You are on page 1of 88

CONSULTANCY SERVICES FOR

2ND RUNWAY AT
SSR INTERNATIONAL AIRPORT
MAURITIUS

FEASIBILITY REPORT

10/06/10 A Govt. of India


Enterprise
PRESENTATION SEQUENCE

 STUDY BACKGROUND
 TRAFFIC FORECAST UPDATE
 TECHNICAL FEASIBILITY
 PRELIMINARY DESIGNS
 COST ESTIMATES
 ENVIRONMENTAL IMPACT ASSESSMENT
 ECONOMIC IMPACT OF RUNWAY CLOSURE
 FINANCIAL VIABILITY
 RISK ASSESSMENT
 CONCLUSIONS & RECOMMENDATIONS
STUDY BACKGROUND
STUDY OBJECTIVES

 PROVIDE AML WITH A TOOL FOR DECISION MAKING


REGARDING CAPITAL INVESTMENT FOR THE
CONSTRUCTION OF A SECOND RUNWAY
 ASSESS THE ECONOMIC AND SOCIAL IMPACT
 ESTABLISH THE TECHNICAL AND FINANCIAL
FEASIBILITY OF THE PROPOSED 2ND RUNWAY
 ASSESS THE IMPACT OF CLOSURE OF MAIN RUNWAY
ON THE ECONOMY OF MAURITIUS
 TO CONCLUDE WHETHER THE PROJECT IS
TECHNICALLY AND FINANCIALLY FEASIBLE, SOCIO-
CULTURALLY AND ENVIRONMENTALLY ACCEPTABLE
AND ECONOMICALLY JUSTIFIED

10/06/10 4
SCOPE OF WORK

 CONSTRUCTION OF 2600 METRES LONG 2ND RUNWAY


WITH A 300 METRE LONG STARTER, 60 METRES WIDE
WITH 7.5 METRE-WIDE SHOULDERS ON BOTH SIDES
– ICAO CODE F STANDARD TO ACCOMMODATE THE
LANDINGS AND TAKE OFFS OF A380 TYPE OF
AIRCRAFT
– CAT II ILS SYSTEM, ASSOCIATED GROUND LIGHTS
– LINKED TO THE EXISTING RUNWAY BY 2 CODE F
TAXIWAYS
 DIVERSION OF PHOENIX-MAHEBOURG ROAD
 DIVERSION OF BLUE BAY LINK ROAD
 REALIGNMENT OF AIRPORT BOUNDARY FENCE
 LAND REQUIREMENTS
SCOPE OF CONSULTANCY SERVICES

 CONFIRMATION/ UPDATE OF THE AIR TRAFFIC FORECAST


CARRIED OUT BY INTERVISTAS IN 2006
 PRELIMINARY DESIGN OF THE AIRFIELD PAVEMENTS
 DETAILED COST ESTIMATE FOR THE WORKS
 ECONOMIC AND SOCIAL IMPACT OF THE RUNWAY CLOSURE
 DETERMINE THE FINANCIAL FEASIBILITY OF THE PROJECT
 ASSESS THE ENVIRONMENTAL IMPACT
 IDENTIFY POTENTIAL PROJECT IMPLEMENTATION RISK
STUDY PERIOD

 100 DAYS FOR SUBMISSION OF DRAFT FEASIBILITY


REPORT (27 JAN 2010 to 06 MAY 2010)
 120 DAYS FOR FINAL SUBMISSION (26 MAY 2010)
DATA REVIEW

 AIR TRAFFIC FORECAST UPDATE, APRIL 2006


 AIRPORT MASTER PLAN UPDATE 2004 REPORT
 SOCIAL & ECONOMIC IMPACT OF SSR INTERNATIONAL
AIRPORT REPORT BY UNIVERSITY OF MAURITIUS
(2000 – 2001)
 RUNWAY RISK ASSESSMENT AT SSR INTERNATIONAL
AIRPORT, JAN 2006
 SURVEY OF OBSTACLE LIMITATION SURFACE (OLS)
REPORT FOR BOTH THE EXISTING AND PROPOSED
SECOND RUNWAY
 ENVIRONMENTAL IMPACT OF SSR INT’L AIRPORT BY
UNIVERSITY OF MAURITIUS, JAN 2001
CONSULTATIONS

 AML  BOARD OF INVESTMENT


 DCA  MAURITIUS EXPORTERS ASSOCIATION
 AIRPORT FUEL COMPANY
 CENTRAL STATISTICAL OFFICE
 PLAISANCE CATERING  MINISTRY OF FINANCE
 MAURITIUS DUTY FREE  MINISTRY OF INDUSTRIES
PARADISE  FREEPORT OPERATORS
 POLICE  MINISTRY OF AGRICULTURE &
 IMMIGRATION FISHERIES
 CUSTOMS  MAURITIUS CHAMBER OF COMMERCE
AND INDUSTRY
 HEALTH  MINISTRY OF ENVIRONMENT
 DEPARTMENT OF FORESTRY

 AIR MAURITIUS  CENTRAL WATER AUTHORITY (CWA)


 BOARD OF AIRLINES  ROAD DEVELOPMENT AUTHORITY
(RDA)
 CENTRAL ELECTRICITY BOARD (CEB)
 MINISTRY OF TOURISM  MAURITIUS TELECOM
 MAURITIUS TOURISM
PROMOTION AUTHORITY (MTPA)
 TOUR OPERATORS
 ASSOCIATION OF HOTELS

32 MEETINGS HELD
FIELD INVESTIGATIONS

 TOPOGRAPHICAL SURVEYS

 SOIL INVESTIGATIONS
– TRIAL PIT INVESTIGATIONS
– BORE HOLE
INVESTIGATIONS

 ENVIRONMENTAL IMPACT
ASSESSMENT
– NOISE
– AIR POLLUTION
– WATER CONTAMINATION
– ECOLOGY
TRAFFIC FORECAST UPDATE
TRAFFIC FORECAST UPDATE

 OBJECTIVE
– CONFIRMATION/UPDATION OF INTERVISTA’S 2006
REPORT
TRAFFIC FORECAST UPDATE

 METHODOLOGY
– BASIC METHODOLOGY KEPT SAME
– ADDITIONAL APPROACHES LIKE ECONOMETRIC MODELS
IN COMBINATION WITH GROWTH RATE PROJECTIONS
USED
– THE CHANGES IN MARKETS AND WORLD WIDE
ECONOMIC RECESSION BETWEEN 2005-06 STUDY AND
THE CURRENT ONE 2009-10 CONSIDERED
– ADDITIONAL INFORMATION FROM VARIOUS SECONDARY
SOURCES HAS ALSO BEEN COLLECTED TO ARRIVE AT
MEANINGFUL RESULTS.
TRAFFIC FORECAST 2006
 Annual E/D Passengers (Thousands)  

