Professional Documents
Culture Documents
Question Bank
of
Objective Questions
Northern Railway
Objective Questions Engineering Department
INDEX
1.OBJECTIVE QUESTIONS.....................................................................................................................3
A] FILL IN THE BLANKS: ...............................................................................................................................5
2.OBJECTIVE QUESTIONS ON TRACK MACHINES.......................................................................7
3.OBJECTIVE QUESTIONS P & D,SOD..............................................................................................10
4. LEVEL CROSSINGS............................................................................................................................12
5. QUESTIONNAIRE FOR 70% QUOTA EXAMINATION ..............................................................14
7. TRACK RECORDING.........................................................................................................................16
8.GENERAL MIXED QUESTIONS........................................................................................................20
A] FIND THE CORRECT STATEMENT..............................................................................................20
[...............................................................................................................................................................20
B] FIND THE INCORRECT STATEMENT..........................................................................................21
C] WHAT IS MY NAME.......................................................................................................................22
D] TRUE/ FALSE...................................................................................................................................22
9.WORKS...................................................................................................................................................25
10.WATER SUPPLY & HYDRAULICS..................................................................................................28
11.SOIL MECHANICS & CONSTRUCTION MATERIALS..............................................................29
12.MULTIPLE CHOICE QUESTIONS ON LAND MANAGEMENT:..............................................32
14. ESTABLISHMENT MATTERS AND LABOUR LAWS.................................................................39
Page 2 of 41
Northern Railway
Objective Questions Engineering Department
1.OBJECTIVE QUESTIONS
1) Lubrication of ERC and inserts in corrosion prone areas and platform line is
done once in a ________.
2) Minimum rail section recommended for section having traffic more than
20GMTs is _____.
4) Permanent closure in running lines for locations such as 500 metre length on
both side approaches of tunnels, tunnel proper, major and important bridges
including bridge proper, deep cuttings and high embankments should not be
less than______ in length, between two adjoining fish plates.
i) 1 in 20
ii) 1 in 10
iii) 1 in 15
iv) NIL
i) 6mm
ii) 8mm
iii) 10mm
iv) 12 mm
9) Minimum height above rail level for high passenger platform is _________.
Page 3 of 41
Northern Railway
Objective Questions Engineering Department
13) Permissible wear of web & foot of rail due to corrosion is ________.
14) Service life in terms of total GMT carried for 52 kg. 90 UTS rail is______
i) 5 years
ii) 10 years
iii) 7 years
iv) 6 years.
17) Maximum distance apart of trolley refuges on bridges with main spans of 100metre
or more is
i) 50 mtr
ii) 100 mtr
iii) 200 mtr
iv) a refuge over each pair .
18) Permissible vertical wear for tongue rail of 52kg. lefthand fanshape curved switch is
_____.
i) 50 mm
ii) 100 mm
iii) 125 mm
iv) 150 mm.
20) Maximum distance covered in a day by a Patrolman should not normally exceed
i) 2 km.
ii) 5 km.
iii) 10 km.
iv) 20 km .
21) In case of 52 kg CMS Crossing dimension to be deducted (to account for slope
in casting of wing rail to 1:20 cant) from the observed wear measurements to
find out the actual wear is ______
Answers
1) Year 2) 60 kg 3) 1200 meter 4) 11 meter 5) 30
meter
Page 4 of 41
Northern Railway
Objective Questions Engineering Department
11) 20Kmph 12) 13 mm 13) 1.5 mm 14) 525 GMT 15) ±20
mm
16) 7 years 17) a refuge over each pier 18) 5 mm 19) 150
mm
2. Maximum super elevation for BG, group ‘A’ route under normal conditions is
165 mm.
4. Maximum values of normal cant deficiency prescribed for BG, A & B groups is
75 mm.
6. Minimum depth of ballast cushion below the bottom of sleeper at the rail seat
should be 300 mm on BG group A route.
9. Sleeper density for group ‘A’ route with traffic density more than 20 GMT is
1660 sleepers per kilometer.
