed and side lining of canal including finishing the junction of bed and sides to required curveture, cost of all materials, machinery, labour, formwork including supports, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum ) (Cement content: 220 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.80 cum Fine aggregate : 0.45 cum Cement content : 220 kg RATE ANALYSIS A. MATERIALS: Sl No particulars 1 2 3 4 5 6

DATA:

Blending ratio : 65 :35 Super plasticizer : 0.88 kg. UNIT : 27.00 cum Unit Quantity Rate in Rs. Amount in Rs.

Cement for mix kg 5940 Cement for incidentals @ 5 kg / cum kg 135.00 Coarse aggregate 20-10 mm cum 14.04 Coarse aggregate 10 mm below cum 7.56 Fine aggregate cum 12.15 Super Plasticizer kg 23.76 Use rate of manual paver sqm 234.00 Sundries LS 2.00 Add seignorage charges on CA & Rs. (includedd in material rate) Add seignorage charges on FA & Rs. (includedd in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 16.00 16.00 0.50 0.50 1.00 1.00 16.00 16.00

Rate in Rs.

Amount in Rs.

Concrete mixer 600/400 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 16.00 0.50 1.00 16.00 2.00 1.00 1.00 22.00 8.00 6.00 27.00 2.00

Rate in Rs.

Amount in Rs.

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Vibrator Hour Mason Class-I Day work inspector Day Fitter Day mazdoor for batching materials Day for loading mortar pans Day for laying and moving paver Day for conveying concrete Day for cleaning/ washing/ curing Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for

Rs: Rs: Rs: Rs: Rs: Rs: Rs.

0.00 0.00 0.00 0.00 0.00 0 0.00

Total 0% 27.00 cum

118

IRR-CAW

Rate per cum=(A+B+C+D) /27

Rs:

0.00

IRR-CAW-7-14

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for bed and side lining of canal(150 mm thick) including finishing the junction of bed and sides to required curveture, cost of all materials, machinery, labour, formwork including supports, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 210 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--50:30:20, FA : 0.45 cum) Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum Cement content : 210 kg uper plasticizer : 0.84 kg S RATE ANALYSIS UNIT : A. MATERIALS: Sl No particulars Unit Quantity 1 2

DATA:

29.70 cum Rate in Rs. Amount in Rs.

3 4 5 6

Cement for mix kg 6237 Cement for incidentals @ 5 kg / cum kg 148.00 Coarse aggregate 40-20 mm cum 13.365 Coarse aggregate 20-10 mm cum 8.019 Coarse aggregate 10 mm below cum 5.346 Fine aggregate cum 11.88 Super Plasticizer kg 24.95 Use rate of manual paver sqm 216.00 Sundries LS 2.00 Add Seignorage charges on CA & Rs. (includedd in material rate) Add Seignorage charges on FA & Rs. (includedd in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 16.00 16.00 0.50 0.50 1.00 1.00 16.00 16.00

Rate in Rs.

Amount in Rs.

Concrete mixer 600/400 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 16.00 0.50 1.00 16.00 2.00 1.00 1.00 22.00 8.00 6.00 30.00 2.00

Rate in Rs.

Amount in Rs.

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Vibrator Hour Mason Class-I Day work inspector Day Fitter Day mazdoor for batching materials Day for loading mortar pans Day for laying Day for conveying concrete Day for cleaning/ washing/ curing Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /29.70

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 29.70 cum

IRR-CAW-7-15

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for bed and side lining of canal(100 mm thick) including finishing the junction of bed and sides

119

IRR-CAW

to required curveture, cost of all materials, machinery, labour, formwork including supports, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 240 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.80 cum Fine aggregate : 0.45 cum Cement content : 240 kg RATE ANALYSIS A. MATERIALS: Sl No particulars 1 2 3 4 6 7

Blending ratio : 65 :35 Super plasticizer : 0.96 kg UNIT : 25.20 cum Unit Quantity Rate in Rs. Amount in Rs.

Cement for mix kg 6804 Cement for incidentals @ 5 kg / cum kg 126.00 Coarse aggregate 20-10 mm cum 13.104 Coarse aggregate 10 mm below cum 7.056 Fine aggregate cum 11.34 Super Plasticizer kg 24.19 Use rate of manual paver sqm 270.00 Sundries LS 2.00 Add Seignorage charges on CA & Rs. (includedd in material rate) Add Seignorage charges on FA & Rs. (includedd in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 16.00 16.00 0.50 0.50 1.00 1.00 16.00 16.00

Rate in Rs.

Amount in Rs.

Concrete mixer 600/400 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit

Quantity 16.00 0.50 1.00 16.00 2.00 1.00 1.00 22.00 8.00 6.00 25.00 2.00

Rate in Rs.

Amount in Rs.

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Water tanker Hour Crew for Vibrator Hour Mason Class-I Day work inspector Day Fitter Day mazdoor for batching materials Day for loading mortar pans Day for laying and moving paver Day for conveying concrete Day for cleaning/ washing/ curing Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /25.20

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 25.20 cum

IRR-CAW-7-16

Providing and laying150mm thick insitu vibrated M-15 (28 days cube compressive strength-not less than 15.00 N / sq mm) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver including cost of all materials mechinery labour batching mixing placing in position forming contractiom joints fixing pvc joint seiling strips shifting of paver from one side of canal to other side etc.complete with 1km lead & all lifts. (Cement content: 240 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)

DATA:

120

IRR-CAW

RATE ANALYSIS UNIT : 800 Sqm A. MATERIALS: Sl.No Particulars Unit Qty Rate in Rs. Amount 1 Cement 43 Gr Kg 21120.00 2 Coarse aggregate 20 mm cum 45.76 Coarse aggregate 10 mm cum 24.64 3 Fine aggregate (Screened) cum 38.72 4 Super plasticiser ltr 84.48 5 PVC sealing strip Rm 533.00 6 Use rate of paving cylinder sqm 800.00 Add seignorage charges on CA &(included in material rate) Rs. 0.00 Add seignorage charges on FA &(included in material rate) Rs. 0.00 Total cost of Materials Rs. 0.00 B. MACHINERY: Sl.No Particulars Unit 1 Batching plant Hour 2 Transit mixer 3 Nos Hour Fuel / Energy charges Hour 3 Mechanical paver Hour lubricants etc @ 5% Hour 4 DG set for batching plant 50 KVAHour Fuel / Energy charges Hour 5 DG set for paver 30 KVA Hour Fuel / Energy charges Hour 6 Water tanker Hour Fuel / Energy charges Hour 7 Pump 5 hp (diesel) 2 Nos. 4 hrs each Hour Fuel / Energy charges Hour Total hire charges of Machinery C. LABOUR: Sl No Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Qty Rate in Rs. 8.00 24.00 24.00 5.00 5.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 Rs.

Amount

0.00

Unit

Quantity 8.00 24.00 8.00 16.00 2.00 8 8 2 1 1 1 2 5 10

Rate in Rs.

Amount in Rs.

Crew for Batching plant Hour Crew for Transit mixer Hour Crew for Concrete paver Hour Crew for DG set Hour Crew for Shovel Hour Crew for Water tanker Hour Crew for Pump Hour Mason Class I Day Mechanic Day Fitter Day Electrician Day work inspector Day mazdoor ( BP site ) Day mazdoor ( Paver site ) Day Total cost of Labour ABSTRACT A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Add for shifting & re-erection of BP @ Add for LH / RH shifting & erection of Paver @ Add for ledge cutting / erection of tracks etc @ D.Add for contractor's profit and overheads on A+B+C+percentages above Total cost for Rate per sqm=(A+B+C+D) /800

Rs: Rs. Rs. Rs. TOTAL Rs. 0% Rs. 0.0% Rs. 0% Rs. Total Rs:

0.00 0.00 0.00 0.00 0.00 0 0 0 0.00

0% 800.00 Sqm Rs. Rs.

Rs:

0 0.00 0.00

IRR-CAW-7-17

Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15 grade concrete using 20 mm down size coarse aggregates and 10 kg reinforcement steel moulded as per specifications and drawing in CM 1:4 proportion including cost of all materials, machinery, labour, formwork, fabricating and placing reinforcement steel, mixing, laying, conveying and fixing in position including necessary excavation for seating, finishing joints in CM 1:4, curing etc., complete with initial lead upto 1 km and all lifts. Details of template wall blocks: 1.80 m long inverted T - section with keys on either end. Base : 225 mm x Topmm . mm x 63 mm 87 : 75

DATA:

Key : 150 mm depth

121

IRR-CAW

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 particulars Unit

UNIT : Quantity

20.00 templete Rate in Rs. Amount in Rs.

Cement 43 Gr kg 310.00 Sand ( screened ) cum 0.50 Coarse aggregate 20-10 mm cum 0.50 Coarse aggregate 10-4.75 mm cum 0.30 Reinforcement steel kg 200.00 Binding wire kg 3.00 Use rate of mould set 20.00 Sundries( water charges & misc. ) LS 1.00 Add Seignorage charges on CA & Rs. (includedd in material rate) Add Seignorage charges on FA & Rs. (includedd in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit Hour

Quantity 8.00 0.00

Rate in Rs.

Amount in Rs.

Hand mixer Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 1.00 1.00 2.00 1.00 4.00 2.00 2.00

Rate in Rs.

Amount in Rs.

work inspector Day Mason Class I for fixing Day Mason Class II for casting Day Bar bender Day mazdoor ( casting yard ) Day mazdoor ( for fixing ) Day mazdoor for conveying Day Total cost of Labour ABSTRACT: A. Cost of Materials including serignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /20

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 20.00 template

IRR-CAW-7-18

Providing and fixing 50 mm dia perforated GI pressure relief pipes 12.50 cm long with one end closed with perforated GI plate and other end provided with alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all leads and lifts. Consider 10 Nos perforated 50 mm dia GI pipes 12.50 cm long each.

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars GI pipe 50 mm dia 10 Nos GI plate & Alluminium lid ( hinged ) Total cost of Materials Unit Rm LS

UNIT : Quantity 1.25 10.00 Rate in Rs.

10 Nos. Amount in Rs.

Rs:

0.00

B. MACHINERY: Sl No 1

Description

Unit LS

Quantity 0.50 0.00

Rate in Rs.

Amount in Rs.

Drilling 8 mm dia holes Total hire charges of Machinery

Rs:

0.00

122

IRR-CAW

C. LABOUR: Sl No 1 Pipe fitter mazdoor

Description

Unit Day Day

Quantity 0.50 0.50

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /10 0% 10.00 Nos. Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0

IRR-CAW-7-19

Providing and fixing 50 mm dia perforated GI pressure relief pipes 22.50 cm long with one end closed with perforated GI plate and other end provided with alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all leads and lifts. Consider 10 Nos perforated 50 mm dia GI pipes 22.50 cm long each. Nos. RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars GI pipe 50 mm dia 10 Nos GI plate & Alluminium lid ( hinged ) Total cost of Materials Unit Rm LS UNIT : Quantity 2.25 10.00 Rs: 0.00 Rate in Rs. 10 Amount in Rs.

DATA:

B. MACHINERY: Sl No 1

Description

Unit LS

Quantity 5.00 0.00

Rate in Rs.

Amount in Rs.

Drilling 8 mm dia holes Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 Pipe fitter mazdoor

Description

Unit Day Day

Quantity 0.50 0.50

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /10 0% 10.00 Nos. Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0

IRR-CAW-7-20

Providing and fixing 50 mm dia perforated GI pressure relief pipes 30 cm long with one end closed with perforated GI plate and other end provided with alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all leads and lifts. Consider 10 Nos perforated 50 mm dia GI pipes 30 cm long each. Nos. RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars GI pipe 50 mm dia 10 Nos GI plate & Alluminium lid ( hinged ) Total cost of Materials Unit Rm LS UNIT : Quantity 3.00 10.00 Rs: 0.00 Rate in Rs. 10 Amount in Rs.

DATA:

B. MACHINERY: Sl No 1

Description

Unit LS

Quantity 7.00 0.00

Rate in Rs.

Amount in Rs.

Drilling 8 mm dia holes

123

IRR-CAW

Total hire charges of Machinery C. LABOUR: Sl No 1 Pipe fitter mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /10 0% 10.00 Nos. Rs.

Rs:

0.00

Description

Unit Day Day

Quantity 0.50 0.50

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

IRR-CAW-7-21

Providing and fixing 50 mm dia perforated GI pressure relief pipes 45 cm long with one end closed with perforated GI plate and other end provided with alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all leads and lifts. Consider 10 Nos perforated 50 mm dia GI pipes 45 cm long each. RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars GI pipe 50 mm dia 10 Nos GI plate & Alluminium lid ( hinged ) Total cost of Materials Unit Rm LS UNIT : Quantity 4.50 10.00 10 Nos. Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

DATA:

B. MACHINERY: Sl No 1

Description

Unit LS

Quantity 10.00 0.00

Drilling 8 mm dia holes Total hire charges of Machinery

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

C. LABOUR: Sl No 1 Pipe fitter mazdoor

Description

Unit Day Day

Quantity 0.50 0.50

Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /10

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 10.00 Nos.

IRR-CAW-7-22

Providing and fixing 50 mm dia perforated GI pressure relief pipes 75 cm long with one end closed with perforated GI plate and other end provided with alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all leads and lifts. Consider 10 Nos perforated 50 mm dia GI pipes 75 cm long each. RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars GI pipe 50 mm dia GI plate & Alluminium lid ( hinged ) Total cost of Materials Unit Rm LS UNIT : Quantity 7.50 10.00 Rs: 0.00 Rate in Rs. 10 Nos. Amount in Rs.

DATA:

B. MACHINERY: Sl No

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

124

IRR-CAW

Drilling 8 mm dia holes Total hire charges of Machinery

LS

15.00 0.00 Rs: 0.00

C. LABOUR: Sl No 1 2 Pipe fitter mazdoor

Description

Unit Day Day

Quantity 0.50 0.50

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /10 0% 10.00 Nos. Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

IRR-CAW-7-23

Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Weep holes including cost of all materials, labour, drilling 8 mm dia holes etc. complete with all leads and lifts. Consider 10 Nos 100 mm dia PVC pipes 40 cm long each RATE ANALYSIS A. MATERIALS: Sl.No Particulars 1 PVC pipe 100 mm dia 10 Nos Total cost of Materials Unit Rm Qty Rate in Rs 10.00 Rs. Amount in Rs. 0.00 UNIT: 10 Nos.

DATA:

B. MACHINERY Sl.No 1 Nill Total hire chargs of Machinery C. LABOUR Sl.No Particulars 1 Pipe fitter 2 Man Mazdoor Total cost of Labour ABSTRACT A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /10 Unit Day Day Qty Rate in Rs 0.25 0.25 Rs. Rs. Rs. Rs. Total 0% 10.00 Nos. Rs. Rs. Amount in Rs. Description Unit Quantity 0.00 0.00 Rs. 0.00 Rate in Rs. Amount in Rs.

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Rs: Rs:

IRR-CAW-7-24

Drilling 32 mm dia pressure relief hole below pressure relief pipe for bed and side lining of canal laid on rock including cost of all materials, machinery, labour etc., complete with all leads and lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Use rate of drill rod 1.6 m long Reconditioning charges @ Use rate of air hose 2 Nos. Total cost of Materials Unit Rm Hour UNIT : Quantity 10.00 10% 2.00 Rs: 0.00 Rate in Rs. 10 Nos. Amount in Rs.

B. MACHINERY: Sl No 1

Description

Unit Hour

Quantity 1.00

Rate in Rs.

Amount in Rs.

Air compressor 8.5 cmm diesel

125

IRR-CAW

Fuel / Energy charges Jack hammer 2 Nos. Fuel / Energy charges Total hire charges of Machinery

Hour Hour Hour

1.00 2.00 2.00 Rs: 0.00

C. LABOUR: Sl No 1 2

Description Crew for Air compressor Crew for Jack hammer Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /10

Unit Hour Hour

Quantity 1.00 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 10.00 Nos.

IRR-CAW-7-25

Providing and forming 35 x 35 x 40 cm deep filter drain consisting of 75 mm thick 10 mm down coarse aggregate around pressure relief pipe and 75 mm thick sand around coarse aggregate filter including cost of all materials, labour, excavation of pit etc., complete with lead upto 50 m and all lifts. Consider 10 Nos filter drains. Requirement of 10 mm down aggregate @ 0.015 cum / No. Requirement of sand @ 0.035 cum / No. RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit

DATA:

: : UNIT : Quantity

0.15 cum 0.35 cum 10 Nos. Rate in Rs. Amount in Rs.

Coarse aggregate 10-4.75 mm cum 0.15 Sand ( unscreened ) cum 0.35 Add seignorage charges for Sand ( included in the material cost) Add seignorage charges for CA ( included in the material cost) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00

Rate in Rs.

Amount in Rs. 0.00 0.00

Rs:

C. LABOUR: Sl No 1 2

Description Mason Cl- II mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Day Day

Quantity 0.10 0.10

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /10 0% 10 Nos.

IRR-CAW-7-26

Providing and fixing 25 to 40 mm thick Shahabad / Talikota / other similar stone slabs with pointing and finishing joints neatly in CM 1:3 proportion for canal / field channel lining including cutting slabs to required size, mixing mortar, finishing joints neatly, curing etc., complete with lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Shahabad Stone slabs Unit sqm UNIT : Quantity 105.00 100.00 sqm Rate in Rs. Amount in Rs.

126

IRR-CAW

2 3

Cement 43 Gr kg 200.00 Sand ( screened ) cum 0.40 Add seignorage charges for Slabs ( included in the material cost) Add seignorage charges for sand ( included in the material cost) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit Hour Hour

Quantity 2.00 2.00

Rate in Rs.

Amount in Rs.

5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Operator pump work inspector Mason Class I Mason Class II mazdoor Cartman with Bullock cart for water Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

Unit Hour Day Day Day Day Day

Quantity 2.00 1.00 4.00 2.00 8.00 1.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100 sqm

IRR-CAW-7-27

Fixing PCC slabs of various sizes in CM 1 : 3 proportion to the side slopes of canal including preparing bed, flush pointing joints in CM 1 : 3 propn, cost of all materials ( excluding PCC slabs ), labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit UNIT : Quantity 100.00 sqm Rate in Rs. Amount in Rs.

Cement 43 Gr kg 240.00 Sand ( screened) cum 0.50 Add seignorage charges for sand ( included in the material cost) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit Hour Hour

Quantity 2.00 2.00

Rate in Rs.

Amount in Rs.

5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5

Description Operator pump work inspector Mason Class I mazdoor Cartman with Bullock cart for water Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

Unit Hour Day Day Day Day

Quantity 2.00 1.00 4.00 9.00 1.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100 sqm

IRR-CAW-7-28

Fixing PCC lug slabs of various sizes in CM 1 : 3 proportion for supporting PCC slab lining

127

IRR-CAW

including necessary excavation, refilling, flush pointing joints in CM 1 : 3 propn, cost of all materials ( excluding PCC lug slabs ), labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit UNIT : Quantity 100.00 Rm Amount in Rs. 0.00 0.00 0.00 0.00

Rate in Rs. Cement 43 Gr kg 58.00 0.00 Sand ( screened) cum 0.12 0.00 Add Seignorage charges on FA @ Rs. (included in material rate) Rs: Total cost of Materials Rs:

B. MACHINERY: Sl No 1

Description

Unit Hour Hour

Quantity 1.00 1.00

5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Operator pump work inspector Mason Class I Mason Class II mazdoor Cartman with Bullock cart for water Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /100

Unit Hour Day Day Day Day Day

Quantity 1.00 1.00 2.00 1.00 5.00 1.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100 Rm

IRR-CAW-7-29

Fixing 30 cm height pre-cast drops for field channels as directed including excavation, etc., complete with all leads and lifts. Requirement of materials for fixing drops. : Nill Consider 1 work inspector, 1 Mason CL- II & 1 mazdoor for fixing 7 drops per day. RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Nill Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 Rate in Rs. 7 Nos. Amount in Rs.

DATA:

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description work inspector Mason Cl- II mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Day Day Day

Quantity 1.00 1.00 1.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

Total

128

IRR-CAW

D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /7

0% 7 Nos

Rs: Rs: Rs:

0 0.00 0.00

IRR-CAW-7-30

Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials, labour, laying, joining etc., complete with all leads and lifts. a. Using 500 micron thick LDPE sheet. Consider 250 sqm LDPE sheet 500 micron thick laying per day. Consider 10 percent extra sheet for joints & wastage. Hot bitumen Grade 85 / 25 and 80 / 100 in the ratio of 2 : 1 considered for joining sheets. Consider 1 mazdoor for assisting in laying work by supplier.

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars LDPE sheet 500 micron thick Bitumen 85 / 25 and 80 / 100 Gr Total cost of Materials Unit sqm kg

UNIT : Quantity 275.00 4.00

250.00 sqm Rate in Rs. Amount in Rs.

Rs:

0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description

Unit

Quantity 250.00 1.00

Rate in Rs.

Amount in Rs.

Joining & laying @ 10 % of sheet cost qm s mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /250

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 250 sqm

Note :

i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide average 75 mm thick unscreened sand backing to LDPE sheet. For providing average 75 mm thick sand backing :

DATA:

Quantity of sand ( unscreened ) ( 250 x 0.075 ) 2 mazdoors for laying 6 cum per day. RATE ANALYSIS UNIT : Unit cum Quantity 18.75 0.00 250.00 sqm Rate in Rs.

18.75

A. MATERIALS: Sl No 1

particulars Sand ( unscreened )

Amount in Rs.

129

IRR-CAW

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 mazdoor

Description

Unit Day

Quantity 6.00

Rate in Rs. Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /250 0% 250 sqm

IRR-CAW-7-31

Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials, labour, laying, joining etc., complete with all leads and lifts. b. Using 750 micron thick LDPE sheet. Consider 250 sqm LDPE sheet 750 micron thick laying per day. Consider 10 percent extra sheet for joints & wastage. Hot bitumen Grade 85 / 25 and 80 / 100 in the ratio of 2 : 1 considered for joining sheets. Consider 1 mazdoor for assisting in laying work by supplier. RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars LDPE sheet 750 micron thick Bitumen 85 / 25 and 80 / 100 Gr Total cost of Materials Unit UNIT : Quantity 275.00 4.00 Rs: 0.00 250.00 sqm Rate in Rs. Amount in Rs.

DATA:

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description

Unit

Quantity 250.00 1.00

Rate in Rs.

Amount in Rs.

Joining & laying @ 10 % of sheet cost qm s mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /250

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 250 sqm

Note :

i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide average 75 mm thick unscreened sand backing to LDPE sheet. For providing average 75 mm thick sand backingper sqm add Rs: 0.00

IRR-CAW-7-32

Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials, labour, laying, joining etc., complete with all leads and lifts. c. Using 1000 micron thick LDPE sheet. Consider 250 sqm LDPE sheet 750 micron thick laying per day. RATE ANALYSIS

DATA:

UNIT :

250.00 sqm

130

IRR-CAW

A. MATERIALS: Sl No 1 2

particulars LDPE sheet 1000 micron thick Bitumen 85 / 25 and 80 / 100 Gr Total cost of Materials

Unit

Quantity 275.00 4.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description

Unit

Quantity 250.00 1.00

Rate in Rs.

Amount in Rs.

Joining & laying @ 10 % of sheet cost qm s mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /250

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 250 sqm

Note :

i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide average 75 mm thick unscreened sand backing to LDPE sheet. For providing average 75 mm thick sand backingper sqm add Rs: 0.00

IRR-CAW-7-33

Providing and fixing 12 mm thick 380 mm depth tarfelt expansion joint filler boards for stone masonry lining of canal including cost of all materials, labour etc., complete with all leads and lifts. Consider 100 m length of expansion joint. RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Unit UNIT : Quantity 38.75 0.00 Rs: 0.00 100.00 Rm Rate in Rs. Amount in Rs.

DATA:

Tarfelt joint filler board 12 mm thick sqm Total cost of Materials

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description Carpenter Cl- II mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /100

Unit Day Day

Quantity 1.00 1.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100 Rm

IRR-CAW-7-34

Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler boards for cement concrete lining of canal including cost of all materials, labour etc., complete with all leads and lifts.

131

IRR-CAW

DATA:

Consider 100 m length of expansion joint. RATE ANALYSIS A. MATERIALS: Sl No particulars 1

UNIT : Unit Quantity 10.00 0.00

100.00 Rm Rate in Rs. Amount in Rs.

Tarfelt joint filler board 20 mm thick sqm Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description Carpenter Cl- II mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /100

Unit Day Day

Quantity 1.00 1.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100 Rm

IRR-CAW-7-35

Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler boards for cement concrete lining of canal including cost of all materials, labour etc., complete with all leads and lifts. Consider 100 m length of expansion joint. RATE ANALYSIS A. MATERIALS: Sl No particulars 1

DATA:

UNIT : Unit Quantity 15.30 0.00

100.00 Rm Rate in Rs. Amount in Rs.

Tarfelt joint filler board 20 mm thick sqm Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description Carpenter Cl- II mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /100

Unit Day Day

Quantity 1.00 1.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100 Rm

IRR-CAW-7-36

Providing and forming 35 mm wide and 10 mm thick construction / contraction joints for concrete lining by mastic filler including cost of all materials, labour etc., complete with all leads and lifts. Consider 100 m length mastic filler joint.

DATA:

132

IRR-CAW

RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Unit

UNIT : Quantity

100.00 Rm Rate in Rs. Amount in Rs.

Asphalt 80/100 Gr kg 35.00 Sand ( screened ) cum 0.04 Add for seignorage charges for sand (included in the material rates)Rs: Total cost of Materials Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

C. LABOUR: Sl No 1 2

Description Mason Cl- II mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Day Day

Quantity 0.50 1.00

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /100 0% 100 Rm

IRR-CAW-7-37

Manufacturing 550 x 550 x 55 mm size PCC lining slabs in M-15 grade ( 28 days cube compressive strength not less than 15 N /sqmm ) cement concrete using 20 mm down graded coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying, compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 240 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum) RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 particulars Cement for mix Cement for incidentals @ 1 kg / slab Coarse aggregate 20-10 mm Coarse aggregate 10 mm below Fine aggregate ( screened ) Super Plasticizer Use rate of moulds for 500 uses Add Seignorage charges on CA @ Rs. (Included in material rate) Add Seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials Unit kg kg cum cum cum kg No. UNIT : Quantity 900.00 225.00 1.95 1.05 1.69 3.60 225.00 225 Nos. Rate in Rs. Amount in Rs.

DATA:

Rs:

0.00

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 0.10 0.10 0.20 0.20 0%

Rate in Rs.

Amount in Rs.

Concrete mixer 300/200 ltr ( diesel) Hour Fuel / Energy charges Hour 5 hp pump ( diesel ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Total hire charges of Machinery Aportioned hire charges of machinery for lining slab

Rs: Rs:

0.00 0.00

C. LABOUR: Sl No 1

Description Crew for Concrete mixer

Unit Hour

Quantity 8.00

Rate in Rs.

Amount in Rs.

133

IRR-CAW

2 3 4 5 6

Crew for Pump Hour Crew for Water tanker Hour Mason Class-I Day work inspector Day mazdoor for batching materials / laying CC Day for demoulding / oiling / laying Day for shifting slabs to curing pond Day for stacking after curing Day for cleaning & miscellaneous Day Total cost of Labour Aportioned cost of labour for lining slabs ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /225

0.10 0.20 2.00 1.00 3.00 2.00 1.00 1.00 1.00 0% Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 225 Nos

IRR-CAW-7-38

Manufacturing 550 x 300 x 55 mm size PCC lug slabs in M-15 grade ( 28 days cube compressive strength not less than 15 N / sqmm ) cement concrete using 20 mm down graded coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying, compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 240 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum) For 1 cum CC :- Coarse aggregates : 0.80 cum Blending ratio : 65 : 35 Fine aggregate : 0.45 cum Cement content : 240 kg Super plasticizer : 0.96 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No particulars Unit Quantity 1 2 3 4 5

DATA:

25 Nos. Rate in Rs. Amount in Rs.

Cement for mix kg 54.00 Cement for incidentals @ 0.5 kg/slab kg 12.50 Coarse aggregate 20-10 mm cum 0.12 Coarse aggregate 10 mm below cum 0.06 Fine aggregate ( screened ) cum 0.10 Super Plasticizer kg 1.08 Use rate of moulds for 500 uses No. 25.00 Add Seignorage charges on CA @ Rs. (Included in material rate) Add Seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 0.10 0.10 0.20 0.20 0%

Rate in Rs.

Amount in Rs.

Concrete mixer 300/200 ltr ( diesel) Hour Fuel / Energy charges Hour 5 hp pump ( diesel ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Total hire charges of Machinery Aportioned hire charges of machinery for lug slabs

Rs: Rs:

0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 8.00 0.10 0.20 2.00 1.00 3.00 2.00 1.00 1.00 1.00 0%

Rate in Rs.

Amount in Rs.

Crew for Concrete mixer Hour Crew for Pump Hour Crew for Water tanker Hour Mason Class-I Day work inspector Day mazdoor for batching materials / laying CC Day for demoulding / oiling / laying Day for shifting slabs to curing pond Day for stacking after curing Day for cleaning & miscellaneous Day Total cost of Labour Aportioned cost of labourfor lug slabs ABSTRACT:

Rs: Rs:

0.00 0.00

134

IRR-CAW

A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /25 0% 25 Nos

Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0 0.00 0.00

IRR-CAW-7-39

Manufacturing 450 x 300 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying, compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 280 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA : 0.43cum)

DATA:

For 1 cum CC :-

Coarse aggregates : 0.68 cum Cement content : 280 kg RATE ANALYSIS particulars Unit

Fine aggregate : 0.43 cum Super plasticizer : 1.12 kg UNIT : 225 Nos. Quantity Rate in Rs. Amount in Rs.

A. MATERIALS: Sl No 1 2 3 4 5

Cement for mix kg 252.00 Cement for incidentals @ 0.5 kg/slab kg 112.50 Coarse aggregate 10 mm below cum 0.61 Fine aggregate ( screened ) cum 0.39 Super Plasticizer kg 1.44 Use rate of moulds for 250 uses No. 225.00 Add Seignorage charges on CA @ Rs. (Included in material rate) Add Seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 0.10 0.10 0.20 0.20 0%

Rate in Rs.

Amount in Rs.

Hand mixer 45 / 30 ltr Hour Fuel / Energy charges Hour 5 hp pump ( diesel ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Total hire charges of Machinery Aportioned hire charges of machinery for lining slab

Rs: Rs:

0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 0.10 0.20 2.00 1.00 2.00 2.00 1.00 1.00 1.00 0%

Rate in Rs.

Amount in Rs.

Crew for Pump Hour Crew for Water tanker Hour Mason Class-I Day work inspector Day mazdoor for batching / mixing / laying Day for demoulding / cleaning / oiling Day for shifting slabs to curing pond Day for stacking after curing Day for cleaning & miscellaneous Day Total cost of Labour Aportioned cost of labour for lining slabs ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /225

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 225 Nos

IRR-CAW-7-40

Manucturing 450 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying, compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.

