ROOF TOP SOLAR PV SYSTEMS FOR DISTRIBUTED GENERATION & NET METERING IN PUNJAB UNDER SOLAR MISSION BY PEDA

SOLAR CONCLAVE ON 11TH JAN,2010 BY VISWAJEET KHANNA, IAS, SECRETARY, NRSE, GOP

PUNJAB ENERGY DEVELOPMENT AGENCY


PLOT NO. 1 & 2, SECTOR 33-D, CHANDIGARH

PUNJAB: SALIENT FEATURES


TOTAL GEOGRAPHICAL AREA: 50,362 sq. Kms POPULATION: 243.59 LACS (2001 CENSUS) No. OF DISTRICTS : 20

ENERGY GENERATION STATISTICS


Total power sales by PSEB: 41625 MUs Total power generation: 26897 MUs Net energy purchased: 14728 MUs Energy Purchase from NTPC : 7291 MUs NRSE Generation: 231 MUs

Time bound clearances with in a period of 60 days by an Empowered Committee headed by the Chief Secretary. PSEB shall provide wheeling of power through its network with in the state at a uniform wheeling rate of 2% of the energy fed to the grid.

Inter-state Sale of power


The State Of Punjab is the first state in the country which has allowed Inter State Sale of Power generated from NRSE projects in accordance with Open Access Regulations of the appropriate Commission as per the addendum notified to the NRSE Policy-2006 issued on 11/6/2009. PEDA has initiated steps for adoption of CERC Tariffs in the state.

Small/Micro Hydro Power Projects PEDA (8 nos.) Private Developers (25 nos.) Biomass Cogeneration Power Projects Private Developers ( 20 nos.) Biomass Power Projects Private Developers (3 no.) Waste-to-energy power Projects PEDA (1 no.) Solar Power Projects PEDA (4 nos.) Private Developer Azure Power TOTAL (32 nos.)

9.8 MW 25.00 MW

218.65 MW

28.5 MW

1 MW

325KW 2MW 285.25 MW

(TO BE COMMISSIONED BY JUNE 2010)

S.No. Name of Scheme 1 2 3 6 Mini Hydel Projects (Commissioned) Projects under Execution by Private Developers on BOO basis Self Identified Sites by Private Developers Potential identified under Master Plan on Tail Race of Existing Hydel Channel i.e. Mukerian Hydel Channel Total

Capacity (MW) 35 26.70 7.50 42.00

105.75 MW

SOLAR PHOTOVOLTAIC POWER PROJECTS (MW Scale) ON BUILD, OWN & OPERATE BASIS
PROJECTS ALLOCATED TOTAL CAP. 19 MW. SPV Power Plant Cap. 2MW in Distt. Amritsar commissioned and Inaugurated on 15th Dec.2009. MOU signed with BPCL for development of a 1 MW SPV Power Plant at Lalru in Punjab- PPA SIGNED, planned to be commissioned by March2010 MOU signed with M/s. Enterprise Business Solutions Inc., USA for setting up of a 5MW SPV Power Plant in Punjab, PPA signed and planned to be commissioned by June2010.

First Solar PV Power Plant on BOO basis commissioned in the Country on 1st December ,2009, Cap. 2 MW, V. Awan, Amritsar, Punjab

PSEB Grid interconnection at 11 KV Transmission Line

Proposed Roadmap for the State of Punjab under the Solar Mission
Under the National solar Mission, the state of Punjab plans to setup and achieve the following generation levels from Solar Power Installations under the first phase (2010-2013) Based on RPO of 0.25%. S.No. 1 2 3 Application segment Solar Collectors Off grid solar applications Utility grid power, including roof top Target for Phase-I (2010-13) 0.469 Million Sq.Mtrs. 14 MW 67 MW

PEDA shall facilitate the signing of PPA with the NTPC Vidyut Vyopar Nigam Ltd. as enshrined under the Solar Mission or the Utility PSEB on project case to case basis. The tariff shall be applicable as per CERC guidelines. MNRE, GOI should consider providing the generation based incentives to projects getting inter-connected to 11 KV system in the state.

