You are on page 1of 2

Compiled by: Page No.

1 of 2
F Bam Document No. PR/HPU/60/10.2
Approved by: Revision No. Rev 0
TR van der Bergh Revision Date May 4, 2005

UNIT-60
PROCEDURE TO TAKE SAMPLE TYPE NO.5
Non condensing gas above 600C
SC-0031 / 32 / 33

S.NO. STEPS / ACTIONS ACTION HAZARDAS


BY
1 Obtain the correct marked sample bomb Lead / Contaminated bombs will give
from the lab. Take the sample as per Field wrong results.
schedule. operator
2 Connect the sample bomb to the sample Lead / Use the correct PPE’s.
point. Field
operator
3 After connecting the sample bomb make Lead /
sure all the valves are closed, open valve Field
no. 9. operator
4 Open block valve no. 1, 2, 8 to flush the Lead / To get rid of hold up material.
sample line. Field
operator
5 Close valve no. 8 and open valve no. 3, 4, Lead / Leaks will cause injuries.
5, 6 & check for leaks. Field
operator
6 If no leaks, open valve no. 7 to flush the Lead /
sample bomb properly. Field
operator
7 Close valve no.6 & 7 to pressurize the Lead /
sample bomb. Field
operator
8 Close valve no 1 & 5. Lead /
Field
operator
9 Open valve no. 8 & 7 to depressurize the Lead /
sample lines . Field
operator
10 Close valves no. 2, 3, 4, 7, 8 and Lead /
disconnect the sample bomb. Field
operator
11 Lable the sample correctly & send it to lab. Lead /
Field
operator
Compiled by: Page No. 2 of 2
F Bam Document No. PR/HPU/60/10.2
Approved by: Revision No. Rev 0
TR van der Bergh Revision Date May 4, 2005

TYPE 05

PROCESS LINE LP / HP FLARE


LINE

01

02

CWR 08

03

07
04
09

CWS 05 06
SAMPLE GAS BOMB
OILY
SEWER