PASSENGERS TO REACH 3.9 MILLION BY 2015 (5.9% PER ANNUM) &


5.6 MILLION BY 2025 (4.8% PER ANNUM) .
COMPARISION -2006 FORECAST & ACTUAL
Year Forecast Actual % difference
(Base Case)
2005 2192000 2167437 -1.12%
2006 2331630 2217167 -4.91%
2007 2480155 2562830 3.33%
2008 2638141 2609805 -1.07%
2009 2806190 2381810 -15.12%
2010 2984945
UPDATE OF TRAFFIC FORECAST
FORECAST OF TRAVEL BY GDP DEPENDENT MODEL
MAURITIUS RESIDENTS GROWTH RATES OF MODEL USED FOR
ORIGIN DESTINATION FORECAST

FORECAST OF TOURIST BASED ON GROWTH RATES FOR EACH


TRAFFIC ROUTE- CONSIDERING BOEING, WORLD
BANK AND AIRBUS PROJECTIONS
BETWEEN REGIONS
GDP, POPULATION & HOTELS DEPENDENT
MODEL

FORECAST OF DOMESTIC ECONOMY GROWTH BASED


MOVEMENT
FORECAST OF TRANSFER GROWTH HALF OF TOURIST PASSENGERS
PASSENGERS – SAME AS IN INTERVISTA’S REPORT

TOTAL PASSENGER ADDITION OF ALL ABOVE FORECASTS AS


MOVEMENT WELL AS ECONOMETRIC MODEL
FACTORS FOR ECONOMETRIC
MODEL
Hotels in
Mauritius have
nearly remained
constant from
2000 (95
numbers) to 2008
(97 numbers).
Total rooms
available at the
end of 2008 were
11488. Annual Real Growth in GDP at Basic Price
• Annual real growth rates of GDP
6
for Mauritius fell to 2.5% for 2008-
Growth Rate (%)

5 5.3
5.5
4
3
5.1
09 from nearly 5% growth between
2.5
2
1 2005-06 to 2007-08
0
2005/06 2006/07 2007/08 2008/09
• Growth rates of almost all
Years economies on which traffic is
2005/06 2006/07 2007/08 2008/09
dependent was negative in 2009

Population of Republic of Mauritius will grow from


1,186,873 in 2000 to around 1,486,000 in 2040, at
an average annual rate of 0.56%.
OLS (ORDINARY LEAST SQUARES) estimates
Actual and fitted Tourists_By_Air MODEL-1
Dependent variable: Tourists_By_Air 1e+006
fitted
Model-1 Model-2 Model-3 actual
constant -8.65E+05 -2.16E+05 -1.462e+05** 900000

(-635100) (-497100) (-16790)


800000
Population_IN_ 7.64E+05 7.67E+04 Omitted

Tourists_By_Air MODEL-1
Millions
(-685000) (-542800) 700000
Hotel Rooms -25.2 Omitted Omitted
(-16.27) 600000
Real_GDP_index 4260** 4004** 4116**
(-783.2) (-796.5) (-94.59) 500000

n 20 20 20
400000
R2 0.9930 0.9895 0.990

Adj. R2 0.9903 0.9895 0.9901 300000

lnL -223.9 -225.3 -225.3


200000
Standard errors in parentheses 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008
* indicates significance at the 10 percent level YEARS
** indicates significance at the 5 percent level
T O U R I S T S FO R E C A S T M O D E L - 1
Year Forecast Forecast Arrival Forecast “The 2006 3e+006
Model-1 Model-1 Arrival+ Plus Dep as By WTTC Report”s’ T o u r is ts _ B y _ A ir
fo re ca s t
(Arrival) as per Dep= 2xArrival per growth (Table 3.18) Report (000) 9 5 p e rce n t in te rv a l
Table-5.20 (000) rate) (000) (000) 2 .5 e + 0 0 6

2e+006

TOURISTS
(1) (2) 3=(2)/1000 *2 (4) (5)
1 .5 e + 0 0 6
2010 940371 1881 1822 1858 2377
2014 1081948 2164 2262 2228
1e+006
2015 1139863 2280 2385 2317 3112
2019 1450642 2901 2917 2739
500000
2020 1530502 3061 3071 2857 3823 2000 2005 2010 2015 2020 2025
YEARS
2024 1854809 3710 3733
2025 1940623 3881 3894 4518
2029 2268204 4536 4737
Comparison E/D Passengers (in
‘000)
Figures in Millions
  2006 FORECAST  Actual 2010 FORECAST  

Year Low Case Base High case Updated Updated


Case -Growth Econome
based tric
Model
2000       1.813    
2005 2.192 2.192 2.192 2.167    
2006 2.284 2.332 2.398 2.217    
2007 2.366 2.482 2.623 2.563    
2008 2.437 2.640 2.870 2.610    
2009 2.498 2.809 3.140 2.356 2.356 2.356
2010 2.693 2.985 3.442   2.410 2.530
2015 3.215 3.883 4.761   3.112 2.898
2020 3.721 4.759 5.658   3.980 3.805
2025 4.208 5.579 6.519   5.002 4.732
2029         6001 5454
AIRCRAFT MOVEMENTS

 THE DOMESTIC AIRCRAFT MOVEMENT WAS PROJECTED TO INCREASE FROM 1858 IN


2005 TO 2200 IN 2010 AT A GROWTH RATE OF 4.1%.
 THE BASE CASE TOTAL AIRCRAFT MOVEMENTS (DOMESTIC PLUS INTERNATIONAL)
WERE PROJECTED TO GROW FROM 17944 TO 23200 FROM YEAR 2005 TO 2010 AT A
GROWTH RATE OF 5.3%.
 ACTUAL GROWTH RATE FROM 2005 TO 2009 FOR DOMESTIC AIRCRAFT MOVEMENTS IS
(-) 5.83% AND FOR TOTAL AIRCRAFT MOVEMENTS IS (-) 2.34%.
 CHANGES WHICH AFFECTED THE ASSUMPTIONS OF 2006 FORECAST
– PLANNING FOR CONSTRUCTION OF NEW TERMINAL AND UPGRADING OF RUNWAY FOR “CODE
F” AT SSR INTERNATIONAL AIRPORT
– LIKELIHOOD OF INTRODUCTION OF AB380 ON EUROPEAN ROUTE,
– PLANS FOR CONSTRUCTION OF NEW RUNWAY OF 3000M LENGTH AT RODRIGUES
UPDATION OF AIRCRAFT
MOVEMENTS
 THE AVERAGE AIRCRAFT SIZE BASED ON THE PRESENT
FLEET, SIZE OF AIRCRAFTS, LOAD FACTOR, LIKELYHOOD OF
INTRODUCTION OF LARGER AIRCRAFTS WORKED OUT
 ROUTE WISE PASSENGER FORECAST USED FOR AIRCRAFT
MOVEMENTS.
 INDIVIDUAL ROUTE WISE ANALYSIS (DOMESTIC, ASIAN,
AFRICAN, EUROPEAN, REUNION)
 EFFECT OF RODRIGUES PLANS FOR 3000 M RUNWAY
(INCREASE IN AIRCRAFT SIZE REDUCTION IN AIRCRAFT
MOVEMENTS), EFFECT OF LIKELYHOOD OF INTRODUCTION
OF A380 ON EUROPEAN ROUTE ETC. CONSIDERED.
AIRCRAFT MOVEMENTS-
COMPARISON

