PLANT STARTUP TIMELINE

(Based on Gas Availability at 1200 hrs on Apr 9th) 8-Apr-2011


MILESTONES TIME (hrs) DATE REMARKS
ID Fan Startup 0800 9-Apr
F-201 Furnace Purge & Leak Test 1200 9-Apr
aMDEA Circulation 1600 9-Apr

Furnace Firing & Steam Introduction @ 400 C Arch Temperature 0600 10-Apr

Feed-In 0800 10-Apr


Air Compressor Startup 1400 10-Apr
Air Introduction 1800 10-Apr
LTS lineup 0000 11-Apr
Gas Introduction to aMDEA 0200 11-Apr
On-spec CO2 availability 0400 11-Apr
Methanator Lin-up 0800 11-Apr
Refrig Compressor Startup 1000 11-Apr
Syn Startup (at Minimum Governor) 1600 11-Apr
Syn Compressor Extraction Control Testing 2000 11-Apr
Converter Heat up & Ammonia Production 1000 12-Apr
CO2 Compressor Startup 1400 12-Apr
CO2 Compressor Extraction Control Testing 1800 12-Apr
Urea Ammonization 0000 13-Apr
Urea Feed-in 0100 13-Apr
Urea Prilling 0500 13-Apr