You are on page 1of 6

HARGA HARGA JUMLAH

SATUAN UPAH BAHAN HARGA


Rp. Rp. Rp. Rp.
1 M1 Pekerjaan Bouwplank
0.005 M3 Kayu Papan Kls. III 1,350,000.00 - 6,750.00
0.005 M3 Kayu Balok Kls III 1,050,000.00 - 5,250.00
0.020 Kg Paku 15,000.00 - 300.00
0.125 Hr Tukang 45,000.00 5,625.00 -
0.005 Hr Kepala Tukang 47,500.00 237.50 -
0.075 Hr Pekerja 35,000.00 2,625.00 -
0.015 Hr Mandor 55,000.00 825.00 -
9,312.50 12,300.00 21,612.50

1 M3 Galian Tanah Biasa


0.750 Hr Pekerja 35,000.00 26,250.00 -
0.040 Hr Mandor 55,000.00 2,200.00 -
28,450.00 - 28,450.00

1 M3 Timbunan Sub Base Kembali Dipadatkan


1.200 M3 Sub Base 100,000.00 - 120,000.00
1.000 Ls Pemadatan 8,500.00
1.000 Ls Angkutan 10,000.00 - 10,000.00
0.150 Hr Pekerja 35,000.00 5,250.00 -
0.018 Hr Mandor 55,000.00 990.00 -
6,240.00 130,000.00 136,240.00

1 M3 Urugan Tanah Kembali Dipadatkan


1.000 Ls Pemadatan 3,000.00 - 3,000.00
1.000 Ls Angkutan 9,000.00 - 9,000.00
0.400 Hr Pekerja 35,000.00 14,000.00 -
0.025 Hr Mandor 55,000.00 1,375.00 -
15,375.00 12,000.00 27,375.00

1 M3 Urugan Pasir
1.200 M3 pasir Urug 90,000.00 - 108,000.00
0.300 Hr Pekerja 35,000.00 10,500.00 -
0.037 Hr Mandor 55,000.00 2,035.00 -
12,535.00 108,000.00 120,535.00

1 M3 Pasang batu belah 1:4


1.100 M3 Batu belah 185,000.00 - 203,500.00
3.100 Zak Semen @ 50 Kg 54,000.00 - 167,400.00
0.523 M3 Pasir Pasang 132,500.00 - 69,300.15
0.900 Hr Tukang 45,000.00 40,500.00 -
0.120 Hr Kepala Tukang 47,500.00 5,700.00 -
2.900 Hr Pekerja 35,000.00 101,500.00 -
0.180 Hr Mandor 55,000.00 9,900.00 -
157,600.00 440,200.15 597,800.15

1 M2 Pasang dinding bata 1:4


95.000 Bh Batu bata 370.00 - 35,150.00
0.250 Zak Semen @ 50 Kg 54,000.00 - 13,500.00
0.075 M3 Pasir Pasang 132,500.00 - 9,937.50
0.325 Hr Tukang 45,000.00 14,625.00 -
0.025 Hr Kepala Tukang 47,500.00 1,187.50 -
0.400 Hr Pekerja 35,000.00 14,000.00 -
0.015 Hr Mandor 55,000.00 825.00 -
30,637.50 58,587.50 89,225.00

1 M' Pekerjaan Plester + Acian Atas Bak Makan


0.300 Zak Semen @ 50 Kg 54,000.00 - 16,200.00
0.012 M3 Pasir Pasang 132,500.00 - 1,625.00
0.300 Hr Tukang 45,000.00 13,500.00 -
0.030 Hr Kepala Tukang 47,500.00 1,425.00 -
0.020 Hr Pekerja 35,000.00 700.00 -
0.010 Hr Mandor 55,000.00 550.00 -
16,175.00 17,825.00 34,000.00

1 M' Pekerjaan Acian Dalam Bak Makan


0.168 Zak Semen @ 50 Kg 54,000.00 - 9,075.00
0.150 Hr Tukang 45,000.00 6,750.00 -
0.030 Hr Kepala Tukang 47,500.00 1,425.00 -
0.020 Hr Pekerja 35,000.00 700.00 -
0.010 Hr Mandor 55,000.00 550.00 -
9,425.00 9,075.00 18,500.00