Year Domestic Indian Europe Africa Asia Others TotalAs Per


Ocean 2006
Report
2010 1759 6303 6650 1868 1450 886 18,916 23,200

2015 2167 7679 7380 2345 1872 1011 22,454 28,600

2020 2267 9702 9215 3211 2563 1052 28,010 33,600

2025 2386 12063 10837 4141 3306 1295 34,028 38,000

2029 2639 13556 12011 5084 3788 1431 38,509  

Aircraft Movements will be deferred by 5 years


TO SUM UP

 THE FORECAST WAS GENERALLY BEING FOLLOWED, BEFORE


GLOBAL RECESSIONARY PHASE.
 THE GLOBAL RECESSION, PLANNING FOR CONSTRUCTION OF
NEW TERMINAL AND UPGRADING OF RUNWAY FOR “CODE F”,
LIKELIHOOD OF INTRODUCTION OF AB380 ON EUROPEAN
ROUTE, PLANS FOR CONSTRUCTION OF NEW RUNWAY OF
3000M LENGTH AT RODRIGUES ARE SOME OF THE CHANGES
WHICH AFFECTED THE ASSUMPTIONS OF 2006 FORECAST.
 THE TOURIST TRAFFIC, THE TOTAL PASSENGERS (E/D), AND
THE AIRCRAFT MOVEMENTS PROJECTED FOR BASE CASE ARE
LIKELY TO BE DEFERRED BY APPROX. 4-5 YEARS. THE
ACTUAL REALISATION WILL BE MORE NEAR TO LOW CASE.
 1.5 MILLION TOURIST ARRIVALS ARE LIKELY TO BE REALISED
IN 2019-2020. THE INCREASE IN TOURIST TRAFFIC MAY
SHOW RESISTANCE TO INCREASE ONCE A 1.5 MILLION
TOURIST ARRIVAL FIGURE IS REALISED.
TECHNICAL FEASIBILITY
TECHNICAL FEASIBILITY

 EVALUATION OF THE FACILITIES PROPOSED IN THE


MASTER PLAN CONCERNING THE 2ND RUNWAY FOR THE
INTENDED USE AND THEIR COMPLIANCE TO LATEST
STANDARDS AND RECOMMENDED PRACTICES OF ICAO

 ANALYSIS OF OBSTACLE LIMITATION SURFACES TO


EVALUATE THE FEASIBILITY OF ILS CAT-II
OPERATIONS
PLANNING PARAMETERS

 ARC – 4F % Aircraft Movement


 ART – 29.7° C
 ELEVATION – 56 M 4%
 RUNWAY SLOPE – 0.9% 18%
ATR-42 / 72
 FARTHEST DESTINATION Boeing 737
9765 KM (LONDON) 3% Boeing 747
37%
Boeing 767
Boeing 777
9%
Airbus 319
Airbus 330
2%
Airbus 340
7% Others

6%
14%
EVALUATION OF PROPOSED
FACILITIES

RUNWAY
LENGTH FOR LANDING (2600 M) √ FOR ALL AIRCRAFT

LENGTH FOR TAKE-OFF (2900 M) √ BUT WITH RESTRICTED


PAYLOAD
WIDTH (60 M) √
SHOULDER (7.5 M) √
RUNWAY STRIP (150 M) √
RESA √ (ASDA 2600M FOR RUNWAY
32)
RUNWAY LENGTH ANALYSIS
RUNWAY LENGTH ANALYSIS

B 777-300
2900 m
A 340-600 take off
length
B767-400

Landing Length
AIRCRAFT

B 747-400
Take-off Length
A 330-200 Reference Field Length

A 380-800

A 300-600
2600 m
A 310-200 landing
length
0 1000 2000 3000 4000 5000
RUNWAY
HOWEVER, FOR THE GIVEN RANGELENGTH (m) 10,000KM, THE WIDE BODIED
OF ABOUT
AIRCRAFT CAN TAKE-OFF WITH LOAD RESTRICTION VARYING FROM 30 – 45%
EVALUATION OF PROPOSED
FACILITIES
 TAXIWAY
– 2 TAXIWAYS INITIALLY PROPOSED
– ADDITIONAL TAXIWAY CONNECTING THE 14THRESHOLD
INCLUDED AS DESIRED BY AML
– EXISTING ILS REQUIRE RELOCATION
 ARFF
– EXISTING CATEGORY 9
– REQUIRED CATEGORY 10 FOR A380
– NEEDS TO BE UPGRADED TO 10 IN FUTURE
– WILL JUST MEET THE RESPONSE TIME FROM EXISTING STATION
– BETTER TO HAVE DEDICATED FIRE STATION IF CONTINUOUS
OPERATIONS ARE INTENDED ON 2ND RUNWAY
 CONTROL TOWER
– HAS AN EYE ELEVATION OF 80 M AMSL
– ADEQUATE FOR 2ND RUNWAY ALSO
CAT-II APPROACH

Significant obstacles that penetrate


OAS
•Telephone Exchange Tower: 13703M,
TE 1583.9Ft (482.79M)
• Bigara Radio mast: 19355M, TE
2578.7Ft (786.00M)

PENETRATION OF OBSTACLE ASSESSMENT SURFACE IS A


MAJOR LIMITATION IN HAVING A 3° GLIDEPATH RESULTING IN
LIMITING THE ILS TO CAT I OPERATIONS ONLY.
CAT-II APPROACH

 PROVISION OF HORIZONTAL SEGMENT IS


MANDATORY AS PER ICAO PAN-OPS
 APPROACH PROCEDURE FOR THE MAIN RUNWAY
DOES NOT INCLUDE HORIZONTAL SEGMENT
 MASTER PLAN 2004 MIGHT HAVE CONSIDERED
SIMILAR APPROACH FOR 2ND RUNWAY
 REMOVAL OF HORIZONTAL SEGMENT PROVIDES
A SLOPE OF 3 DEGREE DESCENT IN THE FINAL
APPROACH
ILS OCA SURFACE
RUNWAY LIGHTING

