schedule

23/03/12 6:26 AM

Task

Effort

1) Design plans and specifications


1.1) Design of plans

1w 2d

1.2) Technical specifications

1w 2d

2) Milestone construction schedule

Dependencies

2w 4d
1.1SS

1w 4d

Duration

Start

End

Mar 2012

23/03/12 8:00 AM

30/03/12 3:00 PM

1w 2d

23/03/12 8:00 AM

30/03/12 3:00 PM

Technical office

1w 2d

23/03/12 8:00 AM

30/03/12 3:00 PM

Technical office

1w 1d

30/03/12 3:00 PM

06/04/12 12:00 PM

2.1) WBS

4d

1.2, 1.1

4d

30/03/12 3:00 PM

04/04/12 3:00 PM

2.2) Define resources

3d

1.1

3d

30/03/12 3:00 PM

03/04/12 4:00 PM

2d

2.1

2d

04/04/12 3:00 PM

06/04/12 12:00 PM

03/04/12 4:00 PM

11/04/12 12:00 PM

2.3) Estimate time


3) Cost/Estimate

2w

1w 2d

3.1) Define materials

1d

1.1, 1.2

1d

03/04/12 4:00 PM

04/04/12 3:00 PM

3.2) Estimate quantity of the materials

2d

1.1

2d

04/04/12 3:00 PM

06/04/12 12:00 PM

3.3) Research the cost/unit of the

4d

3.1

4d

06/04/12 12:00 PM

11/04/12 12:00 PM

3.4) Estimate other costs

3d

3.1SS+1d

3d

06/04/12 12:00 PM

10/04/12 2:00 PM

12w 3d 1h

4) Earthwork

04/04/12 3:00 PM

14/06/12 10:00 AM

4.1) Grading

3d

3.1

3d

04/04/12 3:00 PM

07/04/12 11:00 AM

4.2) Excavation

4w

4.1

2w

07/04/12 11:00 AM

19/04/12 9:00 AM

4.3) Filling

3d

5.3.3

1d 4h

08/06/12 11:00 AM

11/06/12 9:00 AM

4.3

3d 4h

11/06/12 9:00 AM

14/06/12 10:00 AM

9w 1h

19/04/12 9:00 AM

08/06/12 11:00 AM

4d 3h

19/04/12 9:00 AM

24/04/12 12:00 PM

27/04/12 9:00 AM

10/05/12 12:00 PM

4.4) Landscape design


5) Concrete structure

6w 3d

1w 2d
9w

5.1) Foundations

1w 2d

5.2) Columns and beams

2w 4d

4.2

2w 1d 6h

5.2.1) 1st floor

1w 2d

5.1+3d

4d 3h

27/04/12 9:00 AM

02/05/12 12:00 PM

5.2.2) 2nd floor

1w 2d

5.2.1+3d

4d 3h

05/05/12 9:00 AM

10/05/12 12:00 PM

4w 3d

14/05/12 2:00 PM

08/06/12 11:00 AM

5.3) Floors

4w 4d

5.3.1) 1st floor

1w 2d

5.2.2+3d

4d 3h

14/05/12 2:00 PM

18/05/12 12:00 PM

5.3.2) 2nd floor

1w 2d

5.3.1+4d

4d 3h

23/05/12 12:00 PM

28/05/12 4:00 PM

2w

5.3.2+4d

1w 1d 2h

01/06/12 11:00 AM

08/06/12 11:00 AM

1w 3d

28/05/12 4:00 PM

06/06/12 11:00 AM

1w 1d

28/05/12 4:00 PM

04/06/12 2:00 PM

1w 1d

28/05/12 4:00 PM

04/06/12 2:00 PM

> 1d 4.25h

28/05/12 4:00 PM

30/05/12 9:18 AM

5.3.3) Roof
6) Elec. and mech. installation
6.1) Elec. installations
6.1.1) Electric systems
6.1.2) Power generators
6.2) Mech. installations

4w 4d
2w
1w 1d
4d

5.3.2
6.1.1SS

1w 3d

28/05/12 4:00 PM

06/06/12 11:00 AM

6.2.1) HVAC

1w 1d

5.3.2

1w 1d

28/05/12 4:00 PM

04/06/12 2:00 PM

6.2.2) Mechanical parts

1w 3d

6.2.1SS

1w 3d

28/05/12 4:00 PM

06/06/12 11:00 AM

3d

15/06/12 9:00 AM

19/06/12 10:00 AM

7) Final product

2w 4d

3d

7.1) Testing

2d

6.1.1+1d,

2d

15/06/12 9:00 AM

18/06/12 11:00 AM

7.2) Start of operation

1d

7.1

1d

18/06/12 11:00 AM

19/06/12 10:00 AM

23/03/12 8:00 AM

15/06/12 3:00 PM

8) Control and checking of tasks

15w 6h

/Users/Master/Documents/Project Management/X470/Assignments/schedule.omniplan

Apr 2012

1w 2d

15w 6h

May 2012

Jun 2012

Jul 20

Technical office
Technical office
Technical office
Technical office
Technical office
Technical office
Technical office
Grader
Dozer; Excavator
Loader; Grader
Grader; Loader
Skilled workers team; Unskilled workers team {60% of 60%}
Skilled workers team; Unskilled workers team {60% of 60%}
Skilled workers team; Unskilled workers team {60% of 60%}
Skilled workers team; Unskilled workers team {60% of 60%}
Skilled workers team; Unskilled workers team {60% of 60%}
Skilled workers team; Unskilled workers team {60% of 60%}

Electrical technician
Skilled workers team; Unskilled workers team {60% of 60%}; Electrical technician
Mechanical technician
Mechanical technician

Technical office