10 M' Saluran Pipa Air Minum Pipa PVC 3"


10.000 M' Pipa PVC 3/4" 30,000.00 - 300,000.00
1.000 Ls Alat Bantu & Accessories 15,000.00 - 15,000.00
3.750 Hr Tukang 45,000.00 168,750.00 -
0.375 Hr Kepala tukang 47,500.00 17,812.50 -
0.250 Hr Pekerja 35,000.00 8,750.00 -
0.110 Hr Mandor 55,000.00 6,050.00 -
201,362.50 315,000.00 516,362.50
Unt 1 M' = 0.1 x Anl. 51,636.25
10 M' Saluran Pipa Air Minum Pipa PVC 3/4"
10.000 M' Pipa PVC 3/4" 10,000.00 - 100,000.00
1.000 Ls Alat Bantu & Accessories 2,500.00 - 2,500.00
3.750 Hr Tukang 45,000.00 168,750.00 -
0.375 Hr Kepala tukang 47,500.00 17,812.50 -
0.250 Hr Pekerja 35,000.00 8,750.00 -
0.110 Hr Mandor 55,000.00 6,050.00 -
201,362.50 102,500.00 303,862.50
Unt 1 M' = 0.1 x Anl. 30,386.25

1 M2 Begisting / Cetakan Beton


0.003 M3 Kayu Kls. III 1,350,000.00 - 4,050.00
0.400 Lbr Block board 18 mm 200,000.00 - 80,000.00
0.100 Kg Paku 15,000.00 - 1,500.00
0.250 Hr Tukang 45,000.00 11,250.00 -
0.300 Hr Kepala Tukang 47,500.00 14,250.00 -
0.150 Hr Pekerja 35,000.00 5,250.00 -
0.010 Hr Mandor 55,000.00 550.00 -
31,300.00 85,550.00 116,850.00
Dihitung 58 % 66,855.73

1 Kg Pembesian (Besi Beton / Sleeve)


1.050 Kg Besi Beton 7,700.00 - 8,085.00
0.095 Kg Kawat Beton 14,000.00 - 1,330.00
1.000 Ls Peralatan 64.50 - 64.50
0.025 Hr Tukang 45,000.00 1,125.00 -
0.006 Hr Kepala Tukang 47,500.00 285.00 -
0.012 Hr Pekerja 35,000.00 420.00 -
0.005 Hr Mandor 55,000.00 275.00 -
2,105.00 9,479.50 11,584.50

1 M2 Pembesian (Besi BRC)


1.050 m2 Besi BRC 28,500.00 - 29,925.00
1.000 Ls Alat Bantu 2,060.00 - 2,060.00
0.100 Hr Tukang 45,000.00 4,500.00 -
0.020 Hr Kepala Tukang 47,500.00 950.00 -
0.025 Hr Pekerja 35,000.00 875.00 -
0.002 Hr Mandor 55,000.00 110.00 -
6,435.00 31,985.00 38,420.00

1 M3 Beton K.100
0.880 M3 Split 240,000.00 - 211,200.00
0.540 M3 pasir Cor 137,500.00 - 74,250.00
4.000 Zak Semen @ 50 Kg 54,000.00 - 216,000.00
1.000 Ls Peralatan 830.00 - 830.00
1.000 Hr Tukang 45,000.00 45,000.00 -
0.100 Hr Kepala Tukang 47,500.00 4,750.00 -
3.750 Hr Pekerja 35,000.00 131,250.00 -
0.144 Hr Mandor 55,000.00 7,920.00 -
188,920.00 502,280.00 691,200.00

1 M3 Beton K.225
0.875 M3 Split 240,000.00 - 210,000.00
0.625 M3 pasir Cor 137,500.00 - 85,937.50
6.200 Zak Semen @ 50 Kg 54,000.00 - 334,800.00
1.000 Ls Peralatan 3,592.50 - 3,592.50
1.100 Hr Tukang 45,000.00 49,500.00 -
0.200 Hr Kepala Tukang 47,500.00 9,500.00 -
3.429 Hr Pekerja 35,000.00 120,000.00 -
0.144 Hr Mandor 55,000.00 7,920.00 -
186,920.00 634,330.00 821,250.00
###
1 M3 Beton K.300
0.700 M3 Split 240,000.00 - 168,000.00
0.620 M3 pasir Cor 137,500.00 - 85,250.00
8.200 Zak Semen @ 50 Kg 54,000.00 - 442,800.00
1.000 Ls Peralatan 3,030.00 - 3,030.00
1.100 Hr Tukang 45,000.00 49,500.00 -
0.200 Hr Kepala Tukang 47,500.00 9,500.00 -
4.200 Hr Pekerja 35,000.00 147,000.00 -
0.144 Hr Mandor 55,000.00 7,920.00 -
213,920.00 699,080.00 913,000.00