135

IRR-CAW

( Cement content : 280 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA : 0.43cum)

DATA:

For 1 cum CC :-

Coarse aggregates : 0.68 cum Cement content : 280 kg RATE ANALYSIS particulars

Fine aggregate : 0.43 cum Super plasticizer : 1.12 kg UNIT : Unit Quantity 14.00 7.50 0.03 0.02 0.06 25.00 Rate in Rs.

25 Nos. Amount in Rs.

A. MATERIALS: Sl No 1 2 3 4 5

Cement for mix kg Cement for incidentals @ 0.3 kg/slab kg Coarse aggregate 10 mm below cum Fine aggregate ( screened ) cum Super Plasticizer kg Use rate of moulds for 250 uses No. Add Seignorage charges on CA @ Rs. Add seignorage charges on FA @ Rs. Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 0.10 0.10 0.20 0.20 0%

Rate in Rs.

Amount in Rs.

Hand mixer 45 / 30 ltr Hour Fuel / Energy charges Hour 5 hp pump ( diesel ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Total hire charges of Machinery Aportioned hire charges of machinery for lug slabs

Rs: Rs:

0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 0.10 0.20 2.00 1.00 2.00 2.00 1.00 1.00 1.00 0%

Rate in Rs.

Amount in Rs.

Crew for Pump Hour Crew for Water tanker Hour Mason Class-I Day work inspector Day mazdoor for batching / mixing / laying Day for demoulding / cleaning / oiling Day for shifting slabs to curing pond Day for stacking after curing Day for cleaning & miscellaneous Day Total cost of Labour Aportioned cost of labour for lug slabs ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /25

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 25 Nos

IRR-CAW-7-41

Manufacturing 600 x 300 x 100mm size PCC lining slabs in M-15 grade (28 days cube compressive than 15 N/Sqmm) cement concrete using 10mm down grades coarse aggregate including cost of all machinery, labour, batching, mixing, laying, compacting, formwork, finishing, curing etc., complete 50 m and all lifts. ( Cement content : 280 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum, FA : 0.45cum, Blending Ratio of CA--65:35) For 1 cum CC :- Coarse aggregates : 0.80 cum Fine aggregate : 0.45 cum Cement content : 280kg Super placticizer : 1.12 kg UNIT: RATE ANALYSIS 225 Nos. A. MATERIALS : Sl. No 1 2 3 4 Particulars Unit Quantity 252 112.5 0.468 0.252 Rate in Rs. Amount in Rs.

DATA

Cement for mix Kg Cement for incidentals @ 0.5kg/slab Kg Coarse aggregate 20 mm below Cum Coarse aggregate 10 mm below Cum

136

IRR-CAW

5 6 7

Fine aggregate (screened) Cum 0.414 Super Plasticizer kg 1.01 Use rate of moulds for 250 uses No. 225 Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total Cost of Materials Rs.

0 0 0

B. MACHINERY : Sl. No 1 2 3 Particulars Unit Quantity 8 8 0.1 0.1 0.2 0.2 Rs. 0% 0.00 0.00 Rate in Rs. Amount in Rs.

Diesel mixer 300/400 Hour Fuel/Energy charges Hour 5 hp pump (diesel) Hour Fuel/Energy charges Hour Water tanker 8000 ltr Hour Fuel/Energy charges Hour Total hire charges of Machinery Aportioned hire charges of

C. LABOUR : Sl. No 1 2 3 4 5

Particulars

Unit

Quantity 0.1 0.2 2 1 2 2 1 1 1 Rs. 0%

Rate in Rs.

Amount in Rs.

Crew for Pump Hour Crew for water tanker Hour Mason Class-I Day Class II Mason Day ManMazdoor For batching materials/laying Day For demoulding/cleaning/oiling For shifting slabs to curing pond For stacking after curing For cleaning & miscellaneous Day Total Cost of Labour Aportioned cost of labour for ABSTRACT : A. Cost of Material including seignorage B. Hire Charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /225

0.00 0.00 Rs. Rs. Rs. Rs: Rs: Rs. Rs. 0 0.00 0.00 0.00 0 0.00 0

Total 0% 225 Nos

IRR-CAW-7-42

Manucturing 400 x 400 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube compressive strength not less than 15 N / sqmm )cement concrete using 10 mm down graded coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying, compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 280 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA : 0.43cum) For 1 cum CC :- Coarse aggregates : 0.68 cum Fine aggregate : 0.43 cum Cement content :Super plasticizer : 1.12 kg 280 kg RATE ANALYSIS UNIT : 225 Nos. A. MATERIALS: Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Cement for mix kg 302.40 Cement for incidentals @ 0.5 kg/slab kg 112.50 2 Coarse aggregate 10 mm below cum 0.73 3 Fine aggregate ( screened ) cum 0.46 4 Super Plasticizer kg 1.21 5 Use rate of moulds for 250 uses No. 225.00 Rs: 0.00 Add Seignorage charges on CA @ Rs. Rs: 0.00 Add seignorage charges on FA @ Rs. Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No 1 2

DATA:

Description

Unit Hour Hour Hour Hour

Quantity 8.00 8.00 0.10 0.10

Rate in Rs.

Amount in Rs.

Hand mixer 45 / 30 ltr Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges

137

IRR-CAW

Water tanker 8000 ltr Hour Fuel / Energy charges Hour Total hire charges of Machinery Aportioned hire charges of machinery for lining slab

0.20 0.20 0% Rs: Rs: 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 0.10 0.20 2.00 1.00 2.00 2.00 1.00 1.00 1.00 0%

Rate in Rs.

Amount in Rs.

Crew for Pump Hour Crew for Water tanker Hour Mason Class-I Day work inspector Day mazdoor for batching / mixing / laying Day for demoulding / cleaning / oiling Day for shifting slabs to curing pond Day for stacking after curing Day for cleaning & miscellaneous Day Total cost of Labour Aportioned cost of labour for lining slabs ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /225

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 225 Nos

IRR-CAW-7-43

Manufacturing 400 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube compressive strength not less than 15 N /sqmm ) cement concrete using 10 mm down graded coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying, compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 280 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA : 0.43cum)

DATA:

For 1 cum CC :-

Coarse aggregates : 0.68 cum Cement content : 280 kg RATE ANALYSIS particulars Unit

Fine aggregate : 0.43 cum Super plasticizer : 1.12 kg UNIT : 25 Nos. Quantity 12.60 7.50 0.03 0.02 0.05 25.00 Rs: Rs: Rs: 0.00 0.00 0.00 Rate in Rs. Amount in Rs.

A. MATERIALS: Sl No 1 2 3 4 5

Cement for mix kg Cement for incidentals @ 0.3 kg/slab kg Coarse aggregate 10 mm below cum Fine aggregate ( screened ) cum Super Plasticizer kg Use rate of moulds for 250 uses No. Add Seignorage charges on CA @ Rs. Add Seignorage charges on FA @ Rs. Total cost of Materials

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity 8.00 8.00 0.10 0.10 0.20 0.20 0%

Rate in Rs.

Amount in Rs.

Hand mixer 45 / 30 ltr Hour Fuel / Energy charges Hour 5 hp pump ( diesel ) Hour Fuel / Energy charges Hour Water tanker 8000 ltr Hour Fuel / Energy charges Hour Total hire charges of Machinery Aportioned hire charges of machinery for lug slabs

Rs: Rs:

0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5

Description Crew for Pump Crew for Water tanker Mason Class-I work inspector mazdoor for batching / mixing / laying

Unit Hour Hour Day Day Day

Quantity 0.10 0.20 2.00 1.00 2.00

Rate in Rs.

Amount in Rs.

138

IRR-CAW

for demoulding / cleaning / oiling Day for shifting slabs to curing pond Day for stacking after curing Day for cleaning & miscellaneous Day Total cost of Labour Aportioned cost of labour for lug slabs ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /25

2.00 1.00 1.00 1.00 0% Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 25 Nos

IRR-CAW-7-44

Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side lining using stones and chips from approved quarry including cost of all materials, machinery, labour, forming weep holes at specified intervals, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (rubble stones : 0.96 cum, Stone Chips : 0.15cum, Through Stones 20 x 20 x 30cm : 1/sqm)

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 particulars Unit UNIT : Quantity 10.00 cum Rate in Rs. Amount in Rs.

Cement 43 Gr kg 1152.00 Sand ( screened ) cum 4.00 Uncoursed rubble stones at quarry cum 9.60 Through stones 20x20x30 cm Nos 32.00 Stone chips at quarry cum 1.50 Add seignorage charges on UCR (/ Included in material rate ) chips @ Rs Add seignorage charges on sand (@ Rs Included in material rate ) Total cost of Materials

Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit Hour Hour

Quantity 4.00 4.00

Rate in Rs.

Amount in Rs.

5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description

Unit

Quantity 4.00 1.00 2.00 2.00 8.00 1.00

Rate in Rs.

Amount in Rs.

Operator pump Hour work inspector Day Mason Class I Day Mason Class II Day mazdoor Day Cartman with Bullock cart for water Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 10 cum

IRR-CAW-7-45

Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side lining using stones from approved quarry including cost of all materials, machinery, labour, forming weep holes at specified intervals, curing etc., complete with initial lead upto 50m and all lifts.(without pin headers) ( rubble stones : 1.1 cum)

DATA

Requirement of materials for laying 10 cum UCR Masonry lining in CM 1:5 UNIT: RATE ANALYSIS
A. MATERIALS :

10 Rate Amount in Rs.

Sl. No

Particulars

Unit

Quantity

139

IRR-CAW

Sl. No 1 2 3

Particulars

Unit

Quantity

in Rs. Cement 43 Gr Kg 979.2 Sand (Screened) Cum 3.4 Uncoursed rubble stones at Cum 11 quarry Add seignorage charges on UCR/chips @ (Included in material rate) Add seignorage charges on sand @ Rs. (Included in material rate) Total Cost of Materials Rs. B. MACHINERY :

Amount in Rs.

0 0 0

Sl. No 1 2

Particulars Hand Mixing Charges 5 hp pump (diesel) Fuel / Energy charges

Unit Hour Hour Hour

Quantity 8 4 5 Rs.

Rate in Rs.

Amount in Rs.

Total hire charges of Machinery C. LABOUR : Sl. No 1 2 3 4 5 Particulars Unit

0.00

Quantity 4 13 6 29 1 Rs.

Rate in Rs.

Amount in Rs.

Operator pump Hour Mason Class I Day Mason Class II Day Man Mazdoor Day Cartman with Bullock cart for Day water Total Cost of Labour ABSTRACT : A. Cost of Material including seignorage B. Hire Charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10

0.00 Rs. Rs. Rs. Rs: Rs: Rs. Rs. 0 0 0.00 0.00 0 0.00 0.00

Total 0% 10 cum

IRR-CAW-7-46

Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side lining using stones and chips from canal excavation including cost of all materials, machinery, labour, forming weep holes at specified interval, finishing, curing etc., complete with initial lead upto 50 m and all lifts. ( rubble stones : 0.96 cum, Stone Chips : 0.15cum, Through Stones 20 x 20 x 30cm : 1/sqm) Stones and chips will be issued from dump yard at specified issue rate.

Note: DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 particulars Unit

UNIT : Quantity

10.00 cum Rate in Rs. Amount in Rs.

Cement 43 Gr kg 1144.00 Sand ( screened ) cum 4.00 Uncoursed rubble at dump yard cum 9.60 Through stones 20x20x30 cm Nos 33.00 Stone chips at dump yard cum 1.50 Add seignorage charges on UCR (/ Included in material rate ) chips @ Rs Add seignorage charges on sand (@ Rs Included in material rate ) Total cost of Materials

Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit Hour Hour

Quantity 4.00 4.00

Rate in Rs.

Amount in Rs.

5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description Operator pump work inspector Mason Class I

Unit Hour Day Day

Quantity 4.00 1.00 2.00

Rate in Rs.

Amount in Rs.

140

IRR-CAW

4 5 6 7

Mason Class II Day Crowbarman Day mazdoor Day Cartman with Bullock cart for water Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10

2.00 1.00 9.00 1.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs: 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 10 cum

IRR-CAW-8 IRR-CAW-8-1

ROCK PITCHING: Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side lining using stones from canal excavation including cost of all materials, machinery, labour, forming weep holes at specified intervals, finishing, curing etc., complete with initial lead upto 50m and all lifts. ( rubble stones : 1.1cum, cement : 98kg, sand 0.34 cum) Requirement of materials for laying 10 cum UCR Masonry lining in CM 1:5 UNIT: RATE ANALYSIS A. MATERIALS: Sl. No 1 2 3 Particulars Cement 43 Gr Sand (Screened) Uncoursed rubble at dump yard Unit Kg Cum Cum Quantity 980 3.4 11 0 0 0

DATA

10

Cum

Rate in Rs.

Amount in Rs.

Add seignorage charges on UCR/chips @ (Included in material rate) Add seignorage charges on sand @ Rs. (Included in material rate) Total Cost of Materials Rs. B. MACHINERY : Sl. No 1 2 Particulars Hand Mixing Charges Unit Hour Quantity 8 4 5 Rs. Rate in Rs.

Amount in Rs.

5 hp pump (diesel) Hour Fuel / Energy charges Hour Total hire charges of Machinery C. LABOUR :

Sl. No 1 2 3 4 5

Particulars Operator pump Mason Class I Mason Class II

Unit Hour Day Day

Quantity 4 13 6 29 1 Rs.

Rate in Rs.

Amount in Rs.

Man Mazdoor Day Cartman with Bullock cart for Day water Total Cost of Labour ABSTRACT : A. Cost of Material including seignorage B. Hire Charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10

0.00 Rs. Rs. Rs. Rs: Rs: Rs. Rs. 0 0 0.00 0.00 0 0.00 0.00

Total 0% 10 cum

IRR-CAW-8-2

Providing and constructing 25 cm thick dry rubble stone pitching with pin headers at 2 per sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial lead upto 50 m and all lifts. ( rubble stones : 0.23 cum/sqm, Stone Chips : 0.0375cum/sqm, Pin Headers 30cm : 2/sqm) Requirement of materials for constructing 100 sqm pitching: RATE ANALYSIS A. MATERIALS:

DATA:

UNIT :

100.00 sqm

141

IRR-CAW

Sl No 1 2 3

particulars

Unit

Quantity

Rate in Rs.

Amount in Rs.

Uncoursed rubble stones at quarry cum 23.00 Pin header (Through stone) 30 cm Nos 200.00 Stone chips at quarry cum 3.75 Add seignorage charges on UCR (/ Included in material rate ) chips @ Rs Total cost of Materials

Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit

Quantity 1.00 5.00 6.00

Rate in Rs.

Amount in Rs.

work inspector Day Mason Class II Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100 sqm

Note: DATA:

If 15 cm thick murum bed is to be provided below pitching (Murum : 18 cum/sqm) Consider 100 sqm area of pitching: Requirement of labour for spreading and tamping: Consider 4 mazdoors. RATE ANALYSIS UNIT : Unit cum Quantity 100.00 sqm Rate in Rs. Amount in Rs.

A. MATERIALS: Sl No 1 Murum

particulars

18.00 0.00 Add seignorage charges on murum @ Rs in material rate ) ( Included Total cost of Materials

Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 mazdoor

Description

Unit

Quantity 4.00

Rate in Rs. Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

Total 0% 100 sqm

IRR-CAW-8-3

Providing and constructing 25 cm thick dry rubble stone pitching including cost of all materials, labour, hand packing, finishing etc., complete ( rubble stones : 0.33 cum/sqm) Requirement of materials for constructing 100 Sqm pitching : RATE ANALYSIS UNIT: 100

DATA

142

IRR-CAW

A. MATERIALS : Sl. No 1 Particulars Unit Quantity Rate in Rs. Amount in Rs.

Uncoursed rubble stones at Cum 33 quarry Add seignorage charges on UCR/chips @ (Included in material rate) Total Cost of Materials Rs. B. MACHINERY :

0 0

Sl. No 1

Particulars Nil

Unit

Quantity 0 0 Rs.

Rate in Rs.

Amount in Rs.

Total hire charges of Machinery C. LABOUR : Sl. No 1 2 Particulars Mason Class II Mazdoor Unit Day Day Total Cost of Labour

Quantity 0.4 3.1 Rs.

Rate in Rs.

Amount in Rs.

0.00 Rs. Rs. Rs. Rs: Rs: Rs. Rs. 0 0 0.00 0.00 0 0.00 0.00 0.00

ABSTRACT : A. Cost of Material including seignorage B. Hire Charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C 0% Total cost for 100 sqm Rate per sqm=(A+B+C+D) /100 If 15 cm thick murum bed is to be provided below pitching addRs. in ( As per rate analysis under item 91- Note )

NOTE:

IRR-CAW-8-4

Providing and constructing 30 cm thick dry rubble stone pitching with pin headers at 2 per sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial lead upto 50 m and all lifts. ( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Unit UNIT : Quantity 100.00 sqm Rate in Rs. Amount in Rs.

Uncoursed rubble stones at quarry cum 27.50 Pin header (Through stone) 30 cm Nos 200.00 Stone chips at quarry cum 4.50 Add seignorage charges on UCR (/ Included in material rate ) chips @ Rs Total cost of Materials

Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit

Quantity 1.00 5.00 6.00

Rate in Rs.

Amount in Rs.

work inspector Day Mason Class II Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for

Rs: Rs: Rs: Rs: Rs: Rs: Rs.

0.00 0.00 0.00 0.00 0.00 0 0.00

Total 0% 100 sqm

143

IRR-CAW

NOTE:

Rate per sqm=(A+B+C+D) /100 If 15 cm thick murum bed is to be provided below pitching add ( As per rate analysis under item 91- Note )

Rs:

0.00 0.00

IRR-CAW-8-5

Providing and Constructing 30 cm thick dry rubble stone pitching including cost of all materials,labour,hand packing,finishing etc.,complete ( rubble stones : 0.33 cum/sqm)

DATA : RATE ANALYSIS A. MATERIALS : Sl No Particulars Uncoursed rubble stones at Quarry Unit UNIT : Quantity 100.00 sqm Rate in Rs Amount in Rs

Cum

33.00 0.00 0.00

Add for seignorage Charges on UCR/Chips @Rs ( Included in material Rate) Total Cost of materials B.MACHINERY : Sl No 1 Description Nill Unit Quantity 0.00 0.00 Rate in Rs Rs :

Amount in Rs

Total hire charges of machinery Rs : C.LABOUR : Sl No Description Unit Quantity 0.40 2.10 Rate in Rs

0.00

Amount in Rs

1 Mason Class II Day 2 Mazdoor Day Total cost of labour Rs : ABSTRACT A.Cost of Materials including ryolty charges B. Hire charges of Machinery C.Cost of Labour

0.00 Rs: Rs: Rs: Rs: Rs: Rs. Rs : Rs : 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C 0% Total cost for 100 sqm Rate per sqm=(A+B+C+D) /100 If 15 cm thick murum bed is to be provided below pitching Add ( As per rate analysis under item 91 - Note)

NOTE:

IRR-CAW-8-6

Providing and constructing 45 cm thick dry rubble stone pitching with pin headers at 2 per sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial lead upto 50 m and all lifts. ( rubble stones : 0.40 cum/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Uncoursed rubble stones at quarry Pin header (Through stone) 45 cm Stone chips at quarry Total cost of Materials Unit cum Nos cum UNIT : Quantity 40.00 200.00 6.75 Rs: 0.00 100.00 sqm Rate in Rs. Amount in Rs.

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

144

IRR-CAW

C. LABOUR: Sl No 1 2 3

Description

Unit

Quantity 1.00 7.00 9.00

Rate in Rs.

Amount in Rs.

work inspector Day Mason Class II Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

Total

NOTE:

D.Add for contractor's profit and overheads on A+B+C 0% Rs: Total cost for 100 sqm Rs. Rate per sqm=(A+B+C+D) /100 Rs: If 15 cm thick murum bed is to be provided below pitching add ( As per rate analysis under item 91 - Note )

IRR-CAW-8-7

Providing and Constructing 45 cm thick dry rubble stone pitching including cost of all materials,labour,hand packing,finishing etc.,complete ( rubble stones : 0.495 cum/sqm)

DATA : RATE ANALYSIS A. MATERIALS : Sl No Particulars Unit UNIT : Quantity 100.00 sqm Rate in Rs Amount in Rs

Uncoursed rubble stones at Cum Quarry Add for seignorage Charges on UCR @Rs ( Included in material Rate) Total Cost of materials Rs :

49.50 0.00 0.00

B.MACHINERY : Sl No 1 Description Nill Unit Quantity 0.00 0.00 0.00 Rate in Rs Amount in Rs

Total hire charges of machinery Rs : C.LABOUR : Sl No 1 2 Description Unit Quantity 0.40 2.10 Rate in Rs

Amount in Rs

Mason Class II Day Mazdoor Day Total cost of labour Rs : ABSTRACT A.Cost of Materials including ryolty charges B. Hire charges of Machinery C.Cost of Labour

0.00 Rs: Rs: Rs: Rs: Rs: Rs. Rs : Rs : 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C 0% Total cost for 100 sqm Rate per sqm=(A+B+C+D) /100 If 15 cm thick murum bed is to be provided below pitching Add ( As per rate analysis under item 91 - Note)

NOTE:

IRR-CAW-8-8

Providing and constructing 30 cm thick rubble stone pitching set in CM 1: 5 proportion with pin headers at 2 per sqm in including cost of all materials, labour, packing chips and mortar, finishing, curing etc., complete with initial lead upto 50 m and all lifts. ( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)

DATA: RATE ANALYSIS A. MATERIALS: UNIT : 100.00 sqm

145

IRR-CAW

Sl No 1 2 3 4 5

particulars

Unit

Quantity

Rate in Rs.

Amount in Rs.

Uncoursed rubble stones at quarry cum 27.50 Pin header (Through stone) 30 cm Nos 200.00 Stone chips @ 15 % at quarry cum 4.50 Cement kg 3000.00 Sand ( screened ) cum 10.50 Add seignorage charges on UCR (/ Included in material rate ) chips @ Rs Add seignorage charges on Sand( @ Rs Included in material rate ) Total cost of Materials

Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit

Quantity 2.00 2.00

Rate in Rs.

Amount in Rs.

5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 2.00 1.00 5.00 12.00 2.00

Rate in Rs.

Amount in Rs.

Crew for Pump Hour work inspector Day Mason Class II Day mazdoor Day Catrman with double bullock cart Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

NOTE:

Total D.Add for contractor's profit and overheads on A+B+C 0% Rs: Total cost for 100 sqm Rs. Rate per sqm=(A+B+C+D) /100 Rs: If 15 cm thick murum bed is to be provided below pitching add ( As per rate analysis under item 91 - Note )

IRR-CAW-8-9

Providing and Constructing 30 cm thick rubble stone pitching set in CM 1:5 Proportion including cost of all materials,labour, packing chips and mortar ,finishing etc.,complete ( rubble stones : 0.33 cum/sqm )

DATA : RATE ANALYSIS A. MATERIALS : Sl No Particulars Unit Quantity Rate in Rs Amount in Rs UNIT : 100.00 Sqm

1 2 3

Uncoursed rubble stones at Cum Quarry Cement Kg Sand ( Screened) Cum Add for seignorage Charges on UCR @Rs ( Included in material Rate) Add for seignorage Charges on Sand @Rs ( Included in material Rate) Total Cost of materials Rs :

33.00 3232.00 11.22 0.00 0.00 0.00

B.MACHINERY : Sl No 1 Description Nill Total hire charges of machinery Rs : C.LABOUR : Sl No 1 2 Description Mason Class I Mason Class II Unit Day Day Quantity 0.54 1.26 Rate in Rs Amount in Rs Unit Quantity 0.00 0.00 Rate in Rs Amount in Rs

146

IRR-CAW

Mazdoor Day Total cost of labour Rs : ABSTRACT A.Cost of Materials including seigniorage charges B. Hire charges of Machinery C.Cost of Labour

2.80 0.00 Rs: Rs: Rs: Rs: Rs: Rs. Rs : Rs : 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

NOTE:

Total D.Add for contractor's profit and overheads on A+B+C 0% Total cost for 100 sqm Rate per sqm=(A+B+C+D) /100 If 15 cm thick murum bed is to be provided below pitching Add ( As per rate analysis under item 91 - Note)

IRR-CAW-8-10

Providing and constructing 30 cm thick dry khandki stone pitching using 20 to 25 cm size khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial lead upto 50 m and all lifts. ( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm) RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Unit UNIT : Quantity 100.00 sqm Rate in Rs. Amount in Rs.

DATA:

Khandki stones 20-25 cm height Nos 1200.00 Pin header (Through stone) 30 cm Nos 200.00 Stone chips cum 4.50 Add seignorage charges on UCR (/ Included in material rate ) chips @ Rs Total cost of Materials

Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit

Quantity 1.00 5.00 6.00

Rate in Rs.

Amount in Rs.

work inspector Day Mason Class II Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

Total

NOTE:

D.Add for contractor's profit and overheads on A+B+C 0% Rs: Total cost for 100 sqm Rs. Rate per sqm=(A+B+C+D) /100 Rs: If 15 cm thick murum bed is to be provided below pitching add ( As per rate analysis under item 91 - Note )

IRR-CAW-8-11

Providing and constructing 45 cm thick dry khandki stone pitching using 25 to 30 cm size khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial lead upto 50 m and all lifts. ( Khandki stones 25- 30 cm height : 1200 Nos/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Unit UNIT : Quantity 100.00 sqm Rate in Rs. Amount in Rs.

Khandki stones 25-30 cm height Nos 730.00 Pin headers 45 cm Nos 200.00 Stone chips cum 6.75 Add seignorage charges on UCR (/ Included in material rate ) chips @ Rs Total cost of Materials

Rs:

0.00

147

IRR-CAW

B. MACHINERY: Sl No 1

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit

Quantity 1.00 7.00 9.00

Rate in Rs.

Amount in Rs.

work inspector Day Mason Class II Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

NOTE:

Total D.Add for contractor's profit and overheads on A+B+C 0% Total cost for 100 sqm Rate per sqm=(A+B+C+D) /100 If 15 cm thick murum bed is to be provided below pitching add ( As per rate analysis under item 91 - Note )

IRR-CAW-8-12

Providing and constructing 30 cm thick khandki stone pitching using 20 to 25 cm size khandki stones with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in CM 1:3 proportion including cost of all materials, labour, packing chips and mortar, finishing, curing etc.complete with initial lead upto 50 m and all lifts. ( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 particulars Unit UNIT : Quantity 100.00 sqm Rate in Rs. Amount in Rs.

Khandki stones 20-25 cm height Nos 1200.00 Pin headers 30 cm long Nos 200.00 Stone chips @ 15 % at quarry cum 4.50 Cement kg 2902.00 Sand with ( screened ) cum 9.67 Add seignorage charges on UCR (/ Included in material rate ) chips @ Rs Add seignorage charges for Sand( @ Rs Included in material rate ) Total cost of Materials

Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit Hour Hour

Quantity 2.00 2.00

Rate in Rs.

Amount in Rs.

5 hp diesel pump Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 2.00 1.00 2.00 5.00 11.00

Rate in Rs.

Amount in Rs.

Crew for Pump Hour work inspector Day Cartman with double bullock cart Day Mason Class II Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

NOTE:

Total D.Add for contractor's profit and overheads on A+B+C 0% Total cost for 100 sqm Rate per sqm=(A+B+C+D) /100 If 15 cm thick murum bed is to be provided below pitching add ( As per rate analysis under item 91 - Note )

148

IRR-CAW

IRR-CAW-8-13

Providing and constructing 45 cm thick khandki stone pitching using 25 to 30 cm stones with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in CM 1 : 3 proportion including cost of all materials, labour, packing chips and mortar, finishing, curing etc., complete with initial lead upto 50 m and all lifts. ( Khandki stones 25- 30 cm height : 730 Nos/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 particulars Unit UNIT : Quantity 100.00 sqm Rate in Rs. Amount in Rs.

Khandki stones 25-30 cm height Nos 730.00 Pin headers 45 cm Nos 200.00 Stone chips @ 15 % at quarry cum 6.75 Cement kg 4050.00 Sand ( screened ) cum 13.99 Add seignorage charges for Stone/chips @ Rsmaterial rate ) ( Included in Add seignorage charges for Sand( @ Rs Included in material rate ) Total cost of Materials

Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description

Unit Hour Hour

Quantity 4.00 4.00

Rate in Rs.

Amount in Rs.

5 hp diesel pump Fuel / Energy charges Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit

Quantity 4.00 1.00 2.00 7.00 16.00

Rate in Rs.

Amount in Rs.

Crew for Pump Hour work inspector Day Cartman with double bullock cart Day Mason Class II Day mazdoor Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs:

0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

NOTE:

Total D.Add for contractor's profit and overheads on A+B+C 0% Total cost for 100 sqm Rate per sqm=(A+B+C+D) /100 If 15 cm thick murum bed is to be provided below pitching add ( As per rate analysis under item 91 - Note )

IRR-CAW-8-14

Providing 10 cm thick approved type grass turfing to the side slopes of canal icluding cost of all materials, labour, watering for minimum 15 days etc.,complete with lead 50 m and all lifts. (FA : 2 cum/sqm)

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Turfing sods Sand ( unscreened ) Total cost of Materials Unit sqm cum UNIT : Quantity 100.00 2.00 Rs: 0.00 100.00 sqm Rate in Rs. Amount in Rs.

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description work inspector Cartman with double bullock cart

Unit Day Day

Quantity 0.10 2.00

Rate in Rs.

Amount in Rs.

149

IRR-CAW

mazdoor

Day Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

14.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs. Rs: 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00

Total 0% 100 sqm

IRR-CAW-8-15

Providing 10 cm Thick approved type gross turfing to the side slopes of canal including cost of all materials ,labour,watering for minimum 15 days etc.,,complete. with initial lead upto 50 m and all lifts ( WITHOUT USING SAND) RATE ANALYSIS A. MATERIALS : Sl No 1 Particulars Turfing Sods Total Cost of materials B.MACHINERY : Sl No 1 Description Nill Total hire charges of machinery Rs : C.LABOUR : Sl No 1 2 Description Unit Quantity 7.00 2.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs. 0.00 0.00 0.00 0.00 0 0.00 0 Rate in Rs Amount in Rs Unit Quantity 0.00 0.00 0.00 Rate in Rs Amount in Rs Rs : Unit Sqm Quantity 100.00 0.00 Rate in Rs Amount in Rs UNIT : 100.00

Mazdoor Day Cart men with double bullock Day cart Total cost of labour Rs : ABSTRACT A.Cost of Materials including ryolty charges B. Hire charges of Machinery C.Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

Total 0% 100 sqm

150

IRR-CCDW

CHAPTER-IV Standard Data


Index- code IRR-CCDW
IRR-CCDW-1

CANAL CROSS DRAINAGE WORKS


EXCAVATION & FOUNDATION TREATMENT WORKS :

IRR-CCDW-1-1 Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canal cross drainage and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m. DATA: Out turn of two mazdoors assumed at 4 cum per day.

RATE ANALYSIS A. MATERIALS: Sl No 1 Particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit

UNIT : Quantity 0.00 0.00

10.00 cum Rate in Rs. Amount in Rs.

