Umi Hamimah Binti Rasid

2008286868
SUG673 Project Management

Project Name : Stadium Date : 2 August 2010


WBS No.: 2.1 WBS Name : Design Document
Parents WBS : 2 Parents WBS Name : Planning
Responsible Individual/Organization : Construction Team (Precise)
Scope of work: Infrastructure design drawing, engineer design drawing then architecture
design drawing
Dependencies : Design document with management then approval document
Prepared by : Umi Approved by : Tuan Megat
Title : Project Manager Title : Sponsor
Date : 28 September 2010

Project Name : Stadium Date : 2 August 2010


WBS No.: 2.4 WBS Name : Building Structure
Parents WBS : 3 Parents WBS Name : Structure
Responsible Individual/Organization : Construction Team (Precise)
Scope of work: Construct first floor, construct second floor then build automatic roof
Dependencies : Finishing first floor then finishing second floor then build automatic roof
Prepared by : Umi Approved by : Tuan Megat
Title : Project Manager Title : Sponsor
Date : 16 September 2013

Project Name : Stadium Date : 2 August 2010


WBS No.: 2.5 WBS Name : Landscape Structure
Parents WBS : 3 Parents WBS Name : Structure
Responsible Individual/Organization : Construction Team (Precise)
Scope of work: Construct park and road
Dependencies : Building Structure
Prepared by : Umi Approved by : Tuan Megat
Title : Project Manager Title : Sponsor
Date : 21 February 2011
Project Name : Stadium Date : 2 August 2010
WBS No.: 3.4 WBS Name : Second floor
Parents WBS : 3 Parents WBS Name : Building Structure
Responsible Individual/Organization : Construction Team (Precise)
Scope of work: Construct light weight bearing wall, construct long-span column structure,
construct pre-fabrication floor, finishing floor then painting the seats
Dependencies : First floor
Prepared by : Umi Approved by : Tuan Megat
Title : Project Manager Title : Sponsor
Date : 13 Mei 2013

Project Name : Stadium Date : 2 August 2010


WBS No.: 3.5 WBS Name : Roof
Parents WBS : 3 Parents WBS Name : Building Structure
Responsible Individual/Organization : Construction Team (Precise)
Scope of work: Construct I-beam steel structure, construct cement insulation tile, construct
water repellent cement floor, arranging lights then score board
Dependencies : First floor then second floor
Prepared by : Umi Approved by : Tuan Megat
Title : Project Manager Title : Sponsor
Date : 16 September 2013