10. The permissible speed, for 1 in 8 ½ symmetrical split with curved switch on BG
track, is 30 kmph.
11. Speed in excess of 15 kmph should not be permitted on turn in curves laid with
wooden sleepers.
12. SWR shall not be laid on curves sharper than 500 metres radius in both BG and
MG.
13. The lubrication of ERCs and insert should be done once in a year in corrosion
prone areas and platform lines and once in two years in other areas.
14. For all bridges, in case of LWR track, full ballast section, as specified in LWR
Manual should be provided upto 100 metres from the abutments.
Page 5 of 41
Northern Railway
Objective Questions Engineering Department
15. Flange-way clearance of BG turnouts between running rail and check rail at
nose of crossing is 48 mm (maximum) and 44 mm (minimum).
17. There are special chairs provided behind the heel of switch to give a suitable
ramp to the tongue rail, which is raised by 6 mm at the heel.
Page 6 of 41
Northern Railway
Objective Questions Engineering Department
(2) How many on On-Track track machines can work in a block section at a
time as per subsidiary rule?
(4) What shall be the minimum safe distance between track machines when
moving in the block section in convey?
(5) As per IRTMM, the auxiliary track for PQRS working can be higher than
the existing track by not more than:
(A) 40 mm (B) 50 mm
(C) 25 mm (D) 10 mm
(6) The size of wooden battens for loading PSC sleepers on special BFRs for
TRT working shall be
(A) 50 mm X 50 mm (B) 75 mm X 75 mm
(7) Maintenance tamping of track during summer season shall not be done
when the rail temperature is more than:
Page 7 of 41
Northern Railway
Objective Questions Engineering Department
(8) What shall be the distance between two track machines during working in
a block section?
(9) What is the minimum cushion of clean ballast is recommended for proper
functioning of tamping machines?
(A) 50 mm (B) 75 mm
(11) The tamping tools shall be replaced when the sectional area of the tool
blade is reduced by
(13) Which small track machine is not required for doing welding of rails in
LWRs?
(14) What is the capacity of non-infringing track jacks normally used for track
maintenance
(A) 8T (B) 9T
(C) 10 T (D) 12 T
Page 8 of 41
Northern Railway
Objective Questions Engineering Department
(A) 0.2 sec to 0.4 sec (B) 0.4 sec to 0.6 sec
(C) 0.6 sec to 0.8 sec (D) 0.8 sec to 1.0 sec
(17) What shall be the ramp gradient before closing the tamping work and
obligatory point?
(18) Two insertions during tamping of concrete sleepers and required for lift
more than
(A) 10 mm (B) 30 mm
(C) 50 mm (D) 75 mm
(19) After one round of tamping along with DTS after deep screening, the
traffic can be resumed with speed restriction of:
Answers: - 1-B, 2-C, 3-D, 4-C, 5-B, 6-B, 7-C, 8-A, 9-D, 10-C, 11-B, 12-D, 13-A, 14-A,
15-D, 16-B, 17-C, 18-B, 19-B, 20-C.
Page 9 of 41
Northern Railway
Objective Questions Engineering Department
Page 10 of 41
Northern Railway
Objective Questions Engineering Department
prepared?
17. In how many days soffit formwork to beams can be 7 days
removed?
18. What is minimum distance from center line of track 6.0 m
to duty hut at L-Xing?
19 What is the characteristic compressive strength of 20 N/mm2
150mm cube at 28 days of M20 concrete?
20. What is recommended gradient in station yard? 1:1000
Page 11 of 41
Northern Railway
Objective Questions Engineering Department
4. LEVEL CROSSINGS
Q.3 What is the minimum number of gatekeepers required in special class, A- class &
B-class?
Ans.3 3 numbers in special class.
2 numbers in A & B classes.
Ans. 4. The multiplication of total number of train units from both side and number of
road vehicle unit is cold TVU of level crossing.
Q.5. What is the distance of WIL Boards for unmanned level crossings on single line
section and where visibility is clear?
Q.6. What is the minimum distance of height gauge in case of level crossings?