Rs:

0.00

Description NIL Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.25 6.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 0% 10.00 cum

IRR-CCDW-1-2 Excavation for Structures- Mechanical Means ( Data adopted from MORTH) Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Depth upto 3 m Unit = cum Taking output = 240.00 cum 240 cum a) Labour Sl No Description Unit Quantity 1 2 work inspector Mazdoor Total in Rs. day day 0.32 8.00

Rate in Rs.

Amount in Rs.

0.00

b)Machinery Sl No 1.0

Description Hydraulic excavator 1.0 cum bucket capacity Fuel/ Energy charges crew for excavator Total in Rs. Abstract a) Labour b) Machinery c) Material Total D.Add for contractor's profit and overheads on A+B+C Total for Rate per cum=(A+B+C+D) /240

Unit hour hour hour

Quantity 6.00 6.00 6.00

Rate in Rs.

Amount in Rs.

0.00 Rs Rs Rs Rs Rs Rs Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 240 cum

IRR-CCDW-1-3 Excavation in ordnary rock without blasting including boulders above 0.3 m upto 0.60 m dia. for foundations of canal cross drainage and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m. DATA: Out turn of 1 crowbarman / Stone breaker, two mazdoors : 4 cum per day.

152

IRR-CCDW

RATE ANALYSIS A. MATERIALS: Sl No 1 Particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit

UNIT : Quantity 0.00 0.00

10.00 cum Rate in Rs. Amount in Rs.

Rs:

0.00

Description NIL Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 Crowbarman Stone breaker work inspector mazdoor

Description

Unit Day Day Day Day Total cost of Labour

Quantity 1.25 1.25 0.25 6.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 0% 10.00 cum

IRR-CCDW-1-4 Excavation in ordnary rock without blasting for foundations of canal cross drainage and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m. ( Data adopted from MORTH) Mechanical Means Unit = cum Taking output = 180 cum a) Labour Sl No 1 2 work inspector Mazdoor Total in Rs. b) Sl No 1.0 Machinery Description Hydraulic excavator 1.0 cum bucket capacity Fuel/ Energy charges crew for excavator Total in Rs. Abstract a) Labour b) Machinery c) Material Total D.Add for contractor's profit and overheads on A+B+C Total for Rate per cum=(A+B+C+D) /180 Unit hour hour hour Quantity 6.00 6.00 6.00 Rate in Rs. 0.00 0.00 0.00 Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 180.00 cum

Description

Unit day day

Quantity 0.24 6.00

Rate in Rs. 0.00 0.00

Amount in Rs. 0.00 0.00 0.00

0.00 180 cum

Rs Rs Rs Rs Rs Rs Rs

IRR-CCDW-1-5 Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. for foundations of canal cross drainage and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Particulars Use rate of drill rod 1.6 m length Reconditioning charges @ Use rate of air hose 2 Nos. Explosive small dia ( Kelvex-220 ) Electric detonators Detonating fuse coil Sundries Total cost of Materials Unit Rm 10% Hour kg Nos Rm LS UNIT : Quantity 43.50 6.00 20.00 29.00 70.00 0.50 Rs: 0.00 100 cum Rate in Rs. Amount in Rs.

153

IRR-CCDW

B. MACHINERY: Sl No 1 2

Description Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Jack hammers 2 Nos. Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour

Quantity 3.00 3.00 6.00 6.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Air compressor Crew for Jack hammer work inspector Blaster Helper blaster Crowbarman Stone breaker mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Day Day Day Day Day Day

Quantity 3.00 6.00 1.00 0.50 0.50 6.00 3.00 51.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total for Rate per cum=(A+B+C+D) /100 0% 100.00 cum

IRR-CCDW-1-6 Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for foundations of canal cross drainage and other appurtenant structures and placing the excavated rock neatly in specified dump area or stack yard as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Particulars Explosive small dia ( Kelvex-220 ) Ordinary detonator Electric detonator Detonating fuse coil Use rate of air hose 2 Nos. Use rate of drill rod Reconditioning charges @ Total cost of Materials Unit kg No. No. Rm Hour Rm 10% UNIT : Quantity 32.00 8.00 104.00 150.00 16.00 98.30 Rs: 0.00 100.00 cum Rate in Rs. Amount in Rs.

B. MACHINERY: Sl No 1 2

Description Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Jack hammer 2 Nos Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour

Quantity 8.00 8.00 16.00 16.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Air compressor Crew for Jack hammer Blaster licensed Helper blasting work inspector Crowbarman Stone breaker mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Day Day Day Day Day Day

Quantity 8.00 16.00 1.00 1.00 1.00 6.00 6.00 51.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /100 0% 100.00 cum

IRR-CCDW-1-7 Excavation in hard rock with blasting prohibited for foundations of canal cross drainage and other appurtenant structures and placing the excavated rock neatly in or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and initial lift upto 3 m. Hard Rock ( blasting prohibited ) ( Data adopted from MORTH) Unit = cum

154

IRR-CCDW

Taking output = 10 cum Mechanical Means a) Labour Sl No 1 2 work inspector Mazdoor Total in Rs. Description Unit day day Quantity 0.20 5.00 0.00 10.00 Rate in Rs. cum Amount in Rs.

b)

Machinery Sl No

Description Air Compressor 250 cfm with 2 leads of pneumatic breaker Fuel/ Energy charges crew for compressor Total in Rs. Abstract a) Labour b) Machinery c) Material Total D.Add for contractor's profit and overheads on A+B+C Total for Rate per cum=(A+B+C+D) /10

Unit hour hour hour

Quantity 6.00 6.00 6.00

Rate in Rs.

Amount in Rs.

1.0

0.00 Rs Rs Rs Rs Rs Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 10 cum

IRR-CCDW-1-8 Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel anchor rods with 1.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded in concrete / masonry including cost of all materials, machinery, labour, drilling and cleaning hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead upto 50 m and all lifts. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 Particulars Cement for grouting 25 mm dia steel Use rate of 32 mm dia drill rod Reconditioning charges @ Use rate of air hose Total cost of Materials B. MACHINERY: Sl No 1 2 Unit kg kg Rm 10% Hour UNIT : Quantity 5.00 101.00 12.50 2.00 Rs: 0.00 10.00 Nos. Rate in Rs. Amount in Rs.

Description Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Jack hammer 2 Nos Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour

Quantity 1.00 1.00 2.00 2.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Air compressor Crew for Jack hammer Mason Class-II Bar bender work inspector mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Day Day Day Day

Quantity 1.00 2.00 0.50 0.50 0.50 1.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /10 IRR-CCDW-2 STEEL AND CEMENT CONCRETE WORKS : 0% 10.00 Nos.

IRR-CCDW-2-1 Providing, fabricating and placing in position reinforcement steel bars for RCC works including cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with 1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc., complete with initial lead upto 50 and all lifts. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Rein.Steel with 5 % wastage Binding wire 1.25 mm dia Sundries ( chairs / spacers etc ) Unit kg kg LS UNIT : Quantity 1050.00 8.00 3.00 1000.00 kg Rate in Rs. Amount in Rs.

155

IRR-CCDW

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description Nil Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 work inspector Bar bender mazdoor

Description

Unit Day Day Day Total cost of Labour

Quantity 1.00 6.00 11.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Kg=(A+B+C+D) /10 0% 1000.00 kg

IRR-CCDW-2-2 Providing, fabricating and fixing in position structural steel cutting edge consisting of 100 x 100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter foundation wells foundation wells including cost of all materials, machinery, labour, bending, welding, providing anchors etc., complete with initial lead upto 50 m and all lifts. DATA: Consider 4.50 m outer dia. well kerb for analysis.

DETAILS OF FOUNDATION WELL CUTTING EDGE RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 Particulars Str.Steel angle with 2.5 % wastage Str.Steel plate with 2.5 % wastage Steel for anchors Acetyline gas Oxygen gas Welding electrodes Sundries Total cost of Materials Unit kg kg kg cum cum Nos LS UNIT : Quantity 216.10 342.30 56.60 0.50 1.50 300.00 5.00 Rs: 0.00 615.00 kg Rate in Rs. Amount in Rs.

B. MACHINERY: Sl No 1 2

Description

Unit Hour Hour Hour Hour LS

Quantity 8.00 8.00 30.00 30.00 10.00

Rate in Rs.

Amount in Rs.

Bending machine Fuel / Energy charges Welding set Fuel / Energy charges 3 Sundries Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 Str. Steel fabricator Welder / Gas cutter work inspector mazdoor

Description

Unit Day Day Day Day Total cost of Labour

Quantity 2.00 5.00 1.00 5.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Kg=(A+B+C+D) /615 0% 615.00 kg

IRR-CCDW-2-3 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for foundation filling including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

156

IRR-CCDW

complete with initial lead upto 50 m and all lifts. (Cement content: 210 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) RATE ANALYSIS A. MATERIALS: Sl No 1 2 Particulars Unit UNIT : Quantity 19.00 cum Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 4 5 6

Cement for mix kg 3990.00 Cement for incidentals @ 3 kg / cum kg 57.00 Coarse aggregate 40-20 mm cum 8.55 Coarse aggregate 20-10 mm cum 5.13 Coarse aggregate 10 mm below cum 3.42 Fine aggregate cum 7.60 Super Plasticizer kg 15.96 Use rate of shuttering for 40 uses sqm 19.00 Scaffolding @ of shuttering 10% Sundries LS 0.50 Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 1.00 1.00 8.00 8.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Needle vibrator work inspector Mason Class-I mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day sqm 10%

Quantity 8.00 0.50 1.00 8.00 1.00 1.00 11.00 4.00 3.00 19.00 1.00 19.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /19 0% 19.00 cum

IRR-CCDW-2-4 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded aggregates for foundation filling including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 210 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.98 cum Blending ratio : 35 :30 : 20 : 15 Fine aggregate : 0.35 cum Cement content : 210 kg Super plasticizer : 0.65 ltr RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix Cement for incidentals @ 3 kg / cum Coarse aggregate 80-40 mm Coarse aggregate 40-20 mm Coarse aggregate 20-10 mm Coarse aggregate 10 mm below Fine aggregate Super Plasticizer Use rate of shuttering for 40 uses Scaffolding @ of shuttering Sundries kg kg cum cum cum cum cum kg sqm 10% LS 3570.00 51.00 5.83 5.00 3.33 2.50 5.95 14.28 17.00 0.50

17.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

157

IRR-CCDW

Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials B. MACHINERY: Sl No 1 2 3 4

Rs: Rs: Rs:

0.00 0.00 0.00

Description Concrete mixer 600/400 ltr ( diesel) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 60 mm dia ( petrol) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 1.00 1.00 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day sqm 10%

Quantity 8.00 0.50 1.00 8.00 1.00 1.00 11.00 4.00 3.00 17.00 1.00 17.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /17 0% 17.00 cum

IRR-CCDW-2-5 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for foundation filling including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 190 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum Cement content : 190 kg Super plasticizer : 0.76 kg RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit 1 2

UNIT : Quantity

19.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Cement for mix kg 3610.00 Cement for incidentals @ 3 kg / cum kg 57.00 Coarse aggregate 40-20 mm cum 8.55 Coarse aggregate 20-10 mm cum 5.13 Coarse aggregate 10 mm below cum 3.42 Fine aggregate cum 7.60 Super Plasticizer kg 14.44 Use rate of shuttering for 40 uses sqm 19.00 Scaffolding @ of shuttering 10% Sundries LS 0.50 Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 1.00 1.00 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No

Description

Unit

Quantity

Rate

Amount

158

IRR-CCDW

in Rs. 1 2 3 4 5 6 7 Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /19 0% 19.00 cum Hour Hour Hour Hour Day Day Day Day Day Day Day sqm 8.00 0.50 1.00 8.00 1.00 1.00 11.00 4.00 3.00 19.00 1.00 19.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

in Rs.

8 9

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-2-6 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded aggregates for foundation filling including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 190 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.98 cum Blending ratio : 35 :30 : 20 : 15 Fine aggregate : 0.35 cum Cement content :190 kg Super plasticizer : 0.76 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg 3230.00 Cement for incidentals @ 3 kg / cum kg 51.00 Coarse aggregate 80-40 mm cum 5.83 Coarse aggregate 40-20 mm cum 5.00 Coarse aggregate 20-10 mm cum 3.33 Coarse aggregate 10 mm below cum 2.50 Fine aggregate cum 5.95 Super Plasticizer kg 12.92 Use rate of shuttering for 40 uses sqm 17.00 Scaffolding @ of shuttering 10% Sundries LS 0.50 Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

17.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4

Description Concrete mixer 600/400 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 60 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 1.00 1.00 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day sqm 10%

Quantity 8.00 0.50 1.00 8.00 1.00 1.00 11.00 4.00 3.00 17.00 1.00 17.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

159

IRR-CCDW

C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /17 0% 17.00 cum

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

IRR-CCDW-2-7 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for foundation filling including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum ) (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum Cement content : 220 kg Super plasticizer : 0.88 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg 4400.00 Cement for incidentals @ 3 kg / cum kg 60.00 Coarse aggregate 40-20 mm cum 9.00 Coarse aggregate 20-10 mm cum 5.40 Coarse aggregate 10 mm below cum 3.60 Fine aggregate cum 8.00 Super Plasticizer kg 17.60 Use rate of shuttering for 40 uses sqm 20.00 Scaffolding @ of shuttering 10% Sundries LS 0.50 Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

20.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 1.00 1.00 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day sqm 10%

Quantity 8.00 0.50 1.00 8.00 1.00 1.00 11.00 4.00 3.00 20.00 1.00 20.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /20 0% 20.00 cum

IRR-CCDW-2-8 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for sub-structure / super- structure works including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 270 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.90 cum Fine aggregate : 0.40 cum Cement content : 270 kg

Blending ratio : 50 :30 : 20 Super plasticizer : 1.08 kg

160

IRR-CCDW

RATE ANALYSIS A. MATERIALS: Sl No 1 2 Particulars Unit

UNIT : Quantity

18.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Cement for mix kg 4860.00 Cement for incidentals @ 5 kg / cum kg 90.00 Coarse aggregate 40-20 mm cum 8.10 Coarse aggregate 20-10 mm cum 4.86 Coarse aggregate 10 mm below cum 3.24 Fine aggregate cum 7.20 Super Plasticizer kg 19.44 Use rate of shuttering sqm 36.00 Scaffolding @ of shuttering 25% Sundries LS 0.50 Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 1.00 1.00 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying including lifting for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day sqm 25%

Quantity 8.00 0.50 1.00 8.00 1.00 1.00 11.00 4.00 4.00 18.00 1.00 18.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /18 0% 18.00 cum

IRR-CCDW-2-9 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for sub-structure / super- structure works including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.80 cum Blending ratio : 65 :35 Fine aggregate : 0.45 cum Cement content : 300 kg Super plasticizer : 1.2 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement for mix kg 5400.00 Cement for incidentals @ 5 kg / cum kg 90.00 Coarse aggregate 20-10 mm cum 9.36 Coarse aggregate 10 mm below cum 5.04 Fine aggregate cum 8.10 Super Plasticizer kg 21.60 Use rate of shuttering sqm 36.00 Scaffolding @ of shuttering 25% Sundries LS 0.50 Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

18.00 cum Rate in Rs. Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No

Description

Unit

Quantity

Rate

Amount

161

IRR-CCDW

in Rs. 1 2 3 4 Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery Hour Hour Hour Hour Hour Hour Hour Hour 8.00 8.00 0.50 0.50 1.00 1.00 8.00 8.00 Rs:

in Rs.

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day sqm 25%

Quantity 8.00 0.50 1.00 8.00 1.00 1.00 11.00 4.00 4.00 18.00 1.00 36.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /18 0% 18.00 cum

IRR-CCDW-2-10 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for sub-structure / super- structure works including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 270 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.80 cum Blending ratio : 65 :35 Fine aggregate : 0.45 cum Cement content : 270 kg Super plasticizer : 1.08 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement for mix kg 4320.00 Cement for incidentals @ 5 kg / cum kg 80.00 Coarse aggregate 20-10 mm cum 8.32 Coarse aggregate 10 mm below cum 4.48 Fine aggregate cum 7.20 Super Plasticizer kg 17.28 Use rate of shuttering for 40 uses sqm 32.00 Scaffolding @ of shuttering 25% Sundries LS 0.50 Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

16.00 cum Rate in Rs. Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 1.00 1.00 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Vibrator Mason Class-I work inspector

Unit Hour Hour Hour Hour Day Day

Quantity 8.00 0.50 1.00 8.00 1.00 1.00

Rate in Rs.

Amount in Rs.

162

IRR-CCDW

mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Day Day Day Day Day sqm 25%

11.00 4.00 4.00 16.00 1.00 32.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /16 0% 16.00 cum

IRR-CCDW-2-11 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for sub-structure / super- structure works including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.80 cum Blending ratio : 65 :35 Fine aggregate : 0.45 cum Cement content : 220 kg Super plasticizer : 0.88 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement for mix kg 3960.00 Cement for incidentals @ 5 kg / cum kg 90.00 Coarse aggregate 20-10 mm cum 9.36 Coarse aggregate 10 mm below cum 5.04 Fine aggregate cum 8.10 Super Plasticizer kg 15.84 Use rate of shuttering for 40 uses sqm 36.00 Scaffolding @ of shuttering 25% Sundries LS 0.50 Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

18.00 cum Rate in Rs. Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 1.00 1.00 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Crew for Vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Hour Day Day Day Day Day Day Day sqm 25%

Quantity 8.00 0.50 1.00 8.00 1.00 1.00 11.00 4.00 4.00 18.00 1.00 36.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /18 0% 18.00 cum

163

IRR-CCDW

IRR-CCDW-2-12 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for well kerb including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.80 cum Blending ratio : 65 :35 Fine aggregate : 0.45 cum Cement content : 350 kg Super plasticizer : 1.4 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement for mix kg 5250.00 Coarse aggregate 20-10 mm cum 7.80 Coarse aggregate 10 mm below cum 4.20 Fine aggregate cum 6.75 Super Plasticizer kg 21.00 Use rate of curved shutter (40 uses) sqm 82.50 Sundries LS 0.50 Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

7500

15.00 cum Rate in Rs. Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 3.00 15.00 1.00 82.50

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /15 0% 15.00 cum

IRR-CCDW-2-13 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for well steining including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 270 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum Cement content : 270 kg Super plasticizer : 1.08 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix Cement for incidentals @ 2 kg / cum Coarse aggregate 40-20 mm Coarse aggregate 20-10 mm Coarse aggregate 10 mm below Fine aggregate Super Plasticizer Use rate of curved shutter (40 uses) Sundries kg kg cum cum cum cum kg sqm LS 4860.00 36.00 8.10 4.86 3.24 7.20 19.44 72.00 0.50

18.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

164

IRR-CCDW

Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials B. MACHINERY: Sl No 1 2 3

Rs: Rs: Rs:

0.00 0.00 0.00

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 3.00 18.00 1.00 72.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /18 0% 18.00 cum

IRR-CCDW-2-14 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for well bottom plug by tremie or skip box method including cost of all materials, machinery, labour, batching, mixing, placing in position as per detailed specifications etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 350 kg / cum ) (Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For placing concrete under water by using tremie the slump of concrete shall be about 150 mm. Minimum cement content as per IS: 456-2000 Clause-14.2.2 : 350 kg / cum. For 1 cum CC :Coarse aggregates : 0.80 cum Blending ratio : 65 : 35 Fine aggregate : 0.45 cum Cement content : 350 kg Super plasticizer : 1.40 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 Cement for mix Coarse aggregate 20-10 mm Coarse aggregate 10 mm below Fine aggregate Super Plasticizer 4900.00 7.28 3.92 6.30 19.60 TOTAL Add for tremie arrangement @ 1% Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials kg cum cum cum kg

14.00 cum Rate in Rs. Amount in Rs.

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Sundries( Hopper etc. ) Total hire charges of Machinery

Unit Hour Hour Hour Hour LS

Quantity 8.00 8.00 0.50 0.50 5.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5

Description Crew for Concrete mixer Crew for Pump Fitter shuttering work inspector mazdoor for erecting/ dismantling tremie for batching materials

Unit Hour Hour Day Day Day Day

Quantity 8.00 0.50 1.00 1.00 4.00 11.00

Rate in Rs.

Amount in Rs.

165

IRR-CCDW

for loading mortar pans for feeding tremie hopper for conveying concrete Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Day Day Day

4.00 2.00 16.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /14 0% 14.00 cum

IRR-CCDW-2-15 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for well top plug including cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 270 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum Cement content : 270 kg Super plasticizer : 1.08 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg 3600.00 Coarse aggregate 40-20 mm cum 6.75 Coarse aggregate 20-10 mm cum 4.05 Coarse aggregate 10 mm below cum 2.70 Fine aggregate cum 6.00 Super Plasticizer kg 14.40 Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

15.00 cum Rate in Rs. Amount in Rs.

3 4

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 3.00 15.00 1.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /15 0% 15.00 cum

IRR-CCDW-2-16 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for well cap including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.80 cum Fine aggregate : 0.45 cum Cement content : 300 kg

Blending ratio : 65 :35 Super plasticizer : 1.2 kg

166

IRR-CCDW

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Particulars Unit

UNIT : Quantity

18.00 cum Rate in Rs. Amount in Rs.

Cement for mix kg 5400.00 Cement for incidentals @ 5 kg / cum kg 90.00 Coarse aggregate 20-10 mm cum 9.36 Coarse aggregate 10 mm below cum 5.04 Fine aggregate cum 8.10 Super Plasticizer kg 21.60 Use rate of curved shutter (40 uses) sqm 18.00 Sundries LS 0.50 Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 3.00 18.00 1.00 18.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /18 0% 18.00 cum

IRR-CCDW-2-17 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded aggregates for piers and abutments including cost of all materials, labour, machinery, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 210 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.98 cum Blending ratio : 35 :30 : 20 : 15 Fine aggregate : 0.35 cum Cement content : 210 kg Super plasticizer : 0.84 kg RATE ANALYSIS A. MATERIALS: Sl No Particulars Unit 1 2

UNIT : Quantity

17.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Cement for mix kg 3570.00 Cement for incidentals @ 5 kg / cum kg 85.00 Coarse aggregate 80-40 mm cum 5.83 Coarse aggregate 40-20 mm cum 5.00 Coarse aggregate 20-10 mm cum 3.33 Coarse aggregate 10 mm below cum 2.50 Fine aggregate cum 5.95 Super Plasticizer kg 14.28 Use rate of shuttering for 40 uses sqm 46.75 Scaffolding @ of shuttering 30% Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2

Description Concrete mixer 600/400 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel )

Unit Hour Hour Hour

Quantity 8.00 8.00 0.50

Rate in Rs.

Amount in Rs.

167

IRR-CCDW

Fuel / Energy charges Needle vibrator 60 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Hour Hour Hour

0.50 8.00 8.00 Rs: 0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm 30%

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 6.00 17.00 1.00 34.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /17 0% 17.00 cum

IRR-CCDW-2-18 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded aggregates for piers and abutments including cost of all materials, labour, machinery, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 190 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.98 cum Blending ratio : 35 :30 : 20 : 15 Fine aggregate : 0.35 cum Cement content :190 kg Super plasticizer : 0.76 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg 3230.00 Cement for incidentals @ 5 kg / cum kg 85.00 Coarse aggregate 80-40 mm cum 5.83 Coarse aggregate 40-20 mm cum 5.00 Coarse aggregate 20-10 mm cum 3.33 Coarse aggregate 10 mm below cum 2.50 Fine aggregate cum 5.95 Super Plasticizer kg 12.92 Use rate ofshuttering for 40 uses sqm 46.75 Scaffolding @ of shuttering 30% Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

17.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 600/400 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 60 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm 30%

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 6.00 17.00 1.00 46.75

Rate in Rs.

Amount in Rs.

168

IRR-CCDW

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /17 0% 17.00 cum

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-2-19 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for piers and abutments including cost of all materials, labour, machinery, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 190 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum Cement content : 190 kg Super plasticizer : 0.76 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg 3610.00 Cement for incidentals @ 5 kg / cum kg 95.00 Coarse aggregate 40-20 mm cum 8.55 Coarse aggregate 20-10 mm cum 5.13 Coarse aggregate 10 mm below cum 3.42 Fine aggregate cum 7.60 Super Plasticizer kg 14.44 Use rate of shuttering for 40 uses sqm 52.25 Scaffolding @ of shuttering 30% Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

19.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm 30%

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 5.00 19.00 1.00 52.25

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /19 0% 19.00 cum

IRR-CCDW-2-20 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for cantiliver / counterfort retaining walls including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 190 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.

169

IRR-CCDW

DATA:

Requirement of materials : For 1 cum CC :Coarse aggregates : 0.90 cum Blending ratio : 50 : 30 : 20 Fine aggregate : 0.40 cum Cement content : 270 kg Super plasticizer : 1.08 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg 5130.00 Cement for incidentals @ 5 kg / cum kg 95.00 Coarse aggregate 40-20 mm cum 8.55 Coarse aggregate 20-10 mm cum 5.13 Coarse aggregate 10 mm below cum 3.42 Fine aggregate cum 7.60 Super Plasticizer kg 20.52 Use rate of shuttering for 40 uses sqm 61.75 Scaffolding @ of shuttering 25% Sundries LS 0.50 Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

19.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm 25%

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 5.00 19.00 1.00 61.75

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /19 0% 19.00 cum

IRR-CCDW-2-21 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravity type retaining walls / piers / abutments etc., including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 204 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum, plums of size 150 to 80 mm : 0.25cum ) DATA: Requirement of materials : For 1 cum plum CC :Coarse aggregates : 0.765 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.34 cum Cement content : 204 kg Super plasticizer : 0.816 kg Plums of size 150 to 80 mm : 0.25 cum RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix Cement for incidentals @ 4 kg / cum Coarse aggregate 40-20 mm Coarse aggregate 20-10 mm Coarse aggregate 10 mm below Plums of size 150 to 80 mm Fine aggregate Super Plasticizer Use rate of shuttering for 40 uses Scaffolding @ of shuttering Add seignorage charges on CA @ kg 4080.00 kg 80.00 cum 7.65 cum 4.59 cum 3.06 cum 5.00 cum 6.80 kg 16.32 sqm 55.00 30% Rs. (Included in material rate)

20.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Rs:

0.00

170

IRR-CCDW

Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials B. MACHINERY: Sl No 1 2 3

Rs: Rs:

0.00 0.00

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 60 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for placing plums for conveying concrete for conveying plums for cleaning/ washing/ curing Labour for shuttering Labour for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day Day Day sqm 30%

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 5.00 2.00 20.00 2.00 1.00 55.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /20 0% 20.00 cum

IRR-CCDW-2-22 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,graded aggregates for cast in-situ pipes including cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 210 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20 Fine aggregate : 0.40 cum Cement content : 210 kg Super plasticizer : 0.84kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg 3990.00 Cement for incidentals @ 5 kg / cum kg 95.00 Coarse aggregate 40-20 mm cum 8.55 Coarse aggregate 20-10 mm cum 5.13 Coarse aggregate 10 mm below cum 3.42 Fine aggregate cum 7.60 Super Plasticizer kg 15.96 Use rate of shuttering for 40 uses sqm 38.00 Scaffolding @ of shuttering 15% Sundries LS 0.50 Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

19.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description Crew for Concrete mixer Crew for Pump

Unit Hour Hour

Quantity 8.00 0.50

Rate in Rs.

Amount in Rs.

171

IRR-CCDW

3 4 5 6

Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour for shuttering Labour for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Hour Day Day Day Day Day Day Day sqm 15%

8.00 1.00 1.00 11.00 4.00 3.00 19.00 1.00 38.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /19 0% 19.00 cum

IRR-CCDW-2-23 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded aggregates for cast in-situ pipes including cost of all materials, labour, machinery, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 210 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.98 cum Blending ratio : 35 :30 : 20 : 15 Fine aggregate : 0.35 cum Cement content : 210 kg Super plasticizer : 0.84 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix kg 3570.00 Cement for incidentals @ 5 kg / cum kg 85.00 Coarse aggregate 80-40 mm cum 5.83 Coarse aggregate 40-20 mm cum 5.00 Coarse aggregate 20-10 mm cum 3.33 Coarse aggregate 10 mm below cum 2.50 Fine aggregate cum 5.95 Super Plasticizer kg 14.28 Use rate of shuttering for 40 uses sqm 34.00 Scaffolding @ of shuttering 15% Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

17.00 cum Rate in Rs. Amount in Rs.

3 4 5 6

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 600/400 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 60 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm 15%

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 3.00 17.00 1.00 34.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /17 0% 17.00 cum

172

IRR-CCDW

IRR-CCDW-2-24 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum ) Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.80 cum Blending ratio : 65 :35 Fine aggregate : 0.45 cum Cement content : 300 kg Super plasticizer : 1.2 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement for mix kg 5250.00 Cement for incidentals @ 5 kg / cum kg 87.50 Coarse aggregate 20-10 mm cum 9.10 Coarse aggregate 10 mm below cum 4.90 Fine aggregate cum 7.88 Super Plasticizer kg 21.00 Use rate of shuttering for 30 uses sqm 43.75 Scaffolding @ of shuttering 250% Sundries LS 1.00 Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

17.50 cum Rate in Rs. Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm 250%

Quantity 8.00 0.50 8.00 2.00 1.00 11.00 4.00 4.00 17.50 1.00 43.75

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /17.50 0% 17.50 cum

IRR-CCDW-2-25 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for columns and beams including cost of all materials, labour, machinery, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum ) Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.80 cum Blending ratio : 65 :35 Fine aggregate : 0.45 cum Cement content : 300 kg Super plasticizer : 1.2 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 Cement for mix Cement for incidentals @ 5 kg / cum Coarse aggregate 20-10 mm kg kg cum 5250.00 87.50 9.10

17.50 cum Rate in Rs. Amount in Rs.

