September October November December January February March April May June

ID Task Name Duration 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/3 3/10 3/17 3/24 3/31 4/7 4/14 4/21 4/28 5/5 5/12 5/19 5/26 6/2 6/9
1 Project Management 214 days

2 Project Kickoff Meeting 1 day

3 Existing System Evaluation 10 days

4 Project Scope Definition 10 days

5 Detailed Design Specifica 71 days

6 Preliminary Specifica 54 days

7 General Specifica 18 days

8 Sequence of Op 11 days

9 Preliminary D 5 days

10 Design Revi 1 day

11 Design Final 5 days

12 PLC Standard S 16 days

13 Preliminary D 10 days

14 Design Revi 1 day

15 Design Final 5 days

16 Operator Interfa 16 days

17 Graphics De 10 days

18 Graphics De 1 day

19 Graphics De 5 days

20 Logic Softwa 5 days

21 Control Panels 11 days

22 Layout - Pre 5 days

23 Layout - Rev 1 day

24 Layout - Fina 5 days

25 SCADA System 21 days

26 Database 10 days

27 Control Logi 5 days

28 Screen Arch 5 days

29 Graphics De 10 days

30 Graphics De 1 day

31 Graphics De 5 days

32 Local Area Netw 16 days

33 LAN Design 10 days

34 LAN Design 1 day

35 LAN Design 5 days

36 Specification Managem 5 days

37 Specification Finalize 10 days

38 System Development 61 days

39 Programmable Contr 36 days

40 Software Config 25 days

41 Memory Map 5 days

42 Standard So 10 days

43 Control Logi 10 days

44 Software Docum 11 days

45 Documentat 5 days

46 Documentat 1 day

47 Documentat 5 days

48 Operator Interfaces 25 days

49 Software Configu 15 days

50 Documentation 10 days

51 Control Panels 30 days

52 Fabrication 20 days

Task Progress Summary Rolled Up Split Rolled Up Progress Project Summary


Project: Project
Date: Thu 10/31/02 Split Milestone Rolled Up Task Rolled Up Milestone External Tasks

Page 1
September October November December January February March April May June
ID Task Name Duration 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/3 3/10 3/17 3/24 3/31 4/7 4/14 4/21 4/28 5/5 5/12 5/19 5/26 6/2 6/9
53 Delivery 10 days

54 SCADA System 20 days

55 Database Configu 10 days

56 Control Logic Con 5 days

57 Graphics Configu 20 days

58 Local Area Networks 5 days

59 Speed Test 5 days

60 PC's 5 days

61 Archive Data/Alar 5 days

62 Disaster Recover 5 days

63 Configuration File 5 days

64 Documentation 187 days

65 Drawings - Pre-Cons 75 days

66 P&ID Drawings 20 days

67 Input/Output Layo 10 days

68 Panel Drawings 10 days

69 LAN Architecture 5 days

70 DC Power Distrib 2 days

71 AC Power Distrib 2 days

72 Drawings - As Built 10 days

73 Manuals 25 days

74 Hardware Manua 5 days

75 Operations Manu 15 days

76 Maintenance Man 5 days

77 PLC Manual 5 days

78 OI Manual 5 days

79 Programming Ma 5 days

80 SCADA Manual 5 days

81 Manuals - As Built 2 days

82 Hard/Soft Copy Delivery 5 days

83 In house Preliminary Syste 20 days

84 Factory Acceptance Test 5 days

85 Commissioning 20 days

86 SAT 5 days

87 Documentation Review - A 1 day

88 Training 10 days

Task Progress Summary Rolled Up Split Rolled Up Progress Project Summary


Project: Project
Date: Thu 10/31/02 Split Milestone Rolled Up Task Rolled Up Milestone External Tasks