You are on page 1of 11

PIT TO PLANT

CURRENT TRENDS

A l l a n D. F e r n i e
Wright E n g i n e e r s L i m i t e d
Vancouver, B . C . , Canada

For p r e s e n t a t i o n a t t h e SNE-AIME F a l l X e e t i n g and E x h i b i t


S a l t Lake C i t y , Utah - October 19-21, 1 9 8 3

Permission is hereby given to publish with appropriate acknowledgments,


excerpts or summaries not ta exceed one-fourth of the entire text of the paper.
Permission to print in more extended form subsequent to publication by the Institute
must be obtained from the Executive Director of the Society of Mining Engineers
of AIME.
If and when this paper is published by the Society of Mining Engineers of AWE, it
may embody certain changes made by agreement between the Technical Publications
Committee and the author, so that the form in which it appears here is not necessarily
that in which it may be published later.
These preprints are available for sale. Mail orders to PREPRINTS, Society of Mining
Engineers, Caller No. D, Littleton, Colorado 80129,
PREPRINT AVAILABILITY LIST IS PUBLISHED PERIODICALLY IN

Abstract.
Growing i n t e r e s t i n p i t c r u s h i n g
and conveying i s e v i d e n t from t h e m y
a r t i c l e s , t e c h n i c a l p a p e r s , and new equipment
development r e c e n t l y presented.
A p p l i c a t i o n o f a p i t c n u h i n g and conveying
system is complex, as many f a c t o r s puch as
mine d e s i g n , p r o d u c t i o n s c h e d u l i n g as w e l l as
i n i t i a l and ongoing capitel. and o p e r a t i n g
c o s t s must be thoroughly and r e a l i s t i c a l l y
examined.
T h i s paper w i l l a d d r e s s t h e fundamentals t o
b e considered and review s e v e r a l approaches t o
developing a t o t a l system f o r a new and e x i s t i n g mine s i t u a t i o n .
The p l a n n i n g f u n c t i o n
w i l l be o u t l i n e d and o p e r a t i n g and d e s i g n
c r i t e r i a d e f i n e d t o i n t e r f a c e t h e mining opera t i o n and t h e p i t c r u s h l n g conveying system.
Introduction
I n - p i t c r u s h i n g and- conveying (ICC) is n o t
t h e u n i v e r s a l panacea f o r r e d u c i n g t h e opera t i n g c o s t s o f open p i t mining o p e r a t i o n s ;
however, economic f o r c e s have caused a move
towards ICC due t o t h e r a p i d i n c r e a s e i n
l a b o u r , f u e l and maintenance c o s t s .
As a l l open p i t mines a r e d i f f e r e n t , and
s i n c e p l a n n i n g a multi-system method o f o r e
and waste e x t r a c t i o n i s far more complex t h a n
f o l l o w i n g t h e t r a d i t i o n a l t r u c k / s h o v e l method
w i t h i t s b u i l t i n f l e x i b i l i t y , a n independent
e v a l u a t i o n o f s e v e r a l mining schemes i s
required
to
select
t h e most
economical
operation.
Hine P l a n n i n g
There a r e two p l a n n i n g s c e n a r i o s f o r ICC t o
c o n s i d e r i n t o d a y ' s changing mining scene,
The first i s f o r a new mine and i n v o l v e s
d e v e l o p i n g b a s i c c o n c e p t s and l o n g r a n g e
p l a n s ; t h e o t h e r i s f o r an o p e r a t i n g mine, and
i n v o l v e s developing c o n c e p t s which can be
worked i n t o t h e e x i s t i n g p i t w i t h o u t i n t e r f e r e n c e w i t h d a i l y production.
Both
planning
functions
may
require
e v o l v i n g s e v e r a l d i f f e r e n t schemes t o f i n d t h e
most p r a c t i c a l and c o s t e f f e c t i v e method o f
t r a n s p o r t i n g t h e o r e from p i t t o p l a n t .
There a r e a number o f b a s i c fundamentals
which must be a d d r e s s e d i n t h e development o f
a n I C C system, whether i t i s planned f o r a new
mine o r an e x i s t i n g o p e r a t i o n . For example:
can a permanent h i g h w a l l b e e s t a b l i s h e d ,
is i t mandatory t h a t t h e p i t develop a s a
cone
no f i x e d wall,
can t h e p i t be mined w i t h push backs,
a l t e r n a t i n g from s i d e t o s i d e ,
c a n a permanent ramp be e s t a b l i s h e d p a r t o f
t h e way i n t o t h e p i t , o r t o t h e p i t bottom,
is t h e s u r f a c e topography and p l a n t s i t e o r
w a s t e dump such t h a t a system o f o r e p a s s e s
and a conveyor ramp t o an a d i t would be
practical.
I n p l a n n i n g t h e p i t i t must be remembered
t h a t a c c e s s o r Bervice ramps need n o t be a s
wide a 3 h a u l a g e ramps and do n o t have t o
t o l l o w o r e production.
The p i t ramp e x i t i s
n o t a s c r i t i c a l f o r a s e r v i c e ramp a s f o r a
haulage road b u t should provide ready a c c e s s
t o t h o p i t shop.

