Professional Documents
Culture Documents
A Project by
HASEEB AHMAD
Submitted to the Office of Graduate Studies of Gotland University in partial fulfillment of the requirements for the degree of MASTER OF SCIENCE IN WIND POWER PROJECT MANAGEMTENT June, 2012 Major Subject: "Energy Technology" Master of science in Wind Power Project Management 2012
Examiner:
ABSTRACT
The Lillgrund Offshore Wind Farm, located in a shallow area of resund between Sweden and
Denmark, suffered from a series of accidents, sea collisions and extreme winds. Fourteen out of
forty eight turbines have become dysfunctional along with substation and foundations. So the
objective of this project is to decommission the foundations, old turbines and substation and
install the new foundations, turbines and substation. The same turbine and substation technology
is used for reinstallation. In the first part of this report, decommissioning process and costs are
presented. In the second part, installation process and related costs are presented while in the last
part, total cost estimation is done by calculating net present value. Since there is a change in the
configuration, the substation which was located offshore in the original project is placed onshore
now. The comparison between both configurations is done by calculating net present value for
both. There is no difference in the estimated productions of wind turbines because these are
placed at their original spots. However, electrical losses are calculated because there is a change
of cable lengths. Microsoft Excel and WindPRO are used for calculations in this project while
NOMENCLATURE
MW EAR CPM VDR SDR TDC OSV EIA EHA MVA GBP USD MWh NPV
Megawatt Erection All Risk Copenhagen Malm Port Vessel Day Rate Spread Day Rate Total Daily Cost Offshore Support Vessel Environmental Impact Assessment Environmental Hazard Assessment Mega Volt Ampere Great Britain Pound United States Dollar Megawatt hours Net Present Value
Contents
LIST OF FIGURES ....i LIST OF TABLES .ii Chapter 1 Chapter 2 Introduction ........................................................................................................ 1 Decommissioning Proc ess .............................................................................. 2
Turbine Removal ........................................................................................................................ 3 Foundation and Transition Piece Removal ................................................................................. 4 Substation Removal .................................................................................................................... 5 Cable Removal ........................................................................................................................... 6 Scour Removal ........................................................................................................................... 6 Chapter 3 Installation Process .......................................................................................... 7
Foundation Installation ............................................................................................................... 7 Turbine Installation .................................................................................................................... 8 Cable Installation ........................................................................................................................ 9 Substation Installation ................................................................................................................ 9 Scour Protection ....................................................................................................................... 10 Chapter 4 Cost Esti mations ............................................................................................. 10
Capital Cost Estimation ............................................................................................................ 10 Total Cost Estimation ............................................................................................................... 11 Gantt chart for Project .............................................................................................................. 12 Chapter 5 Comparison between Confi gurations ....................................................... 13
LIST OF TABLES
Table 1. Decommission of Turbines............................................................................................... 5 Table 2. Decommissioning of Foundations .................................................................................... 5 Table 3. Decommissioning of Substation ....................................................................................... 6 Table 4. Decommissioning of Cables ............................................................................................. 6 Table 5. Installation of Foundations ............................................................................................... 8 Table 6. Installation of Turbines..................................................................................................... 9 Table 7. Installation of Cable ......................................................................................................... 9 Table 8. Installation of Substation ................................................................................................ 13 Table 9. Comparison between Configurations ............................................................................. 14
ii
LIST OF FIGURES
Figure 1. Shaded Area and Substation needs to be reinstalled ....................................................... 2 Figure 2. Gantt chart for the Project ............................................................................................. 12 Figure 3. New Configuration ........................................................................................................ 14
Chapter 1 Introduction
The Lillgrund offshore wind power plant is located in a shallow area of resund, 7 km off the coast of Sweden and 9 km off the coast of Denmark. The wind power plant is situated 7 km south of the resund Bridge, which connects Copenhagen and Malm. The offshore wind power plant is comprised of 48 wind turbines, each rated at 2.3 MW, resulting in a total wind power plant capacity of 110 MW. The wind power plant system also includes an offshore substation, an onshore substation and a 130 kV sea and land cable for connection to shore. (Joakim Jeppsson, Poul Erik Larsen, ke Larrson, 2009) The offshore wind farm started its operation in the beginning of 2008. The construction of Lillgrund took about 2 years and there is a warranty period for the turbines of 5 years. (Olsson, February 2009) For managing the construction risk, Vattenfall purchased an owner-controlled All risk insurance policy from Codan that covered both of the two main suppliers as well as all minor sub-contractors. For the construction phase of Lillgrund, Vattenfall signed an EAR insurance with additional third party liability insurance and marine insurance. The policy covered all construction work at Lillgrund, e.g. total construction costs for wind turbines, including foundations, cables and offshore substations. However, temporary buildings and off-site construction areas were not included, e.g. vessels. (Olsson, February 2009) Vettenfall did not sign any insurance policy which covers decommissioning costs. Generally decommissioning funds are used to provide security against environmental and decommissioning liabilities. In Netherlands requires that offshore owners/operators must pay monies into a segregated decommissioning fund for a minimum of 10 years, starting from the first year of operation of the project. The US Environmental Protection Agency Brownfield Superfund requires operators to
set aside monies through annual payments into a fund in order to accrue clean-up costs. (Offshore Renewable Energy Installation Decommissioning Study, Final Report)
Following are different steps to be performed for the decommissioning of the wind farm. The port selected for decommissioning process is the Port of Malm. Malm is located on the south western coast of Sweden and is the largest Swedish port in the area. The port is operated by Copenhagen Malm Port (CMP). The water depth is up to 13 meters alongside at normal waters. The port is accessible all year round and 24 hrs per day with no tidal or light restrictions. (The Port of Malm). The weather factor is taken as 0.8, discount factor is 0.85 of installation time and inflation factor for cable is 2.
