Terminal Dimensioning

Tiago A. R. Santos
Transporte Martimo e Portos I

Summary

General Dimensioning Methodology


Container Terminals
Terminal planning

Dry Bulk Terminals


Terminal planning

Transporte Martimo e Portos I

Terminal planning
Planning is generally performed in two steps:
Preliminary planning
Simulation

Transporte Martimo e Portos I

Terminal planning

Planning is necessary at three


levels:
Infrastructure,
Superstructure,
Operational.

Transporte Martimo e Portos I

Port Infrastructure

Wharf: structure of timber, masonry, cement, or other material built along


or at an angle to the navigable waterway, with sufficient depth of water to
accommodate vessels and receive and discharge cargo or passengers.
Quay: when applied to great solid structures in large ports.

Transporte Martimo e Portos I

Port Infrastructure

Transporte Martimo e Portos I

Port Superstructure

Warehouse: building for storage of cargo.


Shed: building located on or near a pier (piershed) or wharf (wharf shed)
used for short-term storage of cargo in transit.

Transporte Martimo e Portos I

Terminal planning

Seasonality

Transporte Martimo e Portos I

Container Terminal Planning

Saanen (2012)

Transporte Martimo e Portos I

Container Terminal Planning

Saanen (2012)

Transporte Martimo e Portos I

Numerical method - 1

Thoresen (2003), Port designer handbookss: recommendations and guidelines.

Transporte Martimo e Portos I

Numerical method - 2

Transporte Martimo e Portos I

Numerical method - 3

UNCTAD (1985)

Thoresen (2003)

Transporte Martimo e Portos I

Numerical method - 4

Transporte Martimo e Portos I

Numerical method - 5

Transporte Martimo e Portos I

Numerical method - 6

Transporte Martimo e Portos I

Numerical method - 7

Transporte Martimo e Portos I

Numerical method - 8

Transporte Martimo e Portos I

Numerical method - 9

Transporte Martimo e Portos I

Numerical method - 10

Transporte Martimo e Portos I

Numerical method - 11

Transporte Martimo e Portos I

Graphical Method - 1
UNCTAD Handbook of Port Planning

~12 Ha

Transporte Martimo e Portos I

Graphical Method - 2
UNCTAD Handbook of Port Planning

~375 days

Need for two quays!

ships arriving each year

Transporte Martimo e Portos I

Graphical Method - 3
UNCTAD Handbook of Port Planning

~3.8 million USD

Transporte Martimo e Portos I

Graphical Method - 4
UNCTAD Handbook of Port Planning

Transporte Martimo e Portos I

Dry bulk terminal planning


UNCTAD Handbook of Port Planning

Transporte Martimo e Portos I

Dry bulk terminal planning


UNCTAD Handbook of Port Planning

1 million dollar

Transporte Martimo e Portos I

Dry bulk terminal planning

Transporte Martimo e Portos I

Dry bulk terminal planning


UNCTAD Handbook of Port Planning

~140000 ton
~70000 ton

Transporte Martimo e Portos I

Dry bulk terminal planning


UNCTAD Handbook of Port Planning

~140000 ton

Transporte Martimo e Portos I