You are on page 1of 5

M/s.

GHV (INDIA) PVT LTD


Project Name :
MHOW - NEEMUCH
Contractor :
Sub Contractor :
Calibration of Batching Plant
CBP 300
Plant ID No.:FBPB
M/c. Sr. No. 110018
Next Calibaration Due : SIX MONTH LATER
Result : OK
Calibration of Aggregate Weighing Scale in Kg.
Standard
Sr. No. Weight in Kg.
(A)

Actual Weight
in Kg.
(B)

Varaition in %
( B-A )/A*100

Standard
Weight in Kg.
(D)

1
0
0
0
2
20
20
0
3
40
40
0
4
60
60
0
5
80
79
-1.25
6
100
100
0
7
120
120
0
8
140
140
0
9
160
160
0
10
180
180
0
11
200
200
0
12
220
220
0
13
240
240
0
14
260
260
0
15
280
280
0
16
300
300
0
17
320
320
0
18
340
340
0
19
360
360
0
20
380
380
0
21
400
400
0
22
420
420
0
23
440
441
0.23
24
460
461
0.22
25
480
480
0
26
500
501
0.2
27
28
29
30
31
32
33
34
35
36
37
38
39
40
Average Variation = sum of total percentage variation/ no of readings
-0.82
Sub Contractor
Contractor

500
480
460
440
420
400
380
360
340
320
300
280
260
240
220
200
180
160
140
120
100
80
60
40
20
0

Client :

PMC :

Calibration Date : 24-09-11


YES

Actual Weight
during
Variation in % ( CRemark
Unloading in Kg. D )/D*100
(C )
501
481
461
441
421
401
381
361
341
320
300
280
260
240
220
200
180
160
140
120
100
80
59
39
19
-1

0.2
0.21
0.22
0.23
0.24
0.25
0.26
0.28
0.29
0
0
0
0
0
0
Plus or minus 3%
0
as per IS 4926
0
2003 clause 9.1.3
0
0
0
0
0
-1.67
-2.5
-5

Service Engineer

M/s. GHV (INDIA) PVT LTD


Project Name :
MHOW - NEEMUCH
Contractor :
Sub Contractor :
Calibration of Batching Plant
CBP 300
Plant ID No.:FBPB
M/c. Sr. No.110018
Next Calibaration Due : SIX MONTH LATER

Sr. No.

Client :

Calibration Date : 24-09-11


Result : OK
YES

Calibration of Cement Weighing Scale in Kg.


Standard Actual Varaition Standard Actual Variation
Weight in Weight in in % ( B- Weight in Weight
in % ( CKg. (A)
Kg.
A )/A*100 Kg. (D)
during D)/D*100
(B)
Unloading
in Kg. (C )

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300

0
20
41
60
82
100
118
141
158
182
200

221
242
260
280
300

0
0
2.4
0
2.5
0
-1.67
0.71
-1.25
1.11
0
0.45
0.83
0
0
0

PMC :

0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300

0
21
38
59
80
98
119
139
159
179
199

Remark

0
5
-5
-1.67
0
-2 Plus or
-0.83 minus 2%
-0.71 as per IS
-0.63 4926 2003
-0.56 clause
9.1.3
-0.5
-0.45
-0.42
0
0.71
0

219
239
260
282
300

Average Variation = sum of total percentage variation/ no of readings


-0.062
Sub Contractor

Contractor

Service Engineer

M/s. GHV (INDIA) PVT LTD


Project Name :
MHOW -NEEMUCH
Contractor :
Sub Contractor :
Calibration of Batching Plant
CBP 300
Plant ID No.: FBPB
M/c. Sr. No. 110018
Next Calibaration Due : SIX MONTH LATER

Sr. No.

Client :

Calibration Date :24-09-11


Result : OK
YES

Calibration of Water Weighing Scale in Kg.


Standard Actual Varaition Standard Actual Variation
Weight in Weight in in % ( B- Weight in Weight
in % ( CKg. (A)
Kg.
A )/A*100 Kg. (D)
during D)/D*100
(B)
Unloading
in Kg. (C )

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21

0
20
40
60
80
100
120
140
160
180
200

0
21
40
60
81
100
121
141
161
180
201

5.00
0.00
0.00
1.25
0.00
0.83
0.71
0.63
0.00
0.50

PMC :

0
20
40
60
80
100
120
140
160
180
200

0.0
5.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.5

0
21
40
60
80
100
120
140
160
180
201

Remark

Plus or
minus 2%
as per IS
4926 2003
clause
9.1.3

Average Variation = sum of total percentage variation/ no of readings


0.66

Sub Contractor

Contractor

Service Engineer

M/s. GHV (INDIA) PVT LTD


Project Name :
Mhow -Neemuch
Contractor :
Sub Contractor :
Calibration of Batching Plant
Plant ID No.:FBPB
M/c. Sr. No. 110018
Next Calibaration Due : SIX MONTH LATER

Sr. No.

Client :

PMC :

Calibration Date : 24-09-11


Result : OK
YES

Calibration of Admixture Scale in gm.


Standard Actual Varaition Standard Actual Variation
Weight in Weight in in % ( B- Weight in Weight in % ( C-D
kg. (A)
kg.
A )/A*100 Kg. (D)
during
)/D*100
(B)
Unloading
in kg. (C )

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

1
2
3
4
4.5

1.02
1.96
2.99
4.04
4.52

2
2
0.33
1
0.44

1
2
3
4
4.5

1.02
1.98
3
4.05
4.52

Remark

2
1
0
1.25
0.44
Plus or minus 2% as per
IS 4926 2003 clause
9.1.3

Average Variation = sum of total percentage variation/ no of readings


1.046

Sub Contractor

Contractor

Service Engineer

admixture