I n d w e l o p i n g a n ICC s y s t e a , c o n s i d e r a b l y
more d e t a i l e d long-term p l a n n i n g is r e q u i r e d .
It i s p o s s i b l e t h a t more i n i t i a l d r i l l i n g
might have t o b e done i n o r d e r t o e s t a b l i s h
confidence i n being a b l e t o reach t h e ore with
a conveyor system and moveable c r u s h e r , s a y 20
t o 30 y e a r s hence. Tbis does n o t mean l o s s of
f l e x i b i l i t y , it i s t o prove t h a t i t is
possible.
It i s p o s s i b l e t h a t phased developnent w i l l
become p w t o f t h e o v e r a l l scheme. iUso f o r a
new mine, i t i s q u i t e l i k e l y t h a t a p i t r i m
c r u s h e r ( f i x e d o r moveable) w i l l be r e q u i r e d
f o r a p e r i o d of t i m e , a s t h e economics of I C C
hinge on r e p l a c i n g t h e h i g h l i f t and long
t r u c k h a u l a g e ramp.
I n o r d e r t o e s t a b l i s h a f l x e d ranp f o r sone
l e n g t h i n t o t h e p i t , it nay be n e c e s s a r y t o
remove a d d i t i o n a l waste d u r i n g pre-production
o r d u r i n g t h e first few y e a r s o f mining. T h i s
a d d i t i o n a l c o s t may be o f f s e t i n l a t e r y e a r s
by p r o v i d i n g extended p i t l i f e w i t h mineable
o r e a t d e p t h by t h e u s e o f ICC.
One n o t a b l e d i f f e r e n c e i n ore/waste haulage
by conveyor v e r s u s t r u c k i s t h e much narrower
conveyor ramp a t 20-25s s l o p e r a t h e r than t h e
7-81 limit placed on t r u c k ramps.
This
r e s u l t s i n a much s h o r t e r o v e r a l l d i s t a n c e
from t h e s h o v e l a t t h e f a c e t o t h e p i t r i m .
I n some c a s e s t h e s e r v i c e ramp f o r p i t
equipment a c c e s s and conveyor ramps t o g e t h e r
a r e t h e same c o s t a s t h e much wider main
h a u l a g e ramp.
An i m p o r t a n t p a r t of t h e concept planning
process i s t h e application of
financial
a n a l y s e s f o r t h e v a r i o u s schemes p r o j e c t e d f o r
a minimum o f 20 y e a r s . Comparative system and
f i n a n c i a l a n a l y s e s w l l l i n d i c a t e t h e concept
most s u i t e d t o t h e mine.
Further detailed
p l a n n i n g on t h e s e l e c t e d scheme can then be
done t o prove t h e f e a s i b i l i t y and v i a b i l i t y
through t h e v a r i o u s phases of t h e o p e r a t i o n .
h e o f t h e more s e n s i t i v e economic f a c t o r s
i n the f i n a n c i a l projections r e l a t e s t o petroleum f u e l c o s t compared t o e l e c t r i c power
cost.
The h i g h e r t h e p r i c e of e l e c t r i c i t y ,
This
t h e l e s s c o s t advantage t h e r e i s t o I C C .
can i n f l u e n c e a d e c i s i o n i f o r when t o proceed
w i t h a system.
Taking t h e complexity o f t h e p l a n n i n g
f u n c t i o n o f I C C i n t o a c c o u n t , i t is n o t
p r a c t i c a l t o develop a p i t and then t r y t o f i t
a n I C C i n t o i t . The planning must be an i n t e g r a t e d process.
H a t e r i a l s Handling
Large volume movement o f ore/waste by t r u c k
from a n open p i t i s u s u a l l y c l a s s i f i e d a s
c y c l i c o r non-continuous a s compared t o c o n t i nuous systems such a s a bucket wheel e x c a v a t o r
combined w i t h moveable conveyors.
The combination o f a t r u c k / s h o v e l o p e r a t i o n
w i t h ICC b r i n g s t h e m a t e r i a l s h a n d l i n & system
v e r y c l o s e t o continuous.
The e l i m i n a t i o n of
long up-hill
h a u l d i s t a n c e s , t r a v e l time,
d e l a y s on t h e ramp, t r u c k queuing a t t h e
c r u s h e r and s h o v e l , means t h a t with s h o r t h a u l , f a s t - c y c l e t r u c k haulage, and a f e e d e r
ahead o f t h e c r u s h e r , c o n t i n u o u s movement of
m n t e r i a l from t h e p i t c a n be achieved.