Ans.6. Height gauge should be located at a minimum distance of 8.00 m from gate
posts.
Page 12 of 41
Northern Railway
Objective Questions Engineering Department
Q.7 What is the minimum length of fencing parallel to track with each gatepost on
special &A class?
Ans.7. 15 meters
Q.8. What is the minimum length of fencing parallel to track with each gatepost on B &
C class?
Ans. 8. 15 meters
Ans.9 1:15 is the gradient provided on ‘C’ class level crossing gates.
Q.11 What is the distance of speed breakers on the approaches of unmanned level
crossing?
Ans. 11.Speed breakers are provided at a distance of 20 M from gate.
Ans. 12.Stop, look out for trains before crossing in English, Hindi and Regional
language is written on stop Boards.
Q.13. What is the visibility requirements for unmanned level crossing for road users?
Ans. 13For new unmanned level crossing the visibility requirements for road users
along the track shall be 600 m with single or double line track.
Page 13 of 41
Northern Railway
Objective Questions Engineering Department
Q-2 Level crossing beyond the outer must stop signals is called
1. Operating gate.
2. Engineering Gate.
3. Operating & Engg. gate.
4. None of the above.
Page 14 of 41
Northern Railway
Objective Questions Engineering Department
Q.9 PWI/In charge and his Assistant should carry out the inspection of Points &
crossings of passenger running line by rotation
1. Once in two months
2. Once in three months
3. Once in four months
4. None of the above.
Q.10 When check rails of level crossing cannot be refixed & train have to be passed,
speed restriction should be imposed
1. 15 kmph
2. 30 kmph
3. 45 kmph
4. None of the above.
Q-11 Averted collision is categories as
(a) (b) (c) (d)
Q-12 An accident has taken place at out station and main line is blocked and relief
train is to be turned out without medical car. The hooter shall be:
3 long 4 long 4 long, 1 short 3 long, and 1 short
Q-13 Permissible limit for wheel tread diameter for the same axle is
0.5mm 1.00mm 1.75mm 1.25mm
Q-14 Lateral and longitudinal clearance between axle box and axle guard should not
exceed
6mm 8mm 10mm 12mm
Q-15 In a semi permanent (BG) diversion the gradient should not be steeper than
1 in 75 1 in 125 1 in 100 1 in 150
Page 15 of 41
Northern Railway
Objective Questions Engineering Department
7. Track Recording.
Q1. What is the limits of riding index.
Ans. (i) 4.5 Imposition of speed restriction.
(ii) 3.5 For taking early maintenance.
(iii) 300 For satisfaction level of maintenance.
Q2. What are the parameters which contributes to higher value of riding index.
Ans. Twist, Misalignment, Unevenness and Gauge.
Q5. What is the value of TGI for bad, good or very good.
Ans. Below 36-Bad.
36 to 49 -Good.
50 to 79 -Very Good.
80 and above -Outstanding.
Q6. What are the deficiencies in track which leads to vertical acceleration peak?
Ans. (i)Low joint (ii) Twist (iii)Slacks (iv) Vertical wear of the rails.(v)Ballast
cushion deficiency (vi)Loose packing (vii)Weak formation (viii)Wornout sleeper seat.
Q7. What are the deficiencies in track which leads to horizontal (lateral) acceleration
peak?
Ans. (i) Gauge variation (ii) Mis-alignment (iii) Deficient ballast (iv) Weak rail
holding seats of the sleeper (v) Side lateral wear of the rail etc.
Q8. What is the 8 peaks recorded by TRC and how do you make use of it
Ans. 8 peaks recorded by TRC means worst location which need attention for
improving the TGI Value.
Q9. Prior to TRC what should be your priority for attaining various parameters for
effective improvement.
Ans. (i) Attending gauging from one side to the other.
(ii) Attend low joints with picking of slacks.
Page 16 of 41
Northern Railway
Objective Questions Engineering Department
Q13. What is the value for Good, Bad, Outstanding track during OMS recording.
Ans. Av.PPKM. Category of track.
(i) More than 2.00 below average.
(ii)1.00 to 2.00 Good.
