Professional Documents
Culture Documents
Jamal Rostami Penn State University, University Park, PA Mohsen Kashi SRS Engineering, Tehran, Iran
OUTLINE
Introduction Tunnel Alignment and Profile Site Development Portals and Construction Shafts Tunneling Operation Crossing an active Subway Station Conclusions
South Portal
BACKGROUND
Tehran & Suburbs is the home for over 10 million people City is spread over an area of around 50 km in the E-W and 30 km in N-S direction Tehran has experienced a rapid growth in past 3 decades, The original fabric is old and does not have sufficient ratio of traffic space to residential space to accommodate the flow Streets are congested, slow traffic 2 subway lines are operational, 5 under construction A network of highways has been constructed around the town A series of road tunnels are planned to connect the highways First highway tunnel (Resalat) was completed in 2004 (6 lanes) 2nd one is Towheed, Inaugurated in Feb 2010, 3rd is under construction for 9 km + a 2000 car capacity underground parking
Project Map
Traffic Congestion
Fuel Cost The Least Neighborhood Interference Travel Time
Tunnel
VERTICAL ALIGNMENT
North Portal
Toeheed Shaft
Azadi Shaft
Jomhoury Shaft
South Portal
557-m
557-m 677-m
2136-m
496-m
Metro Line No. 4 Metro Line No.2
310-m
406-m
Work Sites 1
2
3 4
Site Name
The North Portal
Toeheed Shaft
Azadi Shaft Jomhouri Shaft The South Portal
Longitudinal Profile
North Ramp Slope 6% Tunnel Overall Slope 4% South Ramp Slope 4.29%
TUNNEL PROFILE
GENERAL INFORMATION
Overall Project length: The Tunnel Length: 3003-m 2136-m
305-m2
Bill of Quantities
Project Budget ~$400M
Activity
Open Excavation Tunnel Excavation Pile Construction Formwork Steel Reinforcement Concrete Placement Shotcrete Application Wire Mesh Precast Concrete Elements
Unit
m3 m3 m m2 Ton m3 m2 m2 m2
Quantity
750000 660000 26000 56000 25000 200000 450000 250000 50000
Subway Line No. 2 (Existing). The longitudinal profile of the tunnel is designed to go under the Subway Station Line No. 2 located around station 2+392 of this tunnel. Subway Line No. 4 (under construction). The Toeheed tunnel passes beneath the Subway Line No. 4 currently under construction. Subway Line No. 7 (future construction). The tunnel will essentially run parallel to the No. 7 Subway Line and provisions shall be made in the design and construction of this subway line to assure constructability and other operational issues involved. Urban Utilities. Several underground utilities including water, gas, electric and telephone lines did interfere with the tunnel and other auxiliary structures such as the shafts, galleries, and the access ramps.
GROUND CONDITION
Mainly course grained soils, gravel/sand Primarily dry except for certain sections Intersecting old water works (qanats)
Borehole BH-1 BH-2 BH-3 BH-7 BH-8 BH-9 Test Pits TP-1 TP-2 TP-3 TP-4 0+270 0+400 0+520 1+200 0-5 0-10 4-13 15-22 GW/SW/GP GP/GP-GM/GW/GP GW-GM/GM/GP/GM GW/GC/GW Table 1. Borehole/Test Pit Soil Classifications Station Depths at Tunnel USCS Soil Symbols (km) Section(m) 0+360 5-15 SC/GC-GM/GC 0+850 9-18 SC-SM/GC-GM 1+070 12-21 GM/GC-GM/SC-SM 1+810 20-30 SC 1+920 21-30 GC-GM/GM/SC-SM 2+150 22-31 SC-SM
Power House
Equipment
Relocating 600-mm Water main Pipe Traffic Diversion Barriers Road Widening Supporting 1000-mm Water main Pipe Relocating the military base walls
REDIRECTING TRAFFIC
Toeheed Shaft
METRO Station
AZADI SHAFT
AZADI SHAFT
677-M TO TOEHEED SHAFT 496-M TO JOMHOORI SHAFT
METRO LINE
AZADI SHAFT
METRO LINE
JOMHOORI
SHAFT
28(m)
U Turn
South Ramp
28(m)
1 2
1 3 2 3
Construction of cast in placement of concrete piles Installation of a portion of final lining in the side galleries
1 3 2 4 3
5 3
1 2 4
5 3
5 3
5 6 3
5 3 7 6
1 2 4
5 6 7 3
5 3 7 6 8
1 2 4 8
5 6 7 3
5 3 9
5 6 7 3 9
5 3 9 7 6 8
1 2 4 8
5 6 7 3 9
10
10
Shotcrete Application
Permanent Linings
CHALLANGES
CHALLENGES
Crossing the active subway line, under the station Small footprint for work Redirecting of traffic Restriction in access, muck haulage Fast -Track project, accelerated schedule Maintaining existing utilities, (i.e. a1.8 m water main) Dealing with historical waterworks (qanats)
PROFILE
Middle
South
RESULTS
CONSTRUCTION PROGRESS
FINISHING TOUCHES
70 jet fans, each powered at 30 KW. North fan combined ventilation equipment: 3 axial fans, powered at 600 KW. Niyayesh fan combined ventilation equipment: 2 axial fans (to let in fresh air into Tunnel) powered at 410 KW. 4 axial fans (to let out exhaust air from Tunnel) powered at 500 KW. South portal fan combined ventilation equipment: 3 axial fans powered at 990 KW. Air purification system at the air entering Niyayesh fans. Lghts in the Tunnel: 1,064 lights powered at 550 KW. Length of cables for the utilities: 220 km. Special and standby power generators Air pollution monitoring sensors Smart firefighting system. Traffic alarms. Intercom telephones. Closed-Circuit TV. Vehicles counter. Road closure system. Traffic signs. Thermal sensors.
FINISHED TUNNEL
FINISHED TUNNEL
Thank You
Questions ?????