Design c r i t e r i a f o r a mining materials


~t is acknowledged t h a t t h e i n - p i t c ~ ~ s h e r
handling system !Dust be c l e a r l y defined in
can have 20-302 g r e a t e r u t i l i z a t i o n than t h e
o r d e r t o c o r r e c t l y s e l e c t , s i z e and determine ,
surface
crusher,
thus
achieving g r e a t e r
a l l t h e components which i n f l u e n c e c a p i t a l and
tonnage v i t h a s m a l l e r u n i t (54" m r a t o r y
operating costs.
T h i s paper does not atteapt
i n s t e a d o f 60").
t o g i v e a complete design c r i t e r i a o u t l i n e but
Conveyors do not run o u t of f u e l , develop
d e a l s more s p e c i f i c a l l y v i t h f a c t o r s *ich
'
f l a t t i r e s , g e t s t u c k with a box t h a t w i l l n o t
i n f l u e n c e i n - p i t c r u s h e r s and l a r g e capacity
l i f t , have t o wait f o r t h e snow plow and s o
high t e n s i o n conveyors.
on.
Conveyors have a h i s t o r y of high a v a i l M n y o f t h e f a c t o r s s e t o u t a basis
a b i l i t y when operated and maintained a s a
f o r equipment
tender
documents
and ,
t r a n s p o r t a t i o n system.
This means p r o v i s i o n
construction/installation c o n t r a c t s .
of a weekly scheduled p r e v e n t a t i v e m i n t e n a n c e
program d i l i g e n t l y followed and p r e f e r a b l y
General
computer monitored.
Location of I C C equipment from benches
0 Geographic l o c a t i o n , e l e v a t i o n , topography
being b l a s t e d is of concern. Today's b l a s t i n g
o Access, t r a n s p o r t a t i o n , r o a d s , r a i l , e t c ,
equipment and techniques keep f l y rock t o a
0 Climatic c o n d i t i o n s :
minimum,
therefore
allowing
mining
and
temperature range
m a t e r i a l s handling t o work c l o s e l y t o g e t h e r .
p r e c i p i t a t i o n , r a i n , snow
It i s v i s e t o keep t h e main haulage
wind v e l o c i t y
conveyors more than a s a f e d i s t a n c e from
seismic data
b l a s t i n g ; however, t h e c r u s h e r and i n - p i t
o Operating data:
conveyors can be w i t h i n 100-120 metres with
r e l a t i v e s a f e t y . me most v u l n e r a b l e p a r t s o f
mine o r e h a s t e production
t h e crusher and conveyors a r e t h e d r i v e s which
system u t i l i z a t i o n i n hours p e r year
can be s h i e l d e d t o a degree, thus reducing t h e
deducting:
r i s k o f being s t r u c k .
s t a t u t o r y holidays
The q u e s t i o n of system downtime f o r moving
unscheduled d e l a y s
t h e crusher i s of concern.
Most l a r g e open
fog, whiteout days
p i t o p e r a t i o n s which a r e adding I C C have a t
snow days
l e a s t one f i x e d crusher on s u r f a c e .
It is
P.M. S h i f t s
o f t e n p o s s i b l e t o f i n d some "make-upn o r e i n
equipment moves
t h e limbs of t h e p i t whlch can be kept in-hand
o p e r a t i n g hours p e r day a c t u a l deducting:
and hauled by t r u c k t o t h e s u r f a c e c r u s h e r
lunch breaks