(iii)0.25 to1.00 Very Good.
(iv)Upto 0.25. Outstanding.
Q16. What is the value of different chords on which SD value is measured for the
calculation of TGI.
Ans. Uneveness 9.6M.
Twist 3.6M.
Alignment. 7.2M.
Q17. As per CRS stipulation, after how month of recording on ‘A’route speed of
Rajdhani will be reduced.
Ans. After expiry of 6 months of recording speed of Rajdhani will be reduced to 110
kmph.
Q18. Write down the values of short chord and long chord of different parameter.
Ans. Parameter. Standard. Long Chord.
Unevenness. 3.6M. 9.6M.
Twist. 3.6M. 4.8M.
Alignment. 7.2M. 9.6M.
Q19. What do you understand by three stars (xxx) and two stars (xx) printed in
printout of TRC.
Ans. Three stars (xxx) means urgent maintenance and two stars(xx) means planned
maintenance is required.
Page 17 of 41
Northern Railway
Objective Questions Engineering Department
Q21. In TRC printout, if the index value of any parameter is less than 36.What does it
indicates.
Ans. It indicates that the measured SD value is equal to or greater than SD value
specified for urgent maintenance.
Question on LWR.
Page 18 of 41
Northern Railway
Objective Questions Engineering Department
Page 19 of 41
Northern Railway
Objective Questions Engineering Department
1. In case of heel and C.I blocks behind the heel, all holes are perpendicular to:
<WA>Perpendicular to left hand side<WA>Drilled at angle Q/2<CA>Right hand side
of block<WA>None of these
3. No part of the tree shall be nearer than ... from the nearest live conductor
<CA>4 m<WA>5 m<WA>6 m<WA>7 m
.6. During welding of a rail joint with tensor, tensor may be opened after
<WA>5 minutes <WA>10 minutes <WA>15 minutes <CA>20 minutes
10. The speed restriction on level Xing if check rail is not fixed <WA>20
Kmph<CA>30 Kmph<WA>40 Kmph<WA>50 Kmph
Page 20 of 41
Northern Railway
Objective Questions Engineering Department
1. Maximum Horizontal distance from centre of track to face of any platform wall in
BG is 1905mm.
2. Maximum height above rail level for high level passenger platform is 840 mm.
3. Maximum height above rail level for low passenger platform is 405mm.
4. Minimum horizontal distance from centre of track to face of any platform wall in BG
is 1675mm
Answer 3
1.Minimum distance of stop board from centre line of track on unmanned level crossing
is 5 m .
2.Minimum distance of whistle board at level crossing from end of road is 600 m.
3.Minimum distance of speed breakers at level crossing from gate post is 30 m
4.Minimum distance of fish plated joints in SWR track from end of level crossing is 6
m.
Answer 3
Page 21 of 41
Northern Railway
Objective Questions Engineering Department
The normal life of detonators is seven years. The life of the detonators can be extended
to ten years on an yearly basis subject to the condition that two detonators from each
lot of over 7 year old ones are tested for the explosive content and the results being
found satisfactory.
For new unmanned level X-ings the visibility requirements for road users along the
track shall be 600 m with single or double line track. Where this is not feasible, the
distance may be reduced suitably with the approval of Chief Engineer provided the
maximum permissible speed is less than 100 kmph
C] WHAT IS MY NAME
I can rebuild the lateral resistance of track 2. My maximum self propelled speed
is 60 Kmph
2. My working speed is 0 to 2.5 Kmph 4.I am Primarily used behind the tamping
machine 5. My weight is 57 Tonnes
ANSWER Dynamic track stablizer
3 . I am essential for protection of the track. 2. I need careful custody 3. My colour
is red 4. My extended life is 10 years 5. I sound caution to the driver
ANSWER DETONATOR
4. I am an activity to be performed once in every 10 years 2. I am useful in
improving drainage
5 . I am useful in improving running on track 4. I am an activity to be performed
under speed restriction
6. I am an activity for which sufficient ballast has to be arranged
ANSWER DEEP SCREENING
7 . I am an activity to be performed during moderate temperature 2. I require
looking mirror and convex lens
8 . When performed on large scale speed restriction shall be required 4. If I am
carefully performed the fracture instances will be minimised 5. I facilitate expansion
and contraction of fish plated joints
ANSWER Lubrication of fish plated joints
D] TRUE/ FALSE
Page 22 of 41
Northern Railway
Objective Questions Engineering Department
Q3. What are new track tolerances Give values for Gauge, Alignment, Cross Level
and Sleeper Spacing.