 APPROACH LIGHTING IS TO
BE PROVIDED OVER THE
RIVER OF 25-30M DEEP

 HIGHMAST LATTICE
STRUCTURE PROPOSED
USE OF PARALLEL TAXIWAY

 THE LENGTH OF THE PARALLEL TAXIWAY (2350 M) IS SHORT


FOR TAKE-OFF AND LANDING OF WIDE BODIED AIRCRAFT
 SHOULD BE EXTENDED ATLEAST TO 2900 M TO SERVE AS 2ND
RUNWAY IN CASE OF EMERGENCY
 THE PHYSICAL CHARACTERISTICS OF THE TAXIWAY SHALL BE
DESIGNED TO MEET THE REQUIREMENTS OF RUNWAY
 ONLY VFR OPERATIONS WILL BE POSSIBLE
 THE PARKING APRON IN FRONT OF THE EXISTING TERMINAL
BUILDING WILL REQUIRE RECONFIGURATION
 THE AIR TRAFFIC CONTROL TOWER & CARGO BUILDING WILL
BE OBSTRUCTIONS
 OBSTRUCTIONS IN THE APPROACH NEEDS FURTHER
EVALUATION FOR APPROACH PROCEDURES

NOT A REPLACEMENT FOR SECOND RUNWAY


ROAD DIVERSIONS
MEAHEBOU
RG ROAD
PROPOSE
D
DIVERSIO
N

BLUE BAY
ROAD

EXISTING PROPOSE
RUNWAY D
DIVERSIO
NEW N
RUNWA
Y
ROAD DIVERSION
LAND REQUIREMENT
S.No. Description Area (Ha)
(1) LEASED TO :
A) THIRD PARTY BEAU VALLON 4.50
B) MINISTRY OF AGRICULTURE 71.70
C) THIRD PARTY (MR.MODAY KHAN) 0.80
D) BEAU VALLON 1.60
F) MTMD 2.10
TOTAL (1) 80.70 HA
(2) LAND TO BE PURCHASED BY AML
A) LAND BELONGING TO INDIVIDUAL OWNERS 4.80

B) TITLE NOT CLEAR 6.40


C) 0.30
TOTAL (2) 11.50 HA
(3) (SUGAR CANE CULTIVATION FIELDS) 104.80 HA
(4) LAND ALREADY PURCHASED BY AML 28.40 HA
(5) LAND FOR ROAD DIVERSION 10.20 HA
TOTAL AREA (HA) 235.60 HA
PRELIMINARY DESIGNS
PRELIMINARY DESIGN

 PAVEMENT PROFILE
 DESIGNED IN ACCORDANCE WITH THE ICAO STANDARDS AND
RECOMMENDED PRACTICES FOR AERODROME REFERENCE
CATEGORY 4F
THE LONGITUDINAL PROFILE IS GOVERNED BY THE EXISTING
RUNWAY PROFILE, LENGTH OF LINK TAXIWAYS AND THE
PERMISSIBLE SLOPES
- DESIGNED TO MATCH TOPOGRAPHY OF THE AREA SLOPING
FROM NORTH-WEST TO SOUTH-EAST TO OPTIMISE
EARTHWORK QUANTITIES
- THE SOUTH EAST AREA OF THE AIRPORT LAND IS LOW LYING
AND HENCE LEVEL OF THRESHOLD 32 OF THE RUNWAY IS
KEPT SUFFICIENTLY ABOVE THE GROUND LEVEL
- HARD STRATA OF SOIL AT SHALLOW DEPTH AND THE DEPTH
OF CUTTING IS ALSO MINIMIZED
- THE TRANSVERSE SLOPE OF THE RUNWAY STRIP IS DEFINED
KEEPING IN VIEW THE GENERAL DRAINAGE PATTERN OF THE
AREA
PRELIMINARY DESIGN

 THE MAXIMUM DEPTH OF CUTTING IS 1.85 M


 THE MAXIMUM DEPTH OF FILLING IS 5.57 M
 EARTHWORK IN FILL IS 580,000 CUM
 EARTHWORK IN CUT IS 400,000 CUM
 NEARLY 200,000 CUM OF EARTH WILL BE REQUIRED TO BE
BROUGHT FROM BORROW AREAS
PRELIMINARY DESIGN

Max. Fill –
5.57m

32
PRELIMINARY DESIGN

 STRUCTURAL DESIGN OF AIRFIELD PAVEMENTS


– DESIGN PARAMETERS
 TYPE OF PAVEMENT : FLEXIBLE
 SUB GRADE CBR : 14.8 (BASED ON RECOMMENDATIONS
OF GT REPORT)
 PAVEMENT DESIGN LIFE : 20 YEARS
 DESIGN AIRCRAFT : A-340, B-777
 ANNUAL DEPARTURES : EQUIVALENT ANNUAL
DEPARTURES OF DESIGN AIRCRAFT HAS BEEN
CONSIDERED
– DESIGN METHODOLOGY
 FAA SOFTWARE FAARFIELD
 ICAO DESIGN METHODOLOGY – USA
 DESIGN CURVES OF THE MANUFACTURER OF AIRBUS
 DESIGN CURVES OF THE MANUFACTURER OF BOEING
– DESIGN ALSO VERIFIED WITH ACN-PCN METHOD
PRELIMINARY DESIGN

 STRUCTURAL DESIGN OF AIRFIELD PAVEMENTS

FOLLOWING LAYER STRUCTURE IS PROPOSED


– SURFACING LAYERS / WEARING COURSE
 BITUMINOUS CONCRETE (0/14 MM) - 50MM
 BITUMINOUS CONCRETE (0/20 MM) - 75MM
– BASE COURSE LAYERS
 BITUMINOUS BASE (0/31.5 MM) - 150MM
– SUB BASE COURSE LAYERS
 GRADED CRUSHED STONE

(CRUSHER RUN 0/31.5 MM) -


350MM
 TOTAL THICKNESS 625MM

 PCN WORKS TO 83 F/B/W/T AND MEETS THE


REQUIREMENT
COST ESTIMATES
COST ESTIMATES - Quantities

 EARTHWORK QUANTITIES FROM MX ROAD SOFTWARE


USING THE TOPOGRAPHIC SURVEY INPUTS & DESIGN
PROFILES
 PAVEMENT WORK ITEMS CALCULATED BASED ON
PAVEMENT DESIGN
 DRAINAGE AND FENCING – LENGTHS MEASURED FROM
DRAWING
 RUNWAY LIGHTING AND NAV-COM AIDS - IN
CONSULTATION WITH LEADING INTERNATIONAL
SUPPLIERS OF AIRPORT LIGHTING AND INSTRUMENT
SYSTEMS
 THE DIVERSIONS OF SERVICES HAVE BEEN FINALISED
IN CONSULTATION WITH/ WITH APPROVAL OF
CONCERNED AUTHORITIES
 2 BRIDGES OF SPAN 70M AND 110 M INCLUDED IN THE
PHONEIX – MAHEBOURG ROAD
COST ESTIMATES - Rates

