QUALITY CONTROL PROCEDURE

TABLE OF CONTENTS

PAGE

1. SCOPE 2

2. DIFINATION 2

3. REFERENCE 2

4. RAW MATERIAL PROCUREMENT 2

5. MATERIAL RECEIVING INSPECTION 3

6. MATERIAL CONTROL 3

7. QUALITY CONTROL INSPECTION PROGRAMS FOR

FABRICATION 4

8. ACCEPTANCE CRITERIA FOR DIMENSION CHECK 5

9. QUALITY CONTROL INSPECTION PROGRAMS FOR

PAINTING 5

10. QUALITY CONTROL INSPECTION PROGRAMS FOR

PAINTING 6

11. DOCUMENTATION 7

APPENDIXES 8

APPENDIX 1 DIMENSION TOLERANCE 8

APPENDIX 2 WELDING DIMENSION TOLERANCE. 9

12. ATTACHENT 11

ATTACHMENT 1 –Inspection Record For Incoming Material. 12

ATTACHMENT 2 – Dimension Inspection Report. 13

ATTACHMENT 3 – Welding Inspection Report. 14

ATTACHMENT 4 – Coating Inspection Report. 15


Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

1. SCOPE

a) Inspection and test of equipment shall be based on approved drawing and


approved applicable procedures.
b) The quality Control Department shall responsible for the following but not be
limited:
• Continuous check for all production process during the whole fabrication
periods.
• Conduct all required tests, checks, and inspection.
• Maintain the record for all the quality control document for
review/reference at all times and final MDR.

2. DEFINITIONS

The following definitions shall apply throughout the specification:

a) The Contractor shall mean…………..PT…..


b) The Subcontractor shall mean PT …………

3. REFERENCE

• Material : ASTM: A36,ASME: SA 240, JIS: E3101:2004, SNI,


SII.
• Welding : AWS D1.1
• Client Specification : PT. …………….. Drawing Approval.
4. RAW MATERIAL PROCUREMENT

a) A l l r a w m a t e r i a l w i l l b e s u p p l i e d b y S ub c o n t r a c t o r s h a l l b e B a c k e d u p b y a n d
conform to their relevant mill/test’s certificates.

b) when material received from the mill does not satisfy the standard’s
tolerance for camber, profile, flatness or sweep corrective work by the use of
c o n t r o l l e d h e a t i n g , c h e m i c a l a n d m e c h a ni c a l s t r a i g h t e n i n g , s u b j e c t t o t h e
limitation of the standards, may be perform. It could be done or shall be
replace with a new one and precise one.

c) Steel material for fabrication shall not be heavily pitted or rusted.

d) Subcontractor shall provide the following documents for record and control
of material.

• Material List & Cutting Plan.


• Material Test Report/Mill Certificate(from the supplier)
• Delivery List
Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

5. MATERIAL RECEIVING INSPECTION

a) U p o n a r r i v a l o f t h e m a t e r i a l a t f a b ri c a t i o n y a r d s , W a r e h o u s e S e c t i o n w i l l
inform QA-QC Department and Project Control to recheck the raw material.
Scope of the inspection shall include visual dimension, sharpness, thickness,
heat no. or manufacturer no., etc.

b) Identification marks of material grade shall be clearly marked on all pieces


of material including those cut from stock or from the whole material itself.
This identification marks shall r e m ai n clearly visible at all times.
Recommended type of medium for identification marking shall be stamp,
paint or crayons. Subcontractor shall propose to Contractor the method
inspection.

c) Any non-conformance between Client document and material received by PT.


………………, QA/QC Department will inform with Quality Assurance
Confirmation (QAC).

d) When some material are unacceptable, QA/QC Department marked the


material as “REJECTED”

e) R e p a i r m a t e r i a l s h a l l c l i e n t s p e c i fi c a t i o n a n d r e p a i r p r o c e d u r e a p p r o v e d b y
client.

f) Inspection result shall be reported in Material Receiving Report .

6. MATERIAL CONTROL

a) After material received inspection has been conducted and material been
accepted, the Warehouse Section shall store the material and issue to the
fabrication section upon instruction.

b) The material received by Warehouse Section and material issue for


fabrication shall be continuously reported to Project Control of status the
Project’s materials.

c) The excess raw material from the fabrication section shall clearly be
identified and returned to the Warehouse Section for restore.

d) Stock material on warehouse shall be checked for visual and Dimension by


quality control. Material should be store in secure place to preserve the
accuracy and quality before process fabrication.
Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

7. QUALITY CONTROL INSPECTION PROGRAMS FOR FABRICATION

A l l f a b r i c a t e d p a r t s h a l l b e i ns p e c t e d t o t h e f o l l o w i n g i t e m s :

7.1. IDENTIFICATION MARKS

a) Transfer of identification marks (include heat no.) shall be

check prior to cutting.

b) Material traceability report shall be made.

7.2. MARKING

a) Giving the mark OK, if result of mark is correct.

b) After giving mark OK, we can do the next process.