ROOF TOP SOLAR PV PROJECT FOR THE CITY OF SAS NAGAR MOHALI , PUNJAB
SAS Nagar is a planned city of the State of Punjab adjoining Chandigarh and population in 2006 was about 2 Lacs Distributed utility Solar PV grid connected Project With Proposed project capacity : 5 MWp Roof tops of houses proposed to be covered : 5000 Nos approx. Each roof top to have 1 KWp spv grid connect system Each House having a connected load of 5 -8 Kwp. Each project shall be Grid connected on 415V LT utility Grid Facility of Bidirectional Import export energy meters. Nett Energy Metering concept to be deployed. Solar energy generated from the roof top systems project should be given CERC tariff.

ROOF TOP SOLAR PV SYSTEM CONCEPT AND PLAN


ROOF TOP SOLAR PV SYSTEM CAPACITY 1 KWp SOLAR PV PANELS 1 KWp POWER CONDITIONING UNIT 1.5 KVA BATTERY BANK: ADEQUATELY SIZED FOR 5 HRS BACK-UP BIDIRECTIONAL ENERGY METER OF O.5 CLASS GRID INTERCONNECTION AT 415V L.T. POWER GENERATED FROM THE PV SYSTEM SHALL BE USED BY THE HOUSE IN CASE LOAD EXCEEDS GENERATION POWER SHALL BE EXPORTED TO GRID DURING NO LOAD/LESS LOAD CONDITIONS POWER GENERATED SHALL ALSO PROVIDE BACK-UP POWER TO EMERGENCY LOADS DURING GRID FAILURE FOR WHICH A BATTERY BANK IS ALSO THERE.

ROOF TOP SPV SYSTEMSYSTEMBENEFITS


COMPLETE SYSTEM OF 5 MWp SHALL OPERATE AS A SMALL DISTRIBUTED UTILITY HAVING MAJOR BENEFITS: SYSTEM SHALL USE EXISTING ROOF TOP SPACE SHALL PROVIDE MAJOR VOLTAGE SUPPORT TO THE GRID. SHALL PROVIDE IMMEDIATE RELIEF TO THE GRID BY EXCESS GENERATION DURING DAY TIME. SHALL PROVIDE EMERGENCY POWER RELIEF DURING POWER SHUTDOWN SITUATIONS. SHALL LOWER THE LOAD ON THE L.T. SYSTEM.

ROOF TOP SPV SYSTEMSYSTEMCOMMERCIALS


EACH 1 KWp SYSTEM TO COST 2.5 LACS APPROX. PROPOSAL -1 EACH BENEFICIARY TO PAY 50% OF THE COST, BALANCE COST BY MNRE, GOI. UTILITY TO GIVE CREDIT FOR GENERATION EXPORTED TO THE GRID AT CERC TARIFF. CONSUMER TO BE BILLED FOR NET ENERGY AT REGULAR UTILITY TARIFF. UTILITY TO GET COMPENSATION THROUGH GBI UNDER SOLAR MISSION. PROPOSAL-2 EACH BENEFICIARY TO PAY 100% OF PROPOSALTHE COST, ENTIRE GENERATION TO BE ALLOWED FOR BILLING AT CERC TARIFF.

SOLAR PV POWER PROJECTS


PUNJAB SOLAR RPO @ 0.25% = 100 MU=67MW CAPACITY GOOD SOLAR INSOLATION LEVELS OF 4 -7Kwh/sq mtr/day. 4mtr/day. GRID INTERCONNECTION AT 11 KV/66KV PEDA, THE STATE NODAL AGENCY SHALL PROVIDE COMPLETE FACILITATION FOR PROJECTS. PROJECT DEVELOPERS CAN INVEST AND SET UP PROJECTS IN THE STATE. LAND AVAILABLE ON LEASE FROM VILLAGE PANCHAYATS. BANKABLE/SECURED POWER PURCHASE AGREEMENTS WITH PSEB. VARIOUS INCENTIVES UNDER THE NRSE POLICY -2006. POLICYROOFTOPS OF HOUSES IN VILLAGES UNDER A CLUSTER APPROACH CAN BE PROVIDED TO PVT. DEVELOPERS FOR SETTING UP OF ROOFTOP PV PROJECTS.

Further details regarding Govt. Policies / Projects / Programmes being undertaken by PEDA, can be accessed from our official website http://peda.gov.in OR
CONTACT Chief Executive, Director, Jt. Director, PEDA Phone nos 0172-2663392,2664402, 2667005 0172-