You are on page 1of 24

AL REYAMI ELECTROMECHANICAL

METHOD OF STATEMENT
MECHANICAL
WORKS

2009

DUBAI

CONTENTS
M - 01 M - 02 M - 03 M - 04 M 05 M - 06 M 07 Method of Statement Method of Statement Method of Statement Method of Statement Method of Statement Method of Statement Method of Statement Under ground drainage Installation of high level drainage Installation of water supply line at High level Installation of water supply line at High level Installation of Ducting Installation of copper piping for FAHU Installation of copper piping for Decorative unit Installation of Booster pump Installation of Transfer pump Installation of Submersible pump Installation of Fire pump

M - 08 M - 09 M - 10 M - 11

Method of Statement Method of Statement Method of Statement Method of Statement

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M 01

UNDER GROUND DRAINAGE PIPE WORK


1.0 2.0 3.0 Purpose To define the method of installation of underground pipe work. Scope This method is applicable for drainage pipe work below ground. Method 3.1 Preparation Work 3.1.1 Check the trench route to be made to ensure that the pipes to be installed are as indicated on approved construction drawings. 3.1.2 Check the materials to be used are as per the approved make. 3.1.3 Levelling of ground before excavation to be done by the main contractor. 3.1.4 Excavate the trench as per the route marked on approved drawing. The trench bed must be compacted smooth and must be free from foreign particles 3.1.5 Check whether the inside portion of pipe is properly cleaned before installation / fit up. 3.1.6 Place concrete blocks at standard distance to support the pipes. 3.1.7 Lay the pipes as per the invert levels & slope mentioned in the approved layout with proper supports, using the water level & measuring tape with respect to the benchmark level. 3.1.8 Inspection of pipe work and levels to be checked.

3.1.9 Tangent Glue is applied on the pipe after cleaning it and abrading the surface to roughness using sand paper and left for few minutes to dry it. 3.1.10 Inspect the pipe work for leakage by gravity leakage test. (by Consultant) AL REYAMI ELECTROMECHANICAL Page 2

3.1.11 Make bedding up to the bottom level of the pipe with aggregate and compact properly. 3.1.12 Cover the pipe (up to top level) with aggregate as per standards. 4.0 Reference documents 4.1 5.0 Approved shop drawings. the

Inspection and Measuring Equipment Used 5.1 Spirit level. 5.2 Water level. 5.3 Measuring tape

6.0

Safety 6.1.1 Safety equipment (example Hard hats, Safety shoes, Coverall gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M 02

INSTALLATION OF PIPE WORK AT HIGH LEVEL ( DRAINAGE )


1.0 2.0 Purpose This method of statement is to define the installation of Pipe work at high level. Scope This method of statement is applicable for installation of Pipe works at high level for drainage pipe works. Installation Procedure 3.1.1 Installation of pipes 3.1.2 Mark out the location of hanger thread rods for pipe installation as per the approved construction drawing. 3.1.3 Drill the marked position for hangers and supports by using the drill bit of appropriate size. 3.1.4 Fix the unfix anchor at drilled position by gentle and uniformly hammering. 3.1.5 Fix the threaded rod of 6mm diameter appropriate size & length in the anchor by twisting by turning. 3.1.6 After fixing the threaded rod, insert a 6mm diameter washer of appropriate size in to the rod. 3.1.7 Finally fix the washer near to the slab by tightening a nut over it, this will improve the strength and load bearing capacity of threaded rod. 3.1.8 After cutting the pipes in the required length, both ends should be chamfered properly to remove the unevenness and surface is made rough using sand paper for length of 3 cm (approx) for good adhesive surface preperations. 3.1.9 Install the pipe in position as per the approved layout and make the end connection of pipes as standard specification for each service.

3.0

3.1.10 After completion of pipe end connection, fix / tight the support clamps properly to make the pipe straight and level as per the layout. AL REYAMI ELECTROMECHANICAL Page 2

3.1.11 Check the levels of pipe work with spirit levels and measuring tape. 3.1.12 Pressure test and final inspection of the pipe work (by Consultant) as per the testing philosophy ref. 4.0 Reference Documents 4.1 5.0 Shop Drawings

Inspection and Measuring Equipment Used 5.1 5.2 5.3 Pressure gauge Level gauge / Spirit level. Measuring tape

6.0

Equipment Required 6.1 6.2 6.3 6.4 Electric Drill Machine Grinder Electric Cutting Machine Pressure test pump.