7.3. DIMENSION

a) Checking the “ MAL “ according on the place.


b) MAL made the duplicated equipment as same as one from
paper/plywood.
c) Identity that the MAL has been made and checked in accordance
to drawing approval.
d) Only approved MAL will be used for fabrication process (marking,
cutting, bending, rolling, beveling)
e) Progressive dimensional check shall be conducted at stages
before, during and after the manufacturing process.
f) Dimensional marking shall be c h e ck e d prior to cutting, beveling,
bending, and rolling. After part or final assembling, all dimensional
marks are to be reconfirmed for accuracy prior to further works such as
reforming, etc. in which the dimensional inspection shall be conducted.
g) All measuring Tools to be used for Measuring and Inspections shall be
calibrated by an Authorized Agency. The Calibration records shall be
kept as a QA records.
h) Check with measuring tools all dimensional of individual members/shop
assemblies, within the specified tolerance.
i) Inspection result shall be reported in the from of Dimension
Inspection Report (Attachment – 2)
Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

8. ACCEPTANCE CRITERIA FOR DIMENSIONAL CHECK

a) Steel Structures :
Dimension tolerance for steel structure fabrication shall be accordance with
Appendix – 1

9. QUALITY CONTROL INSPECTION PROGRAMS FOR WELDING

a) Prior to welding activity, welding p ro c e d u r e qualification test, welding


procedure specification, welding map, welder performance test and welder
list shall be reviewed and approved by Contractor and Company.

b) All fabricated parts shall be inspected as to the following :

• Visual Inspection.

- Welding inspection shall ensure all parameter and condition

- As per WPS/PQR and welder has been full filled before welding, during
welding and after welding.
- A l l w e l d i n g w i l l b e v i s u a l l y i n s p e c t ed t o c h e c k i f t h a t t h e r e a r e d e f e c t s
such as undercut, crack, blow hole, slag inclusion, and fused spatter.
- All parts shall be thoroughly cleaned.All dirt, welding electrode stubs
and foreign matter shall be removed.
- The leg size of fillet should be in accordance with the design
stipulation.
- Formed corner of bracket shall be visually checked, and shall be no
crack or harmful defects is produced.
- Welding tolerance shall be accordance with Appendix – 2

• NDE
- Non destructive examination (NDE) of pressure boundary Weld and
attachment welds to pressure boundary shall be done in accordance
with the approved NDE Procedure.

c) When PWHT and hardness test is required, therefore Subcontractor shall


maintain these activities to comply with the approved procedures.

d) Inspection result shall be reported in the from Welding Inspection Report.


Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

10. QUALITY CONTROL INSPECTION PROGRAMS FOR PAINTING

e) All surfaces prepared for painting are to be inspected and the surface
preparation standard and paint used shall be reviewed and approved by
Contractor prior to the start of the work.

f) Contractor shall be notified of any defects, improper material or


workmanship or any conditions which affect the satisfactory performance
and permanency of work.

g) No work shall proceed at any stage of the job until the following stage
inspections have been carried out and approved :
• Before blasting :

- The surface shall cleaned from dirt, dust, and other foreign matter.

- The surface have cleaned shall be dried.

• After blasting :

- Grades surface preparation.

- Surface profile.

h) Improper procedures during application, even though the specified total dry
film thickness has been achieved, shall be sufficient cause for complete
removal of the applied material and re-application using the specified
procedure.

i) Inspection result shall be reported in the form Coating Inspection Report


(Attachment – 3).
Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

11. DOCUMENTATION

Inspection report shall be maintained by Subcontractor and approved by the


involved parties.
Table Content of MDR :

- Inspection Release Certificate (IRC)


- Certificate Of Compliance for fabricated for item
- Inspection Test and Plan
- Non Conformance Report (NCR)
- Welding Procedure Including Production Test Result WPS/PQR.
- Welder List Qualification Records
- Material Mill Certificate.
- Fabrication Procedure
- Painting Procedure
- Packing Procedure
- Inspection Report for Incoming Material
- Material Certificate
- Inspection Report
- Dimension Report and Welding Report
- Painting Report
- Environment Condition
- Surface Preparation
- Coating Application
- Film Thickness (DFT)
- Shop Inspection Test
- NDE report
- NDE Personal Qualifications
- Deviation Control
- Leak Test Procedure
- Major Welds Repair
Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

No Description Figure Tolerance

Excess Weld

6 Metal

(e2)

Under Cut

7 (e3) e3 ≤ 1 mm

8 Over Lap e4 = Unacceptable

(e4)
Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

No Description Figure Tolerance

1. α ≤ 1.5 mm
Porosity 2. α ≤ 1.5 mm
9 (α ) 3. Cluster is
unacceptable

Unacceptable
Crack

Sparter Unacceptable

Excess B – b ≤ 5 per 150 mm


Cupping
Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE
Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

b) Attachment – 2 : Dimension Inspection Report

c) Attachment – 3 : Welding Inspection Report


Document No. :
Company Revision/Edition :
Date :
TECHNICAL IMPLEMENTATION MANUAL Page :
QUALITY CONTROL PROCEDURE

You might also like