 THE RATES OF TAXIWAY WORK UNDERTAKEN BY AML DURING 2006-07


(LOA JULY 2006), DULY ENHANCED @ 1% PER MONTH, TO BRING THEM
AT PAR TO THE CURRENT PRICE LEVEL.
 THE RATES OF ROAD WORK UNDERTAKEN BY RDA DURING 2009 (LOA
JAN 2009), DULY ENHANCED @ 1% PER MONTH, TO BRING THEM AT PAR
TO THE CURRENT PRICE LEVEL.
 BASIC RATES OF MATERIALS (AGGREGATES, CEMENT, STEEL, BITUMEN),
MACHINERY AND LABOUR COLLECTED BY CONSULTING THE LEADING
HIGHWAY CONTRACTORS IN MAURITIUS AND USED TO ANALYZE THE
RATES OF MAJOR ITEMS OF WORK SUCH AS
– EARTHWORK
– GRANULAR SUB BASE, CRUSHED STONE AGGREGATE BASE
– BITUMINOUS MACADAM, DENSE BITUMINOUS MACADAM
– BITUMINOUS CONCRETE, RUNWAY MARKINGS, FENCING ETC.
 AVERAGES OF THE ABOVE RATES WERE CONSIDERED FOR PREPARATION
OF THE COST ESTIMATES.
COST ESTIMATES

 INCLUSIONS
– AIRFIELD PAVEMENT WORKS
– AIRFIELD LIGHTING WORKS & NAV-COM AIDS
– FENCE, DRAINAGE
– DIVERSION OF ROAD (PHOENIX-MAHEBOURG & BLUE BAY)
INCLUDING 2 BRIDGES
– DIVERSION OF UTILITIES
– PRELIMINARY AND GENERAL ITEMS @ 24.36% FOR RUNWAY AND
13.37% FOR SERVICES INCLUDING ESCALATION DURING CONSTN.
– DAY WORK ITEMS @ 1.42% FOR RUNWAY AND 1.21% FOR SERVICES
– CONTINGENCIES @ 5%
– CONSULTANCY @ 2% FOR DESIGN AND 5% FOR CONSTRUCTION
– ESCALATION @ 8% PER ANNUM UPTO DESIGN STAGE ONLY
– LAND COST 2ND RUNWAY & ROAD DIVERSION @ MUR 4.OO M PER
HA
– REHABILITATION COST FOR SMALL PLANTERS & HOUSES
– LAND LEASE CHARGES FOR 24 YEARS
 EXCLUSIONS
– COST OF OBSTRUCTION REMOVAL
– COST OF OFC CABLE
– VAT NOT INCLUDED
COST ESTIMATES

 REQUIREMENTS OF MAJOR MATERIALS


– EARTH TO BE BROUGHT FROM OUTSIDE 200,000 CUM
APPROX.
– AGGREGATES FOR SUB BASE, BASE AND SURFACING
LAYERS 350,000 TONNES APPROX.
– BITUMEN TO BE IMPORTED : 8,000 MT (INCLUDING ROAD
DIVERSION)
COST ESTIMATES

 THE TOTAL COST OF THE SCOPE MENTIONED IN TOR WORKS


OUT TO MUR 3,335.09 MILLION
COST ESTIMATES
Component Wise Cost
Distribution
ENVIRONMENTAL IMPACT ASSESSMEN
LAND ENVIRONMENT

– THE TOPOGRAPHY IS UNDULATING AND HAS A SLOPE OF ABOUT 1 IN


100 TOWARDS BLUE BAY. THESE SLOPES ARE NOT VENERABLE TO
SOIL EROSION.
– THE THICKNESS OF OVER BURDEN VARIES BETWEEN 0.95 M TO 2.88
M ALONG THE RUNWAY. THE SOILS ARE BROWN GRAVELLY MEDIUM
PLASTICITY CLAY UP TO A DEPTH OF 1.0
– BASED ON SOIL CHARACTERISTICS, LAND USE AND RAINFALL,
PASTURE MEASURES IN THE AREA FOR SOIL CONSERVATION MAY BE
ALRIGHT. BASED ON THESE MEASURES, THE SOIL EROSION RATE
WILL BE 0.034 TONS / HA/ YEAR. THE EROSION RATES HAVE BEEN
CLASSIFIED AS VERY LOW (TOLERABLE). THE AVERAGE EROSION
WILL BE ABOUT 9.06 TONS PER YEAR FOR THE PROPOSED
ADDITIONAL AREA FOR 2ND RUNWAY.
– THE OVER BURDEN TOP SOIL SHALL BE STORED FOR REUSE TO
AVOID ANY LEACHING OF NUTRIENTS IN WATER BODY DURING
RAINFALL. THE LAND USE CHANGE FROM AGRICULTURE WILL
REDUCE PESTICIDE AND OTHER POLLUTANTS IN SOIL / WATER.
– MUCK IF ANY SHALL BE DISPOSED AND SITE SHALL BE VEGETATED.
WATER ENVIRONMENT
 THE TOTAL WATER REQUIREMENT DURING CONSTRUCTION IS 62.0 M3/DAY.
 TO DRAW WATER FROM LA CHAUX RIVER AND ITS FEEDERS, PERMISSION FROM
THE SUPREME COURT OF MAURITIUS SHALL BE REQUIRED AS PER SECTION 22
AND SECTION 25 OF PART I
 ABOUT 70 CONTRACTORS LABOR WILL BE WORKING DURING CONSTRUCTION,
CONTRACTOR SHALL MAKE ARRANGEMENT FOR SANITATION (SEPTIC TANK AND
SOAK PIT) 12 CUM /DAY AND SOLID WASTE DISPOSAL FACILITIES (28 KG/DAY)
 WATER ANALYSIS IN LA CHAUX RIVER AND BLUE BAY HAS INDICATED OIL &
GREASE POLLUTION AS NIL.
 DIVERSION OF WATER SUPPLY AND OTHER LINES PASSING THROUGH THE AREA.
 DRAINS FOR STORM WATER RUNOFF WITH BALANCING PONDS AT 500M WITH
OIL AND GREASE SKIMMING TANK / TRAP WITH UNLINED AT BOTTOM.
AIR ENVIRONMENT
 THE AIR QUALITY OF MAURITIUS IS MOSTLY WITHIN THE NAAQS. THE MAXIMUM
CONCENTRATION OF POLLUTANTS IN AIRPORT AREA OBSERVED AT OLD GUARD ROOM.