during t h e p i t c r u s h e r move.
Each mine w i l l
s h i f t changes
b e d i f f e r e n t b u t a way t o keep t h e m i l l going
t r a v e l time
f o r s e v e r a l days can u s u a l l y be found.
system m e c h a n i c a l / e l e c t r i c a l a v a i l a b i l i t y
The two most important t h i n g s t o keep i n
unscheduled shutdown
mind a r e t o minimize t h e number of moves, and
system start-up/shutdown
if p o s s i b l e t o schedule t h e moves a t a time
o Annual production o r e and waste i n t o n s
when t h e p l a n t s t o c k p i l e is f u l l and when t h e
o Daily production t o meet p l a n t r a t e i n tons
m i l l is scheduled f o r a maintenance shutdown.
o Average production/hour
One of t h e c r i t i c i s m s of I C C i s l o s s o f
o Design r a t e +20% over average r a t e , peak
f l e x i b i l i t y i n an o r e body with varying t y p e s
r a t e ( s h o r t term) +20% over design r a t e
and grades. Location of t h e p i t c r u s h e r under
these
circumstances
becomes
critical
as
Material Characteristics
blending i n t h e p i t t o one feed p o i n t becomes
difficult.
I n some c a s e s , i t may be more
o Ore t y p e , waste rock t y p e , overburden j
economical t o have two p i t c r u s h e r s i n
description
d i f f e r e n t l o c a t i o n s feeding a main conveyor
o S p e c i f i c g r a v i t y of o r e h a s t e
haulage system.
o Bulk d e n s i t y o f crushed ore/waste
An o r e p a s s system w l t h two r a i s e s t o
o Run-of-mine lump s i z e
separate locations i n t h e p i t is another
o C h a r a c t e r i s t i c s of b l a s t e d ore/waste
a l t e r n a t i v e f o r d e a l i n g with t h e blending
slabs
problem.
blocks
There a r e s e v e r a l b a s i c c o n f i g u r a t i o n s f o r
high f i n e s
p i t crushing/conveying a l l of which have been
o Size
analysis
of
run-of-mine
broken
s u c c e s s f u l l y applied:
orehaste
Fig.1 Underground ramp system
o S i z e a n a l y s i s of crushed o r e h a s t e
Fig.2 ( a ) ( b ) and ( c ) Conveyor ramp system
o Moisture c o n d i t i o n s i n p i t influencing
Fig.3 Active o r e pass, underground c r u s h e r and
orehaste
conveyor ramp
o Ore/waste hardness, a b r a s i o n
Fig.4 Mobile c r u s h e r , c r o s s - p i t conveyor and
o Angle of repose crushed o r e / n a s t e
highwall bridge conveyor t o p i t r i m .
o Angle o f withdrawal, crushed ore/waste
From t h e foregoing d e s i g n c r i t e r i a , I C C ,
Design C r i t e r i a
system concepts can be e v o h e d and following a
s c r e e n i n g s t u d y , t h e most a c c e p t a b l e scheme
A comprehensive
design c r i t e r i a i s
The next
can be chosen f o r f u p t h e r study.
u s u a l l y defined a f t e r a p r e - f e a s i b i l i t y study.
s t a g e i n v o l v e s s e l e c t i o n o f equipment t o s e t
The s t u d y u s u a l l y d e f i n e s t h e production r a t e
i n t o t h e concept.
based on o r e grades, r e s e r v e s and i n d i c a t e d
metallurgical recoveries.