7.0

Safety Safety equipment (example Hard hats, Safety shoes, Coverall Gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M 03

INSTALLATION OF PIPE WORK AT HIGH LEVEL ( WATER SUPPLY)


3.0 4.0 Purpose This method of statement is to define the installation of Pipe work at high level. Scope This method of statement is applicable for installation of Pipe works at high level for water supply pipe works. Installation Procedure 3.1.1 Installation of pipes 3.1.13 Mark out the location of hanger thread rods for pipe installation as per the approved construction drawing. 3.1.14 Drill the marked position for hangers and supports by using the drill bit of appropriate size. 3.1.15 Fix the unfix anchor at drilled position by gentle and uniformly hammering. 3.1.16 Fix the threaded rod of 6mm diameter appropriate size & length in the anchor by twisting by turning. 3.1.17 After fixing the threaded rod, insert a 6mm diameter washer of appropriate size in to the rod. 3.1.18 Finally fix the washer near to the slab by tightening a nut over it, this will improve the strength and load bearing capacity of threaded rod. 3.1.19 After cutting the pipes in the required length, both ends should be chamfered properly to remove the unevenness and surface is made rough using sand paper for length of 3 cm (approx) for good adhesive surface preparations. 3.1.20 Install the pipe in position as per the approved layout and make the end connection of pipes as standard specification for each service. 3.1.21 After completion of pipe end connection, fix / tight the support clamps properly to make the pipe straight and level as per the layout. AL REYAMI ELECTROMECHANICAL Page 2

3.0

3.1.22 Check the levels of pipe work with spirit levels and measuring tape. 3.1.23 Flow and Leakage test and final inspection of the pipe work (by Consultant) as per the testing philosophy ref. 4.0 Reference Documents 4.1 5.0 Shop Drawings

Inspection and Measuring Equipment Used 5.1 5.2 5.3 Pressure gauge Level gauge / Spirit level. Measuring tape

6.0

Equipment Required 6.1 6.2 6.3 6.4 Electric Drill Machine Grinder Electric Cutting Machine Pressure test pump.

8.0

Safety Safety equipment (example Hard hats, Safety shoes, Coverall Gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M 04

INSTALLATION OF PIPE WORK AT HIGH LEVEL ( FIRE FIGHTING)


5.0 6.0 Purpose This method of statement is to define the installation of Pipe work at high level. Scope This method of statement is applicable for installation of Pipe works at high level for fire fighting pipe works. Installation Procedure 3.1 Installation of pipes 3.1.2 Mark out the location of hanger thread rods for pipe installation as per the approved construction drawing. 3.1.3 Drill the marked position for hangers and supports by using the drill bit of appropriate size. 3.1.4 Fix the unfix anchor at drilled position by gentle and uniformly hammering. 3.1.5 Fix the threaded rod of 6mm diameter appropriate size & length in the anchor by twisting by turning. 3.1.6 After fixing the threaded rod, insert a 6mm diameter washer of appropriate size in to the rod. 3.1.7 Finally fix the washer near to the slab by tightening a nut over it, this will improve the strength and load bearing capacity of threaded rod. 3.1.8 After cutting the pipes to the required length, if the diameter of the pipe is less than 2.5 inch both ends should be threaded by using a threading machine and for pipe diameter above 2.5 inch the pipes are groove cut to the required depth as per the installation specification. 3.1.9 The pipes are connected to each other using a grooved coupler as per the standard pipe installation procedure.

3.0

AL REYAMI ELECTROMECHANICAL

Page 2

3.1.10 After completion of pipe end connection, fix / tight the support clamps properly to make the pipe straight and level as per the layout. 3.1.11 Check the levels of pipe work with spirit levels and measuring tape. 3.1.12 Flow and Leakage test and final inspection of the pipe work (by Consultant) as per the testing philosophy ref. 4.0 Reference Documents 4.1 5.0 Shop Drawings

Inspection and Measuring Equipment Used 5.1 5.2 5.3 Pressure gauge Level gauge / Spirit level. Measuring tape

6.0

Equipment Required 6.1 6.2 6.3 6.4 6.5 Electric Drill Machine Threading Machine Electric Cutting Machine Pressure test pump. Grooving Machine

9.0

Safety Safety equipment (example Hard hats, Safety shoes, Coverall Gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M - 05

INSTALLATION OF DUCTING
1.0 2.0 3.0 Purpose To define the method of installation of Ducting. Scope This method is applicable for Ducting. Installation Procedure 3.1 Installation procedure 3.1.1 Fabrication of ductwork will be as per DW142/ASHRAE Standard , using pre-insulated material of applied make. 3.1.2 Mark out the location of hanger thread rods for duct installation as per the approved construction drawing. 3.1.3 Drill the marked position for hangers and supports by using the drill bit of appropriate size. 3.1.4 Fix the unfix anchor at drilled position by gentle and uniform hammering. 3.1.5 Fix the threaded rod of 6mm diameter & length in the anchor by twisting. 3.1.6 After fixing the threaded rod of 6mm diameter, insert a washer of appropriate size in to the rod. 3.1.7 Finally fix the washer near to the slab by tightening a nut over it, this will improve the strength and load bearing capacity of threaded rod. 3.1.8 Fix all the duct pieces from the mouth of the unit 3.1.9 Joint all the ducts using flanges or cleats and corners. 3.1.10 Install the VCDs as per the approved drawings. 3.1.11 Insulate the ducts using Fibre Glass wool if it is a GI duct. AL REYAMI ELECTROMECHANICAL Page 2

3.1.12 Dip the canvas cloths in Foster and fostering all the ducts in case of GI duct

4.0

Inspection and Measuring Equipment Used 4.1 Measuring tape, Sheet cutter, and adjuster.