Parameter Year 2000 Year 2010 % increase / year

Av. Max Av. Max Av Max

THE NOx (ppb) 2.64 26.0 19.33 32.0 22.0 2.1


 CONTRIBUTION OF POLLUTANTS LIKE SPM, SO2, NOX, HC ETC ARE NOT LIKELY TO
SO2THRESHOLD
CROSS (ppb) 0.75
LIMITS 2.0
DURING 4.14
CONSTRUCTION. 6.0 18.6 11.6
O3 (ppb) 17.42 22.0 20.55 28.0 1.70 2.4
 THE CO CONCENTRATION IN AND AROUND RUNWAY WILL BE ABOUT 0.8 PPM IN 2025
CO (ppm)
PRESENT 0.023
BEING 0.33 PPM. 0.21 0.33 0.80 30.5 14.3

 THE GREEN HOUSE GASES EMISSION IN 2025 WILL BE 276 TONS PER DAY (INCREASE
63%). THESE EMISSIONS WILL EXIST WITH OUT 2ND RUNWAY ALSO.
NOISE ENVIRONMENT

 THE NOISE LEVELS INDICATE THAT NOISE AT THE START OF


RUNWAY IS 59 TO 90 DB(A)
 THE BACKGROUND LEVEL IS VARYING FROM 41 TO 49
DB(A)
 THE DAY AND NIGHT AVERAGE NOISE LEVEL ABOVE 55
DB(A) WILL BE COVERING HALF OF BLUE BAY
CONSERVATION AREA, BLUE BAY RESIDENTIAL AREA, AND
COMPLETE AIRPORT AREA.
 THE 55 DB(A) WEIGHTED MAX LEVEL WILL BE COVERING
MUCH LARGER AREA. THIS AREA SHOULD BE PLANNED AS
LESS POPULATION AREA IN FUTURE PLANNING PROCESS
ECOLOGICAL ENVIRONMENT

 THERE ARE 72 FISH, 38 CORAL, TWO MANGROVES AND 31


SPECIES OF ALGAE ARE REPORTED. OUT OF THESE DURING
SURVEY 51 FISH SPECICES WERE IDENTIFIED AND 39 ARE IN
ABUNDANCE IN BLUE BAY CONSERVATION AREA.
 DENSITY OF FISH IS MAX-1,273 FISH / 100 SQM AND MIN 11
FISH/100 SQM
 14 SPECIES OF AVIAN FAUNA IN THE AREA HAS BEEN
OBSERVED DURING SURVEY, NO BIRDS MIGRATORY ROUTE
 ABOUT 5.5 HA OF FOREST WILL BE LOST DUE TO RUNWAY
LIGHTING IN LA CHAUX RIVER AND ABOUT 2500 MAJOR
TREES DUE TO LAND ACQUISITION. THIS WILL FORCE THE
BIRDS TO SHIFT THEIR HABITAT.
 NO IMPACT IS ANTICIPATED DUE TO 2ND RUNWAY ON BLUE
BAY MARINE CONSERVATION PARK.
ENVIRONMENTAL MONITORING

Monitoring Parameter Sites Sampling Frequency


monitoring Duration
Ambient air PM10 ,SO2, NOx Both End of One day Once in a year during
quality and CO Runway and Old monitoring, construction and
Guard Room 24 hours / one operation phase
hourly sampling as
per regulation /
standards

Noise Levels dB(A) -do- -DO- -Do-

Water Quality pH, COD, Drain outfall Composite Once in a year


TDS, Total near runway 32, sample of 3
Solids, Oil and La Chaux River samples during a
Grease day

Ecology, Density, La Chaux If required -


Diversity Forest, re-
forestation area,
ENVIRONMENTAL COSTS

S. No. Description Cost (MUR)

1. Monitoring Programs 2,485,000


2. Management Plans 5,415,000
Total 7,900,000
Add Contingencies @ 5% 395,000
Add for Detailed EIA (LS) 2,000,000
Add for Implementation of 2,500,000
Management and Supervision
Sub-TOTAL 12,795,000
Add for Escalation @ 8% per annum 2,129,088
for two years
GRAND TOTAL 14,924,088
SOCIO-ECONOMIC IMPACT
ACTIVITY WISE THROUGHPUT

ANNUAL
SECTOR THROUGHPUT
(MILLION MUR)
AIR LINES 18003.8
AIRPORTS OF MAURITIUS LTD. 1072.0
AVIATION SUPPORT SERVICES 2651.8
GOVERNMENT RELATED ACTIVITIES 277.1
DIRECTLY AIRPORT RELATED ACTIVITIES, 1945.0
LOCATED OFF AIRPORT
TOTAL 23949.8

 GDP AT MARKET PRICE IS 278.454 BILLION (2009)


 CONTRIBUTION OF CIVIL AVIATION 8.6%
CONTRIBUTION BY DIFFERENT
AGENCIES IN CIVIL AVIATION
DIRECT AND INDIRECT
CONTRIBUTION BY DIFFERENT
AGENCIES (MIL. MUR)
ELEMENTS/ ACTIVITIES DIRECT INDIRECT TOTAL MULTIPLIER
CONTRIBUTIO CONTRIBUTIONS EFFECT EFFECT
N
AIR LINES 10,504.07 7,777.72 18,281.79 1.74
AIRPORT MAURITIUS LTD. 901.15 170.82 1,071.97 1.19
(INFRASTRUCTURE)
AVIATION SUPPORT SERVICES 1,302.04 1,353.36 2,655.39 2.04

GOVERNMENT RELATED 277.12 0.00 277.12 1.00


ACTIVITIES
AIRPORT RELATED ACTIVITIES, 85.52 1868.10 1953.63 22.8433
LOCATED OFF AIRPORT

SUB TOTAL 13,069.90 11170.00 24239.90 1.8590


OUT SIDE AGENCIES
HOTELS, RESTAURANT, 40354.81 40354.87
SHOPPING & ENTERTAINMENT
TOTAL INCLUDING HOTEL & 13,069.90 51524.87 64594.77 4.7979
DIRECT AND INDIRECT
EMPLOYMENT GENERATION
ELEMENTS/ACTIVITIES EMPLOYMENT GENERATION (NO.)
DIRECT INDIRECT TOTAL
AIR LINES 2,898 285 3,183
AIRPORT MAURITIUS LTD. (INFRASTRUCTURE) 692 454 1,146
AVIATION SUPPORT SERVICES 1,346 259 1,605
GOVERNMENT RELATED ACTIVITIES 645 0 645
DIRECTLY AIRPORT RELATED ACTIVITIES, LOCATED OFF 434 9,650 10,084
AIRPORT
SUB TOTAL 6,015 10,648 16,663
OUT SIDE AGENCIES

HOTELS, RESTAURANT, SHOPPING & ENTERTAINMENT 29,944 29,944

TOTAL INCLUDING HOTEL & ALLIED SERVICES 6,015 40,592 46,607


MULTIPLYING FACTORS
EXCL. HOTEL & ALLIED SERVICES EMP. 2.770
INCL. HOTEL & ALLIED SERVICES EMP. 7.748
IMPACT OF RUNWAY CLOSURE