1 Kg Kolom Baja IWF / Plat Tapak


1.050 Kg Besi IWF 8,150.00 - 8,557.50
1.000 Ls Asesories & peralatan 200.00 - 200.00
1.000 Ls Las 155.51 - 155.51
0.035 Hr Tukang 45,000.00 1,575.00 -
0.055 Hr Pekerja 35,000.00 1,925.00 -
0.011 Hr Mandor 55,000.00 605.00 -
4,105.00 8,913.01 13,018.01

1 Kg Kuda-kuda Baja Siku L.60.60.6


1.050 Kg Siku 8,250.00 - 8,662.50
1.000 Ls Asesories & peralatan 200.00 - 200.00
1.000 Ls Las 200.00 - 200.00
0.035 Hr Tukang 45,000.00 1,575.00 -
0.059 Hr Pekerja 35,000.00 2,065.00 -
0.011 Hr Mandor 55,000.00 605.00 -
4,245.00 9,062.50 13,307.50
1 Kg Pekerjaan Gording Baja CNP
1.035 Kg Besi CNP 8,850.00 - 9,159.75
1.000 Ls Asesories & peralatan 450.00 - 450.00
1.000 Ls Las 100.00 - 100.00
0.025 Hr Tukang 45,000.00 1,125.00 -
0.050 Hr Pekerja 35,000.00 1,750.00 -
0.010 Hr Mandor 55,000.00 550.00 -
3,425.00 9,709.75 13,134.75

10 M' Pipa Besi Tiang Light - A Ø 3" T = 4.05 mm


10.000 M' Pipa Besi Ø 3" t = 4.05 115,000.00 - 1,150,000.00
0.150 Kg Besi Beugel Ø 10 mm 7,700.00 - 1,155.00
1.000 Ls Alat Bantu & Las 1,500.00 - 1,500.00
5.500 Hr Tukang 45,000.00 247,500.00 -
0.550 Hr Kepala tukang 47,500.00 26,125.00 -
2.000 Hr Pekerja 35,000.00 70,000.00 -
0.175 Hr Mandor 55,000.00 9,625.00 -
353,250.00 1,152,655.00 1,505,905.00
a. Untuk 1 M' = 0.1 x Anl. 149,965.70
b. Untuk 1 Kg' = 0.18 x Anl.a 22,494.86

10 M' Pipa Besi Railing SIO Ø 3" T = 2.9 mm


10.000 M' Pipa Besi Ø 3" t = 2.9 90,000.00 - 900,000.00
0.150 Kg Besi Beugel Ø 10 mm 7,700.00 - 1,155.00
1.000 Ls Alat Bantu & Las 1,500.00 - 1,500.00
5.000 Hr Tukang 45,000.00 225,000.00 -
0.500 Hr Kepala tukang 47,500.00 23,750.00 -
1.750 Hr Pekerja 35,000.00 61,250.00 -
0.175 Hr Mandor 55,000.00 9,625.00 -
319,625.00 902,655.00 1,222,280.00
a. Untuk 1 M' = 0.1 x Anl. 119,966.78
b. Untuk 1 Kg' = 0.18 x Anl.a 17,995.02

1 M2 Atap Asbes Gelombang Mini


1.050 M2 Asbes 24,000.00 - 25,200.00
0.289 Bh Paku Asbes 15,000.00 - 4,335.00
0.167 Hr Tukang 45,000.00 7,500.00 -
0.020 Hr Kepala Tukang 47,500.00 950.00 -
0.014 Hr Pekerja 35,000.00 490.00 -
0.010 Hr Mandor 55,000.00 550.00 -
9,490.00 29,535.00 39,025.00