5.0

Safety 5.1.1 Safety equipment (example Hard hats, Safety shoes, Coverall gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M - 06

INSTALLATION OF COPPER PIPPING FOR FAHU


1.0 2.0 3.0 Purpose To define the method of installation of Copper piping Scope This method is applicable for installation of Copper piping and DX-AHU. Method 3.1 3.2 3.3 3.4 3.5 3.6 Check the plinth for AHU is of required size. Mark out the exact location of AHU Units on plinth. Fix the Vibration isolators (RIBBED RUBBER PADS) for AHU on Plinth. Place the AHU on the Vibration isolator. Hang the condenser unit with proper supports Install the Copper pipes from AHU to Condenser Units as per the approved layout using flare nuts as brazing as per the unit specification and manufacturers recommendation. Expansion valve, sight glass Dryer and filter are installed on liquid line Control valve and sight glass are installed on suction line. Braze the joints as per the standard specification Pressure testing and flushing to be carried out prior to vacuum suction.

3.7 3.8 3.8 3.9

3.10 Vacuuming to be carried out using vacuum pump. 3.11 R-22 gas to be charged referring to charging chart as per the manufacturers recommendation. 3.12 Insulation is wrapped around the copper piping and further wrapped with 6oz cloth and Childers. AL REYAMI ELECTROMECHANICAL

Page 2

4.0

Reference documents 4.1 Approved Drawings.

5.0

Inspection and Measuring Equipment Used 4.2 Pressure Gauge, Brazing set, pipe cutter and pipe bender.

6.0

Safety 6.1 Safety equipment (example Hard hats, Safety shoes, Coverall, gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M - 07

INSTALLATION OF COPPER PIPPING FOR DECORATIVE UNIT


1.0 2.0 Purpose To define the method of installation of Copper piping Scope This method is applicable for installation of Copper piping for decorative wall mounted unit. Method 3.1 Check the plinth for the outdoor unit is of required size. 3.2 Mark out the exact location of outdoor Units on plinth. 3.3 Fix the Vibration isolators (RIBBED RUBBER PADS) for outdoor on Plinth.. 3.4 Place the outdoor unit on the Vibration isolator. 3.5 Hang the indoor unit with proper supports 3.6 Install the Copper pipes from the Condenser Units as per the approved layout using flare nuts and brazing as per the unit specification and manufacturers recommendation. 3.7 Braze the joints as per the standard specification 3.8 Pressure testing and flushing to be carried out prior to vacuum suction. 3.9 Vacuuming to be carried out using vacuum pump. 3.10 R-22 gas to be charged referring to charging chart as per the Manufacturers recomendation 3.13 Insulation is wrapped around the copper piping and further wrapped with 6oz cloth and Childers.

3.0

AL REYAMI ELECTROMECHANICAL

Page 2

4.0

Reference documents 4.1 Approved Drawings.

5.0

Inspection and Measuring Equipment Used 4.3 Pressure Gauge, Brazing set, pipe cutter and pipe bender.

6.0

Safety 6.1 Safety equipment (example Hard hats, Safety shoes, Coverall, gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M - 08

INSTALLATION OF BOOSTER PUMP


1.0 2.0 3.0 Purpose To define the method of installation of Booster pump Scope This method is applicable for installation of Booster pump. Method 3.1 Check the plinth for the Booster pump is of required size. 3.2 Booster pump installation works shall be carried out in accordance with the specification. 3.3 Fixing position shall be marked out on the concrete base. 3.4 Rubber pad shall be laid before fixing the pump. 3.5 Pump installation shall be completed according to the manufactures recommendation. 3.6. The size of the suction pipe shall be as per manufactures .recommendation 3.7 Discharge side shall be connected to the water supply network of the building through pressure gauge and isolating valve 3.8 The suction & discharge side of the Pump shall be connected to flexible connector 3.9 Anti-vibration pad shall be fixed to the pump

4.0

Reference documents 4.1 4.2 Approved Drawings. Approved Material Submittal.

AL REYAMI ELECTROMECHANICAL

Page 2

5.0

Inspection and Measuring Equipment Used 4.4 Pressure Gauge, Measuring tape, Spirit level.