 LOSS = THROUGPUT-COST OF
MATERIAL

 FINANCIAL
 ECONOMIC
IMPORTANT AGENCIES
AFFECTED
 THE AIRPORTS OF MAURITIUS CO. LTD.,
 AIR MAURITIUS, THE AIRLINE OF THE NATION
AND THE OTHER AIRLINES IN OPERATION
 TOURISM AND ASSOCIATED SECTORS LIKE
HOTELS, CAR RENTALS ETC
 FUEL SUPPLIERS IN THE AIRPORT
 FLIGHT CATERERS IN THE AIRPORT
 EXPORT INDUSTRY INCLUDING CARGO
AGENTS.
 GOVERNMENT AGENCIES I.E. CUSTOMS,
EXCISE AND OTHER TAX AGENCIES
AVERAGE DAILY NUMBER OF
PASSENGER ARRIVAL
SEASON MONTH AV. DAILY PASSENGER AV. DAILY
SEASONA
L
PEAK DEC 4531 3984
(20%>normal)
JAN 3911
NOV 3493
NORMAL JUL 3483 3275
OCT 3382
AUG 3211
MAR 3201
APR 3092
LEAN FEB 2894 2676
(20%>normal)
MAY 2759
SEP 2687
JUN 2377
OVERALL AVERAGE 3258
FINANCIAL IMPACT ON AIR
MAURITIUS ON 15 DAYS CLOSURE
OF SSR AIRPORT
REVENUE MUR UNIT OF COST PER UNIT REVENUE LOSS DURING 15
COMPOSITION (MILLION) OUTPUT (MUR) DAYS OF CLOSURE (IN
MUR)
NORMAL MONTHS

PASSENGER 12088.12 PER PASSENGER 19,177 499,361,169


REVENUE
FREIGHT 1403.84 PER DAY 3,846,124 57,691,866
OTHERS 403.50 PER DAY 1,105,473 16,582,093
PASSENGER
RELATED &
HELICOPTER REV.

LEASE RECEIVED & 294.22 PER DAY 806,074 12,091,110


SUNDRY REVENUE

EXCESS BAGGAGE, 0.00 PER DAY 0 0

MAIL & COURIER 151.31 PER DAY 414,552 6,218,285


REVENUE FROM 4516.02 PER DAY 12,372,660 185,589,896
OTHER SOURCES
TOTAL REVENUE 18857.00 777,534,418
SUMMARY OF LOSS-15 DAY
CLOSURE
Loss On Entities Average Loss % Loss Peak Period
Loss
AML 64.16 1.73% 76.99
Duty Free Shop 50.55 1.37% 60.66
Air Mauritius 967.70 26.14% 1161.25
Other Airlines 25.91 0.70% 31.10
Tourism 2207.21 59.63% 2648.65
In-flight Catering 13.91 0.38% 16.70
Loss on exports 5.47 0.15% 6.56
Route Navigational 5.30 0.14% 6.36
Charges
Loss on Fuel 21.00 0.57% 25.20
Other Agency 140.12 3.79% 168.15
Taxes 200.04 5.40% 240.04
TOTAL 3701.38 100.00% 4441.66
ECONOMIC IMPACT - 7 DAYS
CLOSURE
SECTOR FINANCIAL ECONOMIC

AIRPORTS OF MAURITIUS LTD. 18.62 8.37


AIR MAURITIUS 362.85 169.11
OTHER AIRLINES 16.09 7.50
IN FLIGHT CATERING 2.75 1.18
MAURITIUS DUTY FREE PARADISE 15.05 10.54
FOREIGN EXCHANGE AGENCIES & BANKS 1.44 0.46
OTHER RETAILERS (INCL. TERMINAL CATERING) 10.82 9.33
GOVERNMENT STAFF COSTS (OTHER THAN CIVIL AVIATION) 5.31 5.31
HOTEL & ALLIED SERVICES 596.72 259.03
TOTAL LOSS EXCL. DCA SHARE 1029.65 470.85
DCA COSTS 2.52 2.52
TOTAL LOSS INCL. DCA SHARE 1032.17 473.36
EXPANDED AFFECT OF AIRPORT CLOSURE 1289.58 591.07
ADDITIONAL LOSS IN FUEL EXPENDITURE (BECAUSE OF LOW 65.83 65.83
OCCUPANCY)
TOTAL EXPANDED LOSS 1355.41 656.91
COMPARATIVE CAPITAL COST RECOVERY
SCENARIO FINANCIAL ECONOMIC
FINDINGS

CASE COST
(MUR MILLIONS) % SHARE OF
CAP.
PROJECT COST 3293.13
AVERAGE LOSS FOR 15 3701.38 112.40
DAYS CLOSURE
PEAK PERIOD LOSS 4441.66 134.87
FOR 15 DAYS CLOSURE
FINANCIAL VIABILITY
ASSUMPTIONS FOR FINANCIAL
PROJECT FEASIBILITY
 CAPITAL COST ( MUR Million )
 LAND : 696.61
 INFRASTRUCTURE : 2596.53
 TOTAL : 3293.131
 RUNWAY CIVIL & ELECTRICAL COSTS: 1863.23
 CONSTRUCTION PERIOD : 4 YEARS
 YEAR OF START : 2010
 DISTRIBUTION OF
 CONSTRUCTION COST : 2010 – Land Cost 2011- DER 2012-
40% of Construction Cost, 2013- 60% of Construction Cost
 PROJECT LIFE : 20
YEARS
 RESIDUAL VALUE : LAND -100%,
OTHERS–25%.
Financial Viability - Cost Stream (Million
MUR)

S.No Year Cost Stream


    Capit Operating/ Periodic Others Total
al Maintenance Re-
Cost Costs +land carpeting
Lease Chgs.
1 2010 696.6 0.0 0.0 0.0 696.6
2 2011 43.8 1.5 0.0 0.0 45.3
3 2012 1021. 1.5 0.0 0.0 1022.6
1
4 2013 1531. 1.5 0.0 0.0 1533.1
6
1 2014 0.0 20.1 0.0 0.2 20.3
2 2015 0.0 20.1 0.0 0.2 20.3
             
19 2032 0.0 20.1 0.0 0.2 20.3
20 2033 - 20.1 0.0 0.2 -1314.5
Financial Viability - Benefit & Net
Streams Million MUR
S.No Year Benefit Stream Net
Passen Others, Incl. Total Earnings
-ger Risk involved Earnings
Benefits
1 2010 0.0 0.0 0.0 -696.6
2 2011 0.0 0.0 0.0 -45.3
3 2012 260.9 0.0 260.9 -761.7
4 2013 268.8 0.0 268.8 -1264.3
1 2014 281.9 21.2 303.1 282.7
2 2015 296.7 21.2 317.8 297.5
           
19 2032 574.0 21.2 595.2 574.8
20 2033 574.0 21.2 595.2 1909.6
        IRR 11.02%
FINANCIAL VIABILITY -
SENSITIVITY ANALYSIS

S. No. CASE DESCRIPTION FIRR FIRR


Intl. Pax. Intl. Pax,
UDF 200 UDF 100
1 BASE CASE WITH NO UDF CHARGES NR NR
2 BASE CASE WITH ASSUMED UDF 10.54% 3.66
CHARGES
3 10% DECLINE IN PASSENGER REVENUE 9.39% 2.94