173

IRR-CCDW

3 4 5 6

Coarse aggregate 10 mm below cum 4.90 Fine aggregate cum 7.88 Super Plasticizer kg 21.00 Use rate of shuttering sqm 87.50 Scaffolding @ of shuttering 50% Sundries LS 1.00 Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm 50%

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 3.00 17.50 1.00 87.50

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /17.50 0% 17.50 cum

IRR-CCDW-2-26 Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N / sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for wearing coat including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting, finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum ) Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data (Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.80 cum Blending ratio : 65 :35 Fine aggregate : 0.45 cum Cement content : 300 kg Super plasticizer : 1.2 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement for mix kg 5250.00 Cement for incidentals @ 5 kg / cum kg 87.50 Coarse aggregate 20-10 mm cum 9.10 Coarse aggregate 10 mm below cum 4.90 Fine aggregate cum 7.88 Super Plasticizer kg 21.00 Use rate of shuttering sqm 8.75 Sundries ( asphalt mortar etc ) LS 5.00 Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

17.50 cum Rate in Rs. Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( petrol ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR:

174

IRR-CCDW

Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm

Quantity 8.00 0.50 8.00 2.00 1.00 11.00 4.00 4.00 17.50 2.00 8.75

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /17.50 0% 17.50 cum

IRR-CCDW-2-27 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for troughs including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum ) Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data (Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :Coarse aggregates : 0.80 cum Blending ratio : 65 :35 Fine aggregate : 0.45 cum Cement content : 300 kg Super plasticizer : 1.2 kg RATE ANALYSIS UNIT : A. MATERIALS: Sl No Particulars Unit Quantity 1 2 3 4 5 6 Cement for mix kg 5250.00 Cement for incidentals @ 5 kg / cum kg 87.50 Coarse aggregate 20-10 mm cum 9.10 Coarse aggregate 10 mm below cum 4.90 Fine aggregate cum 7.88 Super Plasticizer kg 21.00 Use rate of shuttering for 40 uses sqm 78.75 Scaffolding @ of shuttering 25% Sundries LS 0.50 Add seignorage charges on CA @ Rs. (Included in material rate) Add seignorage charges on FA @ Rs. (Included in material rate) Total cost of Materials

17.50 cum Rate in Rs. Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Needle vibrator 40 mm dia ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 8.00 8.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Concrete mixer Crew for Pump Crew for Needle vibrator Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering Labour cost for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm 25%

Quantity 8.00 0.50 8.00 1.00 1.00 11.00 4.00 5.00 17.50 1.00 78.75

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C 0%

175

IRR-CCDW

Total cost for Rate per cum=(A+B+C+D) /17.50 IRR-CCDW-3 FOUNDATION WELL SINKING WORKS :

17.50 cum

Rs: Rs:

0.00 0.00

Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil, sand and soft rock by approved well sinking method including cost of all materials, machinery, labour, kent - ledge arrangements, disposal of excavated material as directed etc., complete with lead upto 50 m for IRR-CCDW-3-1 disposal of excavated material.(diameter of well 6.00m) Unit = Running meter Taking output = 1m diameter of well = 6.00m A Sandy Soil (i) Depth below bed level upto 3.0m Rate of sinking = 0.50 m /hour a) Labour 0.12 Mate day 1.00 Sinker ( skilled) day 2.00 Sinking helper ( Semi skilled) day sub total (a) b) Machinery 2.00 Hire & running charges of crane with grab hour bucket of 0.75 cum capacity and accessories. Consumables in sinking @ 10% of (b) sub total (b) sub total (a+b) D.Add for contractor's profit and overheads on A+B 0.00 Rate per metre = (a+b+c)/1 or say ( Rate upto 3.0m for 6.0 m well sinking ) (ii) a) Labour 0.15 1.25 2.50 b) Machinery 3.00 Mate Sinker ( skilled) Sinking helper ( Semi skilled) sub total (a) Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Consumables in sinking @ 10% of (b) sub total (b) sub total (a+b) D.Add for contractor's profit and overheads on A+B Rate per metre = (a+b+c)/1 or say ( Rate for 3.0m to 10m well sinking ) IRR-CCDW-3-2 Filling foundation wells with sand in layers of 25 to 30 cm and compacting by watering, ramming as directed including cost of all materials, machinery, labour etc., complete with initial lead upto 50 m and all lifts. DATA: Bulkage of 5 percent considered. Output of 2 mazdoors per day 0.5 mazdoor for levelling and compacting works. RATE ANALYSIS A. MATERIALS: Sl No 1 Sand unscreened Particulars Unit cum 0.00 hour 0.00 day 0.00 day 0.00 day Beyond 3m and upto 10m depth Rate of sinking = 0.33 m per hour.

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00

7.50 cum

UNIT : Quantity 15.75

15.00 cum Rate in Rs. Amount in Rs.

Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials B. MACHINERY: Sl No 1

Rs: Rs:

0.00 0.00

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day

Quantity 0.25 4.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /15 IRR-CCDW-4 MASONRY WORKS : 0% 15.00 cum

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

176

IRR-CCDW

IRR-CCDW-4-1 Providing and constructing un-coursed rubble stone masonry with approved stones in CM 1 : 4 proportion for sub-structure portions of return walls / abutments etc., including cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging stone chips, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum, Stone Chips : 0.15 cum) DATA: For 1 cum masonry :Rubble stones : 0.85 cum Sand : 0.40 cum Cement : 143 kg Cement mortar preparation Output of 1 Mason Stone chips : 0.15 cum. : : Manual 5.00 cum per day UNIT : Unit Quantity 10.00 cum Rate in Rs. Amount in Rs.

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 Particulars

Cement kg 1430.00 Rubble stones cum 8.50 Stone chips cum 1.50 Sand screened cum 4.00 Add seignorage charges on Stone@ Rs: (Included in material rate) Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1 2

Description Water tanker 8000 ltr Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour

Quantity 1.00 1.00 0.50 0.50

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Water tanker Crew for Pump work inspector Mason Class-I Mason Class-II mazdoor for conveying rubble stones for preparing mortar for loading mortar pans for laying & packing mortar for washing rubble / finishing / curing for conveying mortar / chips Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10

Unit Hour Hour Day Day Day Day Day Day Day Day Day

Quantity 1.00 0.50 1.00 1.00 2.00 4.00 2.00 1.00 3.00 1.00 4.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 0% 10.00 cum

IRR-CCDW-4-2 Providing and constructing un-coursed rubble stone masonry with approved stones in CM 1 : 4 proportion for super-structure portions of return walls / abutments etc., including cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging stone chips, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum, Stone Chips : 0.15 cum) DATA: For 1 cum masonry :Rubble stones : 0.85 cum Sand : 0.40 cum Cement : 143 kg Cement mortar preparation Output of 1 Mason Stone chips : 0.15 cum. : : Manual 5.00 cum per day UNIT : Unit kg cum cum cum Quantity 10.00 cum Rate in Rs. Amount in Rs.

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 Cement Rubble stones Stone chips Sand screened Add for scaffolding @ Add seignorage charges on Stone@ Rs: Add seignorage charges on Sand @ Rs: Total cost of Materials B. MACHINERY: Sl No Particulars

1430.00 8.50 1.50 4.00 TOTAL 2.5% (Included in material rate) (Included in material rate)

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

177

IRR-CCDW

1 2

Water tanker 8000 ltr Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Hour Hour Hour Hour

1.00 1.00 0.50 0.50 Rs: 0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Water tanker Crew for Pump work inspector Mason Class-I Mason Class-II mazdoor for conveying rubble stones for preparing mortar for loading mortar pans for laying & packing mortar for washing rubble / finishing / curing for conveying mortar / chips Add for labour for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Day Day Day Day Day Day Day Day Day

Quantity 1.00 0.50 1.00 1.00 2.00 4.00 2.00 1.00 3.00 1.00 4.00 TOTAL 2.5%

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 0% 10.00 cum

IRR-CCDW-4-3 Providing and constructing coursed rubble masonry second sort in CM 1:4 proportion with stones from approved source including cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with initial lead upto 50 m and initial lift upto 3m. (Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum, Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones 25 x 25x 45 cm : 60 Nos) DATA: Thickness of face stone masonry assumed : For 1 cum masonry :- Khandki stones 25x25x30 cm : 18 Nos. Stone chips : Header stones 25x25x45 cm size : 6 Nos. Rubble stones : Sand : 0.35 cum Cement : 133 kg Preparation of mortar : Output of 1 Mason : RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Particulars Cement Header stones 25x25x45 cm Khandki stones 25x25x30 cm Rubble stones Stone chips Sand screened Add for scaffolding materials @ Add seignorage charges on Stone@ Rs: Add seignorage charges on Sand @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 2 Unit kg Nos Nos cum cum cum 60 cm 0.15 cum 0.45 cum Manual 5.00 cum per day UNIT : Quantity 10.00 cum Rate in Rs. Amount in Rs.

1330.00 60.00 180.00 4.50 1.50 3.50 TOTAL 2.5% (Included in material rate) (Included in material rate)

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

Description Water tanker 8000 ltr Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour

Quantity 1.00 1.00 0.50 0.50

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Water tanker Crew for Pump work inspector Stone chiseller Cl -II Mason Class-I Mason Class-II mazdoor for conveying stones / rubble for preparation of mortar for loading mortar pans for laying & packing mortar for washing rubble / finishing / curing for conveying mortar / chips

Unit Hour Hour Day Day Day Day Day Day Day Day Day Day

Quantity 1.00 0.50 1.00 3.00 1.00 2.00 4.00 3.00 1.00 3.00 1.00 2.00

Rate in Rs.

Amount in Rs.

178

IRR-CCDW

Add for labour for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

TOTAL 2.5%

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 0% 10.00 cum

IRR-CCDW-4-4 Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion with stones from approved source including cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with initial lead upto 50 m and initial lift upto 3 m. (Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum, Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 18 Nos, Header stones 25 x 25x 45 cm : 6 Nos) DATA: Thickness of face stone masonry assumed : 60 cm For 1 cum masonry :- Khandki stones 25x25x30 cm : 18 Nos. Stone chips : 0.15 cum Header stones 25x25x45 cm size : 6 Nos. Rubble stones : 0.45 cum Sand : 0.35 cum Cement : 133 kg Preparation of mortar : Manual Output of 1 Mason : 5.00 cum per day RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Particulars Cement Header stones 25x25x45 cm Khandki stones 25x25x30 cm Rubble stones Stone chips Sand screened Add for scaffolding materials @ Add seignorage charges on Stone@ Rs: Add seignorage charges on Sand @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 2 Unit kg Nos Nos cum cum cum UNIT : Quantity 10.00 cum Rate in Rs. Amount in Rs.

1330.00 60.00 180.00 4.50 1.50 3.50 TOTAL 2.5% (Included in material rate) (Included in material rate)

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

Description Water tanker 8000 ltr Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour Hour Hour

Quantity 1.00 1.00 0.50 0.50

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Water tanker Crew for Pump work inspector Stone chiseller Cl -II Mason Class-I Mason Class-II mazdoor for conveying rubble/ stones for preparation of mortar for loading mortar pans for laying & packing mortar for washing rubble / finishing / curing for conveying mortar / chips Add for labour for scaffolding @ Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Hour Hour Day Day Day Day Day Day Day Day Day Day

Quantity 1.00 0.50 1.00 6.00 1.00 2.00 4.00 3.00 1.00 3.00 1.00 2.00 TOTAL 2.5%

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 0% 10.00 cum

IRR-CCDW-4-5 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 2 proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with initial lead upto 50 m and all lifts. DATA: Consider 100 sqm area for analysis. Considering 15 to 20 mm wide and 50 mm deep joints the quantity of cement mortar required

179

IRR-CCDW

will be about 0.70 cum for 100 sqm pointing. Quantity of mortar for 100 sqm with 10 % wastage : Cement : 456 kg Sand :

0.75 cum 0.75 cum RATE ANALYSIS UNIT : Unit kg cum Quantity 100.00 sqm Rate in Rs. Amount in Rs.

A. MATERIALS: Sl No 1 2 Cement Sand screened

Particulars

Add for scaffolding / ramps etc @ Add seignorage charges on Sand @ Rs: Total cost of Materials B. MACHINERY: Sl No 1

456.00 0.75 TOTAL 2.5% (Included in material rate)

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

Description Nil ( Manual mixing) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- I work inspector mazdoor

Description

Unit Day Day Day

Quantity 10.00 1.00 10.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100 0% 100.00 sqm

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-4-6 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 3 proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with initial lead upto 50 m and all lifts. DATA: Consider 100 sqm area for analysis. Considering 15 to 20 mm wide and 50 mm deep joints the quantity of cement mortar required will be about 0.70 cum for 100 sqm pointing. Quantity of mortar for 100 sqm with 10 % wastage : 0.75 cum Cement : 322 kg Sand : 0.75 cum RATE ANALYSIS A. MATERIALS: Sl No 1 2 Cement Sand screened Add for scaffolding / ramps etc @ Add seignorage charges on Sand @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 Particulars Unit kg cum UNIT : Quantity 100.00 sqm Rate in Rs. Amount in Rs.

322.00 0.75 TOTAL 2.5% (Included in material rate)

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

Description Nil ( Manual mixing) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- I work inspector mazdoor

Description

Unit Day Day Day

Quantity 10.00 1.00 10.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100 0% 100.00 sqm

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-4-7 Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume including cost of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts.

180

IRR-CCDW

DATA:

Consider 100 sqm area for analysis. Quantity of mortar for 100 sqm with 10 % wastage : Cement : 629 kg Sand : RATE ANALYSIS A. MATERIALS: Sl No 1 2 Cement Sand screened Add for scaffolding / ramps etc @ Add seignorage charges on Sand @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 Particulars

1.32 cum 1.32 cum UNIT : Unit kg cum Quantity 100.00 sqm Rate in Rs. Amount in Rs.

629.00 1.32 TOTAL 2.5% (Included in material rate)

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

Description Nil ( Manual mixing) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- I work inspector mazdoor

Description

Unit Day Day Day

Quantity 10.00 1.00 20.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100 0% 100.00 sqm

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-4-8 Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume including cost of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts. DATA: Consider 100 sqm area for analysis. Quantity of mortar for 100 sqm with 10 % wastage : Cement : 472 kg Sand : RATE ANALYSIS A. MATERIALS: Sl No 1 2 Cement Sand screened Add for scaffolding / ramps etc @ Add seignorage charges on Sand @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 Particulars Unit kg cum

1.32 cum 1.32 cum UNIT : Quantity 100.00 sqm Rate in Rs. Amount in Rs.

472.00 1.32 TOTAL 2.5% (Included in material rate)

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

Description Nil ( Manual mixing) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- I work inspector mazdoor

Description

Unit Day Day Day

Quantity 10.00 1.00 20.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100 0% 100.00 sqm

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-4-9 Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume including cost of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts. DATA: Consider 100 sqm area for analysis.

181

IRR-CCDW

Quantity of mortar for 100 sqm with 10 % wastage : Cement : 1050 kg Sand : 20 mm thick plastering to be done in 2 layers of 12 mm and 8 mm . Output of 1 mason for rough plastering Output of 1 mason for smooth plastering

2.20 cum 2.2 cum : : 20 sqm per day 10 sqm per day

RATE ANALYSIS A. MATERIALS: Sl No 1 2 Cement Sand screened Add for scaffolding / ramps etc @ Add seignorage charges on Sand @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 Particulars Unit kg cum

UNIT : Quantity

100.00 sqm Rate in Rs. Amount in Rs.

1050.00 2.20 TOTAL 2.5% (Included in material rate)

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

Description Nil ( Manual mixing) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- I work inspector mazdoor

Description

Unit Day Day Day

Quantity 15.00 1.00 25.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100 0% 100.00 sqm

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-4-10 Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts. DATA: Consider 100 sqm area for analysis. Quantity of mortar for 100 sqm with 10 % wastage : 2.20 cum Cement : 788 kg Sand : 20 mm thick plastering to be done in 2 layers of 12 mm and 8 mm . Output of 1 mason for rough plastering : Output of 1 mason for smooth plastering :

2.2 cum 20 sqm per day 10 sqm per day

RATE ANALYSIS A. MATERIALS: Sl No 1 2 Cement Sand screened Add for scaffolding / ramps etc @ Add seignorage charges on Sand @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 Particulars Unit kg cum

UNIT : Quantity

100.00 sqm Rate in Rs. Amount in Rs.

788.00 2.20 TOTAL 2.5% (Included in material rate)

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

Description Nil ( Manual mixing) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- I work inspector mazdoor

Description

Unit Day Day Day

Quantity 15.00 1.00 25.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100 0% 100.00 sqm

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

182

IRR-CCDW

IRR-CCDW-5

COPING & RAILING WORKS :

IRR-CCDW-5-1 Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm) DATA: Consider 10 sqm coping for analysis. Cement : 75 kg Sand : Burnt stone slab 10 cm thick with 5 % wastage :

0.30 cum 10.50 sqm RATE ANALYSIS UNIT : Unit Quantity 10.00 sqm Rate in Rs. Amount in Rs.

A. MATERIALS: Sl No 1 2 3

Particulars

Cement kg 75.00 Sand screened cum 0.30 Burnt stone slab 10 cm thick sqm 10.50 Add seignorage charges on Stone @ Rs: (Included in material rate) Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nil ( Manual mixing) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 Mason Cl- II Stone chiseller Cl- II work inspector mazdoor

Description

Unit Day Day Day Day

Quantity 1.00 1.00 0.50 2.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /10 0% 10.00 sqm

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-5-2 Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm) DATA: Consider 10 sqm coping for analysis. Cement : 75 kg Sand : 0.30 cum Burnt stone slab 10 cm thick with 5 % wastage : 10.50 sqm RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit UNIT : Quantity 10.00 sqm Rate in Rs. Amount in Rs.

Cement kg 75.00 Sand screened cum 0.30 Burnt stone slab 10 cm thick sqm 10.50 Add seignorage charges on Stone @ Rs: (Included in material rate) Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nil ( Manual mixing) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 Mason Cl- II Stone chiseller Cl- I work inspector mazdoor

Description

Unit Day Day Day Day

Quantity 1.00 4.00 0.50 2.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

183

IRR-CCDW

D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /10

0% 10.00 sqm

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-CCDW-5-3 Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm) DATA: Consider 10 sqm coping for analysis. Cement : 75 kg Sand : 0.30 Burnt stone slab 10 cm thick with 5 % wastage : 10.50 sqm RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit UNIT : Quantity

cum

10.00 sqm Rate in Rs. Amount in Rs.

Cement kg 75.00 Sand screened cum 0.30 Burnt stone slab 10 cm thick sqm 10.50 Add seignorage charges on Stone @ Rs: (Included in material rate) Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nil ( Manual mixing) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 Mason Cl- II Stone chiseller Cl-I work inspector mazdoor

Description

Unit Day Day Day Day

Quantity 1.00 8.00 0.50 2.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /10 0% 10.00 sqm

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-5-4 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sqmm ) grade cement concrete using 20 mm down size approved clean, hard, graded aggregates for coping slab including cost of all materials, machinery, labour, formwork, cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing etc., complete with initial lead upto 50 m and initial lift upto 3 m. (Cement content: 270 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) DATA: Requirement of materials : For 1 cum CC :- Coarse aggregates : 0.80 cum Blending ratio : 65 :35 Fine aggregate : 0.45 cum Cement content : 270 kg Super plasticizer : 1.08 kg Average output of 300/200 ltr mixer : 50 x 11 x 8 / 270 say : 16 cum per day RATE ANALYSIS UNIT : 16 cum A. MATERIALS: Sl No Particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Cement for mix kg 4320.00 Cement for incidentals @ 5 kg / cum kg 80.00 2 Coarse aggregate 20-10 mm cum 8.32 Coarse aggregate 10 mm below cum 4.48 3 Fine aggregate cum 7.20 4 Super Plasticizer kg 17.28 5 Use rate of shuttering sqm 88.00 6 Sundries sqm 1.00 Add seignorage charges on Stone @ Rs: (Included in material rate) Rs: 0.00 Add seignorage charges on Sand @ Rs: (Included in material rate) Rs: 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No 1 2 3

Description Concrete mixer 300/200 ltr ( diesel ) Fuel / Energy charges 5 hp pump ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges

Unit Hour Hour Hour Hour Hour Hour

Quantity 8.00 8.00 0.50 0.50 1.00 1.00

Rate in Rs.

Amount in Rs.

184

IRR-CCDW

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3 4 5 6

Rs:

0.00

Description Crew for Concrete mixer Crew for Pump Crew for Water tanker Mason Class-I work inspector mazdoor for batching materials for loading mortar pans for laying and tamping for conveying concrete for cleaning/ washing/ curing Labour cost for shuttering/scaffolding Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /16

Unit Hour Hour Hour Day Day Day Day Day Day Day sqm

Quantity 8.00 0.50 1.00 1.00 1.00 11.00 4.00 3.00 16.00 1.00 88.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 0% 16.00 sqm

IRR-CCDW-5-5 Providing and constructing protective railing consisting of in-situ railing posts of size 15 x 15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 grade concrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos. of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mm dia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primer and two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork, finishing, curing etc., complete with lead upto 50 m and all lifts. DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 Particulars Unit UNIT : Quantity 10.00 Rm Rate in Rs. Amount in Rs.

Cement kg 30.00 20-10 mm coarse aggregate cum 0.04 10-4.75 mm coarse aggregate cum 0.02 Fine aggregate cum 0.04 Reinforcement steel kg 16.39 40 mm dia GI pipes B class Rm 30.00 Use rate of shuttering sqm 3.00 Sundries ( paints/ binding wire etc ) LS 4.00 Add seignorage charges on Stone @ Rs: (Included in material rate) Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 Mason Class I Bar bender work inspector mazdoor Painter Cl- II Fitter shuttering

Description

Unit Day Day Day Day Day Day

Quantity 0.50 0.50 0.50 1.50 0.50 0.50

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /10 IRR-CCDW-6 HUME PIPE LAYING & JOINTING WORKS : 0% 10.00 Rm

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-6-1 Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)

185

IRR-CCDW

DATA:

Consider 10 joints for analysis. Cement : 99 kg Sand : Hemp yarn : 2 Masons & 2 mazdoors considered for 10 joints. 1 mazdoor for curing @ daily 1 hour for one week.

0.10 cum 0.91 kg

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit

UNIT : Quantity

10.00 Joint Rate in Rs. Amount in Rs.

Cement kg 99.00 Sand screened cum 0.10 Hemp yarn kg 0.91 Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- II work inspector mazdoor

Description

Unit Day Day Day

Quantity 2.00 1.00 3.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Joint=(A+B+C+D) /10 0% 10.00 Joint

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-6-2 Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint) DATA: Consider 10 joints for analysis. Cement : 174 kg Sand : Hemp yarn : 2 Masons & 2 mazdoors considered for 10 joints. 1 mazdoor for curing @ daily 1 hour for one week.

0.22 cum 1.27 kg

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit

UNIT : Quantity

10.00 Joint Rate in Rs. Amount in Rs.

Cement kg 174.00 Sand screened cum 0.22 Hemp yarn kg 1.27 Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- II work inspector mazdoor

Description

Unit Day Day Day

Quantity 2.00 1.00 3.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Joint=(A+B+C+D) /10 0% 10.00 Joint

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-6-3 Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

186

IRR-CCDW

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint) DATA: Consider 10 joints for analysis. Cement : 248kg Sand : Hemp yarn : 2.5 Masons & 3 mazdoors considered for 10 joints. 1mazdoor for curing @ daily 1 hour for one week.

0.25 cum 2.20 kg

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit

UNIT : Quantity

10.00 Joint Rate in Rs. Amount in Rs.

Cement kg 248.00 Sand screened cum 0.25 Hemp yarn kg 2.20 Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- II work inspector mazdoor

Description

Unit Day Day Day

Quantity 2.50 1.00 4.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Joint=(A+B+C+D) /10 0% 10.00 Joint

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-6-4 Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint) DATA: Consider 10 joints for analysis. Cement : 321 kg Sand : Hemp yarn : 2.5 Masons & 3 mazdoors considered for 10 joints. 1mazdoor for curing @ daily 1 hour for one week.

0.31 cum 2.50 kg

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit

UNIT : Quantity

10.00 Joint Rate in Rs. Amount in Rs.

Cement kg 321.00 Sand screened cum 0.31 Hemp yarn kg 2.50 Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- II work inspector mazdoor

Description

Unit Day Day Day

Quantity 2.50 1.00 4.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Joint=(A+B+C+D) /10 0% 10.00 Joint

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

187

IRR-CCDW

IRR-CCDW-6-5 Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint) DATA: Consider 10 joints for analysis. Cement : 396 kg Sand : Hemp yarn : 3 Masons & 4 mazdoors considered for 10 joints. 1mazdoor for curing @ daily 1 hour for one week.

0.39 cum 3.10 kg

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit

UNIT : Quantity

10.00 Joint Rate in Rs. Amount in Rs.

Cement kg 396.00 Sand screened cum 0.39 Hemp yarn kg 3.10 Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- II work inspector mazdoor

Description

Unit Day Day Day

Quantity 3.00 1.00 5.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Joint=(A+B+C+D) /10 0% 10.00 Joint

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-6-6 Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint) DATA: Consider 10 joints for analysis. Cement : 446 kg Sand : Hemp yarn : 3 Masons & 4 mazdoors considered for 10 joints. 1mazdoor for curing @ daily 1 hour for one week.

0.45 cum 3.40 kg

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit

UNIT : Quantity

10.00 Joint Rate in Rs. Amount in Rs.

Cement kg 446.00 Sand screened cum 0.45 Hemp yarn kg 3.40 Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- II work inspector mazdoor

Description

Unit Day Day Day

Quantity 3.00 1.00 5.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

188

IRR-CCDW

D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Joint=(A+B+C+D) /10

0% 10.00 Joint

Rs: Rs: Rs:

0.00 0.00 0.00

IRR-CCDW-6-7 Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint) DATA: Consider 10 joints for analysis. Cement : 495 kg Sand : Hemp yarn : 3 Masons & 5 mazdoors considered for 10 joints. 1mazdoor for curing @ daily 1 hour for one week.

0.5 cum 3.77 kg

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit

UNIT : Quantity

10.00 Joint Rate in Rs. Amount in Rs.

Cement kg 495.00 Sand screened cum 0.50 Hemp yarn kg 3.77 Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- II work inspector mazdoor

Description

Unit Day Day Day

Quantity 3.00 1.00 6.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Joint=(A+B+C+D) /10 0% 10.00 Joint

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-6-8 Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint) DATA: Consider 10 joints for analysis. Cement : 569 kg Sand : Hemp yarn : 3 Masons & 5 mazdoors considered for 10 joints. 1mazdoor for curing @ daily 1 hour for one week.

0.58 cum 4.15 kg

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit

UNIT : Quantity

10.00 Joint Rate in Rs. Amount in Rs.

Cement kg 569.00 Sand screened cum 0.58 Hemp yarn kg 4.15 Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- II work inspector mazdoor

Description

Unit Day Day Day Total cost of Labour

Quantity 3.00 1.00 6.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

189

IRR-CCDW

ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Joint=(A+B+C+D) /10 0% 10.00 Joint

Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-6-9 Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint) DATA: Consider 10 joints for analysis. Cement : 668 kg Sand : Hemp yarn : 4 Masons & 6 mazdoors considered for 10 joints. 1mazdoor for curing @ daily 1 hour for one week.

0.69 cum 4.53 kg

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Particulars Unit

UNIT : Quantity

10.00 Joint Rate in Rs. Amount in Rs.

Cement kg 668.00 Sand screened cum 0.69 Hemp yarn kg 4.53 Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Mason Cl- II work inspector mazdoor

Description

Unit Day Day Day

Quantity 4.00 1.00 7.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Joint=(A+B+C+D) /10 IRR-CCDW-7 BACK FILLING & OTHER WORKS : 0% 10.00 Joint

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-7-1 Providing rubble / boulder and sand filling behind abutment and return walls in layers including cost of all materials, machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and initial lift upto 3 m. DATA: Consider 10 cum rubble/ boulder and sand filling. Quantity of rubble/ boulder Quantity of sand 2 mazdoors for rubble filling & 2 mazdoor for packing with sand & watering. RATE ANALYSIS A. MATERIALS: Sl No 1 2 Particulars Unit

: :

10.00 cum 4.00 cum

UNIT : Quantity

10.00 cum Rate in Rs. Amount in Rs.

Rubble / Boulder cum 10.00 Sand unscreened cum 4.00 Add seignorage charges on Stone@ Rs: (Included in material rate) Add seignorage charges on Sand @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs:

0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description Nill ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector Mason Cl II

Description

Unit Day Day

Quantity 0.50 1.00

Rate in Rs.

Amount in Rs.

190

IRR-CCDW

mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Day

4.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 0% 10.00 cum

IRR-CCDW-7-2 Providing and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth masters to achieve density control of not less than 95 percent etc., complete with lead upto 50 m and all lifts. DATA: For foundation filling in pits and around pipes requires collection and rehandling of soil. Output of 2 mazdoors for rehandling at site per day( loose) : Output of 1 mazdoor for levelling & compaction / day ( loose ) : Cartman with double bullock cart for supplying water : 1mazdoor for watering and miscellaneous works at site. RATE ANALYSIS A. MATERIALS: Sl No 1 Murum Particulars Unit

6.00 cum 12.00 cum 0.5 day

UNIT : Quantity

10.00 cum Rate in Rs. Amount in Rs.

cum 12.00 0.00 Add seignorage charges on Soil @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1

Description Nill Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description Cartman with double bullock cart work inspector mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Unit Day Day Day

Quantity 0.50 0.50 6.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 0% 10.00 cum

IRR-CCDW-7-3 Providing and filling murum / gravely soil ( CNS soil ) for foundation or above pipes including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power roller to achieve density control of not less than 98 percent etc., complete with lead upto 50 m and all lifts. DATA: For foundation filling in large area and above pipes no rehandling of soil is considered. Output of 1 mazdoor for spreading & levelling at site per day : Output of 8-10 tonne road roller for compaction per hour : Cartman with double bullock cart for supplying water : 1mazdoor for watering at site. RATE ANALYSIS A. MATERIALS: Sl No 1 Murum Add seignorage charges on Soil @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 Particulars Unit cum

12.00 cum 58.6 cum/hour 0.5 day

UNIT : Quantity

10.00 cum Rate in Rs. Amount in Rs.

12.00 0.00 (Included in material rate)

Rs: Rs:

0.00 0.00

Description Diesel road roller 8-10 tonne Fuel / Energy charges Total hire charges of Machinery

Unit Hour Hour

Quantity 0.17 0.17

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2

Description Operator road roller Cartman with double bullock cart

Unit Hour Day

Quantity 0.17 0.50

Rate in Rs.

Amount in Rs.

191

IRR-CCDW

3 4

work inspector mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Day Day

0.50 1.50 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 0% 10.00 cum Rate per cum

IRR-CCDW-7-4 Providing and fixing one line dressed 111x35x25 cm thick IRC standard kilometre stone in cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts. DATA: For fixing each kilometre stone: Quantity of excavation ( 0.70 x 0.45 x 0.40 ) Quantity of M-10 grade concrete ( 0.13 -- 0.35x0.25x0.30 ) Surface painting 2 coats RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 Particulars Unit

: : :

0.13 cum 0.10 cum 2.00 sqm UNIT : Quantity Rate in Rs. 4 Each Amount in Rs.

One line dressed Km stone No. 4.00 40-20 mm coarse aggregate cum 0.20 20-10 mm coarse aggregate cum 0.15 10-4.75 mm coarse aggregate cum 0.10 Sand screened cum 0.20 Cement kg 100.00 Synthetic enamel paint I st quality ltr 1.00 Sundries ( brush / oil etc ) LS 4.00 Add seignorage charges on Stone @ Rs: (Included in material rate) Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 Mason Cl- II work inspector mazdoor Painter Cl- I

Description

Unit Day Day Day Day

Quantity 1.00 1.00 1.00 1.00

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /4 0% 4.00 Each

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IRR-CCDW-7-5 Providing and fixing one line dressed 65x15x10 cm thick IRC standard hectometre stone in cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts. DATA: For fixing each hectometre stone: Quantity of excavation ( 0.50 x 0.45 x 0.40 ) Quantity of M-10 grade concrete ( 0.10 -- 0.15x0.10x0.30 ) Surface painting 2 coats RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 Particulars One line dressed hectometre stone 40-20 mm coarse aggregate 20-10 mm coarse aggregate 10-4.75 mm coarse aggregate Sand screened Cement Synthetic enamel paint I st quality Unit No. cum cum cum cum kg ltr

: say : :

0.10 cum 0.10 cum 0.40 sqm UNIT : Quantity 4.00 0.20 0.15 0.10 0.20 100.00 0.40 Rate in Rs. 4 Each Amount in Rs.