---

---

--

--

Crushing P l a n t (s
Crusher f i x e d , moveable, mobile (walking o r
crawler mechanism)
o Type
jaw, impact, r o l l gyratory
o S i z e r e l a t e d t o p i t equipment
o S e t t i n g r e l a t e d t o p l a n t requirement
o Feed arrangement
double t r u c k dump
apron o r b e l t f e e d e r
o Discharge arrangement
feeder
"take zway" conveyor

A 202 ramp i s considered


Decline Angle
maximum f o r containing m a t e r i a l on t h e
conveyor under braking conditions.
Conveyor Components:
Belt
Carry s i d e cover t h i c k n e s s 14 mm minimum.
Back cover 6 mm minimum.
Temperatures below -35 degrees C have a
dramatic e f f e c t on rubber f l e x r e s u l t i n g i n
high f r i c t i o n f a c t o r s .
S a f e t y f a c t o r of t h e b e l t should be 6.7
minimum f o r a l l running conditions.
For
a c c e l e r a t i o n and braking t h e s a f e t y f a c t o r
must n o t go lower than 3.0.
Cord p r e s s u r e on p u l l e y s f o r s t e e l c o r d
b e l t s can be about 16 kg/cm*.
Drives
Controlled
torque
and
a c c e l e r a t i o n / b r a k i n g is a must.
Pulleys and S h a f t s
For high tension
conveyors
the
pulley,
hub
and
shaft
combination must be c a r e f u l l y designed a s an
i n t e g r a l u n i t t o t r a n s f e r l a r g e dynamic f o r c e s
t o and from t h e b e l t .
Metallurgy and
treatment
of
steel
used
for
pulleys,
p a r t i c u l a r l y i f c a s t end d i s c s a r e used,
should be c a r e f u l l y s p e c i f i e d .
A l l welds should be s u b j e c t e d t o thorough
examination. P u l l e y s should be s t r e s s r e l i e v e d
a f t e r welding and machining.
Heavy-duty
diamond
lagging
for drive
p u l l e y s pays o f f , a s p u l l e y change o u t s f o r
r e l a g g i n g a r e c o s t l y i n down time.
Non-driving p u l l e y s which a r e i n contact
with t h e c a r r y s i d e of t h e b e l t should have
p l a i n lagging.
A l l p u l l e y s f o r b e l t speeds over 5 m / s
should be turned and dynamically balanced.
Idlers
Very o f t e n b e l t t e n s i o n s a r e
s u f f i c i e n t l y high t o permit wide i d l e r spacing
with minimum sag.
I d l e r s should be checked
f o r load c a p a c i t y p a r t i c u l a r l y t h e r e t u r n s a s
the
high
tension
belt
weight
can
be
significant.
I d l e r s should be heavy-duty, high-quality
r o l l s with through bored end d i s c s .
Minimum
t o t a l i n d i c a t e d runout of 0.8 mm should be
specified
to
prolong
bearing
life,
p a r t i c u l a r l y on high speed b e l t s .
For b e l t t r a c k i n g , two r o l l V-return i d l e r s
have been found d e s i r a b l e with t h e added
b e n e f i t of having f o u r bearings t o carr-jt t h e
heavy r e t u r n b e l t .
S p e c i a l a t t e n t i o n should be paid t o i d l e r
spacing and blocking on convex and concave
curves.
Even though t h e r a d i i appears t o be
l a r g e , t h e load imposed on t h e i d l e r s ,
p a r t i c u l a r l y on convex curves, is s i g n i f i c a n t .
Impact i d l e r l i f e can be g r e a t l y extended
A t load p o i n t s
by using r e s i l i e n t mountings.
having high impact, t h e e n t i r e support frame
f o r a l l t h e impact i d l e r s can be v i b r a t i o n
i s o l a t e d t o t h e b e n e f i t of i d l e r and b e l t
life.
Structure
Conveyor d r i v e heads, t a i l s and
take-up modules should have supporting s t e e l
designed with allowance f o r f a t i g u e s t r e s s e s
r e s u l t i n g from 700,000 load cycles.
Control
Control of a l a r g e crushing,
conveying system and t h e a b i l i t y t o quickly