Page 23 of 41
Northern Railway
Objective Questions Engineering Department
Ans. These are the tolerances prescribed for laying the new track. The measurements
should be taken in floating conditions three months after normalisation of speed.
Following are the tolerances prescribed for the track laid with new material.
*****
Page 24 of 41
Northern Railway
Objective Questions Engineering Department
Page 25 of 41
Northern Railway
Objective Questions Engineering Department
9 The cost of a deposit work is Rs. 10,00,000/- . How much amount the party Rs. 20,000/-
has to deposit with Railway man for preparation of plan and estimate-
Rs. 10,000/-
Rs. 20,000/-
Rs. 15,000/-
Rs.25,000/-
10 The cost of open tender is Rs. 4.50 lacs. Who will be the tender committee Jr. Scale Office of
members? executive
Sr. Scale Office of executive Department and Sr. Scale Officer of Account Department and Jr.
Department. Scale Officer of
Sr. Scale Office of executive Department and Jr. Scale Officer of Account Account
Department. Department
Jr. Scale Office of executive Department and Sr. Scale Officer of Account
Department.
Jr. Scale Office of executive Department and Jr. Scale Officer of Account
Department
11 The approved list of ‘C’ class Contractor is maintained at Divisional Office
Assistance Divisional Office
Divisional Office
Zonal Railway man office
None of the above.
12 How many type of approved list of contractor is being maintained? 5
4
5
6
3
13 How many class of tender is being used? Open tender,
Open tender and limited tender limited tender and
Limited tender and single tender single tender
Open tender, limited tender and single tender
None of the above.
14 Contractor has demanded an arbitration of Rs. 9.50 lacs. How many Sole Arbitrator
Arbitrator will be appointed?
Sole Arbitrator
Two Arbitrator
Three Arbitrator
None of the above.
15 Who is competent to appoint an arbitrator General Manager
DRM
Territorial HOD
Principal HOD
General Manager
16 Delayed Tender is- When tender is
When tender is received before the due date and time. received after the
When tender is received after the due date and time, but before opening the due date and time
tender. and after opening
When tender is received after the due date and time and after opening the the tender.
tender.
None of the above.
Page 26 of 41
Northern Railway
Objective Questions Engineering Department
Page 27 of 41
Northern Railway
Objective Questions Engineering Department
SN Question Answer
1 Device meant for measuring the discharge in a pipe is called ……………. Venturimeter
2 Device meant for measuring velocity in a pipe is called ……………. Pitot Tube
3 The sum of Potential energy, Pressure energy and ......................energy Kinetic
p 2
constitutes Bernaullis theorem with empirical formula (Z+ /w +v /2g )
4 For a circular channel of diameter ‘D’, the depth of flow for maximum 0.81
velocity is ..……..D.
5 For a circular channel of diameter ‘D’, the depth of flow for maximum 0.95
discharge is …….D.
6 Best trapezoidal channel of best section giving maximum discharge should 60O
have side angle………….to the horizontal.
7 Triangular channel of best section giving maximum discharge should have 45O
side angle …………...to the horizontal.
8 The water quality is said alkaline when pH value is………….and acidic 8 to 14 & 1 to 6
when pH is …….
9 The required residual chlorine in drinking water at every tapping point 0.5
should be……….ppm.
10 ……………… is the term used in which liquid offers resistance to any Viscosity
deforming forces.
11 A type of flow in which fluid particles move in layers is called…………… Laminar
…….. flow.
12 Rate of pumping should be ………………than the rate of recharge in a lesser
tubewell for longer life of a tubewell.