192

IRR-CCDW

Sundries ( brush / oil etc ) LS 1.00 Add seignorage charges on Stone @ Rs: (Included in material rate) Add seignorage charges on CA @ Rs: (Included in material rate) Add seignorage charges on FA @ Rs: (Included in material rate) Total cost of Materials

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL ( Manual mixing ) Total hire charges of Machinery

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 Mason Cl- II work inspector mazdoor Painter Cl- I

Description

Unit Day Day Day Day

Quantity 1.00 1.00 1.00 0.50

Rate in Rs.

Amount in Rs.

Total cost of Labour ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /4 0% 4.00 Each Rate per Each

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

193

IRR-GAW

CHAPTER-V Standard Data

IRR-GAW
Notes

HYDRAULIC GATES AND ALLIED EQUIPMENT

1 All materials / bought out components for embedded parts, gates, hoists and allied works shall conform to relevant Indian standards / technical specifications and approved drawings. 2 The basic rates are EXCLUSIVEof preparation of designs / drawings / material schedules etc., as per specifications and other technical data including revisions. If designs &drawings are to be done by private agency 2.% of estimated cost be added 3 The basic rates are inclusive of cost of all materials, machinery, labour, fabrication, erection, commissioning and testing of gates, hoists and other related components as per technical specifications. 4 The basic rates are inclusive of finishing, wastage of materials , incidental works, temperary supports, all enabling works, profit, overheads, small tools / plants, hidden cost on labour etc. 5 The basic rates are inclusive of taxes, duties (excise ), levies and all other incidental charges including turn over tax/sales tax on works contract. Separate provision shall be made in the estimate towards such tax on works contract at the rate prevailing at the time of preparation of estimate. 6 The basic rates are inclusive of all leads and lifts including rehandling. 7 No provision is made for stitch welding and it is part of welding work 8 The basic rates are inclusive of preparatory works such as rectification of damages, repairing shop painting, cleaning, positioning and anchoring first stage embedments, 9 The basic rates are not inclusive of painting with or without sand blasting,and are to be added to the rate as perschedule rates formulated in the same chapter as per applicability and specifications 10 The basic rates are exclusive of cost of river diversion arrangements, dewatering, desilting ,secondary concreting of EM parts etc., which form part of civil works. 11 DESIGNS AND DRAWING CHARGES AT 2% BE ADDED EXTRA TO THE ESTIMATES, IF CONTRACTOR'S SCOPE OF WORK INVOLVES DESIGNS COMPONENT ALSO 12 Add AREA ALLOWANCES AS APPLICABLE ON LABOUR COMPONENT ONLY 13 PAINTING CHARGES ADDED EXTRA TO THE DATA ITEMS AS PER APPLICABILITY DRAFTING FROM ITEM-C 16 TO D- 24 14 HOIST EQUIPMENT 1. where sand blasting is not possible, hand and power tool cleaning be adopted 2. Machined surfaces should not be painted 3. for maintenance unless sand blasting is essential hand and power tool cleaning be adopted 15 PRIMAR COATS-- GATES --Gates and stoplogs--70+/- 5 one coat of inoganiczink silicate(airless spray preferred) --E.M. parts---70+/- 5 one coat of inoganiczink silicate(airless spray preferred) --Lifting beams/ladders--two coats of zinc phosphate primer (airless spray preferred) 40microns/coat FINISHING COATS--GATES --- Gatesand stoplogs-150+/- 5 two coats(each 150) of solventless coaltar epoxy paint -E.M. parts--150+/- 5 two coats(each 150) Two coats of solventless coaltar epoxy paint --Lifting beams/ladders-- two coats 130 microns (each 65+/-5) of alkyd based micaccous iron oxide paint 16

Primary coats-- Hoists and supporting structure


structural components: two coats of zinc phosphate primer silicate(airless spray preferred) 40microns/coat Machinery: one coat of zinc phosphate primer (airless spray preferred) 50microns/coat HYDRAULIC HOIST:(exposed to water) One coat ofcoat of inoganic zink silicate (airless spray preferred) 70microns/coat ( un exposed to water) two coats of zink phosphate primer (airless spray preferred) 40microns/coat (oil tank control cabins,hoist beams and pipe support) one coat of zink phosphate primer (airless spray preferred) 50microns/coat unmachined surfaces: one primer coat ofchlorinated rubber based zinc phosphate primer 50+/- microns FINISHING COATS-- Hoists and supporting structure structural components: one coat 65+/-5 of alkyd based micaccous iron oxide paint followed by two coats of synthetic enamel paint 25 microns/coat Machinery: three coats of aluminium paint orsynthetic enamel zinc phosphate primer , 25 microns/coat HYDRAULIC HOIST:(exposed to water) two coats of solventless coal tar epoxy paint150 microns/coat ( un exposed to water)one coat 65+/-5 of alkyd based micaccous iron oxide paint followed by two coats of synthetic enamel paint25 microns/coat (oil tank control cabins,hoist beams and pipe support) one coat of zink phosphate primer (airless spray preferred) 50microns/coat Unmachined surfaces: three coats of vinyl resin/chlorinated rubber paint 30+/-5 microns

194

IRR-GAW

Index- code

IRR-GAW
IRR-GAW-1 RADIAL GATES

GATE HOIST AND ALLIED WORKS

IRR-GAW-1-1

E.M Parts and anchorages fabrication, supply, erection, testing and commissioning of Embedded parts for radial gate consists of sill beam, wall plates, anchor girders , yoke girders , tie flats, trunnion supports etc., including cost of all materials, machinery, labour, welding, finishing, with leads and lifts &all accessories (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under itemsinthis chapter and add as applicable separately)

DATA:

Consider embedded parts for radial gate for spillway opening of size 15 m x 9 m for analysis. Size of gate for 15 x 9 m spillway opening at crest Length : 15 m Height : 9.75 m Consider actual weight for data rate analysis. 14.4 tonnes RATE ANALYSIS UNIT : 14.334 tonne A. MATERIALS: Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Str steel angle / beam / channel / bars kg 700.00 0.00 2 Structural steel plate / flats kg 13700.00 0.00 3 Stainless steel plate / flats kg 200.00 0.00 4 MS bolts and nuts kg 110.00 0.00 5 Oxygen gas cum 276.00 0.00 6 Acetyline gas cum 92.00 0.00 7 Welding electrodes Nos 665.00 0.00 8 Welding electrodes ( LH ) Nos 5983.00 0.00 9 Welding electrodes ( stainless steel ) Nos 657.00 0.00 10 Use rate welding holder set Hour 780.00 0.00 11 Use rate gas cutting torch set Hour 36.00 0.00 12 Sundries LS 100.00 0.00 Total cost of Materials Rs: B. MACHINERY: Sl No 1 2 3 4 5 6 7 8 9

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description Welding transformer Fuel / Energy charges Tower crane/heavy duty tyre mounted crane Fuel / Energy charges Plate shearing machine Fuel / Energy charges Pug cutting machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges Stationery derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Planing machine Fuel / Energy charges 10 Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 780.00 488.00 4.00 4.00 5.00 5.00 149.00 149.00 32.00 32.00 64.00 64.00 16.00 16.00 16.00 16.00 150.00 150.00 100.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Description Crew for Tower crane Crew for Mobile crane Crew for Shearing machine Crew for Planing machine Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Welder ( X - ray ) Khalasi Helper fabrication / erection Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Hour 4.00 Hour 32.00 Hour 5.00 Hour 150.00 Hour 16.00 Hour 16.00 Day 51.00 Day 92.00 Day 24.00 Day 66.00 Day 7.00 Day 50.00 Day 219.00 Day 5.00 Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D.Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @

Total 0.00% Total 0%

195

IRR-GAW

Total F.Add for contractor's profit and overheads on A+B+C++E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for Rate per tonne=(A+B+C+D+E+F) /14.334 0%

Rs: Rs:

0.00 0.00

0.00 per tonne

0.00 per tonne 14.334 tonne Rs: Rs:

0 0.00 0.00

IRR-GAW-1-2

fabrication, supply, erection, testing and commissioning of radial gate consisting of skin plate, stiffeners, horizontal girders, radial arms, trunnion assemblies, tie beam, pulley supports, bracings, rubber seals, clamps etc., with all accessories for spillway/canals including cost of all materials, machinery, labour, seal fixing etc., complete as per specifications and approved drawings (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under itemsinthis chapter and add as applicable separately)

data

Consider radial gate for spillway opening of size 15 m x 9 m for analysis. Details of material / Gas cutting / Welding considered for rate analysis are based on radial gate drawings for 15 m x 9 m spillway RATE ANALYSIS UNIT : 57.457 tonne A. MATERIALS: Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Structural steel : Angles / beams / channels / bars kg 15806.00 0.00 0.00 Plates / flats kg 38672.00 0.00 0.00 2 Cast steel components : Trunnion hubs / Guide rollers kg 1895.00 0.00 0.00 3 Alloy steel components : Stainless steel plate kg 6.00 0.00 0.00 Trunnion pins kg 1098.00 0.00 0.00 4 Alluminium / Bronze alloy components : Bush for Trunnion / Guide roller kg 1155.00 0.00 0.00 5 Bolt / Nut / Washer : GI bolts / nuts / washers kg 78.00 0.00 0.00 MS bolts / nuts / washers kg 79.00 0.00 0.00 6 Zinc kg 140.00 0.00 0.00 7 Rubber seals : Bottom seal Rm 15.50 0.00 0.00 Side seals ( Z - type ) Rm 25.00 0.00 0.00 8 Oxygen gas cum 657.00 0.00 0.00 9 Acetyline gas cum 219.00 0.00 0.00 10 Welding electrodes ( std ) Nos 2728.00 0.00 0.00 11 Welding electrodes ( LH ) Nos 24554.00 0.00 0.00 12 Use rate welding holder set Hour 3637.00 0.00 0.00 13 Use rate gas cutting torch set Hour 210.00 0.00 0.00 14 Sundries LS 1000.00 0.00 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No 1 2 3 4 5 6 7 8 9

Description Welding transformer Fuel / Energy charges Plate shearing machine Fuel / Energy charges Pug cutting machine Fuel / Energy charges Bending machine Fuel / Energy charges Tower crane 5 t cpacity Fuel / Energy charges Mobile derric crane Fuel / Energy charges Stationery derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges 10 Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 3637.00 2273.00 12.00 12.00 228.00 228.00 238.00 238.00 10.00 10.00 150.00 150.00 300.00 300.00 50.00 50.00 50.00 50.00 1000.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6

Description Crew for Mobile crane Crew for Tower crane Crew for Bending machine Crew for Drilling machine Crew for Grinding machine Foreman

Unit Hour Hour Hour Hour Hour Day

Quantity 150.00 10.00 238.00 50.00 50.00 155.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00

196

IRR-GAW

7 8 9 10 11 12 13

Marker / Fabricator / Erector Gas cutter Welder ( General ) Welder ( X - ray ) Khalasi Helper fabrication / erection Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Day 226.00 Day 56.00 Day 307.00 Day 34.00 Day 250.00 Day 1105.00 Day 30.00 Total cost of Labour

0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for Rate per tonne=(A+B+C+D+E+F) /57.457 0%

Total 0.00% Total 0%

0.00 per tonne

0.00 per tonne 57.457 tonne Rs: Rs.

0 0.00 0.00

IRR-GAW-1-3

RADIAL GATES-ROPE DRUM HOISTS

WITH HOIST BRIDGES

fabrication, supply, erection, testing and commissioning of electrically operated rope drum hoist of adequate capacity consisting of base frames, rope drums,connecting shaft, gear system, brake system, electric motor, wire ropes, gate position indicator, manual operation arrangement etc., with all accessories for spillway radial gate including cost of all materials, machinery, labour,, greasing, providing hand railing and approach staircase with gate to hoist platform, , complete as per specifications and approved drawings (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under itemsinthis chapter and add as applicable separately) DATA: Rope drum hoist for radial gate consists of embedded parts for anchorages, hoist supporting structure, pulley supporting structures, pulleys, drive stool, rope drums, couplings, shafts, gears and pinions, plummer blocks, worm reducer, floating shaft, electric motor, hand operation assembly, brake, wire rope, gate position indicator, switch box etc. with related accessories. Consider rope drum hoist for radial gate for spillway opening of size 15 m x 9 m for analysis. Details of material / Gas cutting / Welding considered for rate analysis are based on rope drum hoist drawings for 15 m x 9 m spillway gate RATE ANALYSIS UNIT : 15.440 tonne wt A. MATERIALS: 90.00 t capacity Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Structural steel Angles / beams / channels / bars kg 2571.00 0.00 0.00 Plates / flats kg 3632.00 0.00 0.00 2 Cast steel components : Rope drums 2 Nos / Gears 4 Nos kg 3680.00 0.00 0.00 Pinions kg 218.00 0.00 0.00 Pulleys 720 PCD 6 Nos kg 1080.00 0.00 0.00 Plummer blocks / Hubs kg 322.00 0.00 0.00 3 Alloy steel components Shafts kg 557.00 0.00 0.00 Pins kg 546.00 0.00 0.00 4 Bronze alloy components : Bronze bearings / bush kg 144.00 0.00 0.00 5 Wire rope 36 mm dia 6/37 construction kg 448.00 0.00 0.00 6 MS Bolt / Nut / Washer kg 85.00 0.00 0.00 7 Worm reducers No. 1.00 0.00 0.00 8 Electric motor 20 hp No. 1.00 0.00 0.00 9 Floating shaft 300 mm dia kg 1000.00 0.00 0.00 10 Manual operating system No. 1.00 0.00 0.00 11 Gate position indicator No. 1.00 0.00 0.00 12 Ele-magnetic brake No. 1.00 0.00 0.00 13 Electric cable / switch / control panel etc LS 1.00 0.00 0.00 14 Oxygen gas cum 213.00 0.00 0.00 15 Acetyline gas cum 71.00 0.00 0.00 16 Welding electrodes Nos 530.00 0.00 0.00 17 Welding electrodes ( LH ) Nos 4776.00 0.00 0.00 18 Grease kg 50.00 0.00 0.00 19 Use rate welding holder set Hour 566.00 0.00 0.00 20 Use rate gas cutting torch set Hour 90.00 0.00 0.00 21 Sundries ( hand rail /staircase / gate etc ) LS 200.00 0.00 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No 1 2

Description Welding transformer Fuel / Energy charges Tower crane 5 t capacity

Unit Hour Hour Hour

Quantity 566.00 353.00 4.00

Rate in Rs. 0.00 0.00 0.00

Amount in Rs. 0.00 0.00 0.00

197

IRR-GAW

3 4 5 6 7

Fuel / Energy charges Pug cutting machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

4.00 53.00 53.00 50.00 50.00 8.00 8.00 16.00 16.00 100.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9 10 11

Description Crew for Mobile crane Crew for Tower crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector / Mechanic Gas cutter Welder ( General ) Khalasi Helper fabrication / erection Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Hour 50.00 Hour 4.00 Hour 16.00 Hour 8.00 Day 35.00 Day 58.00 Day 18.00 Day 53.00 Day 20.00 Day 175.00 Day 3.00 Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. 0%

Total 0.00% Total 0%

0.00 per tonne

Unloading charges of fabricated parts Rs 0.00 per tonne 0 Total cost for 15.440 tonne wt Rs: Total cost for 90.00 t capacity Rs: Rate per tonne wt=(A+B+C+D+E+F) /15.440 Rs: Rate per tonne capacity=(A+B+C+D+E+F) /90

0.00 0.00 0.00

IRR-GAW-1-4

Walk way(cat walk) fabrication, supply, erection and commissioning of 1 metre wide walkway connecting spillway piers / abutments at trunnion platform level including cost of all materials, machinery, labour, cutting, welding etc, complete as per specifications and approved drawings (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under itemsinthis chapter and add as applicable separately) walk way at trunnion level generally consists of 1 m wide structural steel bridge spanning across piers / abutments for maintenance of gate parts at trunnion level. Consider catwalk for a clear span of 15 m and 3 m wide piers. Details of material / Gas cutting / Welding considered for rate analysis are based on foot bridge drawings for 15 m x 9 m radial gate The actual weight of walkway/ foot bridge as per data : 5.318 t RATE ANALYSIS UNIT : 18.00 Rm A. MATERIALS: Sl No particulars Unit Quantity Rate in Rs. 1 Structural steel Angles / beams / channels / bars kg 4258.00 0.00 Plates / flats kg 98.00 0.00 Chequered plates kg 856.00 0.00 2 MS bolts / nuts / washers kg 8.00 0.00 3 Oxygen gas cum 51.00 0.00 4 Acetyline gas cum 17.00 0.00 5 Welding electrodes Nos 1195.00 0.00 6 Use rate welding holder set Hour 128.00 0.00 7 Use rate gas cutting torch set Hour 24.00 0.00 8 Sundries LS 10.00 0.00 Total cost of Materials Rs: B. MACHINERY: Sl No 1 2 3

DATA:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description Welding transformer Fuel / Energy charges Tower crane Fuel / Energy charges Pug cutting machine

Unit Hour Hour Hour Hour Hour

Quantity 128.00 80.00 1.00 1.00 10.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00

Amount in Rs. 0.00 0.00 0.00 0.00 0.00

198

IRR-GAW

4 5 6 7

Fuel / Energy charges Mobile derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Hour Hour Hour Hour Hour Hour Hour LS

10.00 4.00 4.00 2.00 2.00 2.00 2.00 10.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Mobile crane Crew for Tower crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Helper fabrication / erection 10 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity 4.00 1.00 2.00 2.00 6.00 10.00 4.00 12.00 38.00 1.00

Hour Hour Hour Hour Day Day Day Day Day Day Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for Rate per Rm=(A+B+C+D+E+F) /18 0%

Total 0.00% Total 0%

0.00 per tonne

0.00 per tonne 18.00 Rm Rs: Rs:

0 0.00 0.00

IRR-GAW-2 IRR-GAW-2-1

VERTICAL LIFT GATES-EM PARTS Design, fabrication, supply, erection and commissioning of embedded parts consisting of sill beam, slide tracks, seal seats, guide rails, dogging sets for storage of stoplog elements etc., with all accessories for spillway stop log gates and other vertical lift elements including cost of all materials, machinery, labour, etc., complete as per specifications and approved drawings (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) Spillway stoplog gate embedded parts consist of sill beam, slide tracks / seal tracks and gate guides and dogging sets for storage of elements with accessories such as first stage anchors. Consider embedded parts for stoplog gate for spillway opening of size 15 m x 9 m for analysis. The actual weight of embedded parts as per data sheet : 3.179 tonnes Consider actual weight for data rate analysis. RATE ANALYSIS UNIT : 3.179 tonne A. MATERIALS: Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Str steel angle / beam / channel / bars kg 432.00 0.00 0.00 2 Structural steel plate / flats kg 2301.00 0.00 0.00 3 Stainless steel plate / flats kg 411.00 0.00 0.00 4 MS bolts and nuts kg 115.00 0.00 0.00 5 Oxygen gas cum 99.00 0.00 0.00 6 Acetyline gas cum 33.00 0.00 0.00 7 Welding electrodes Nos 166.00 0.00 0.00 8 Welding electrodes ( LH ) Nos 1499.00 0.00 0.00 9 Welding electrodes ( stainless steel ) Nos 1030.00 0.00 0.00 10 Use rate welding holder set Hour 288.00 0.00 0.00 11 Use rate gas cutting torch set Hour 18.00 0.00 0.00 12 Sundries LS 20.00 0.00 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No 1 2 3 4 5

DATA:

Description Welding transformer Fuel / Energy charges Plate shearing machine Fuel / Energy charges Pug cutting machine Fuel / Energy charges Planing machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour

Quantity 288.00 180.00 4.00 4.00 48.00 48.00 135.00 135.00 4.00 4.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

199

IRR-GAW

6 7 8 9

Stationery derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Hour Hour Hour Hour Hour Hour LS

8.00 8.00 16.00 16.00 16.00 16.00 20.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Mobile crane Crew for Planing machine Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Welder ( X - ray ) 10 Helper fabrication / erection 11 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Hour 4.00 Hour 135.00 Hour 16.00 Hour 16.00 Day 16.00 Day 35.00 Day 8.00 Day 24.00 Day 3.00 Day 83.00 Day 2.00 Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for Rate per tonne=(A+B+C+D+E+F) /3.18 0%

Total 0.00% Total 0%

0.00 per tonne

0.00 per tonne 3.18 tonne Rs: Rs:

0 0.00 0.00

vertical lift gates and stop log gate elements ( SLIDING GATES)
IRR-GAW-2-2 Design, fabrication, supply, erection, testing and commissioning of vertical lift gates and stoplog gate elements, consisting of skin plate, horizontal and vertical girders, stiffeners, lifting pins, bronze padded slide blocks/bearings, guide shoes, rubber seals, clamps etc., with all accessories including cost of all materials, machinery, labour, seal fixing etc.,complete as per specifications and approved drawings (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) Spillway stoplog gate consists of number of vertical lift slide gate elements. Each gate element consists of skin plate, horizontal girders, vertical end girders, stiffeners, slide blocks, gate guide shoes, lifting pins and seals with all accessories. Consider gate 15 m x 9 m opening for analysis. RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Structural steel Angles / beams / channels / bars Plates / flats Alloy steel components Lifting pins Alluminium / Bronze alloy components Bronze pads Bolt / Nut / Washer GI bolts / nuts / washers MS bolts / nuts / washers Rubber seals Bottom seal Side seals Oxygen gas Acetyline gas Welding electrodes Welding electrodes ( LH ) Use rate welding holder set Use rate gas cutting torch set Sundries Unit UNIT : Quantity 71.157 tonne Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DATA:

kg kg kg kg kg kg

473.00 71963.00 104.00 48.00 295.00 49.00

2 3 4

6 7 8 9 10 11 12

Rm 123.00 Rm 20.00 cum 663.00 cum 221.00 Nos 2765.00 Nos 24885.00 Hour 2949.00 Hour 30.00 LS 200.00 Total cost of Materials

B. MACHINERY: Sl No 1

Description Welding transformer

Unit Hour

Quantity 2949.00

Rate in Rs. 0.00

Amount in Rs. 0.00

200

IRR-GAW

2 3 4 5 6 7

Fuel / Energy charges Pug cutting machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges Stationery derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

1843.00 412.00 412.00 50.00 50.00 100.00 100.00 50.00 50.00 100.00 100.00 100.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Mobile crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Welder ( X - ray ) Khalasi 10 Helper fabrication / erection 11 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Hour 50.00 Hour 100.00 Hour 50.00 Day 115.00 Day 168.00 Day 56.00 Day 250.00 Day 27.00 Day 50.00 Day 601.00 Day 5.00 Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Total cost for Rate per tonne=(A+B+C+D+E+F) /71.16 0% 71.16 tonne

Total 0.00% Total 0%

IRR-GAW-2-3

STOP LOGS-automatic lifting beam fabrication, supply, erection, testing and commissioning of automatic lifting beam with all accessories for handling, lowering and lifting of spillway stop log gate elements including cost of all materials, machinery, labour, cutting, aligning, welding, finishing, etc., complete as per specifications and drawings with all leads and lifts. (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) Automatic lifting beam for lifting spillway stop log elements consists of fabricated beam with lifting bracket and automatic engaging / dis-engaging type hooks for under water hooking / de-hooking of gate element. Lifting beam is an independent attachment to moving gantry crane. RATE ANALYSIS A. MATERIALS: Sl No particulars 1 Structural steel Angles / beams / channels / bars Plates / flats 2 Alloy steel components Lifting pins 3 Bronze alloy components : Bronze bush 4 Forged steel components : Lifting hooks 5 MS pipe 100 mm dia 6 Bolt / Nut / Washer MS bolts / nuts / washers 7 Oxygen gas 8 Acetyline gas 9 Welding electrodes 10 Welding electrodes ( LH ) 11 Use rate welding holder set 12 Use rate gas cutting torch set 13 Sundries Unit UNIT : Quantity 3.528 tonne Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DATA:

kg kg kg kg kg kg

13.00 3389.00 101.00 5.00 103.00 11.00

kg 3.00 cum 126.00 cum 42.00 Nos 175.00 Nos 1575.00 Hour 187.00 Hour 24.00 LS 25.00 Total cost of Materials

B. MACHINERY: Sl No 1 2 3

Description Welding transformer Fuel / Energy charges Pug cutting machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges

Unit Hour Hour Hour Hour Hour Hour

Quantity 187.00 117.00 60.00 60.00 4.00 4.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00

201

IRR-GAW

4 5 6 7

Stationery derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Hour Hour Hour Hour Hour Hour LS

8.00 8.00 2.00 2.00 2.00 2.00 10.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Mobile crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Helper fabrication / erection 9 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity 4.00 2.00 2.00 10.00 18.00 10.00 18.00 52.00 1.00

Hour Hour Hour Day Day Day Day Day Day Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for Rate per tonne=(A+B+C+D+E+F) /3.528 0%

Total 0.00% Total 0%

0.00 per tonne

0.00 per tonne 3.528 tonne Rs: Rs:

0 0.00 0.00

IRR-GAW-2-4

MOVING GANTRY CRANE-CLASS II fabrication, supply, erection, testing and commissioning of adequate capacity Class- II type moving gantry crane consisting of rail mounted gantry frame, top platform with hand railing, long / cross travel arrangements, rope drums, gear systems, electric motors, electromagnetic brake system, cabin, control panel, wire rope, ladder, motorised cable reeling drum etc., with all accessories for operating spillway stop log gate elements and river sluice / canal sluice emergency gates including cost of all materials, machinery, labour, etc., complete with all leads and lifts. (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) Moving gantry crane consists of rail mounted gantry frame with long travel arrangement, cross travel trolley with track arrangement mounted on gantry frame top platform, rope drum hoist with all accessories mounted on cross travel trolley for operating stoplog gate elements. Consider moving gantry crane for operating spillway stoplog gate element of 8.92 t weight. The same moving gantry crane can also be used for operating river sluice emergency gate. Therefore, the hoisting capacity of the gantry crane depends on the requirement of hoisting capacity for spillway stoplog element or river sluice emergency gate whichever is higher. RATE ANALYSIS UNIT : A. MATERIALS: Sl No particulars Unit Quantity 1 Structural steel Angles / beams / channels / bars Plates / flats Chequered plates Cast steel components : Rope drums 2 Nos Gears and pinions Wheels / Pulleys Plummer blocks / Couplings Forged steel components Hook / Shackle Alloy steel components Shafts Pins Bronze alloy components : Bronze bearings / bush Wire rope 28 mm dia 6/37 construction MS Bolt / Nut / Washer MS pipe 32 mm dia for railing Worm reducers 10 Electric motor 17.5 hp Electric motor 5 hp Electric motor 3 hp 11 Ele-magnetic / Thruster brakes

DATA:

30.856 tonne 25 t capacity Rate Amount in Rs. in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

kg kg kg kg kg kg kg kg kg kg kg kg kg Rm Nos. No. Nos. No. Nos.

