Objective:
To automatically populate the list of Tasks upon selecting 'Priority' in a Notification.
Different sets of Tasks will be populated automatically according to the selected 'Priority' value.
Introduction:
Because this process is based on a 'Priority type' which is assigned to a notification, often custom notification
types are preferred for this process.
(This is where the standard notifications prefer other priority types.)
Here the custom notification type is 'AC' and a case of Overhauling process of HVAC equipments is
demonstrated.
The End result of this document is illustrated here:
Create a notification, select the priority ( Say here 'PAC O/H' ) , then in the menu bar go for
Edit --> Tasks --> Determine .
Set of tasks relevant to 'PAC O/H' are populated automatically, as shown in the images1,2,3 below.
Image1 (IW21/IW22)
Image2
Image3
In above picture, Rel.end field specifies the number of days the job takes to complete.
(Determines the Required Start and Required end dates of the Notification upon selecting the prioirty)
Note the Priority numbers in the above picture (1,2,3,4,5 etc), which will be referred in the forthcoming steps
Specify the Catalog type (2), Code Groups and Codes as under against priority values 1,2,3 etc (Referred
above)
(So many number of priority values as many the equipment types)
Now your Notification Type 'AC' is enabled to determine tasks automatically, different set of tasks with different
value of 'Priority type' as demonstrated in the beginning of this document.
Thank you
-Jogeswara Rao K