13 The radial distance between two tubewells should not be less than ……… 150
….…mtrs.
14 The viscosity of a fluid ……………………...with the increase of decreases
temperature.
15 The density of a fluid…………………..with temperature and pressure. Varies
16 The property of a fluid by virtue of which the molecules of a liquid remain adhesion
attached to each other is called……………………..
17 The property of a fluid which offers a tensile resistance at its surface is Surface Tension
called…………….
18 Viscosity of water is ……………… times higher than the viscosity of air. 50
19 A circular plate of diameter ‘d’ is held vertically in water so that the upper 0.62 d
end of the vertical diameter is at water surface. The depth of centre of
pressure is…………………..
20 When a body is immersed in a liquid, the liquid will exert an upward force Buoyancy
on the body equal to the weight of the liquid displaced. The upward force
is known as ……………….
Page 28 of 41
Northern Railway
Objective Questions Engineering Department
A. (a) 20-30%
Q.2 Water absorption in 1st class bricks should not be more than
A. [c] 20%
Q.6 How many days, a timber may require for natural seasoning
A. [b] 4 – 6 months
Page 29 of 41
Northern Railway
Objective Questions Engineering Department
A. [a] 0.035
a. slump increases
b. consistency decreases
c. compressive strength decreases
A. [b] 7 days
Q.12. The compacting factor test of cement concrete determines its
A. [c] Workability
Q.13. In anticorrosive paints, pigment used is
Page 30 of 41
Northern Railway
Objective Questions Engineering Department
Q.17 The possibility of quick sand condition will be there when flow of water to soil is
(a) horizontal (b) upward
(c) downward (d) radial
A. [b] upwards.
a. settlement is maximum
b. permeability is more
c. dry density is maximum
d. shear strength is less
a. expulsion of water
b. compression of air
c. expulsion of water
d. structural adjustment of grains
Page 31 of 41
Northern Railway
Objective Questions Engineering Department
Ans. c) 200m
Ans. c) CE/MRTS,FA&CAO,CCM
Ans. a) 30 yrs
Page 32 of 41
Northern Railway
Objective Questions Engineering Department
a) 4% b) 3% c) 5% d) 3-5%
Ans. b) 3
Q.10 Revision of license fee will be done at the increment per annum
Ans. a) 10
Q.11 In case of GMF, AEN can extant the licensing period up to the
total of
Ans. b) 5 yrs
Page 33 of 41
Northern Railway
Objective Questions Engineering Department
Q. 18. Records for ownership of land in states other than U.P. is:
Ans. b) LCO
Page 34 of 41
Northern Railway
Objective Questions Engineering Department
13. ROB/RUB
Q.1. What is the carriageway width of two lanes Road Over Bridge:
(a) 8.0m (b) 7.5m (c) 7.00m (d) 8.5m
Ans. 1. (b)
Q.2. What is the minimum clearance between top of highest rail level to bottom of
girder of Road Over Bridge:
Ans. 2. (d)
Q.3. What is the minimum horizontal distance between centerline of track to pier:
Ans. 3. (a)
Q.4. What is the minimum horizontal distance between centerline of track to abutment:
(a) 4500 (b) 4550 (c) 4350 (d) 4375
Ans. 4. (c)
Q.5. How much TVUs are required for cost sharing of two lane ROB in lieu of level
crossing:
Ans. 5. (d)
Q.6. How much and which charges are levied for construction of ROB/RUBs on deposit
terms in replacement of level crossings and work executed by Railway?
Ans. 6. There are following charges which are levied for construction of ROB/RUBs
on deposit terms in replacement of level crossing and work executed by Railway:
1. D&G (supervision) @ 12.5 %
2. P&E charges @ 2%
3. Departmental charges @ 12.5%
4. Capitalized Maintenance charges @ 30% capitalized
5. Contingencies @ 1%
Page 35 of 41
Northern Railway
Objective Questions Engineering Department
Q.7. How much and which charges are levied for construction of ROB/RUBs on BOT
basis involving closure of level crossings and work executed by Railway?