1743.00 19700.00 820.00 1320.00 1165.00 2255.00 817.00 127.00 556.00 524.00 181.00 406.00 63.00 50.00 4.00 1.00 2.00 1.00 4.00

3 4

5 6 7 8 9

202

IRR-GAW

12 13 14 15 16 17 18 19 20

Electric cable / switch / control panel etc Oxygen gas Acetyline gas Welding electrodes Welding electrodes ( LH ) Grease Use rate welding holder set Use rate gas cutting torch set Sundries

LS 3.00 cum 579.00 cum 193.00 Nos 1123.00 Nos 10110.00 kg 50.00 Hour 1197.00 Hour 150.00 LS 200.00 Total cost of Materials

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description Welding transformer Fuel / Energy charges Tower crane 5 t capacity Fuel / Energy charges Pug cutting machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 1197.00 748.00 6.00 6.00 235.00 235.00 100.00 100.00 32.00 32.00 16.00 16.00 500.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Mobile crane Crew for Tower crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Khalasi 10 Helper fabrication / erection 11 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Hour 100.00 Hour 6.00 Hour 16.00 Hour 32.00 Day 74.00 Day 124.00 Day 48.00 Day 112.00 Day 20.00 Day 350.00 Day 10.00 Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for 0%

Total 0.00% Total 0%

0.00 per tonne

0.00 per tonne 0 30.856 tonne Rs: 25.000 t capacity Rs: Rate per tonne wt=(A+B+C+D+E+F) /30.856 Rs: Rate per tonne capacity=(A+B+C+D+E+F) /25 Rs:

0.00 0.00 0.00

IRR-GAW-2-5

DATA:

RAIL TRACK FOR GANTRY CRANE Design, fabrication, supply, erection and commissioning of rail track using 45 kg / m standard rails on spillway bridge for movement of gantry crane for handling and operating spillway stoplog gate elements / river sluice / canal sluice emergency gate including cost of all materials, machinery, labour, complete as per specifications (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) Rail track for moving gantry crane consists of 45 kg / m standard rails fixed by welding and bolting to anchors embedded in concrete at intervals. The width of track shall be as per the requirement of gantry long travel specifications. Consider track length of 200 m for rate analysis. RATE ANALYSIS UNIT : 200.000 Rm A. MATERIALS: Sl No particulars Unit Quantity Rate in Rs. 1 Str steel angle / beam / channel / bars kg 1570.00 0.00 2 Structural steel plate / flats kg 975.00 0.00 3 Rails kg 18450.00 0.00 4 MS bolts and nuts kg 246.00 0.00 5 Oxygen gas cum 201.00 0.00 6 Acetyline gas cum 67.00 0.00 7 Welding electrodes Nos 1805.00 0.00

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

203

IRR-GAW

8 Use rate welding holder set 9 Use rate gas cutting torch set 10 Sundries

Hour 193.00 Hour 133.00 LS 10.00 Total cost of Materials

0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4 5

Description Welding transformer Fuel / Energy charges Mobile derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 193.00 121.00 4.00 4.00 8.00 8.00 50.00 50.00 10.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Mobile crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Helper fabrication / erection 9 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity 4.00 50.00 8.00 8.00 32.00 17.00 18.00 52.00 1.00

Hour Hour Hour Day Day Day Day Day Day Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for Rate per Rm=(A+B+C+D+E+F) /200

Total 0.00% Total 0% Total 0%

0.00 per tonne

0.00 per tonne 200.000 Rm Rate per Rm Rs: Rs:

0 0.00 0.00

IRR-GAW-2-6

VERTICAL LIFT GATES/STOP LOGS - ROLLER MOUNTED Design, fabrication, supply, erection, testing and commissioning of fixed wheel type vertical lift service gate consisting of skin plate, vertical and horizontal girders, wheels, stiffeners, lifting brackets, guide rollers, ballast blocks, teflon claded rubber seals etc., with all accessories for river sluice / canal sluice vent including cost of all materials, machinery, labour,welding ,aligning finishing seal fixing etc.with allleads and lifts, complete as per specifications andvapproved drawings (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) Consider upstream seal vertical lift roller gate. The gate leaf consists of skin plate, horizontal girders, vertical end girders, stiffeners, wheels, gate guide rollers, brackets for pulleys, seals etc., with all accessories. Consider river / canal sluice service gate for 2.5 m x 3 m sluice opening for analysis. RATE ANALYSIS UNIT : A. MATERIALS: Sl No particulars Unit Quantity 1 2 3 4 5 6 Structural steel Plates / flats Cast iron components CI blocks for counter wt Alloy steel components Wheel axles / Pins Cast steel components Wheels / Guide rollers Alluminium / Bronze alloy components Bearings / Bushes Bolt / Nut / Washer SS bolts / nuts / washers GI bolts / nuts / washers MS bolts / nuts / washers Rubber seals Bottom seal ( flat uncladed ) Side seals ( bulb teflon claded ) Top seal ( bulb teflon claded ) Corner seals ( bulb teflon claded )

DATA:

9.202 tonne Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

kg kg kg kg kg kg kg kg Rm Rm Rm Nos

4479.00 4100.00 132.00 492.00 76.00 55.00 76.00 4.00 2.80 5.85 2.25 2.00

204

IRR-GAW

8 9 10 11 12 13 14

Oxygen gas Acetyline gas Welding electrodes Welding electrodes ( LH ) Use rate welding holder set Use rate gas cutting torch set Sundries

cum 99.00 cum 33.00 Nos 282.00 Nos 2532.00 Hour 300.00 Hour 18.00 LS 50.00 Total cost of Materials

0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1 2 3 4 5 6 7 8

Description Welding transformer Fuel / Energy charges Pug cutting machine Fuel / Energy charges Tower crane Fuel / Energy charges Mobile derric crane Fuel / Energy charges Stationery derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 300.00 188.00 48.00 48.00 1.00 1.00 10.00 10.00 20.00 20.00 8.00 8.00 16.00 16.00 25.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Mobile crane Crew for Tower crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Welder ( X - ray grade ) 10 Khalasi 11 Helper fabrication / erection 12 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity 10.00 1.00 16.00 8.00 16.00 25.00 8.00 25.00 3.00 10.00 74.00 2.00

Hour Hour Hour Hour Day Day Day Day Day Day Day Day Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for Rate per tonne=(A+B+C+D+E+F) /9.202 0%

Total 0.00% Total 0%

0.00 per tonne

0.00 per tonne 9.202 tonne Rs: Rs:

0 0.00 0.00

IRR-GAW-2-7

VERTICAL LIFT GATES-ROPE DRUM HOIST UPTO 30 TON CAP. POWER OPERATED Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope drum hoist consisting of hoist platform, rope drum, gear system, electric motor, electromagnetic brake system, hand operation assembly, control panel, wire rope, pulleys, ladder etc., with all accessories for operating river sluice / canal sluice service gate including cost of all materials, machinery, labour, , complete as per specifications and drawings with all leads and lifts (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) Rope drum hoist for river / canal sluice service gate consists of embedded parts for anchorage, hoist supporting structure, pulley support, pulleys, drive stool, rope drums, shafts, couplings, gears and pinions, plummer blocks, gear box, electric motor, hand operation assembly, brake, wire rope, gate position indicator, switch box etc. with related accessories. Consider rope drum hoist for river / canal sluice service gate for vent of size 2.5 m x 3 m. RATE ANALYSIS UNIT : 6.243 tonne wt A. MATERIALS: 25 t capacity Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Structural steel Angles / beams / channels / bars kg 1487.00 0.00 0.00 Plates / flats kg 402.00 0.00 0.00 Chequered plate kg 290.00 0.00 0.00 2 Cast steel components :

DATA:

205

IRR-GAW

4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Rope drums 2 Nos / Gears Pinions Pulleys 3 Nos / Couplings 2 Nos Plummer blocks / Hubs Alloy steel components Shafts Pins Bronze alloy components : Bronze bearings / bush Wire rope 28 mm dia 6/37 construction MS Bolt / Nut / Washer Worm reducers Electric motor 5 hp Manual operating system Gate position indicator Ele-magnetic brake Electric cable / switch / control panel etc Oxygen gas Acetyline gas Welding electrodes Welding electrodes ( LH ) Grease Use rate welding holder set Use rate gas cutting torch set Sundries

kg kg kg kg kg kg

1926.00 79.00 306.00 72.00 346.00 73.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

kg 57.00 kg 325.00 kg 32.00 No. 1.00 No. 1.00 No. 1.00 No. 1.00 No. 1.00 LS 1.00 cum 45.00 cum 15.00 Nos 80.00 Nos 720.00 kg 50.00 Hour 85.00 Hour 16.00 LS 25.00 Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description Welding transformer Fuel / Energy charges Tower crane 5 t capacity Fuel / Energy charges Pug cutting machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 85.00 53.00 2.00 2.00 15.00 15.00 10.00 10.00 2.00 2.00 2.00 2.00 25.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Mobile crane Crew for Tower crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Khalasi 10 Helper fabrication / erection 11 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity 10.00 2.00 2.00 2.00 15.00 19.00 4.00 8.00 4.00 44.00 2.00

Hour Hour Hour Hour Day Day Day Day Day Day Day Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for 0%

Total 0.00% Total 0%

0.00 per tonne

0.00 per tonne 0 6.243 tonne wt Rs: 25.000 t capacity Rs: Rate per tonne wt=(A+B+C+D+E+F+leads) /6.243 Rs: Rate per tonne capacity=(A+B+C+D+E+F) /25 Rs:

0.00 0.00 0.00

IRR-GAW-2-8

HOIST BRIDGE/ WITH TRESSELS Design, fabrication, supply, erection and commissioning of structural steel hoist bridge consisting of columns, beams, bracings, stiffeners, ties, chequered plate covering, hand railing, ladder etc., with all accessories for supporting rope drum hoist for operating barrage gates including cost of all materials, machinery, labour, welding, finishing, etc., complete complete as per specifications and drawings with all leads and lifts

206

IRR-GAW

DATA:

(without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) Structural steel hoist bridge for supporting rope drum hoist for operating barrage gates consists of steel columns and beams with cross beams, ties, bracings, stiffeners, hand railing, ladder, chequered plate covering, anchorages etc., with all accessories. Consider hoist bridge for supporting 50 t rope drum hoist. Consider 15 m span and 10 m over all height for bridge. Details of material / Gas cutting / Welding considered for rate analysis are based on structural steel bridge drawings for barrage gates RATE ANALYSIS UNIT : 10.239 tonne A. MATERIALS: Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Structural steel angles/ beams / channels kg 4564.00 0.00 0.00 Structural steel plates / flats kg 5567.00 0.00 0.00 Chequered plate kg 136.00 0.00 0.00 2 MS pipe 32 mm dia Rm 32.00 0.00 0.00 MS pipe 25 mm dia Rm 64.00 0.00 0.00 3 Bolt / Nut / Washers kg 18.50 0.00 0.00 4 Oxygen gas cum 222.00 0.00 0.00 5 Acetyline gas cum 74.00 0.00 0.00 6 Welding electrodes Nos 388.00 0.00 0.00 7 Welding electrodes ( LH ) Nos 3495.00 0.00 0.00 8 Use rate welding holder set Hour 415.00 0.00 0.00 9 Use rate gas cutting torch set Hour 60.00 0.00 0.00 10 Sundries LS 50.00 0.00 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description Welding transformer Fuel / Energy charges Pug cutting machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges Stationery derric crane Fuel / Energy charges Drilling machine Fuel / Energy charges Grinding machine Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 415.00 259.00 88.00 88.00 20.00 20.00 40.00 40.00 8.00 8.00 8.00 8.00 50.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Mobile crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Helper fabrication / erection 9 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Hour 20.00 Hour 8.00 Hour 8.00 Day 27.00 Day 46.00 Day 18.00 Day 39.00 Day 130.00 Day 5.00 Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for Rate per tonne=(A+B+C+D+E+F) /10.239 0%

Total 0.00% Total 0%

0.00 per tonne

0.00 per tonne 10.239 tonne Rate per tonne Rs: Rs:

0 0.00 0.00

ROPE DRUM HOIST WITHOUT HOIST BRIDGE FOR BARRAGE GATES


IRR-GAW-2-9 Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope drum hoist consisting of rope drum, pulleys, gear system, electri c motor, electro-magnetic brake system, manual operation assembly, position indicator, control panel, wire rope etc., with all accessories for operating vertical lift roller gates for barrage including cost of all materials, machinery, labour, cutting, bending, aligning, anchoring, welding, finishing etc., complete with all leads and lifts. (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately)

207

IRR-GAW

DATA:

Rope drum hoist for vertical lift barrage gate consists of hoist supporting frames, pulley supports, pulleys, drive stool, rope drums, shafts, couplings, gears and pinions, plummer blocks, gear box, electric motor, hand operation assembly, brake, wire rope, gate position indicator, switch box etc. with related accessories. Consider rope drum hoist for operating barrage gate for clear opening of 13.72 m x 8.26 m. RATE ANALYSIS UNIT : A. MATERIALS: Sl No particulars Unit Quantity 1 Structural steel Angles / beams / channels / bars Plates / flats Cast steel components : Rope drums 2 Nos / Gears Pinions Pulleys 3 Nos / Couplings 2 Nos Plummer blocks / Hubs Alloy steel components Shafts / Keys Pins Bronze alloy components : Bronze bearings / bush Wire rope 28 mm dia 6/37 construction MS Bolt / Nut / Washer Worm reducers Electric motor 12.5 hp Manual operating system Gate position indicator Ele-magnetic brake Electric cable / switch / control panel etc Oxygen gas Acetyline gas Welding electrodes Welding electrodes ( LH ) Grease Use rate welding holder set Use rate gas cutting torch set Sundries

5.069 tonne wt 50.00 t capacity Rate Amount in Rs. in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

kg kg kg kg kg kg kg kg

420.00 225.00 1290.00 98.00 650.00 250.00 350.00 96.00

4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

kg 100.00 kg 435.00 kg 26.00 No. 1.00 No. 1.00 No. 1.00 No. 1.00 No. 1.00 LS 1.00 cum 30.00 cum 10.00 Nos 44.00 Nos 392.00 kg 50.00 Hour 47.00 Hour 12.00 LS 25.00 Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description Welding transformer Fuel / Energy charges Tower crane 5 t capacity Fuel / Energy charges Pug cutting machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 47.00 47.00 2.00 2.00 9.00 9.00 10.00 10.00 2.00 2.00 2.00 2.00 25.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Mobile crane Crew for Tower crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Khalasi 10 Helper fabrication / erection 11 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity 10.00 2.00 2.00 2.00 13.00 17.00 3.00 5.00 4.00 36.00 2.00

Hour Hour Hour Hour Day Day Day Day Day Day Day Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. 0%

Total 0.00% Total 0%

0.00 per tonne

208

IRR-GAW

Unloading charges of fabricated parts Rs Total cost for

0.00 per tonne 0 5.069 tonne wt Rs: 50.000 t capacity Rs: Rate per tonne wt=(A+B+C+D+E+F) /5.069 Rs: Rate per tonne capacity=(A+B+C+D+E+F) /50 Rs:

0.00 0.00 0.00

SCREW GEAR HOISTS including plat form( UPTO 10 TON CAP)


IRR-GAW-2-10 Design, fabrication, supply, erection, testing and commissioning of adequate capacity screw gear type hoist consisting of supporting structure, platform, ladder etc., with all accessories for operating canal escape / regulator gate including cost of all materials, machinery, labour, cutting, bending, aligning, anchoring, welding,finishing etc.,complete with all leads and lifts. (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) DATA: Screw type hoist for operating gate consists of supporting structure, hoist body, hoist stem, thrust bearings, operating wheel / handle with related accessories. Consider screw type hoist for canal escape / regulator gate for vent opening of size 2 m x 2 m. RATE ANALYSIS UNIT : A. MATERIALS: Sl No particulars Unit Quantity 1 Structural steel Angles / beams / channels / bars Plates / flats Chequered plate Cast iron components : Hoist body / Lock nut / Main nut Alloy steel components Hoist stem Bronze alloy components : Thrust bearings MS Bolt / Nut / Washer Oxygen gas Acetyline gas Welding electrodes Welding electrodes ( LH ) Grease Use rate welding holder set Use rate gas cutting torch set Sundries

0.871 tonne 3.00 t capacity Rate Amount in Rs. in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

kg kg kg kg kg

402.00 145.00 176.00 55.00 75.00

2 3 4 5 6 7 8 9 10 11 12 13

kg 4.00 kg 8.00 cum 18.00 cum 6.00 Nos 7.00 Nos 66.00 kg 2.00 Hour 8.00 Hour 11.00 LS 2.00 Total cost of Materials

B. MACHINERY: Sl No 1 2 3 4

Description Welding transformer Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery

Unit Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 5.00 2.00 2.00 2.00 2.00 2.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7

Description Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Helper fabrication / erection 8 Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity 2.00 2.00 4.00 5.00 2.00 1.00 9.00 0.50

Hour Hour Day Day Day Day Day Day Total cost of Labour

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs 0%

Total 0.00% Total 0%

0.00 per tonne

0.00 per tonne

209

IRR-GAW

Total cost for Rate per tonne weight=(A+B+C+D+E+F) /0.871 Rate per tonne capacity=(A+B+C+D+E+F) /3

0.871 tonne 3.000 t capacity

Rs: Rs: Rs: Rs:

0.00 0.00 0.00

MANUAL OPERATED ROPE DRUM HOISTS IRR-GAW-2-11 Design, fabrication, supply, erection, testing and commissioning of adequate capacity manually operated rope drum hoist consisting of hoist platform, rope drum, gear system, brake system, wire rope, ladder etc., with all accessories for operating canal regulator radial gate including cost of all materials, machinery, labour, welding, finishing, cleaning, ., complete with all leads and lifts (without painting on sand-blasted or mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as applicable separately) Rope drum hoist for radial gate consists of embedded parts for anchorage, hoist supporting structure, pulley supporting structures, pulleys, drive stool, rope drums, couplings, shafts, gears and pinions, plummer blocks, worm reducer, floating shaft, hand operation assembly, brake, wire rope, gate position indicator etc. with related accessories. Consider rope drum hoist for radial gate for canal regulator opening of size 3 m x 3.7 m. RATE ANALYSIS UNIT : 2.804 tonne A. MATERIALS: 10.00 t capacity Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 Structural steel Angles / beams / channels / bars kg 1229.00 0.00 0.00 Plates / flats kg 453.00 0.00 0.00 Chequered plate kg 195.00 0.00 0.00 2 Cast steel components : Rope drums 2 Nos / Gears kg 384.00 0.00 0.00 Pinions kg 14.00 0.00 0.00 Pulleys 6 Nos kg 108.00 0.00 0.00 Plummer blocks / Couplings kg 47.00 0.00 0.00 3 Alloy steel components Shafts kg 75.00 0.00 0.00 Pins kg 24.00 0.00 0.00 4 Bronze alloy components : Bronze bearings / bush kg 11.00 0.00 0.00 5 Wire rope 12 mm dia 6/36 construction kg 42.00 0.00 0.00 6 MS Bolt / Nut / Washer kg 64.00 0.00 0.00 7 Worm reducers No. 1.00 0.00 0.00 8 Manual operating system No. 1.00 0.00 0.00 9 Brake No. 1.00 0.00 0.00 10 Wire rope sockets No 2.00 0.00 0.00 11 Oxygen gas cum 75.00 0.00 0.00 12 Acetyline gas cum 25.00 0.00 0.00 13 Welding electrodes Nos 69.00 0.00 0.00 14 Welding electrodes ( LH ) Nos 622.00 0.00 0.00 15 Grease kg 10.00 0.00 0.00 16 Use rate welding holder set Hour 73.00 0.00 0.00 17 Use rate gas cutting torch set Hour 42.00 0.00 0.00 18 Sundries LS 25.00 0.00 0.00 Total cost of Materials Rs: 0.00 B. MACHINERY: Description 1 2 3 4 5 6 7 Welding transformer Fuel / Energy charges Pug cutting machine Fuel / Energy charges Mobile derric crane Fuel / Energy charges Stationery derric crane Fuel / Energy charges Grinding machine Fuel / Energy charges Drilling machines Fuel / Energy charges Sundries Total hire charges of Machinery Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS Quantity 73.00 46.00 8.00 8.00 4.00 4.00 8.00 8.00 8.00 8.00 16.00 16.00 25.00 Rate Amount in Rs. in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs:

DATA:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description Crew for Mobile crane Crew for Drilling machine Crew for Grinding machine Foreman Marker / Fabricator / Erector Gas cutter Welder ( General ) Helper fabrication / erection Electrician ABSTRACT: A. Cost of Materials B. Hire charges of Machinery

Unit

Quantity 4.00 16.00 8.00 14.00 20.00 6.00 7.00 44.00 2.00

Rate in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Hour Hour Hour Day Day Day Day Day Day Total cost of Labour

210

IRR-GAW

C. Cost of Labour D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Add 2 leads Add 1 km lead charges for fabricated parts Rs. Unloading charges of fabricated parts Rs Total cost for 0%

Rs: Total 0.00% Total 0%

Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 per tonne

0.00 per tonne 0 2.804 tonne Rs: 10.000 t capacity Rate per tonne Rs: Rate per tonne wt=(A+B+C+D+E+F) /2.804 Rs: Rate per tonne capacity=(A+B+C+D+E+F) /10

0.00 0 0

IRR-GAW-3 IRR-GAW-3-1

SAND BLASTING AND PAINTING AS PER IS:14177-1994


Cleaning gates / hoists / embedded parts/lifting beams etc, to expose fresh metal surface for painting by sand blasting method as per specifications including cost of all materials, l abour, machinery, scaffolding, etc., complete with initial lead for sand upto 1 km and all lifts. Consider 100 sqm area for cleaning by sand blasting: RATE ANALYSIS A. MATERIALS: Sl No particulars 1 2 3 4 Natural river sand Use rate of air hose Use rate of sand blast gun nozzle Sundries( Rust inhibitive, seive etc ) Total Add 10% towards scaffolding/laddor @ Total cost of Materials Description 1 Air compressor 7 cmm diesel Fuel / Energy charges 2 Sand blasting equipment Fuel / Energy charges Total hire charges of Machinery C. LABOUR: Sl No Description 1 Crew for Air compressor 2 Crew for Sand blasting equipment 3 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

DATA:

UNIT : 100 Unit cum Hour Hour LS Quantity 30.00 8.00 8.00 5.00 0.10 Rate in Rs. 0.00 0.00 0.00 0.00

sqm Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Amount in Rs. 0.00 0.00 0.00 0.00 0.00 Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No

Unit Hour Hour Hour Hour

Quantity 8.00 8.00 8.00 8.00

Rate in Rs. 0.00 0.00 0.00 0.00

Unit Hour Hour Day

Quantity 8.00 8.00 15.00

Rate in Rs. 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Total cost for Rate per sqm=(A+B+C+D+E+F) /100 0% 100.00 sqm

Total 0.00% Total 0%

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

IRR-GAW-3-2

painting of embedded metal parts and all types of gates, stoplogs,etc, on sand blasted surfaces with one coat of inorganic zinc silicate (airless spray preferred)70+/- 5 and two super coats with a total thickness of 300 microns (each 150+/- 5) of solventless coaltar epoxy paint each coat 150 microns ( total 300 microns) cost of all materials, labour, scaffolding etc., complete with all leads and all lifts Consider 100 sqm area for painting: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars inorganic zinc silicate 2 Solventless Coal tar epoxy paint 3 Sundries ( brushes,ladders,platforms etc ) Total cost of Materials Description Unit lit ltr UNIT : Quantity 12.00 34.00 2.30 100 sqm Rate in Rs. 0.00 0.00 0.00 Rs: Rate in Rs. Amount in Rs. 0 0 0 0.00 Amount in Rs.

DATA:

B. MACHINERY: Sl No

Unit

Quantity

211

IRR-GAW

NIL Total cost of Machinery

0.00

0.00 Rs:

0.00 0.00 Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No

Description 1 Painter Class-II 2 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit Day Day

Quantity 20.00 7.00

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Total cost for Rate per sqm=(A+B+C+D+E+F) /100 IRR-GAW-3-3 0% 100.00 sqm

Total 0.00% Total 0%

painting of Lifting beams,cat walks and other similar structures-painting hoist machinery, on sand blasted surfaces with two coats of zinc phosphate primer (airless spray preferred) 40microns/coat and twocoats of alkyd based micaccous iro oxide paint , 65 microns/coat cost of all materials, labour, scaffolding etc., complete with all leads and all lifts DATA: Consider 100 sqm area for painting: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars zinc phosphate primer 2 alkyd based micaccous iron oxide paint 3 Sundries ( brushes,ladders,platforms etc ) Total cost of Materials Description 1 C. LABOUR: Sl No NIL Total cost of machinery Description 1 Painter Class-II 2 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Unit Day Day Quantity 15.00 5.00 Unit lit ltr UNIT : Quantity 22.00 20.00 2.10 100 sqm Rate in Rs. 0.00 0.00 0.00 Rs: Rate in Rs. RS: Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Amount in Rs. 0 0 0 0.00 Amount in Rs. 0.00

B. MACHINERY: Sl No

Unit

Quantity

Total D. Add for excise duty 0.00% (on 75 percent cost excluding cost of materials) Total E. Add for transportation upto work site @ 0% Total F.Add for contractor's profit and overheads on A+B+C+E 0% Total cost for 100.00 sqm Rate per sqm=(A+B+C+D+E+F) /100

IRR-GAW-3-4

. DATA:

HOISTS:STRUCTURAL COMPONENTS--painting structurals on sand blasted surfaces with two coats of zinc phosphate primer (airless spray preferred) 40microns/coat and one coat 65+/-5 of alkyd based micaccous iron oxide paint followed by two coats of synthetic enamel paint 25 microns/coat cost of all materials, labour, scaffolding etc., complete with all leads and all lifts Consider 100 sqm area for painting: RATE ANALYSIS UNIT : 100 sqm A. MATERIALS: Sl No particulars Unit Quantity Rate Amount in Rs. in Rs. 1 zinc phosphate primer lit 23.00 0.00 0 2 alkyd based micaccous iron oxide paint ltr 15.00 0.00 0 3 synthetic enamel paint lit 17.00 0.00 0 4 Sundries ( brushes,ladders,platforms etc ) 2.75 0.00 0 Total cost of Materials Rs: 0.00 B. MACHINERY: Sl No Description Unit Quantity Rate Amount in Rs. in Rs. 1 NIL Total cost of Materials Rs: 0.00 C. LABOUR: Sl No Description Unit Quantity Rate Amount in Rs. in Rs. 1 Painter Class-II Day 25.00 0.00 0.00

212

IRR-GAW

2 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Day

8.00

0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Total cost for Rate per sqm=(A+B+C+D+E+F) /100 0% 100.00 sqm

Total 0.00% Total 0%

IRR-GAW-3-5

HOISTS:machineryCOMPONENTS--painting hoist machinery, on sand blasted surfaces with one coats of zinc phosphate primer (airless spray preferred) 50microns/coat and three coats of aluminium paint or synthetic enamel , 25 microns/coat cost of all materials, labour, scaffolding etc., complete with all leads and all lifts Consider 100 sqm area for painting: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Unit UNIT : Quantity 11.00 26.00 1.85 100 sqm Rate in Rs. 0.00 0.00 0.00 Rs: Rate in Rs. Rs: Unit Day Day Quantity 27.00 9.00 Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Amount in Rs. 0 0.00 0.00 0.00 Amount in Rs. 0.00

DATA:

zinc phosphate primer lit 2 aluminium paint or synthetic enamel per coat ltr 3 Sundries ( brushes,ladders,platforms etc ) Total cost of Materials Description 1 NIL Total cost of Materials Description 1 Painter Class-II 2 mazdoor Total cost of Labour ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Unit

B. MACHINERY: Sl No

Quantity

C. LABOUR: Sl No

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Total cost for Rate per sqm=(A+B+C+D+E+F+) /100 0% 100.00 sqm

Total 0.00% Total 0%

IRR-GAW-4 IRR-GAW-4-1

PAINTING WITHOUT SAND BLASTING


E.M Parts OF ALL TYPES OF GATES Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners and removing dust. After cleaning,applying primary coat with one coat of Zinc rich epoxy primer to athickness of 40 microns ,followed by finishing coats 4 coats with coal tar epoxy with material, labour,and all accessories with all leads and lifts where surface cleaning by sand blasting is not feasible and based on specific recommendations of designers, it is to adopt surface preperation done manually by hand and power tool after cleaning by chemical treatment to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting, before applying primer painting.

DATA:

RATE ANALYSIS
A. MATERIALS: Sl No 1 2 3 4 5 particulars Zinc rich epoxy primer Coal tar epoxy paint Rust cleaner / inhibitor Wire brush Sundries Unit

UNIT : Quantity

100.000 Sqare meters Rate in Rs. 0.00 0.00 0.00 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00

ltr 11.00 ltr 68.00 ltr 13.00 Nos 2.00 LS 2.00 Total cost of Materials

B. MACHINERY: Sl No

Description nil Total cost of Machinery

Unit

Quantity

Rate in Rs.

Amount in Rs. 0.00 0.00

213

IRR-GAW

C. LABOUR: Sl No 1 2

Description Helper for cleaning / painting Painter Cl - II ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Day 15.00 Day 33.00 Total cost of Labour

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Total cost for Rate per sqm=(A+B+C+D+E+F+) /100 0% 100.00 sqm

Total 0.00% Total 0%

IRR-GAW-4-2

ALL TYPES OF GATES Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners and removing dust. After cleaning,applying primary coat with one coat of Zinc rich epoxy primer to athickness of 40 microns ,followed by finishing coats 3 coats with coal tar epoxy with material, labour,and all accessories with all leads and lifts where surface cleaning by sand blasting is not feasible and based on specific recommendations of designers, it is to adopt surface preperation done manually by hand and power tool after cleaning by chemical treatment to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting, before applying primer painting.

DATA:

RATE ANALYSIS
A. MATERIALS: Sl No 1 2 3 4 5 particulars Zinc rich epoxy primer Coal tar epoxy paint Rust cleaner / inhibitor Wire brush Sundries Unit

UNIT : Quantity

100.000 Sqare meters Rate in Rs. 0.00 0.00 0.00 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00

ltr 14.00 ltr 51.00 ltr 13.00 Nos 2.00 LS 2.00 Total cost of Materials

B. MACHINERY: Sl No

Description nil

Unit

Quantity

Rate in Rs. Rs:

Amount in Rs. 0.00 0.00

Total cost of Machinery C. LABOUR: Sl No 1 2

Description Helper for cleaning / painting Painter Cl - II ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Day 14.00 Day 27.00 Total cost of Labour

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Total cost for Rate per sqm=(A+B+C+D+E+F) /100

Total 0.00% Total 0%

0% 100.00 sqm Rate per sq.meter

HOIST BRIDGES ,HOISTING EQUIPMENT AAND CRANES,Etc, IRR-GAW-4-3 DATA: Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners and removing dust. After cleaning,applying primary coat with two coats of Zinc chromite red oxide primer ,followed by finishing coats 3 coats with synthetic enamel paint with material, labour,and all accessories with all leads and lifts where surface cleaning by sand blasting is not feasible and based on specific recommendations of designers, it is to adopt surface preperation done manually by hand and power tool after cleaning by chemical treatment to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting, before applying primer painting.

RATE ANALYSIS
A. MATERIALS: Sl No 1 2 3 4 5 particulars Zinc chromite red oxide primer synthetic enamel paint, Rust cleaner / inhibitor Wire brush Sundries Unit

UNIT : Quantity

100.000 Sqare meters Rate in Rs. 0.00 0.00 0.00 0.00 0.00 Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00

ltr 17.00 ltr 26.00 ltr 13.00 Nos 2.00 LS 2.00 Total cost of Materials

214

IRR-GAW

B. MACHINERY: Sl No

Description nil

Unit

Quantity

Rate in Rs. Rs

Amount in Rs. 0.00 0.00

0 Total cost of Machinery

C. LABOUR Sl No 1 2

Description Helper for cleaning / painting Painter Cl - II ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Day 15.00 Day 33.00 Total cost of Labour

Rate in Rs. 0.00 0.00

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Total cost for Rate per sqm=(A+B+C+D+E+F) /100 0% 100.00 sqm

Total 0.00% Total 0%

Rs. Rs. Rs. Rs: Rs: Rs: Rs: Rs: Rs: Rs:

IRR-GAW-4-4

WALK WAYS( CAT WALKS), LIFTING BEAMS,etc, Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners and removing dust. After cleaning,applying primary coat with one coat of Zinc rich epoxy primer to athickness of 40 microns ,followed by finishing coats 2 coats with coal tar epoxy with material, labour,and all accessories with all leads and lifts where surface cleaning by sand blasting is not feasible and based on specific recommendations of designers, it is to adopt surface preperation done manually by hand and power tool after cleaning by chemical treatment to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting, before applying primer painting.

DATA:

RATE ANALYSIS
A. MATERIALS:

UNIT : Unit Quantity

100.000 Sqare meters Rate in Rs. 0.00 0.00 0.00 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00

Sl No 1 2 3 4 5

particulars Zinc rich epoxy primer Coal tar epoxy paint Rust cleaner / inhibitor Wire brush Sundries

ltr 11.00 ltr 34.00 ltr 13.00 Nos 2.00 LS 2.00 Total cost of Materials

B. MACHINERY: Sl No

Description nil

Unit

Quantity

Rate in Rs. Rs:

Amount in Rs. 0.00 0.00

Total cost of Machinery C. LABOUR: Sl No 1 2

Description Helper for cleaning / painting Painter Cl - II ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Unit

Quantity

Day 12.00 Day 12.00 Total cost of Labour

Rate in Rs. 0.00 0.00 Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ Total F.Add for contractor's profit and overheads on A+B+C+E Total cost for Rate per sqm=(A+B+C+D+E+F+leads) /100 0% 100.00 sqm

Total 0.00% Total 0%

215

IRR-PMW

CHAPTER-VI Standard Data


Index- code

PRELIMINARY & MAINTENANCE WORKS

IRR-PMW
IRR-PMW-1 IRR-PMW-1-1 JUNGLE CLEARANCE : Clearing thin jungle growth ( more than 50 percent open space ) including bushes upto 30 cm / parthenium and other weeds including burning or disposing off the same as directed etc., complete. Output of 3 mazdoors per day RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit : 1000 sqm UNIT : Quantity 0.00 0.00 Rs: 0.00 1000 sqm Rate in Rs. Amount in Rs.

DATA:

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.50 3.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /1000

1000 sqm

IRR-PMW-1-2

Clearing thick jungle growth ( less than 50 percent open space ) including bushes upto upto 30 cm / parthenium and other weeds including burning or disposing off the same as directed etc., complete. Output of 5 mazdoors per day : 1000 sqm

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials Unit

UNIT : Quantity 0.00 0.00

1000 sqm Rate in Rs. Amount in Rs.