6.0

Safety 6.1Safety equipment (example Hard hats, Safety shoes, Coverall, Gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M - 09

INSTALLATION OF TRANSFER PUMP


1.0 2.0 3.0 Purpose To define the method of installation of Transfer pump Scope This method is applicable for installation of transfer pump. Method 3.1 Check the plinth for the transfer pump is of required size. 3.2 Transfer pump installation works shall be carried out in accordance with the specification. 3.3 Fixing position shall be marked out on the concrete base. 3.4 Rubber pad shall be laid before fixing the pump. 3.5 Pump installation shall be completed according to the manufactures recommendation. 3.6 The suction side of the pump shall be connected to foot valve and . Isolating valve with suction pipe. The size of the suction pipe shall be as per manufactures recommendation. 3.7 Discharge side shall be connected to the water supply network of the building through pressure gauge and isolating valve 3.8 The suction & discharge side of the Pump shall be connected to flexible connector 3.9 Anti-vibration pad shall be fixed to the pump

4.0

Reference documents 4.1 4.2 Approved Drawings. Approved Material Submittal. AL REYAMI ELECTROMECHANICAL Page 2

5.0

Inspection and Measuring Equipment Used 4.5 Pressure Gauge, Measuring tape, Spirit level.

6.0

Safety 6.1Safety equipment (example Hard hats, Safety shoes, Coverall, Gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M - 10

INSTALLATION OF SUBMERSIBLE PUMP


1.0 2.0 3.0 Purpose To define the method of installation of submersible pump Scope This method is applicable for installation of submersible pump. Method 3.1 Check the support for the submersible pump is of proper size. 3.2 Submersible pump installation works shall be carried out in accordance with the specification. 3.3 Fixing position shall be marked out on the manhole wall. 3.4 Pump installation shall be completed according to the manufactures recommendation. 3.5 The suction side of the pump shall be connected with alarm switch, Float valve and isolating valve. The pipe size to be as per the pump Manufacturers recommendation. 3.6 Discharge side shall be connected through the pressure chamber To the adjacent manhole

4.0

Reference documents 4.1 4.2 Approved Drawings. Approved Material Submittal.

5.0

Inspection and Measuring Equipment Used 4.6 Pressure Gauge, Measuring tape, Spirit level. AL REYAMI ELECTROMECHANICAL

Page 2

6.0

Safety 6.1Safety equipment (example Hard hats, Safety shoes, Coverall, Gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

METHOD STATEMENT M 11

INSTALLATION OF FIRE HOSE REEL PUMP


1.0 2.0 3.0 Purpose To define the method of installation and operation of fire hose reel pump. Scope This method is applicable for installation and operation of fire hose reel pump. Method 3.1 3.2 3.3 3.4 3.5 Check the foundation is ready as indicated on approved Construction drawing. Check the level of suction pipe line is to be below the level of pump(suction header) Check whether the required piping and valves are installed properly Make sure that electrical panel for the pump is given correct power supply with protection. Load the pump on a strong foundation. Use the expansion bolts to the base frame to the concrete foundation. The surface of the foundation should be smooth and level. Ensure easy access to the unit from all sides for maintenance and services. Pump set is accurately aligned in the factory before dispatch. However it is essential to recheck the alignment at site after fixing pump set on the site. The pump set should be located near to the suction reservoir. Fix the gate valves non return valves vibration protected flexible connector etc and suction discharge manifolds as shown on the dawning. Connect the suction and discharge line to the manifold .check whether all joints are straight. Fix the pressure switch and pressure gauge on the discharge header. AL REYAMI ELECTROMECHANICAL Page 2

3.6

3.7 3.8 3.9 3.10

3.11 3.12

Fill the water in the pump and suction line through the priming valve and remove all the air blocks. Interconnecting wiring between the panel and motor diesel engine pressure switches float switches for dry run protection etc should be done. Panel, motors pressure switches and float switches must be grounded with suitable wires. Do the wiring from electrical supply source to the pump control panel. Do the necessary piping between the fuel tank and diesel tank. After installation has been completed an operational test has to be conducted to ensure the proper operation of the pump set. Keep starting point of electrical pump slightly higher than the starting point of diesel pump. Keep starting point of jockey pump is slightly higher than starting point of electrical pump.

3.13 3.14 3.15 3.16

4.0

Reference documents 4.1 Approved Drawings.

5.0

Inspection and Measuring Equipment Used 5.1 Pressure Gauge. 5.2 Spirit level. 5.3 Mulitimeter

6.0

Safety 6.1 Safety equipment (example Hard hats, Safety shoes, Coverall gloves, Goggles when necessary etc) to be worn all the times.

AL REYAMI ELECTROMECHANICAL

Page 2

You might also like