Ans. 7. Following charges are levied for construction of ROB/RUBs on BOT basis
involving closure of level crossings and work executed by Railway:
1. D&G (supervision) @ 12%
2. P&E charges @ 2%
3. Maintenance @ 30% capitalized
4. Contingencies @ 1%
Ans. 8. Under BOT system, the entrepreneur provides the full funds and builds the
ROB/RUB as per plans and drawings approved by the Railway administration/road
authority and the private entrepreneur is permitted to levy toll on road traffic for
specific period. At the end of the agreed period, the structure would revert back to road
authority.
Ans. 9. (c)
Q.10. Which para of Engineering code deals with cost sharing of ROB/RUBs:
Ans.10. (c)
Q.11. How much P&E charges are levied on deposit/BOT works of ROB/RUBs:
Q.12. How much D&G (Supervision) charges are levied on deposit/BOT works of
ROB/RUBs in case of the work is executed by Railway:
Page 36 of 41
Northern Railway
Objective Questions Engineering Department
Q.13. How much charges are levied on deposit/BOT works of ROB/RUBs in case the
work is executed by party under Railway supervision:
Q.14. How much capitalized maintenance charges are levied on deposit/BOT cost
sharing works of ROB/RUBs:
Q.15. How much department charges are levied on BOT work of ROB/RUBs:
Q.16.What and how much charges are levied on cost sharing works of ROB/RUBs?
Ans. 16.There are following charges which are levied on cost sharing works of
ROB/RUBs:
1. D&G @ 8.22% on Railway share
2. D&G @ 12.5% on State share
3. Contingencies @ 1% on Railway and State share
4. Departmental @ 12.5% on State share
5. Capitalized maintenance @ 30% on State share
6. Supervision charges @ 12.5% on capitalized maintenance.
Q.17. Who has to construct the bridge portion and approaches of ROB in case of cost
sharing works?
Ans. 17. The bridge portion will be constructed by Railway and approaches will be
constructed by State Government in case of cost sharing works.
Q.18. Who will bear the cost of extra length for future tracks?
Ans. 18 The Railway will bear the cost of extra length of ROB for future tracks.
Page 37 of 41
Northern Railway
Objective Questions Engineering Department
Q.19. Who will bear the cost of construction of extra width of ROB as per provision in
para 1816 of Engineering code?
Ans. 19. State Government will bear the cost of extra width of ROB as per provision in
para 1816 of Engineering code.
Ans. 20 Build-Operate-Transfer.
Page 38 of 41
Northern Railway
Objective Questions Engineering Department
Ans.1.1. (i)
Ans.1.2. (ii)
1.3 What is the provision of issuing Railway passes to OBC candidate for written
test/viva voce of direct recruitment:
i. Passes are given
ii. Passes are not given
iii. Passes are given only written test
iv. None.
Ans.1.3. (ii)
1.4 How many Union representatives are allowed to attend PNM meeting at
Headquarter level?
i. 20
ii. No limit
iii. 30
iv. None
Ans.1.4. (i)
Ans.1.4. (i)
Page 39 of 41
Northern Railway
Objective Questions Engineering Department
2.2 Which is the standard form used for issuing the charge sheet to a retired Railway
employee?
Ans.2.2. SF-14
2.4 How many cases can be taken by a retired employee to act as defence helper?
3.2 Reservation to SC/ST candidates in promotion from Group ‘C’ to Group ‘B’ is
applicable w.e.f. ---------------------------.
4.1 There is a chance where some punishment cannot be imposed by the authority that
issues S.F 11.
4.2 Three dependent can be included in the Ist class privilege pass but total should not
exceed five.
Page 40 of 41
Northern Railway
Objective Questions Engineering Department
4.3 TA is not admissible to union representatives when they have attended PNM
meeting out of Headquarter.
4.4 A casual labour can be granted Temporary status after completion of 120 days
continuous service in construction organization.
4.5 Special family planning increment cannot be granted on a certificate issued by non-
Railway Hospital.
Page 41 of 41