Rs:

0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.50 5.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery

216

IRR-PMW

C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /1000 0% 1000 sqm

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

IRR-PMW-1-3

Removing stumps, tree roots, roots of bamboo clusters etc., upto 1.50 m girth including excavation, stacking the materials neatly and levelling the surface etc., complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT : 18 Each

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.25 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /18

18 Each

IRR-PMW-1-4

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above 1.50 m and upto 3.0 m including excavation, stacking the materials neatly and levelling the area etc., complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT : 8 Each

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.25 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /8

8 Each

217

IRR-PMW

IRR-PMW-1-5

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above 3.0 m and upto 5.0 m including excavation, stacking the materials neatly and levelling the area etc., complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 Rate in Rs. 5 Each Amount in Rs.

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.50 4.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /5

5 Each

IRR-PMW-1-6

Additional rate for every 0.5 m increase in girth of tree stump / stumps of bamboo cluster beyond 5 m.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT : 7 Nos.

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.22 0.88

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per 0.5 m increase in girth per Each=(A+B+C+D) /7

7 Nos.

IRR-PMW-1-7

Cutting and stacking bamboos excluding removing stumps and roots etc., complete with initial lead upto 50 m and all lifts. Output of 5 mazdoor per day : 150 Nos

DATA:

218

IRR-PMW

RATE ANALYSIS A. MATERIALS: Sl No 1

UNIT :

150 Each.

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.50 5.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /150

150 Each

IRR-PMW-1-8

DATA:

Cutting and removing jauliflora bushes upto 1.5 m girth excluding removal of stumps and including burning or disposing off the materials as directed with initial lead upto 50 m and all lifts. Output of 3 mazdoors per day : RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT :

100 Nos 100 Each.

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.50 3.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /100

100 Each

IRR-PMW-1-9

Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girth excluding removal of stumps and including burning or disposing off the materials as directed with initial lead upto 50 m and all lifts. Output of 3 mazdoors per day RATE ANALYSIS A. MATERIALS: : UNIT : 50 Nos 50 Each.

DATA:

219

IRR-PMW

Sl No 1

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.50 3.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /50

50 Each

IRR-PMW-1-10

Cutting trees above 0.3 m and upto 0.6 m girth excluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts. Av. Diameter of tree for 0.3 to 0.6 m girth Output of 2 mazdoors for cutting trees / day 1 mazdoor for cutting branches, collecting and stacking cut wood. RATE ANALYSIS A. MATERIALS: Sl No 1 : : 0.15 m 14 Nos

DATA:

UNIT :

14 Each.

particulars LS

Unit

Quantity 0.25 0.00

Rate in Rs.

Amount in Rs.

Use rate of ropes etc

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.25 3.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /14

14 Each

IRR-PMW-1-11

Cutting trees above 0.6 m and upto 1.2 m girth excluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts. Av. Diameter of tree for 0.6 to 1.2 m girth Output of 2 mazdoors for cutting trees / day 1 mazdoor for cutting branches, collecting and stacking cut wood. RATE ANALYSIS A. MATERIALS: Sl No : : 0.3 m 4 Nos

DATA:

UNIT :

4 Each.

particulars

Unit

Quantity

Rate in Rs.

Amount in Rs.

220

IRR-PMW

Use rate of ropes etc

LS Total cost of Materials

0.25 0.00 Rs: 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.25 3.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /4

4 Each

IRR-PMW-1-12

Cutting trees above 1.2 m and upto 1.8 m girth excluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts. Av. Diameter of tree for 1.2 to 1.8 m girth Output of 2 mazdoors for cutting trees / day 1mazdoor for cutting branches, collecting and stacking cut wood. RATE ANALYSIS A. MATERIALS: Sl No 1 : : 0.5 m 2 Nos

DATA:

UNIT :

2 Each.

particulars LS

Unit

Quantity 0.25 0.00

Rate in Rs.

Amount in Rs.

Use rate of ropes etc

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.25 3.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /2

2 Each

IRR-PMW-1-13

Cutting trees above 1.8 m and upto 2.4 m girth excluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts. Av. Diameter of tree for 1.8 to 2.4 m girth Output of 2 mazdoors for cutting trees / day 1 mazdoor for cutting branches, collecting and stacking cut wood. RATE ANALYSIS A. MATERIALS: Sl No 1 : : 0.7 m 1 No

DATA:

UNIT :

1 Each.

particulars LS

Unit

Quantity 0.25 0.00

Rate in Rs.

Amount in Rs.

Use rate of ropes etc

221

IRR-PMW

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.25 3.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /1

1 Each

IRR-PMW-1-14

Cutting trees above 2.4 m and upto 3.0 m girth excluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT : 1 Each.

particulars LS

Unit

Quantity 0.50 0.00

Rate in Rs.

Amount in Rs.

Use rate of ropes etc

Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.25 5.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /1

1 Each

IRR-PMW-1-15 DATA:

Additional rate for cutting tree for every 0.5 m increase in girth of tree beyond 3 m.

RATE ANALYSIS A. MATERIALS: Sl No 1

UNIT :

1 Each.

particulars LS

Unit

Quantity 0.15 0.00

Rate in Rs.

Amount in Rs.

Use rate of ropes etc

Total cost of Materials

Rs:

0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00

Rate in Rs.

Amount in Rs.

222

IRR-PMW

0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.10 1.75

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for 0.5 m increase in girth for Rate per 0.5 m increase in girth per Each=(A+B+C+D) /1

1 No.

IRR-PMW-1-16 DATA:

Cutting and burning or disposing off Apu / Jondu from marshy areas as directed with initial lead upto 50 m and all lifts. Output of 3 mazdoors per day : RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT :

250 sqm 1000 sqm

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 1.00 12.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /1000 IRR-PMW-2 IRR-PMW-2-1 PRELIMINARY WORKS : Earthwork excavation for trial pits / borrow pits and other investigation works in all kinds of soil including boulders upto 30 cm dia and disposing off excavated soil as directed with lead upto 10 m and lift upto 3 m. Output of 2 mazdoors per day RATE ANALYSIS A. MATERIALS: Sl No 1 : 4 cum UNIT :

1000 sqm

DATA:

10 cum

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

223

IRR-PMW

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 0.50 6.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 IRR-PMW-2-2

10 cum

Earthwork excavation for trial pits / borrow pits and other investigation works in soft rock including disposing off the excavated rock as directed with lead upto 10 m and lift upto 3 m. Output of 2 mazdoors per day RATE ANALYSIS A. MATERIALS: Sl No 1 2.50 cum UNIT : 10 cum

DATA:

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 work inspector Crowbarman mazdoor

Description

Unit Day Day Day Total cost of Labour

Quantity 0.50 1.00 7.50

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 IRR-PMW-2-3

10 cum

Conducting geophysical investigation studies by electrical resistivity method in stages of 5m for sub-surface details such as depth of formations, shear zones, classification of strata, depth of water table etc., including cost of all materials, equipments, labour, analysing and reporting the details of field studies conducted etc., complete excluding cost of transportation arrangements.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Unit UNIT : Quantity 5.00 0.00 Total cost of Materials B. MACHINERY: Sl No 1 Rs: 0.00 Rate in Rs. 20 Stage Amount in Rs.

Sundries ( misc. consumables )

Description

Unit Hour

Quantity

Rate in Rs.

Amount in Rs.

Electric resistivity meter Battery / charging cost etc @

8.00 20% Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1

Description

Unit Day

Quantity 2.00

Rate in Rs.

Amount in Rs.

Geophysist / Geologist

224

IRR-PMW

2 3 4

Graduate Engineer Lab Assistant mazdoor ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Day Day Day Total cost of Labour

1.00 1.00 4.00 Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per stage=(A+B+C+D) /20

20 Stage

IRR-PMW-2-4

Drilling 80 mm dia hole through over-burden using casing shoe bit vertical or inclined upto 10 degrees to vertical as directed including cost of all materials, machinery, labour, water charges, reaming, collection of wash samples at suitable intervals, logging and lebelling, supplying honne wood core box, fixing casing pipes ( excluding cost of casing pipes ) etc., complete for depth upto 30 m from surface. Note: 1. For drilling through over-burden beyond 30 m from surface increase the basic rate per Rm by 10 percent. 2. For providing HDPE or light black MS casing pipes add the cost of pipe per Rm. RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 particulars Unit Rm Rm Rm Rm Total cost of Materials UNIT : Quantity 3.00 3.00 3.00 3.00 Rs: 0.00 3.00 Rm Rate in Rs. Amount in Rs.

DATA:

Use rate of casing shoe bit Use rate of reamer shell Use rate of extension rod set 16.5 m Use rate of honne core box

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

Core drilling machine Fuel / Energy charges 5 hp pump ( diesel ) 2 Nos. Fuel / Energy charges Sundries ( samplers etc )

Hour 1.00 Hour 1.00 Hour 2.00 Hour 2.00 LS 2.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit Hour Hour Day Total cost of Labour

Quantity 1.00 2.00 2.00

Rate in Rs.

Amount in Rs.

Crew for Core drilling machine Crew for Pump mazdoor ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /3

3.00 Rm

IRR-PMW-2-5

Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bit vertical / inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water charges, collection of core samples, logging and lebelling, supplying honne wood core box including cement grouting ( excluding cost of cement for grouting ) and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 UNIT : 3.00 Rm

particulars

Unit Rm Rm Rm Rm Rm Total cost of Materials

Quantity 3.00 3.00 3.00 3.00 3.00

Rate in Rs.

Amount in Rs.

Use rate of diamond core bit Use rate of reamer shell Use rate of double tube core barrel Use rate of extension rod set 16.5 m Use rate of honne core box

Rs:

0.00

B. MACHINERY:

225

IRR-PMW

Sl No 1 2 3

Description Core drilling machine Fuel / Energy charges 5 hp pump ( diesel ) 2 Nos. Fuel / Energy charges Sundries

Unit

Quantity

Rate in Rs.

Amount in Rs.

Hour 8.00 Hour 8.00 Hour 16.00 Hour 16.00 LS 5.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit Hour Hour Day Total cost of Labour

Quantity 8.00 16.00 2.00

Rate in Rs.

Amount in Rs.

Crew for Core drilling machine Crew for Pump mazdoor ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /3 NOTE:

3.00 Rm

1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the basic rate per Rm by 25 percent. 2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic rate per Rm by 40 percent.

IRR-PMW-2-6

Drilling 47 mm (BX )dia core hole in hard rock using diamond core bit vertical / inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water charges,collection of core samples,logging, lebelling, supplying honne wood core box including cement grouting ( excluding cost of cement for grouting ) and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 particulars Unit Rm Rm Rm Rm Rm Total cost of Materials UNIT : Quantity 3.00 3.00 3.00 3.00 3.00 Rs: 0.00 3.00 Rm Rate in Rs. Amount in Rs.

Use rate of diamond core bit Use rate of reamer shell Use rate of double tube core barrel Use rate of extension rod set 16.5 m Use rate of honne core box

B. MACHINERY: Sl No 1 2 3

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

Core drilling machine Fuel / Energy charges 5 hp pump ( diesel ) 2 Nos. Fuel / Energy charges Sundries

Hour 8.00 Hour 8.00 Hour 16.00 Hour 16.00 LS 5.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit Hour Hour Day Total cost of Labour

Quantity 8.00 16.00 2.00

Rate in Rs.

Amount in Rs.

Crew for Core drilling machine Crew for Pump mazdoor ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /3 NOTE:

3.00 Rm

1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the basic rate for drilling upto 30 m from surface by 25 percent per Rm. 2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic rate for drilling upto 30 m from surface by 40 percent per Rm.

226

IRR-PMW

IRR-PMW-2-7

Providing and fixing 20 x 20 x 75 cm size roughly dressed boundary / demarcation / chainage / arrow stones including cost of all materials, labour, engraving marks, fixing in position, murum filling etc., complete with lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit UNIT : Quantity 18.00 1.00 Rs: Rs: Rs: 0.00 0.00 0.00 Rate in Rs. 18 Nos. Amount in Rs.

Rough stone 20x20x75 cm Each Murrum cum Add seignorage charges on stone ( Included in material cost ) Add seignorage charges on murum ( Included in material cost ) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit Day Day Day Total cost of Labour

Quantity 1.00 1.00 3.00

Rate in Rs.

Amount in Rs.

work inspector Stone chiseller Cl- I mazdoor ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /18

18 Nos.

IRR-PMW-2-8

Providing and fixing 20 x 20 x 75 cm size temporary bench mark stone in CC 1 : 4 : 8 using 40 mm down size graded coarse aggregate including cost of all materials, labour, dressing top surface, engraving BM data etc.,complete with lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Unit UNIT : Quantity 10.00 91.00 0.25 0.15 0.10 0.25 Rs: Rs: Rs: 0.00 0.00 0.00 Rate in Rs. 10 Nos. Amount in Rs.

Rough stone 20x20x75 cm Each Cement for CC & top finishing kg Coarse aggregate 40-20 mm cum Coarse aggregate 20-10 mm cum Coarse aggregate 10-4.75 mm cum Sand ( screened ) cum Add seignorage charges on stone ( Included in material cost ) Add seignorage charges on murum ( Included in material cost ) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit Day Day Day Total cost of Labour

Quantity 1.00 3.00 4.00

Rate in Rs.

Amount in Rs.

work inspector Stone chiseller Cl- I mazdoor ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for

10 Nos.

227

IRR-PMW

NOTE:

Rate per Each=(A+B+C+D) /10 For providing 30 cm thick compacted murum bed in B.C soil area including additional excavation for thickness of murum bedding add per Each

Rs: Rs:

0.00 3.00

IRR-PMW-2-9

Providing and fixing 20 x 20 x 75 cm size permanent bench mark stone in CC 1 :3 : 6 block of size 90 x 90 x 120 cm using 40 mm down size graded coarse aggregate and providing 35 cm thick 30 cm high UCR masonry in CM 1 : 5 proportion protective wall alround the BM stone, including cost of all materials, labour, dressing top surface of stone, engraving BM data on top surface, excavation, finishing, curing etc., complete with lead upto 50 m and all lifts. RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Unit UNIT : Quantity 1.00 262.00 0.50 0.30 0.20 0.25 0.04 0.60 Rs: Rs: Rs: 0.00 0.00 0.00 Rate in Rs. 1 No. Amount in Rs.

DATA:

4 5 6

Rough stone 20x20x75 cm Each Cement kg Coarse aggregate 40-20 mm cum Coarse aggregate 20-10 mm cum Coarse aggregate 10-4.75 mm cum Rubble stone at quarry cum Stone chips at quarry cum Sand ( screened ) cum Add seignorage charges on stone ( Included in material cost ) Add seignorage charges on murum ( Included in material cost ) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4

Description

Unit Day Day Day Day Total cost of Labour

Quantity 1.00 0.50 1.00 5.00

Rate in Rs.

Amount in Rs.

work inspector Stone chiseller Cl- I Mason Cl- II mazdoor ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /1 IRR-PMW-3 IRR-PMW-3-1 MAINTENANCE WORKS : Removing dry stone rock-toe / rivetment and filter layers below rock-toe/ rivetment including stacking all materials separately as directed with initial lead upto 50 m and all lifts.

1 Nos

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 105 cum Rate in Rs. Amount in Rs.

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 work inspector Mason Cl- II mazdoor

Description

Unit Day Day Day Total cost of Labour

Quantity 1.00 6.00 48.00

Rate in Rs.

Amount in Rs.

Rs: Rs:

0.00 0.00

ABSTRACT: A. Cost of Materials including seignorage charges

228

IRR-PMW

B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /105 0% 105 cum

Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00

IRR-PMW-3-2

Re-constructing 60 cm thick hand packed rough stone revetment with through stones at 1.5 m c / c over a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm thick each using sand from approved quarry and stones and filter aggregates obtained from revetment removed for re-construction including cost of all machinery, labour, laying filter and stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 particulars Unit UNIT : Quantity 15.30 15.30 15.30 9.00 57.60 44.00 Rs: Rs: 0.00 0.00 100 sqm Rate in Rs. Amount in Rs.

Sand ( unscreened ) ( from quarry) cum Coarse aggregate 10 mm (available) cum Coarse aggr. 40-20 mm ( available) cum Stone chips ( available ) cum Rough stones ( available ) cum Through stones ( available ) Nos Add seignorage charges on sand @ ( Included in material rate) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 work inspector Mason Cl- II mazdoor

Description

Unit Day Day Day Total cost of Labour

Quantity 1.00 5.00 33.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

100 sqm

IRR-PMW-3-3

Re-constructing dry rubble rock-toe and filter media for rock-toe consisting of sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm thick each using sand from approved quarry and stones and filter aggregates obtained from rock-toe removed for re-construction including cost of all machinery, labour, laying filter and stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 particulars Unit UNIT : Quantity 58.20 8.70 19.40 12.10 9.80 Rs: Rs: 0.00 0.00 100 cum Rate in Rs. Amount in Rs.

Rubble ( available ) cum Stone chips ( available ) cum 80-20 mm filter ( available ) cum 20 mm down filter ( available ) cum Sand ( fresh from quarry ) cum Add seignorage charges on sand @ ( Included in material rate) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

229

IRR-PMW

C. LABOUR: Sl No 1 2 3 work inspector Mason Cl- II mazdoor

Description

Unit Day Day Day Total cost of Labour

Quantity 1.00 7.00 48.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /100

100 cum

IRR-PMW-3-4

Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC / Other types of slab lining set in CM 1 : 3 including flush cement mortar pointing in CM 1 : 3 with lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit UNIT : Quantity 101.00 0.21 Rs: Rs: 0.00 0.00 100 sqm Rate in Rs. Amount in Rs.

Cement 43 Gr kg Sand ( screened ) cum Add seignorage charges on sand @ ( Included in material rate) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4

Description

Unit Day Day Day Day Total cost of Labour

Quantity 1.00 4.00 6.00 1.00

Rate in Rs.

Amount in Rs.

work inspector Mason Class I mazdoor Cartman with Bullock cart for water ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

100 sqm

IRR-PMW-3-5

Removing and resetting disturbed dry rubble / khandki stone pitching 25 to 45 cm thick including packing, wedging, finishing etc., complete with all leads and lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 100 sqm Rate in Rs. Amount in Rs.

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector Mason Class II

Description

Unit Day Day

Quantity 1.00 6.00

Rate in Rs.

Amount in Rs.

230

IRR-PMW

mazdoor ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Day Total cost of Labour

6.00 Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

100 sqm

IRR-PMW-3-6

Removing and refixing disturbed chainage / demarcation / hectometre / guard stones including excavation, back filling etc., complete with all leads and lifts. Assuming 0.75 hour for each stone and 7 hours working 9 stones can be fixed / day. Consider 1 work inspector & 2 mazdoors for removing and refixing 18 stones / day RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 Rate in Rs. 18 Nos. Amount in Rs.

DATA:

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 1.00 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /18

18 Nos

IRR-PMW-3-7

Removing and refixing disturbed km stone / sign board / hecto-metre stone etc., including excavation, back filling with available stuff after refixing, forming base platform of size 90 x 90 x 7.5 cm including watering, ramming etc complete with all leads and lifts. Assuming 2 hours for removing and refixing each stone 4 stones can be fixed / day. Consider 1 work inspector, 1 Mason & 2 mazdoor for refixing 8 stones / day RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 Rate in Rs. 8 Nos. Amount in Rs.

DATA:

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 1.00 2.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs:

0.00 0.00 0.00

ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery

231

IRR-PMW

C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Each=(A+B+C+D) /8 IRR-PMW-3-8 0% 8 Nos

Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00

Providing impervious hearting for breached / damaged portion of embankment with soil from approved borrow areas in layers of 10 to 15 cm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by rolling or by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Add seignorage charges on soil Rs: Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 0.00 480 cum Rate in Rs. Amount in Rs.

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

Angle dozer Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 4 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries

Hour 5.00 Hour 5.00 Hour 8.00 Hour 8.00 Hour 32.00 Hour 32.00 Hour 2.00 Hour 2.00 Hour 4.00 Hour 4.00 Hour 6.00 Hour 6.00 LS 2.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour

Quantity 4.00 8.00 32.00 3.00 5.00 6.00 2.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /480

480 cum

IRR-PMW-3-9

Providing pervious/semi-pervious casing for breached / damaged portion of embankment with soil from approved borrow areas in layers of 10 to 15 cm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by rolling or by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Add seignorage charges on soil @ Rs: Total cost of Materials Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 325 cum Rate in Rs. Amount in Rs.

232

IRR-PMW

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 3 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries

Hour 3.50 Hour 3.50 Hour 8.00 Hour 8.00 Hour 24.00 Hour 24.00 Hour 1.50 Hour 1.50 Hour 3.00 Hour 3.00 Hour 4.00 Hour 4.00 LS 2.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour

Quantity 3.50 8.00 24.00 1.50 3.00 4.00 2.00 4.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /325

325 cum

IRR-PMW-3-10

Providing impervious hearting for breached / damaged portion of embankment with soil from approved dump areas in layers of 10 to 15 cm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil,sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by rolling or by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Add seignorage charges on soil @ Rs: 13.60 / cum Total cost of Materials Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 0.00 612 cum Rate in Rs. Amount in Rs.

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

Angle dozer Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 5 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries

Hour 4.00 Hour 4.00 Hour 8.00 Hour 8.00 Hour 40.00 Hour 40.00 Hour 4.00 Hour 4.00 Hour 7.00 Hour 7.00 Hour 7.50 Hour 7.50 LS 2.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 Crew for Dozer Crew for Shovel Crew for Tipper

Description

Unit Hour Hour Hour

Quantity 4.00 8.00 40.00

Rate in Rs.

Amount in Rs.

233

IRR-PMW

4 5 6 7 8

Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Hour Hour Hour Day Day Total cost of Labour

4.00 7.00 7.50 2.00 6.00 Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /612

612 cum

IRR-PMW-3-11

Providing pervious /semi-pervious casing for breached /damaged portion of embankment with soil from approved dump areas in layers of 10 to 15 cm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by rolling or by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Add seignorage charges on soil @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 Unit UNIT : Quantity 0.00 0.00 Rs: Rs: 0.00 0.00 440 cum Rate in Rs. Amount in Rs.

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 4 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries

Hour 3.00 Hour 3.00 Hour 8.00 Hour 8.00 Hour 32.00 Hour 32.00 Hour 3.00 Hour 3.00 Hour 6.00 Hour 6.00 Hour 5.50 Hour 5.50 LS 2.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour

Quantity 3.00 8.00 32.00 3.00 6.00 5.50 2.00 6.00

Rate in Rs.

Amount in Rs.

Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /440

440 cum

IRR-PMW-3-12

Repairing rain cuts / resectioning canal slopes to required lines and grades as directed using available soil including dressing, clod breaking, packing, tamping etc., complete with all leads and lifts.

DATA: RATE ANALYSIS A. MATERIALS: UNIT : 1000 sqm

234

IRR-PMW

Sl No 1

particulars NIL

Unit

Quantity 0.00 0.00

Rate in Rs.

Amount in Rs.

Total cost of Materials B. MACHINERY: Sl No 1

Rs:

0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 1.00 8.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /1000

1000 sqm

IRR-PMW-3-13

Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing / brushing including chiselling and removing leached lime deposit and disposing off all the waste material out side adits in specified location etc., complete with all leads and lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Unit Each Each LS Total cost of Materials UNIT : Quantity 5.00 10.00 2.00 Rs: 0.00 100 Rm Rate in Rs. Amount in Rs.

Wire brush Coir brush Sundries ( brooms, gloves etc )

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 Chiseller Cl II mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 2.00 6.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /100

100 Rm

IRR-PMW-3-14

Cleaning dam parapet inner face and top using oxalic acid and water by scrubbing / brushing and washing to remove all surface coatings etc., complete .

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 particulars Unit ltr Each Each LS Total cost of Materials UNIT : Quantity 5.00 5.00 10.00 2.00 Rs: 0.00 100 Rm Rate in Rs. Amount in Rs.

Oxalic acid Wire brush Coir brush Sundries ( brooms, gloves etc )

235

IRR-PMW

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 mazdoor

Description

Unit Day Total cost of Labour

Quantity 6.00

Rate in Rs. Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per Rm=(A+B+C+D) /100 0% 100 Rm

Rs: Rs: Rs:

IRR-PMW-3-15

Cleaning gates / hoists / embedded parts for re-painting by removing rust, old paint, grease etc., by using wire brush, scrubber, rust remover and applying a coat of rust inhibitive compound etc., complete.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit Each LS UNIT : Quantity 10.00 5.00 TOTAL 10% 100 sqm Rate in Rs. Amount in Rs.

Wire brush Sundries (Rust remover/ inhibitor / sand paper etc) Add for scaffolding / ladder etc @

Total cost of Materials B. MACHINERY: Sl No 1

Rs: Rs: Rs:

0.00 0.00 0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 Painter Class-II mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 5.00 10.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

100 sqm

IRR-PMW-3-16

Cleaning gates / hoists / embedded parts to expose fresh metal surface for repainting by sand blasting method as per specifications including cost of all materials, labour, machinery, scaffolding, applying a coat of rust inhibitive etc., complete with initial lead for sand upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 particulars Unit cum Hour Hour LS UNIT : Quantity 30.00 8.00 8.00 5.00 TOTAL 10% . 100 sqm Rate in Rs. Amount in Rs.

Natural river sand Use rate of air hose Use rate of sand blast gun nozzle Sundries( Rust inhibitive, seive etc ) Add for scaffolding / ladder etc @

Total cost of Materials B. MACHINERY:

Rs: Rs: Rs:

0.00 0.00 0.00

236

IRR-PMW

Sl No 1 2

Description Air compressor 7 cmm diesel Fuel / Energy charges Sand blasting equipment Fuel / Energy charges

Unit

Quantity

Rate in Rs.

Amount in Rs.

Hour 8.00 Hour 8.00 Hour 8.00 Hour 8.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 3

Description

Unit Hour Hour Day Total cost of Labour

Quantity 8.00 8.00 15.00

Rate in Rs.

Amount in Rs.

Crew for Air compressor Crew for Sand blasting equipment mazdoor ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 0.00% Total 0% Total

F.Add for contractor's profit and overheads on A+B+C+D+E Total cost for Rate per sqm=(A+B+C+D+E+F) /100

0% 100 sqm

IRR-PMW-3-17

Providing two coats of painting to hoist supporting structures / hoists / moving gantry cranes / railings etc., with zinc chromate alluminium primer paint of approved quality including removing rust, cleaning surface, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit ltr LS UNIT : Quantity 17.00 2.00 TOTAL 10% 100 sqm Rate in Rs. Amount in Rs.

Zinc chromate, alluminium primer Sundries Add for scaffolding / ladder etc @

Total cost of Materials B. MACHINERY: Sl No 1

Rs: Rs: Rs:

0.00 0.00 0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 Painter Class-II mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 10.00 5.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

100 sqm

IRR-PMW-3-18

Providing two coats of painting 100 micron dry film thickness each coat to embedded parts / gates with cold applied coal tar epoxy paint of approved quality including removing rust, cleaning surface, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit ltr LS UNIT : Quantity 34.00 4.00 100 sqm Rate in Rs. Amount in Rs.

Coal tar epoxy paint Sundries ( rust remover / brush etc )

237

IRR-PMW

Add for scaffolding / ladder etc @ Total cost of Materials B. MACHINERY: Sl No 1

TOTAL 10%

Rs: Rs: Rs:

0.00 0.00 0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 Painter Class-II mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 13.00 6.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs: Rs: 0% Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100

100 sqm

IRR-PMW-3-19

Providing two coats of painting to hoist supporting structures / hoists / moving gantry cranes / railings etc., with first quality synthetic enemel paint of approved colour including cleaning surface, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit ltr LS UNIT : Quantity 17.00 2.00 TOTAL 10% 100 sqm Rate in Rs. Amount in Rs.

Synthetic enamel paint ( 1st quality ) Sundries Add for scaffolding / ladder etc @

Total cost of Materials B. MACHINERY: Sl No 1

Rs: Rs: Rs:

0.00 0.00 0.00

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 2 Painter Class-II mazdoor

Description

Unit Day Day Total cost of Labour

Quantity 10.00 5.00

Rate in Rs.

Amount in Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

238

IRR-PMW

Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per sqm=(A+B+C+D) /100 0% 100 sqm

Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00

IRR-PMW-3-20

Excavation and removal of silt and silt mixed with sand from canal bed in dry condition including disposing off the same in spoil bank or on the canal embankment in layers as directed etc., complete with initial lead upto 50 m and all lifts. Output of 2 mazdoors assumed at 5 cum per day. RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 Rate in Rs. 10 cum Amount in Rs.

DATA:

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 mazdoor

Description

Unit Day Total cost of Labour

Quantity 4.00

Rate in Rs. Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /10 0% 10 cum

Rs: Rs: Rs:

239

IRR-PMW

IRR-PMW-3-21

Excavation and removal of silt or silt mixed with sand in slussy condition from canal bed including disposing off the same in spoil bank or on the canal embankment in layers as directed etc., complete with initial lead upto 50 m and all lifts. Excavated silt in slussy condition can be disposed off in single operation without heaping silt in mortar pans or by collecting and rehandling after draining out water. Output of 3 mazdoors assumed at 6 cum per day. RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 Rs: 0.00 Rate in Rs. 12 cum Amount in Rs.

DATA:

Description NIL

Unit

Quantity

Rate in Rs.

Amount in Rs.