--

- -

---

Conveyors
There a r e two major components t o be
c a r e f u l l y considered
i n t h e design and
selection
of
high
tension
conveyors,
p a r t i c u l a r l y f o r high l i f t , long c e n t r e p i t
conveyors.
The most c o s t l y p a r t of t h e system
f o r both c a p i t a l and o p e r a t i n g a r e t h e b e l t s ,
t h e second being t h e i n i t i a l c o s t of t h e
drives.
Horsepower and b e l t t e n s i o n must be
optimized t o reduce t h e number of b e l t t e n s i o n
r a t i n g s t o one o r two, a s a s p a r e b e l t is a
high c o s t inventory item. The use of m u l t i p l e
d r i v e s reduces t h e s p a r e s inventory and a l s o
allows continued o p e r a t i o n of a conveyor a t
reduced tonnage should a d r i v e f a i l .
When
lengthening o r s h o r t e n i n g conveyors within t h e
p i t , d r i v e u n i t s may be added o r reduced
accordingly.
Conveyor design must address f u l l y , tempera t u r e c r i t e r i a , a s w e l l a s c h a r a c t i s t i c s of
t h e m a t e r i a l t o be handled. This paper i s not
intended t o t r e a t t h e s u b j e c t of conveyor
design but t h e success of an i n - p i t conveyor
system hinges on many component, s e l e c t i o n
f e a t u r e s which a r e highlighted f o r consideration.
Conveyor S e l e c t i o n :
B e l t Width
To avoid s p i l l a g e from a b e l t
c a r r y i n g c o a r s e crushed ore/waste, p a r t i c u l a r
a t t e n t i o n must be paid t o t h e load p o i n t s and
b e l t edge d i s t a n c e t o t h e load on t h e b e l t .
Based on 305 mm, maximum lump s i z e (which
could have a long dimension o f 457 mm), a
minimum of 203 mm edge d i s t a n c e a t t h e load
p o i n t should be allowed.
For c o a r s e o r e
b e l t s , i t i s d e s i r a b l e t o keep t h e crosss e c t i o n a l load t o l e s s than 80% of t h e
Conveyor Equipment Manufacturers Association
s t a n d a r d s (CEMA) when c a r r y i n g t h e design
tonnage.
T h i s means t h a t flowsheet tonnage
w i l l be 65-702 of CEMA depending on c o n t r o l o f
feed t o t h e conveyor system. Peak tonnage can
The crossbe a s high a s 85% of CEMA.
s e c t i o n a l load should then be c a l c u l a t e d using
a 20 degree surcharge a n g l e using 35 degree
A s t h e m a t e r i a l is
equal l e n g t h i d l e r r o l l s .
conveyed over a long d i s t a n c e , t h e dynamic
s e t t l i n g of t h e load can o f t e n reduce t h e
surcharge a n g l e t o 15 degrees.
This reduces
t h e edge d i s t a n c e t o 198 mm which is adequate
t o c o n t a i n t h e load.
For c o a r s e o r e conveyors 4 t o 5
Speed
For overburden conveyors 5 t o 8 m/s.
m/s.
I n c l i n e k n ~ l e A 25% ramp i s considered
maximum f o r maintenance access.