4 20% DECLINE IN PASSENGER REVENUE 8.40% 2.33

5 WITH 10% INCREASE IN CAPITAL COST 9.67% 3.05


6 WITH 20% INCREASE IN CAPITAL COST 8.91% 2.54
7 10% DECLINE IN PASSENGER REVENUE 8.60% 2.41
+ 10% INCREASE IN CAPITAL COST
FINANCIAL VIABILITY -
SENSITIVITY ANALYSIS-
Delayed

S No. CASE DESCRIPTION CAPITAL FIRR FIRR


COST Intl. Pax. Intl. Pax.
(MIL. MUR) UDF 200 UDF 100

1 3293.1 10.54 3.66


BASE CASE WITH PROPOSED
PROJECT START
2 3725.2 9.52 3.05
PROJECT START DELAYED BY 2YR.
3 3967.5 9.03 2.73
PROJECT START DELAYED BY 3YR.
4 4229.2 8.55 2.41
PROJECT START DELAYED BY 4YR.
5 4511.8 8.06 NR
PROJECT START DELAYED BY 5YR.
RISK ASSESSMENT
RISK ASSESSMENT
 LAND ACQUISITION
– LAND FOR THE RUNWAY AND DIVERSION OF ROAD IS STILL TO BE
ACQUIRED. NON-AVAILABILITY OF LAND IS A POTENTIAL RISK

 NON-AVAILABILITY OF CONSTRUCTION MATERIALS


– IMPORTANT MATERIAL LIKE BITUMEN IS TO BE IMPORTED. NON-
AVAILABILITY OR SCARCITY OF BITUMEN AT SOURCE COUNTRY
WILL LEAD TO TIME AND COST OVERRUNS

 PROJECT FUNDING RISK


– PROJECT HAS TO BE FINANCED THROUGH LOANS. NON-
AVAILABILITY OF FUNDS IS A POTENTIAL RISK IN PROJECT
IMPLEMENTATION

 OPERATIONAL RISK
– OBSTACLES IN THE APPROACH AND LA-CHAUX RIVER AT THE END
OF 32 RUNWAY (14 END) ARE POTENTIAL RISKS. SUITABLE
APPROACH PROCEDURES ARE TO BE PREPARED.
– REACHING OF CFR FROM THE EXISTING LOCATION WILL BE A RISK
IF BOTH THE RUNWAYS ARE OPERATIONAL. DEDICATED CFR IS TO
BE STATIONED FOR THE SECOND RUNWAY TO MINIMIZE LOSSES.
– PRESENCE OF LA-CHAUX RIVER AT 14 END.
CONCLUSIONS

1. CONSTRUCTION OF 2ND RUWAY IS TECHNICALLY FEASIBLE FOR


LANDING OF ALL WIDE BODIED AIRCRAFTS IN OPERATION & A-380.
2. TAKE OFF OF WIDE BODIED AIRCTAFTS WITH LIMITED PAYLOAD
3. CAT-II APPROACH FEASIBLE WITH SIMILAR DISPENSATIONS AS FOR
MAIN RUNWAY- WILL BE DEVIATION FROM ICAO.
4. ATC ELEVATION ADEQUATE FOR 2ND RUNWAY ALSO.
5. COST OF THE PROJECT WILL BE 3335.09 MILLION MUR (INCLUSIVE OF
ESCALATION FOR PLANNING AND EXECUTION PERIOD AND LAND COST)
6. TOTAL DIRECT AND INDIRECT THROUGH PUT OF AIRPORT BASED AND
DEPENDENT ENTITIES IS 64.59 BILLION AGAINST 27.92 BILLION IN
1999 (8.5% INCREASE ANNUALLY) . CREATION OF JOBS INCREASED TO
40592 AGAINST 26300 IN 1999 (4.4% INCREASE ANNUALLY).
JUSTIFYING THE APPREHENSION OF EFFECT ON ECONOMY. MULTIPLIER
FACTOR IS 1.86 AGAINST 1.87 BY UNIVERSITY OF MAURITIUS
Conclusions- (Contd.)

7. TOTAL IMPACT OF RUNWAY CLOSURE IN PEAK


PERIOD WILL BE 4441 MILLION MUR (35% MORE
THAN PROJECT COST)- 1.5% OF GDP. THE LOSS WILL
GROW AS EARNINGS FROM TOURISTS HAVE BEEN
INCREASING AT HIGHER RATE THAN GDP GROWTH.
8. THERE WILL NOT BE ANY ADVERSE IMPACT ON
ENVIRONMENT WITH APPROPRIATE MANAGEMENT
PLANS.

9. PROJECT SHOWS A RETURN OF 10.54 % WITH A


UDF OF 200 MUR AND 3.66% WITH UDF OF 100
MUR (ONLY ON INTL DEPARTING PASSENGERS)
RECOMMENDATIONS

1. THE NECESSACITY TO MITIGATE THE


EVER PRESENT RISK OF MAIN RUNWAY
BEING UNAVAILABLE WARRANTS
CONSTRUCTION OF 2ND RUNWAY-
SHOULD BE IMPLEMENTED AS PART
OF DISASTER MANAGEMNT PLAN FOR
THE NATION- ON TOP PRIORITY BASIS.
 THANKS FOR YOUR ATTENTION
ABOUT RITES

 ESTABLISHED IN THE YEAR 1974


 A GOVERNMENT OF INDIA ENTERPRISE
 PREMIER CONSULTANCY ORGANIZATION IN
TRANSPORT SECTOR SUCH AS AIRPORTS,
HIGHWAYS, RAILWAYS, PORTS &
WATERWAYS, ROPEWAYS, URBAN
TRANSPORT ETC.
 EMPLOYS MORE THAN 2000 ENGINEERS
 WORK EXPERIENCE IN MORE THAN 66
COUNTRIES
 CONSULTANCY TURNOVER ABOUT US $ 140
Million

10/06/10 84
PRELIMINARY DESIGN
NAME SLOPE MAX. PROPOSED
PERMISSIBLE
RUNWAY LONGITUDINAL 1.00% 0.93%
CH: 0 - 784 +0.79%
CH: 784-1865 +1.172%
CH: 1865 – 2175 +0.75%
CH: 2175 – 2900 +0.79%
TRANSVERSE 1.50% -1.00%
RUNWAY TRANSVERSE 2.50% -1.00% (SOUTH)
SHOULDERS -2.50% (NORTH)
RUNWAY TRANSVERSE 2.50% -1.00%
STRIP (SOUTH)
TRANSVERSE -2.50%
(NORTH)
PRELIMINARY DESIGN

NAME SLOPE MAX. PROPOSED


PERMISSIBLE
TAXIWAY1 LONGITUDINAL 1.50% +1.33%
TRANSVERSE 1.50% -1.00%
TAXIWAY2 LONGITUDINAL 1.50% +0.72%
TRANSVERSE 1.50% -1.00%
TAXIWAY3 LONGITUDINAL 1.50% +1.38%
TRANSVERSE 1.50% -1.00%

You might also like