0.00 0.00 Total hire charges of Machinery

Rs:

0.00

C. LABOUR: Sl No 1 mazdoor

Description

Unit Day Total cost of Labour

Quantity 6.00

Rate in Rs. Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on A+B+C Total cost for Rate per cum=(A+B+C+D) /12 0% 12 cum

Rs: Rs: Rs:

240

COM-LDLFT

Index- code

SCHEDULE OF RATES (Common to all Departments)


A. Manual Works
New extra items-- common item for all earth works using only manual labour for all other works without involving contractors (Manual)Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canal cross drainage and other appurtenant structures and placing excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m. (WIthout involving the contractors for specified works ) With 3 Cum per day output (Manual)Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canal cross drainage and other appurtenant structures and placing excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m. (WIthout involving the contractors for specified works ) With 2.5 Cum per day output (Manual)Excavation in soft rock without blasting, including boulders upto 0.30 m dia. for foundations of canal cross drainage and other appurtenant structures and placing excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m. (WIthout involving the contractors for specified works ) Soft rock 1.33 Cum/Day (Manual)Excavation in hard rock, including boulders upto 0.30 m dia. for foundations of canal cross drainage and other appurtenant structures and placing excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m. (WIthout involving the contractors for specified works ) Hard rock 0.67Cum/ day

COM-MWRK

COM-MWRK-1

cum

COM-MWRK-2

cum

COM-MWRK-3

cum

COM-MWRK-4

cum

241

COM-LDLFT

COM-LDLFT
NOTES

B. LEAD/LIFT/LOADING & UNLOADING CHARGES

1. For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be adopted irrespective of mode of conveyance. 2. For total lead exceeding 150 m conveyance by mechanical means only shall be adopted irrespective of mode of conveyance. 3. The rates for loading at quarry including idle hire charges of trucks and hire charges per for each kilometer and upto 5 km are cumulative and inclusive of total charges for preceding lead. 4. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones are for loose volume and not for compacted or in-situ volume. 5. The rates for lift charges,lead charges, hire cahrges are cumulative and inclusive of rates for preceding lift,lead and hire cahrges 6. Lift charges are not payable where conveyance of materials is by mechanical means to final placing point. 7. Loading and unloading charges are not payable for conveyance by head load. 8. Loading charges are not payable for conveyance by mechanical means for disposal of excavated materials, unless specified. 9. Loading and unloading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond initial lead of 1 km wherever specified. 10. The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble, size stone and cut stone are inclusive of stacking. 11. Hire charges are per 1 Km for tippers and trucks for tranport of materials from work site to dump yard and other places are cumulative& includes previous km upto 5 kms ABSTRACT
COM-LDLFT-1

A. (Lead) Conveyance Charges for materials by head load

Sl No. Total distance ( Total lead includes initial lead ) 2 Total lead upto 50 m (covered by item rate)
Total lead upto 100 m Total lead upto 150 m

Earth / Sand /Gravel Cement / Reinforce- PCC slab/ / Murrum/ Lime/ ment steel Str steel Shahbad slab / CC Surki/ Size stone / Rs / tonne block/ BS slab/ Cut stone Rubble / Late-rite / Wood Coarse aggregate Rs / cum

1 2 3

initial lead 0.00 0.00 0.00 0.00

initial lead

initial lead 0.00 0.00

Notes: 1. No loading or unloading charges are admissible for conveyance by head load. 2. For total lead exceeding 150 m conveyance charges by mechanical means only shall be adopted irrespective of mode of conveyance.

COM-LDLFT-2

B.( Lead) Conveyance charges for machinery per kilometer for transporting materials by tippers and trucks excluding loading, unloading and hire charges of machinery. FOR THE YEAR: ( No loading and unloading charges allowed for machinery loading and unloading ) (Lead) charges for trucks and tippers per cu.meter (Lead) charges for for PCC trucks and tippers (Lead) charges for slabs/ for Rubble/Size trucks and tippers Shahabad stones/ Cut for Cement/ Steel/ slabs/ CC & Stones/ Coarse RCC poles/ AC & Laterite aggregate per GI sheets/ Packed blocks/ cu.meter materials/tonne Wood/ cum 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5 0.00 0.00 0.00 0.00 0.00 6 0.00 0.00 0.00 0.00 0.00

Sl No. 1 1 2 3 4 5

Distance 2 Lead upto 1 km Lead upto 2 km Lead upto 3 km Lead upto 4 km Lead upto 5 km

(Lead) charges for trucks and tippers for Earth / Sand /Gravel / Murrum/ Lime/ Surki/ per cu.meter 3 0.00 0.00 0.00 0.00 0.00

(Lead) charges for trucks and tippers per cu.meter for water/ 1000 litres 7

242

COM-LDLFT

6 7

for Every km beyond 5 km upto 30 km for Every km beyond 30 km

0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00

COM-LDLFT-3

C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added) Earth / Sand /Gravel Rubble/ size stone/ Murrum/ / Surki/ cut stone/ Coarse aggregate,Lime in Rs / cum Rs/cum 3 4 0.00 0.00 0.00 0.00

Sl No. 1 1 2
COM-LDLFT-4

Description of item 2 Loading Unloading

cement in Rs/tonne 5 0.00 0.00

steel in Rs./tonne 6 0.00 0.00

brick work Rs/1000 No 7 0.00 0.00

D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks ) Earth / Sand /Gravel Rubble/ size stone/ Murrum/ / Surki/ cut stone/ Coarse aggregate,Lime in Rs / cum Rs/cum 3 4 0.00 0.00 0.00 0.00

Sl No. 1 1 2

Description of item 2 Loading Unloading

cement in Rs/tonne 5 0.00 0.00

steel in Rs./tonne 6 0.00 0

brick work Rs/1000 No 7 0.00 0.00

COM-LDLFT-5

E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks) Earth / Sand /Gravel Rubble/ size stone/ Murrum/ / Surki/ cut stone/ Coarse aggregate,Lime in Rs / cum Rs/cum 3 4 0.00 0.00 0.00 0.00

Sl No. 1 1 2

Description of item 2 Loading Unloading

COM-LDLFT-6

F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD

Sl No. 1 1 2

Total lift ( Total lift includes initial lift ) 2 Total lift upto 3 m (covered by item rate) Initial lift For Every 1.00m Lift beyond 0.00 initial lift of 3 meters

Earth / Sand /Gravel Murrum/ Lime/ Surki/ Size stone / Cut stone Rubble / Coarse aggregate Rs / cum 3

Cement / Reinforcement steel Str steel Rs / tonne 4 Initial lift 0.00

PCC slab/ Shahbad slab / CC block/ BS slab / Laterite / Wood Rs / cum 5 Initial lift 0.00

COM-DTL-LDLFT

DETAILED DATA LEAD / LIFT / LOADING & UNLOADING CHARGES - DATA I. GENERAL DATA FOR LEAD / LIFT / LOADING & UNLOADING: DATA FOR LEAD CHARGES BY HEAD LOAD : For the purpose of working out conveyance charges by head load the category of materials as classified in ( I ) above are grouped together as under : CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate / Rubble stone / Size stone / Cut stone In this group materials which are comperatively lighter and generally conveyed by head load by light / heavy mazdoor are included. Method of conveyance, approximate weight per load and time required to cover specified additional distance will be generally same Therefore common data is considered for conveyance by head load for materials under this category. CATEGORY : Cement in bag / Reinforcement steel / Structural steel sections In this group the materials in packed / rolled / fabricated condition which are heavier per load compared to the materials under Category above and which can not be split into small quantities for the purpose of conveyance are included. The unit of measurement for these materials is per tonne.

243

COM-LDLFT

CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood In this group the materials in moulded condition / cut to standard size which are heavier per load compared to materials under Category above are included. COM-DTL-LDLFT-I A. (Lead) Conveyance Charges for materials by head load
CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate / Rubble stone / Size stone / Cut stone

Lead: Upto 50 m : This is initial lead and cost is covered under item basic rate. Lead: Upto 100 m : Average distance to be covered beyond initial lead of 50 m Average speed of conveyance by head load Round trip cycle time for 25 m considering 50 min/ hr working ( 2 x 25 x 60 / 50 / 60 ) No. of trips per day for additional lead ( 8 x 60 / 1 ) Quantity of material by head load per load Quantity of material by head load per day ( 480 x 0.015 ) say Deploy one mazdoor for every 50 m additional lead beyond initial lead. Unit: Sl No. A Description Mazdoor contractor's profit and overhead charges Unit Day Quantity 1 Total Rs:

25 60 1 480 0.015 7 7 Rate in Rs. 0

m m / minute min cum cum cum Amount in Rs. 0 0 0

0%

Rate per/CUM=A+B/7cum Lead: Upto 150 m : Unit: Sl No. A Description Mazdoor contractor's profit and overhead charges Unit Day Quantity 2 Total Rs:

Rs:

7 Rate in Rs. 0.00

cum Amount in Rs. 0 0 0

0% Rate per/CUM=A+B/7cum Rs:

CATEGORY : Cement in bag / Reinforcement steel / Structural steel sections Lead: Upto 50 m : This is initial lead and cost is covered under item basic rate. Lead: Upto 100 m : Average distance to be covered beyond initial lead of 50 m Average speed of conveyance by head load Round trip cycle time for 25 m considering 50 min/ hr working ( 2 x 25 x 60 / 50 / 30 ) No. of trips per day for lead upto 100 m ( 8 x 60 / 2 ) Quantity of material by head load per load Quantity of material by head load per day ( 240 x 50 / 1000 ) Deploy one mazdoor for every 50 m additional lead beyond initial lead. Unit: Sl No. A Description Cement /steel handling mazdoor Contractor's profit and overhead charges Unit Day Quantity 1 Total Rs:

25 30 2 240 50 12 12 Rate in Rs.

m m / minute min kg tonne tonne Amount in Rs.

B.

0% Rate per/Ton=A+B/12tonne

Lead: Upto 150 m : Average distance to be covered beyond initial of 50 m : Deploy two mazdoors for conveyance beyond initial lead. Unit: Sl No. A Description Cement /steel handling mazdoor Contractor's profit and overhead charges Unit Day Quantity 2 Total Rs:

50 12 Rate in Rs.

m tonne Amount in Rs.

B.

0%

244

COM-LDLFT

Rate per/Ton=A+B/12tonne

CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood Lead: Upto 50 m : This is initial lead and cost is covered under item basic rate. Lead: Upto 100 m : Average distance to be covered beyond initial lead of 50 m Average speed of conveyance by head load Round trip cycle time for 25 m considering 50 min/ hr working ( 2 x 25 x 60 / 50 / 40 ) No. of trips per day for lead upto 100 m ( 8 x 60 / 1.5 ) Quantity of material by head load per load Quantity of material by head load per day ( 320 x 0.017 ) say Deploy one mazdoor for every 50 m additional lead beyond initial lead. Unit: Sl No. 1 Description Mazdoor Unit Day Quantity 1 Total Rs: cum cum

25 40 1.5 320 0.017 5.5 5.5 Rate in Rs. 0

m m / minute min cum cum cum Amount in Rs. 0 0 0 0 0

Contractor's profit and overhead charges 18% Total for materials under this Category for 5.5 Rate per Lead: Upto 150 m : Average distance to be covered beyond initial of 50 m : Deploy two mazdoors for conveyance beyond initial lead.

Rs: Rs:

50 Unit: 5.5 Rate in Rs. 0

m cum Amount in Rs. 0 0 0 0 0

Sl No. 1

Description Heavy mazdoor

Unit Day

Quantity 2 Total Rs: cum cum

Contractor's profit and overhead charges 0% Total for materials under this Category for 5.5 Rate per

Rs: Rs:

COM-DTL-LDLFT-II B.( Lead) Conveyance charges for machinery per kilometer for transporting materials by tippers and trucks

excluding loading, unloading and hire charges of machinery. CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / For total lead upto 1 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges Unit Hour Hour Hour 18% 5 Unit: Quantity 0.15 0.15 0.15 Total Rs: cum 5 Rate in Rs. 0.00 0.00 0.00 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 1 km upto 2 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 0% 5 Quantity 0.21 0.21 0.21 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 2 km upto 3 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 18% 5 Quantity 0.28 0.28 0.28 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 3 km upto 4 km

Rs:

Unit:

245

COM-LDLFT

Sl No. 1 2

Description Tipper hire charges Fuel charges Crew charges

Unit Hour Hour Hour 0% 5

Quantity 0.34 0.34 0.34 Total Rs: cum

Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 4 km upto 5 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0

Unit: Unit Hour Hour Hour 18% 5 Quantity 0.4 0.4 0.4 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum

Rs:

For lead beyond 5 km upto 30 km for every km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges Unit Hour Hour Hour 0% 5

Unit: Quantity 0.06 0.06 0.06 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For lead beyond 30 km for every km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 18% 5 Quantity 0.05 0.05 0.05 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum

Rs:

CATEGORY : Coarse aggregate / Rubble stone / Size stone / Cut stone For total lead upto 1 km Sl No. 1 2 Description Truck hire charges Fuel charges Crew charges Unit Hour Hour Hour 0% 5 Unit: Quantity 0.15 0.15 0.15 Total Rs: cum 5 Rate in Rs. 0.00 0.00 0.00 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 1 km upto 2 km Sl No. 1 2 Description Truck hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 18% 5 Quantity 0.21 0.21 0.21 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 2 km upto 3 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 0% 5 Quantity 0.28 0.28 0.28 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum

Rs:

246

COM-LDLFT

For total lead more than 3 km upto 4 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges Unit Hour Hour Hour 18% 5

Unit: Quantity 0.34 0.34 0.34 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 4 km upto 5 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0

Unit: Unit Hour Hour Hour 0% 5 Quantity 0.4 0.4 0.4 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00 0.00 Rs:

Contractor's profit and overhead charges Total for Rate per cum

For lead beyond 5 km upto 30 km for every km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges Unit Hour Hour Hour 18% 5

Unit: Quantity 0.06 0.06 0.06 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For lead beyond 30 km for every km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 0% 5 Quantity 0.05 0.05 0.05 Total Rs: cum

5 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum

Rs:

CATEGORY : Cement/ Steel/ Pipes/ RCC poles/ AC & GI sheets/ Packed materials For total lead upto 1 km Sl No. 1 2 Description Truck hire charges Fuel charges Crew charges Unit Hour Hour Hour 18% 8 Unit: Quantity 0.15 0.15 0.15 Total Rs: tonne 8 Rate in Rs. 0.00 0.00 0.00 tonne Amount in Rs. 0 0 0 0 0 0 0 tonne Amount in Rs. 0 0 0 0 0 0 0 tonne Amount in Rs. 0 0 0 0 0

Contractor's profit and overhead charges Total for Rate per tonne For total lead more than 1 km upto 2 km Sl No. 1 2 Description Truck hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 0% 8 Quantity 0.21 0.21 0.21 Total Rs: tonne

8 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per tonne For total lead more than 2 km upto 3 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 18% Quantity 0.28 0.28 0.28 Total Rs:

8 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges

247

COM-LDLFT

Total for Rate per tonne For total lead more than 3 km upto 4 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

tonne

Rs:

0 0 tonne Amount in Rs. 0 0 0 0 0 0 0 tonne Amount in Rs. 0 0 0 0 0 0 0 tonne Amount in Rs. 0 0 0 0 0 0 0 tonne Amount in Rs. 0 0 0 0 0 0 0

Unit: Unit Hour Hour Hour 0% 8 Quantity 0.34 0.34 0.34 Total Rs: tonne

8 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per tonne For total lead more than 4 km upto 5 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 18% 8 Quantity 0.4 0.4 0.4 Total Rs: tonne

8 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per tonne

Rs:

For lead beyond 5 km upto 30 km for every km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges Unit Hour Hour Hour 0% 8

Unit: Quantity 0.06 0.06 0.06 Total Rs: tonne

8 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per tonne For lead beyond 30 km for every km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 18% 8 Quantity 0.05 0.05 0.05 Total Rs: tonne

8 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per tonne

Rs:

CATEGORY : PCC slabs/ Shahabad slabs/ BS slabs/ CC & Laterite blocks/ Wood For total lead upto 1 km Sl No. 1 2 Description Truck hire charges Fuel charges Crew charges Unit Hour Hour Hour 0% 3.4 Unit: Quantity 0.15 0.15 0.15 Total Rs: cum 3.4 Rate in Rs. 0.00 0.00 0.00 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 1 km upto 2 km Sl No. 1 2 Description Truck hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 18% 3.4 Quantity 0.21 0.21 0.21 Total Rs: cum

3.4 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 2 km upto 3 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour Quantity 0.28 0.28 0.28

3.4 Rate in Rs. 0.00 0.00 0.00

248

COM-LDLFT

Total Rs: Contractor's profit and overhead charges Total for Rate per cum For total lead more than 3 km upto 4 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges Unit Hour Hour Hour 18% 3.4 0% 3.4 cum Rs:

0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0 cum Amount in Rs. 0 0 0 0 0 0 0

Unit: Quantity 0.34 0.34 0.34 Total Rs: cum

3.4 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For total lead more than 4 km upto 5 km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 0% 3.4 Quantity 0.4 0.4 0.4 Total Rs: cum

3.4 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum

Rs:

For lead beyond 5 km upto 30 km for every km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges Unit Hour Hour Hour 18% 3.4

Unit: Quantity 0.06 0.06 0.06 Total Rs: cum

3.4 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum For lead beyond 30 km for every km Sl No. 1 2 Description Tipper hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 0% 3.4 Quantity 0.05 0.05 0.05 Total Rs: cum

3.4 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per cum CATEGORY : water For total lead upto 1 km Sl No. 1 2 Description Water tanker hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 18% 8000 Quantity 0.15 0.15 0.15 Total Rs: litres

8000 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per 1000 litres For total lead more than 1 km upto 2 km Sl No. 1 2 Description Water tanker hire charges Fuel charges Crew charges

Rs:

litres Amount in Rs. 0 0 0 0 0 0 0 litres Amount in Rs. 0 0 0 0 0 0 0 litres Amount in Rs. 0

Unit: Unit Hour Hour Hour 0% 8000 Quantity 0.21 0.21 0.21 Total Rs: litres

8000 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per 1000 litres For total lead more than 2 km upto 3 km Sl No. 1 Description Water tanker hire charges

Rs:

Unit: Unit Hour Quantity 0.28

8000 Rate in Rs. 0.00

249

COM-LDLFT

Fuel charges Crew charges

Hour Hour 18% 8000

0.28 0.28 Total Rs: litres

0.00 0.00

Contractor's profit and overhead charges Total for Rate per 1000 litres For total lead more than 3 km upto 4 km Sl No. 1 2 Description Water tanker hire charges Fuel charges Crew charges

Rs:

0 0 0 0 0 0 litres Amount in Rs. 0 0 0 0 0 0 0 litres Amount in Rs. 0 0 0 0 0 0 0 litres Amount in Rs. 0 0 0 0 0 0 0 litres Amount in Rs. 0 0 0 0 0 0 0

Unit: Unit Hour Hour Hour 0% 8000 Quantity 0.34 0.34 0.34 Total Rs: litres

8000 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per 1000 litres For total lead more than 4 km upto 5 km Sl No. 1 2 Description Water tanker hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 18% 8000 Quantity 0.4 0.4 0.4 Total Rs: litres

8000 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per 1000 litres

Rs:

For lead beyond 5 km upto 30 km for every km Sl No. 1 2 Description Water tanker hire charges Fuel charges Crew charges Unit Hour Hour Hour 0% 8000

Unit: Quantity 0.06 0.06 0.06 Total Rs: litres

8000 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per 1000 litres For lead beyond 30 km for every km Sl No. 1 2 Description Water tanker hire charges Fuel charges Crew charges

Rs:

Unit: Unit Hour Hour Hour 0% 8000 Quantity 0.05 0.05 0.05 Total Rs: litres

8000 Rate in Rs. 0.00 0.00 0.00

Contractor's profit and overhead charges Total for Rate per 1000 litres

Rs:

COM-DTL-LDLFT-III C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)

MORD -data 1 Loading of Lime, Aggregate, Stone Boulder, Unit a) Loading Brick Aggregate, Kankar, Building Rubbish, Building Rubbish, Crushed Slag, Stone for Masonry Work by manual means including a lead upto 30 m Unit = cum Taking output = 5.5 cum Labour day Head Mazdoor day Mazdoor Total in Rs. Contractor's profit and overhead charges 0% Rate per cum =
b) Unloading 50% of the loading charges i.e.,

Quantity

Rate Rs.

Amount Rs.

0.02 0.5

0 0

0.00 0.00 0.00 0.00 0.00

Rs.

0.00 Unit Quantity Rate Rs. Amount Rs.

Loading of Earth, Sand, Moorum, Manure, Flyash 2 a) Loading by manual means including a lead upto 30 m Unit = cum Taking output = 5.5 cum Labour day Head Mazdoor day Mazdoor

0.01 0.25

0 0

0.00 0.00

250

COM-LDLFT

Total in Rs. Contractor's profit and overhead charges Rate per cum =
b) Unloading 50% of the loading charges i.e.,

0.00 0.00 0.00

0% Rs. 0.00 Unit Quantity Rate Rs.

Loading of Bricks by manual means 3 a) Loading including a lead upto 30 m Unit = 1000 Nos. Taking output = 2000 Nos a) Labour Head Mazdoor Mazdoor Cost for 2000 Nos. = Contractor's profit and overhead charges 0% Rate per cum = 100% of loading charges i.e.,
b) Unloading +Rs. stacking

Amount Rs.

day day

0.01 0.25

0 0

0.00 0.00 0.00 0.00 0.00

Rs.

0.00 Unit Quantity Rate Rs. Amount Rs.

Loading of Cement by manual means 4 a) Loading including a lead upto 30 m Unit = 1 t Taking output = 10 t a) Labour Head mazdoor Mazdoor Cost for 10 t = Contractor's profit and overhead charges 0% Rate per 1 tonne =
b) Unloading +100% of loading charges I.e., Rs. stacking 0.00

day day

0.06 1.5

0 0

0.00 0.00 0.00 0.00 0.00

Rs.

Loading of Structural Steel, Steel Bars by manual means Unit 5 a) Loading including a lead upto 30 m Unit = 1 t Taking output = 10 t a) Labour head Mazdoor day Mazdoor day Cost for 10 t = Contractor's profit and overhead charges 0% Rate per 1 tonne =
b) Unloading +100% of loading charges I.e., Rs. stacking 0.00

Quantity

Rate Rs.

Amount Rs.

0.07 1.8

0 0

0 0.00 0.00 0.00 0.00

Rs.

COM-DTL-LDLFT-IV D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )

1 Loading of Lime, Aggregate, Stone Boulder, a) Loading Brick Aggregate, Kankar, Building Rubbish, Building Rubbish, Crushed Slag, Stone for Masonry Work by manual means including a lead upto 30 m Unit = cum Taking output = 5.5 cum a) Labour day Head Mazdoor day Mazdoor b) Machinery Truck 10t hour Cost for 5.5 cum = Contractor's profit and overhead charges 0% Rate per cum =
b) Unloading 50% of the loading charges i.e.,

Unit

Quantity

Rate Rs.

Amount Rs.

0.02 0.5 0.5

0 0 0.00

0.00 0.00 0.00 0.00 0.00 0.00

Rs.

Loading of Earth, Sand, Moorum, Manure, Flyash 2 a) Loading by manual means including a lead upto 30 m Unit = cum Taking output = 5.5 cum Labour day Head Mazdoor

Unit

Quantity

Rate Rs.

Amount Rs.

0.01

0.00

251

COM-LDLFT

Mazdoor b) Machinery Truck 10t Cost for 5.5 cum = Contractor's profit and overhead charges Rate per cum =

day hour

0.25 0.5

0 0.00

0.00 0.00 0.00 0.00 0.00 Amount Rs.

0% Rs. Unit Quantity Rate Rs.

b) Unloading Unloading of Earth, Sand, Moorum, Manure, Flyash

by manual means including a lead upto 30 m Unit = cum Taking output = 5.5 cum a) Labour Mate Mazdoor(unskilled) b) Machinery Truck 10t Cost for 5.5 cum = Contractor's profit and overhead charges 0% Rate per cum =

day day hour

0.005 0.125 0.166

0 0 0.00

0.00 0.00 0.00 0.00 0.00 0.00

Rs.

Loading of Bricks by manual means 3 a) Loading including a lead upto 30 m Unit = 1000 Nos. Taking output = 2000 Nos a) Labour Mate Mazdoor(unskilled) b) Machinery Truck 10t Cost for 2000 Nos. = Contractor's profit and overhead charges 0% Rate per 1000 bricks =
b) Unloading +100% of loading charges i.e., Rs. stacking 0

Unit

Quantity

Rate Rs.

Amount Rs.

day day hour

0.01 0.25 0.33

0.00 0 0.00

0.00 0.00 0.00 0.00 0.00 0.00

Rs.

Loading of Cement by manual means 4 a) Loading including a lead upto 30 m Unit = 1 t Taking output = 10 t a) Labour Mate Mazdoor(unskilled) b) Machinery Truck 10t Cost for 10 t = Contractor's profit and overhead charges 0% Rate per 1 tonne =
b) Unloading +100% of loading charges i.e., Rs. stacking 0

Unit

Quantity

Rate Rs.

Amount Rs.

day day hour

0.06 1.5 1

0 0 0.00

0.00 0.00 0.00 0.00 0.00 0.00

Rs.

Loading of Structural Steel, Steel Bars by manual means Unit 5 a) Loading including a lead upto 30 m Unit = 1 t Taking output = 10 t a) Labour Mate day Mazdoor(unskilled) day b) Machinery Truck 10t hour Cost for 10 t = Contractor's profit and overhead charges 0% Rate per 1 tonne =
b) Unloading +100% of loading charges i.e., Rs. stacking 0

Quantity

Rate Rs.

Amount Rs.

0.07 1.8 1

0 0 0.00

0.00 0.00 0.00 0.00 0.00 0.00

Rs.

COM-DTL-LDLFT-V E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)

1 Loading of Lime, Aggregate, Stone Boulder, a) Loading Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for Masonry work by mechanical means including a lead upto 30 m

Unit

Quantity

Rate Rs.

Amount Rs.

252

COM-LDLFT

Placing tipper at loading point, loading with front end loader excluding time for haulage and return trip. Unit = cum Taking output = 5.5 cum Time required for i) Positioning of tipper at loading point Min ii) Loading by front end loader 1 cum bucket capacityMin @ 45 / 25 cum per hour iii) Manoevouring, reversing, dumping and turning Min for return iv) Waiting time, unforeseen contingencies, etc. Min Total Min a) Machinery Tipper 10 t capacity hour Front end-loader 1 cum bucket capacity @ 45 cum hour per hour Cost for 5.5 cum = b) Contractor's profit and overhead charges 0% Rate per cum = (a+b)/5.5
b) Unloading see below. 2-B

1 7.33 2 10.33 0.172 0.122 0.00 0.00 0 0 0 0 0

Rs.

Loading of Earth, sand, Moorum, Manure, Flyash, 2 a) Loading by mechanical means including a lead upto 30 m Placing tipper at loading point, loading with front end loader excluding time for haulage and return trip. Placing tipper at loading point, loading with front end loader excluding time for haulage and return trip. Unit = cum Taking output = 5.5 cum Time required for i) Positioning of tipper at loading point Min ii) Loading by front end loader 1 cum bucket capacityMin @ 45 / 25 cum per hour iii) Waiting time, unforeseen contingencies, etc. Min Total Min a) Machinery Tipper 10 t capacity hour Front end-loader 1 cum bucket capacity @ 45 cum hour per hour Cost for 5.5 cum = b) Contractor's profit and overhead charges 0% Rate per cum = (a+b)/5.5
b) Unloading Unloading of Earth, sand, Moorum, Manure, Flyash,

Unit

Quantity

Rate Rs.

Amount Rs.

1 3.3 2 6.3 0.105 0.055 0.00 0 0.00 0 0 0 0

Rs.

lime, Aggregate, Stone boulder, Brick aggregate, Kankar, Building rubbish, Manure, Crushed Slag, Flyash, Stone for Masonry work by mechanical means including a lead upto 30 m Placing tipper at unloading point, excluding time for haulage and return trip. Taking output = 5.5 cum Time required for i) Positioning of tipper at loading point Min ii) Loading by front end loader 1 cum bucket capacityMin @ 45 / 25 cum per hour iii) Waiting time, unforeseen contingencies, etc. Min Total a) Machinery Tipper 10 t capacity hour Cost for 5.5 cum = b) Contractor's profit and overhead charges 0% Rate per cum = (a+b)/5.5

Unit

Quantity

Rate Rs.

Amount Rs.

1 2 2 5 0.08 0.00 0 0 0 0

Rs.

COM-DTL-LDLFT-VI F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD

FOR CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate / Rubble stone / Size stone / Cut stone Lift : Upto 3.00 m This is the initial lift and forms integral part of the activities in the basic rate of work item. Lift charges are admissible only lifting effort beyond initial lift specified in the work item.

253

COM-LDLFT

Lift : ADDITIONAL LIFT CHARGES FOR each 1 METER LIFT BEYOND 3 M INITIAL LIFT For additional lift of 1m beyond initial lift of 3 m one meter lift is taken equivalent to 6 meters lead average speed of conveyance by head load Round trip cycle time for 1.00 m considering 50 min/ hr working 1 x6x 60 / 50 / 60 ) No. of trips per day for lift 1.0 m above 3 m ( 8 x 60 / 0..12) Quantity of material by head load Quantity of material by head load per day ( 4000x 0.015 ) Deploy 1 mazdoor for every additional lift of 1.0 m beyond initial lift. Lift : Upto 3.00 m for materials under this Category Sl No. 1 Description 2 Mazdoor contractor's profit and overhead charges Day 0% Total Rs: for 60 cum Unit 3 1.00 Unit: Quantity 4 0.00

60 m/minute 0.12 4000 0.015 60 min cum cum

60 Rate in Rs. 5

cum Amount in Rs. 6 0.00 0.00 0.00 0.00

Rate per cum

FOR CATEGORY: Cement bag / Reinforcement steel / Structural steel sections Lift : Upto 3.00 m This is the initial lift and forms integral part of the activities in the basic rate of work item. Lift charges are admissible only lifting effort beyond initial lift specified in the work item. Lift : ADDITIONAL LIFT CHARGES FOR each 1 METER LIFT BEYOND 3 M INITIAL LIFT For additional lift of 1m beyond initial lift of 3 m one meter lift is taken equivalent to 6 meters lead average speed of conveyance by head load 25 m/minute Round trip cycle time for 1.00 m considering 50 min/ hr working 1 x6x 60 / 50 / 25 ) 0.29 No. of trips per day foradditional lift 1.0 m above 3 m ( 8 x 60 / 0.29) 1655 Quantity of material by head load 50 Quantity of material by head load per day ( 1655x50x 0.015 ) 83 Deploy 1 mazdoor for every additional lift of 1.5 m beyond initial lift.or2/3 mazdoor Lift : Upto 3.00 m for materials under this Category Sl No. 1 Description 2 Mazdoor contractor's profit and overhead charges Day 0% Total Rs: for 83 Tonnes Unit 3 1.00 Unit: Quantity 4 0.00 83 Rate in Rs. 5

min kgs tons

TONS Amount in Rs. 6 0.00 0.00 0.00 0.00

Rate per tonne FOR CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood Lift : Upto 3.00 m This is the initial lift and forms integral part of the activities in the basic rate of work item. Lift charges are admissible only lifting effort beyond initial lift specified in the work item. Lift : ADDITIONAL LIFT CHARGES FOR EACH 1 METER LIFT BEYOND 3 M INITIAL LIFT For additional lift of 1m beyond initial lift of 3 m one meter lift is taken equivalent to 6 meters lead average speed of conveyance by head load 40 m/minute Round trip cycle time for 1.00 m considering 50 min/ hr working 1 x6x 60 / 50 / 40 ) 0.18 No. of trips per day for lift 1.0 m ( 8 x 60 / 0.18 ) 2667 Quantity of material by head load 0.017 Quantity of material by head load per day ( 1667x 0.018 ) 45 Deploy 1 mazdoor for every additional lift of 1.5 m beyond initial lift.or2/3 mazdoor Lift : Upto 3.00 m for materials under Category Sl No. 1 Description 2 Mazdoor contractor's profit and overhead charges Day 0% Unit 3 1.00 Unit: Quantity 4 0.00 45 Rate in Rs. 5

min cum cum

cum Amount in Rs. 6 0.00 0.00

254

COM-LDLFT

Total Rs: for 45 cum Rate per cum

0.00 0.00

255

You might also like