Turbine Removal
The decommissioning process started with turbines removal. There are different methodologies that can be implemented to decommission the turbine. Number of lifts for each case vary
however the decommissioning process is not as delicate as commissioning so an option is selected keeping in view the disposal of wind turbines component. In the first step hub is removed, in the second step, nacelle is removed and finally tower is removed. There are three lifts required for this process. This option is selected because blades, nacelle and tower have to be disposed off to landfill and scrape separately but more importantly this option will reduce the cost due to optimum number of lifts. The jackup barge vessel is used along with two tugs one cargo barge and one crew boat. The operation started with the mobilization of vessel and cargo barge to the location. The cargo barge can lift seven turbines, so removal vessel (jackup barge) removed 7 turbines and cargo barge sent those turbines to onshore. The removal took place in two turns. The complete cost and operation calculation of the turbine removal is done using Microsoft Excel. However main results are shown in table1.
Model Selected Vessels Spread Total removal time (hours) Vessel Day Rate (VDR, $/day) Spread Day Rate (SDR, $/day) Total Daily Cost (TDC, $/day) Total Project Cost (Cost, million $)
Table 1. Decommission of Turbines
Barge model Jackup Barge 1 cargo barge, 2 tugs, 1 crew boat 1365 64200 25250 89450 5.087469
Method Selected Vessel Spread Time to Remove a Foundation (hours) Time to Remove all Foundation (hours) Vessel Day Rate (VDR, $/day) Spread Day Rate (SDR, $/day) Total Daily Cost (TDC, $/day) Total Cost to Remove Foundations (million $)
Table 2. Decommissioning of Foundations
Single Vessel Method Jack up Barge 1 cargo barge, 2 tugs, 1 crew boat 11 154 64200 21750 85950 0.5515125
Substation Removal
The topside of substation removed first transformer requires no cut so it is lifted as a whole. The next step is to remove the monopile foundation for substation. It is done in the same way as turbine foundations and transported to the port. An OSV is used to support divers and cutting operations and OSV along with heavy-lift vessel remained on site throughout the operation. The
complete cost and operation calculation of the substation removal is done using Microsoft Excel. However main results are shown in table3. Total Time to Remove Substation (hours) Vessels Total day rate ($/day) Cost (million $)
Table 3. Decommissioning of Substation
Cable Removal
Mostly power cables do not constitute a hazard but removal option is selected because these might interfere with commercial trawling or other activities. Only inner array cables for 14 turbines are removed with the help of OSV and spread barge. Inner array cables come in short segments so recovered in one piece. The complete cost and operation calculation of the cable removal is done using Microsoft Excel. However main results are shown in table4. Total Length of Cable (km) Vessels Removal rate (Km/day) Removal time (day) Total day rate ($/day) Cost (million $)
Table 4. Decommissioning of Cables
Scour Removal
Mechanical dredge is employed to conduct the scour removal operation. The cost to remove scour is 12000$/foundation. So the total cost for the whole operation is 0.18 million $. Site clearance is not required while material disposal has been contracted to a company which will do this work without charge.
Foundation Installation
The installation phase is started with the foundations. The jack up barge as an installation vessel with spread containing cargo barge, two tugs and a crew boat is reached at the wind farm from Malm port. In the first trip, cargo barge contained seven foundations. The installation started with the placement of pile into the seabed. After the monopile is secured in the seabed, a
transition piece is lifted and grouted onto the pile. The same vessel is used for transition piece placement and scour protection. Seven more foundations are brought to the site in second trip and installed in the same manner. The complete cost and operation calculation of the foundation installation is done using Microsoft Excel. However main results are shown in table5. Method Selected Vessel Spread Time to Install a Foundation (hours) Time to Install all Foundation (hours) Vessel Day Rate (VDR, $/day) Spread Day Rate (SDR, $/day) Total Daily Cost (TDC, $/day) Total Cost to Install Foundations (million $)
Table 5. Installation of Foundations
Self Transport Model Jack up Barge 1 cargo barge, 2 tugs, 1 crew boat 50 750 64200 25250 89450 2.795313
Turbine Installation
After installing the foundations, turbines are installed. The vessel used for installation is Jack up barge along with spread. The port used for turbines is Nyborg, Denmark due to production facility of Siemens in Denmark. The installation method of turbines comprised of four lifts. The tower is transported in two pieces and lifted in two lifts. The nacelle is lifted separately. The rotor and blades are assembled onshore transported to the offshore site and lifted in one lift. The advantage of using this method is to reduce the number of lifts and onshore off course onshore assembling of rotor provide better and accurate fitting. The complete cost and operation calculation of the turbines installation is done using Microsoft Excel. However main results are shown in table6.