--

a s c e r t a i n t h e cause of and respond t o


unscheduled shutdown i s an a r e a which must be
adequately considered.
The f i r s t a c t i v i t y is t o d e f i n e t h e e x t e n t
and l o c a t i o n of c o n t r o l and monitoring by
producing an Instrument Control Diagram. From
instrument d a t a s h e e t s , loop diagrams can be
prepared.
The use of video d i s p l a y , programmable
logic
controllers,
combined
with
a
t e l e m e t e r i n g system t o a c e n t r a l c o n t r o l panel
allows complete monitoring and c o n t r o l of t h e
system.
The foregoing d i s c u s s i o n of design c r i t e r i a
and component f e a t u r e s covers a s m a l l p a r t of
the total.
Areas such a s mechanical,
s t r u c t u r a l , e l e c t r i c a l , instrumentation, dust
control,
fire
detection
and
suppression
r e q u i r e s complete coverage t o d e f i n e t h e
system.
Summary
I n - p i t crushing and conveying i s i n t h e
development; phase.
New equipment and design
innovabion w i l l come about i n an e f f o r t t o
reduce t h e c o s t of mine m a t e r i a l s handling f o r
a l l open p i t o p e r a t i o n s .
Planning an i n - p i t crushing and conveying
system i s a complex procedure and r e q u i r e s
confirm
its
careful
consideration
to
p r a c t i c a b i l i t y and economic b e n e f i t .
A s t h e p i t c o n f i g u r a t i o n is i n f l u e n c e d by
t h e m a t e r i a l s handling system, mine planning
i n c o r p o r a t i n g p i t crushing and conveying must
be an i n t e g r a t e d design.
The a p p l i c a t i o n o f
crushing and conveying t o a p i t r e q u i r e s long
term planning and p o s s i b l y more i n i t i a l
d r i l l i n g a s i t i s d i f f i c u l t t o change b a s i c
concepts a f t e r 10 o r 15 y e a r s of production.
I n p i t s with varying o r e t y p e s , scheduling
on a weekly b a s i s may be necesary t o determine
t h e p r a c t i c a b i l i t y of feeding a blend t o an
i n - p i t crusher.
T h i s complication combined
w i t h grade cut-off and s t r i p r a t i o becomes a
vital
part
of
planning
crushing
plant
relocations.
The i n - p i t conveyor system must be designed
f o r high u t i l i z a t i o n and a v a i l a b i l i t y .
To
t h i s end p r e p a r a t i o n o f a comprehensive
"Design C p i t e r i a n is an a b s o l u t e n e c e s s i t y , a s
i t p l a y s an important r o l e i n e s t i m a t i n g
c a p i t a l c o s t s , p r o j e c t i n g o p e r a t i n g c o s t s and
s u s t a i n i n g c a p i t a l requirements.
A l l t h e s e f a c t o r s become p a r t o f t h e t o t a l
economic p i c t u r e and determine t h e s u c c e s s of
t h e mining o p e r a t i o n i n c o r p o r a t i n g i n - p i t
c r u s h i n g and conveying.
References
Hays, Ronald M., October 1983
Mine plan in^ Considerations f o r I n - p i t
Crushing and Conveying, SME-AIME, S a l t Lake
C i t y , Utah.

You might also like