1 M' Nok Asbes


1.100 M' Nok Asbes 22,500.00 - 24,750.00
0.282 Bh Paku Asbes 15,000.00 - 4,225.00
0.167 Hr Tukang 45,000.00 7,500.00 -
0.020 Hr Kepala Tukang 47,500.00 950.00 -
0.015 Hr Pekerja 35,000.00 525.00 -
0.010 Hr Mandor 55,000.00 550.00 -
9,525.00 28,975.00 38,500.00

1 M2 Pekerjaan Pengecatan Besi


0.150 Kg Cat Besi 75,000.00 - 11,250.00
0.150 Kg Meni Besi 35,000.00 - 5,250.00
0.150 Ltr Thinner 7,500.00 - 1,125.00
0.050 Lbr Amplas 3,000.00 - 150.00
1.000 Bh Kuas 17,500.00 - 17,500.00
0.020 Hr Tukang 45,000.00 900.00 -
0.002 Hr Kepala Tukang 47,500.00 109.25 -
0.070 Hr Pekerja 35,000.00 2,450.00 -
0.007 Hr Mandor 55,000.00 385.00 -
a. Untuk 1 M' = 0.1 x Anl. 3,844.25 35,275.00 39,119.25
b. Untuk 1 Kg' = 0.02 x Anl.a 760.00

1 Unit Pek. Pasang Pintu Type 1


25.400 M' Pipa Besi Ø 2.5" 75,000.00 - 1,905,000.00
22.700 M' Pipa Besi Ø 2" 54,000.00 - 1,225,800.00
3.300 Kg Plat Baja t = 8 mm 8,250.00 - 27,225.00
4.000 Bh Baut M 24 65,000.00 - 260,000.00
0.600 M' Pipa Sch. 40 Ø 1" 60,000.00 - 36,000.00
8.620 Kg Besi Beugel Ø 10 mm 7,700.00 - 66,374.00
3.000 M' Rantai Ø 10 mm 45,000.00 - 135,000.00
8.600 Hr Tukang 45,000.00 387,000.00 -
1.750 Hr Kepala Tukang 47,500.00 83,125.00 -
6.200 Hr Pekerja 35,000.00 217,000.00 -
0.088 Hr Mandor 55,000.00 4,840.00 -
691,965.00 3,655,399.00 4,347,364.00

1 Unit Pek. Pasang Pintu Type 2 dan 3


12.700 M' Pipa Besi Ø 2.5" 75,000.00 - 952,500.00
11.350 M' Pipa Besi Ø 2" 54,000.00 - 612,900.00
1.650 Kg Plat Baja t = 8 mm 8,250.00 - 13,612.50
2.000 Bh Baut M 24 65,000.00 - 130,000.00
0.300 M' Pipa Sch. 40 Ø 1" 60,000.00
4.310 Kg Besi Beugel Ø 10 mm 7,700.00
1.500 M' Rantai Ø 10 mm 45,000.00
4.800 Hr Tukang 45,000.00 216,000.00 -
1.200 Hr Kepala Tukang 45,000.00 54,000.00 -
2.490 Hr Pekerja 47,500.00 118,275.00 -
0.073 Hr Mandor 35,000.00 2,555.00 -
390,830.00 1,709,012.50 2,099,842.50
1m2 Pek. Pasang Keramik
1.100 dus keramik 20/20 67,000.00 - 73,700.00
0.240 sak portland semen 54,000.00 - 12,960.00
0.032 m3 Pasir pasang 145,000.00 - 4,640.00
0.018 sak semen putih 95,000.00 - 1,710.00
0.300 hr tukang 45,000.00
0.026 hr kepala tukang 47,500.00
0.500 hr pekerja 35,000.00
0.025 hr mandor 55,000.00 1,375.00 -
1,375.00 93,010.00 94,385.00
harga belum dikonversi ke upah dan bahan ke aceh
masih kemungkinan perubahan .

gambar belum fix


masih perlu perencanaan dan perhitungan di konsultan
apabila gambar telah fix (ok) maka perlu perhitungan
ulang rab

rab dibuat hanya berdasrkan perhitungan global dari proyek proyek yang telah ada
material mengacu ke pabrikator lokal .
harga baja bisa berbeda beda tergantung sfesifikasi yang dipakai

You might also like