Method Selected Vessel Spread Time to Install a Turbine(hours) Time to Install all Turbines (hours) Vessel Day Rate (VDR, $/day) Spread Day Rate (SDR, $/day) Total Daily Cost (TDC, $/day) Total Cost to Install Turbines (million $)
Table 6. Installation of Turbines
Barge Model Jack up Barge 1 cargo barge, 2 tugs, 1 crew boat 82.5 1155 64200 25250 89450 4.304781
Cable Installation
Inner array cables are installed between the turbines. Since the old layout is used so the time for pre-excavating a trench is reduced. The cable is laid with the help of cable laying vessel and trenches are filled with the help of dredge. The cables are then connected to wind turbines through J tubes. The complete cost and operation calculation of the cable installation is done using Microsoft Excel. However main results are shown in table7. Total Length of Cable (km) Vessels Installation rate (Km/day) Installation time (day) Total day rate ($/day) Cost (million $)
Table 7. Installation of Cable
Substation Installation
The substation mainly comprise of 120 MVA step up transformer, switch gears and other equipment. The typical cost for 500 MW wind farm onshore substation is approximately 35 million GBP. (RWE npower renewables, August, 2011) So for 110 MW wind farm, the typical
10
cost of onshore substation would be approximately 1.3 million USD. Following is the breakdown for substation cost. (RWE npower renewables, August, 2011) High Voltage and Medium Voltage Equipment = 55% Installation = 15% Civil Engineering = 10% Others = 20 % The installation cost would be around 0.2 million USD. For capital cost estimation 4 million USD will be subtracted from total capital cost
Scour Protection
The total time for the scour protection of fourteen foundations is approximately 10 days and 0.08 million dollars are spent on this.
11
Putting values C = 0.73 + 0.0011*32 + 0.036*5 -0.0036*7 + 0.013*200 Reported millions of Dollars per MW (C) = 3.5704
NPV after 1year = -100.622 million $ NPV after 6 years = 3.219 million $ NPV after 30 years = 278.363 million $
12
13
Now for the sake of comparison between new and old configurations, NPV is calculated to see if the project is profitable or not. Following is the NPV using old configuration (offshore substation) E = gross generated energy = 320000 MWh CD = reported millions of dollars for decommissioning = 6.466 CT = reported millions of dollars for total capital costs CT = C*total capacity = 114.2528 CI = reported millions of dollars for installation = 7.9947 Loss = Losses from WindPRO calculations = 1.84% Price = price of electricity 90.00 $ / MWh OM (operation and maintenance) = 10.00 $ / MWh r = real interest rate 30 years fixed 4.50 %
14
NPV after 1year = -104.658 million $ NPV after 6 years = 0.660 million $ NPV after 30 years = 279.715 million $ Old Configuration Total Capital Cost (million $) Total Installation Cost (million $) Losses (%) NPV after 1year (million $) NPV after 6 years (million $) NPV after 30 years (million $) 1.84 -104.658 0.660 279.715 3.06 -100.622 3.219 278.363 114.2528 7.9947 New Configuration 110.253 7.622
15
VITA
Name: Address: Haseeb Ahmad Gotland University Cramrgatan 3, 621 67 Visby, Sweden Email Address: Education: haseeba@mail.hgo.se Bachelors in Chemical Engineering. The University of Engineering and Technology Lahore, Pakistan, 2003 Certified Professional Manager in Health, Safety and Environment, Pakistan Institute of Modern Studies, 2011 Masters in Wind Power Project Management, Gotland University Sweden, 2012
16
Bibliography
Department of Trade and Industry. (2006). Decommissioning of offshore renewable energy installations under the Energy Act of 2004. London: Department of Trade and Industry. Joakim Jeppsson, Poul Erik Larsen, ke Larrson. (2009). Technical Description Lillgrund Wind Power Plant. Sweden: The Swedish Energy Agency. Kenneth Hansen, Brian Vad Mathiesen, David Connolly . (2011). Framework conditions and public regulation for wind turbines in the resund Region. Sweden: Energiresund. (Final Report). Offshore Renewable Energy Installation Decommissioning Study. UK: Department of Energy and Climate Change UK. Olsson, A. (February 2009). Analysis of All risk insurance from an offshore wind farm perspective. Sweden: The Swedish Energy Agency. Patrik Soderholm, MariaPettersson. (2011). Offshore windpowerpolicyandplanninginSweden. Energy Policy 39 , 518-525. RWE npower renewables. (August, 2011). Onshore Substation Opportunities. An RWE Innology Company. The Port of Malm. (n.d.). Retrieved March 20, 2012, from Maersk Broker Agency: http://www.maerskbrokeragency.com/OFFICES/SWEDEN/MALM%C3%96.aspx