You are on page 1of 2

IT Department and Data Center Preparation

Q1
SCOPE OF WORK
Company Name (Price )
Civil Construction work
· Removal of existing walls in Meeting Room and IT Manager Room [wall-A] - (Reffer FFP Data Center Exsisting Drawing)
· Removal of Existing Data Center Half Wall [wall-B] - (Reffer FFP Data Center Exsisting Drawing)
· Creating separate partition wall with necessary windows which removing from the above mention rooms and data center as per the
drawing (wall-C) - (Reffer FFP Data Center Propose Drawing)
· Installation of new fully tempered glass (12 mm thick) wall with Company Logo for the New Server Room win 80 cm fully glass
sliding door [wall-D & SD1] - (Reffer FFP Data Center Propose Drawing)
· Installation of new fully tempered glass (12 mm thick) with Company Logo, meeting room as per drawing win 80 cm fully glass
sliding door [wall-E & SD2] - (Reffer FFP Data Center Propose Drawing)
· Fixing of a removed existing door as a IT department door as per drawing [D1] - (Reffer FFP Data Center Propose Drawing)
· Installation of aluminum wall cladding inside the server room inner walls as per drawing [wall-F] - (Reffer FFP Data Center
Propose Drawing)
· Installation of raise floor for the new complete Data Center
· Installation of aluminum strips ceiling in the New Data center
· Re arranges or new installation of the ceiling in the removed data center area and complete IT Department Ceiling

Fire System
· Redesign and install necessary fire protection system to the Data Center [CFC 227ea [FM200] and use existing fire protection
equipment to minimize the cost]

Cabling and Data Center Rearrangement


· Removing the server cabinets with servers and relocate them to the new locations
· Rearrange all power modifications and cable re-arrangements

Lighting
· Primary lighting system re-arrange or adding more light outlets to the new Data Center
· Installation of necessary emergency lightings to the Data Center

Cooling System
· Relocate the air condition ducting from existing data center to the new Data Center
· Preparation of necessary Backup Cooling System or rearrange the existing Split AC Unit
· Installation of Dehumidifier
artment and Data Center Preparation
Q2
Company Name (Price )

You might also like