Professional Documents
Culture Documents
July 23, 1998 | Martinez, J. | When it contains stipulations which admit of several meanings | by: M.G. Albao
PETITIONER: Oil and Natural Gas Commission (ONGC), a foreign corp. owned and controlled by Govt of India
RESPONDENT: CA, Pacific Cement Company, Inc. (PACIFIC), a private domestic corporation
SUMMARY: ONGC and PACIFIC entered into a supply contract, but PACIFIC failed to do deliver the cargo to India. They agreed that
PACIFIC will deliver Class G cement instead, but upon seeing that it did not comply with their specs, ONGC resorted to arbitration pursuant to
Clause 16. The arbitrator ruled in ONGCs favor, which decision was adopted by the Indian Civil Court, enabling ONGC to collect form
PACIFIC. ONGC sought to enforce this ruling in the Philippines, but PACIFIC moved to dismiss. SC ruled that although ONGC erroneously
invoked and interpreted Clause 16 as basis of their remedy, the foreign judgment still holds and PACIFIC was, in the end, still liable to ONGC.
DOCTRINE: Noscitur a sociis: where a particular word/phrase is ambiguous in itself or is equally susceptible of various meanings, its correct
construction may be made clear and specific by considering the company of the words in which it is found or with which it is associated
FACTS:
1. Feb 1983 - Indian company ONGC entered into a contract
with domestic company PACIFIC, where the latter was to
supply ONGC with 4,300 metric tons of oil well cement,
in consideration of ONGCs payment of $477k through a
letter of credit in favor of PACIFIC.
2. The cement was loaded on MV SURUTANA NAVA at
Surigao for delivery to Bombay & Calcutta, India.
However, because of dispute b/w shipowner & PACIFIC,
the cargo was held up in Bangkok and didnt reach India.
- PACIFIC already received payments, but despite several
demands of ONGC, the former was not able to deliver
3. Negotiations ensued betweent them, and they resolved
that PACIFIC would deliver replacement of Class G
cement cost free, but upon ONGCs inspection, the Class
G cement did NOT conform to ONGCs specifications.
4. ONGC informed PACIFIC that pursuant to Clause 161 of
their contract, it was referring its claim to an arbitrator.
5. July 1988 - ONGCs chosen arbitrator, Mr. Malhotra,
resolved dispute and set arbitral award in favor of ONGC,
directing PACIFIC to pay 1) the amount received by
PACIFIC thru the letter of credit, 2) reimbursement of
expenditure incurred due to ONGC inspection teams visit
to the Phils., 3.) establishment charges, & 4.) losses
suffered = $899k (+ interest + 1/2 of arbitration expenses)
6. To execute award, ONGC filed Petition before the Court
of the Civil Judge in Dehra Dun, India (hereinafter,
foreign court), praying that the arbitrators decision by
made the Rule of Court in India.
7. Foreign court issued notices to PACIFIC for objections
- PACIFIC complied and sent objections, but when the
court directed it to pay filing fees, it instead sent a letter
asking how much was to be paid
8. Without responding, foreign court did not admit
PACIFICs objections, so it issued its ruling, making the
arbitrators award (Paper No. 3/B-1) the Rule of the
Court, entitling ONGC to get from PACIFIC $899k
9. ONGC sent notices of demand for PACIFICs
compliance, but refused to pay
10. ONGC filed complaint for enforcement of judgment of
1
Clause 16: Except where otherwise provided in the supply order/contract all
questions and disputes, relating to the meaning of the specification designs,
drawings and instructions herein before mentioned and as to quality of
workmanship of the items ordered or as to any other question, claim, right or
thing whatsoever, in any way arising out of or relating to the supply
order/contract design, drawing, specification, instruction or these conditions
or otherwise concerning the materials or the execution or failure to execute
the same
during stipulated/extended period or after the
completion/abandonment thereof shall be referred to the sole arbitration of
the persons appointed by Member of the Commission at the time of dispute.
ISSUE-RATIO:
1. WON non-delivery of the cargo cement is a proper
subject for arbitration under Clause 16? NO
- In their argument, ONGC misquoted the phrase by shrewdly
inserting a comma between the words supply order/contract
and design where none actually exists (see bolded part of
Footnote #1)
- Given the true wording of that part of Clause 16, it is clear
that to be able to invoke said caluse, the claim must arise out
of or relate to the design, drawing, specification, or instruction
of the supply order/contract
(ONGC: non-delivery of the cargo is still covered by the
clause failure to execute the same under Clause 16)
- SC: No! The doctrine of noscitur a sociis (equally applicable
in construction of statutes as well as in ascertainment of
meaning and scope of vague and contractual stipulations),
which means that where a particular word/phrase is
ambiguous in itself or is equally susceptible of various
meanings, its correct construction may be made clear and
specific by considering the company of the words in which
it is found or with which it is associated (its obscurity or
doubt may be reviewed by reference to associated words)
=> hence, even the clause failure to execute the same must
be construed in light of the preceding words with which it is
associated, meaning, it, too, is limited only to the design,
drawing, instructions, specifications, or quality of the
materials of the supply order/contract
- that Clause 16 should pertain only to matters
involving the technical aspects of the contract is but a logical
inference considering that the underlying purpose of a referral
to arbitration is for such technical matters to be deliberated
upon by a person possessed with the required skill and
expertise which may be otherwise absent in the regular courts.
=> SC agrees with CA that the non-delivery of the oil well
cement was a matter cognizable by the regular courts, as
stipulated by the parties in Clause 15
- SC enumerated the ff. fundamental principles in the
interpretation of contracts and other instruments:
i.
CC 1373: If some stipulation of any contract should
admit of several meanings, it shall be understood as
bearing that import which is most adequate to render
it effectual.
ii.
CC 1374: The various stipulations of a contract shall
be interpreted together, attributing the doubtful ones
that sense which may result from all of them taken
jointly.
iii.
Sec. 11, RoC 130: Instrument construed so as to
give effect to all provisions. In the construction of an
instrument, where there are several provisions or
particulars, such a construction is, if possible, to be
adopted as will give effect to all.
=> The whole & every part of a contract must be considered in
fixing the meaning of any of its harmounious whole. The rule
is that a construction that would render a provision inoperative
should be avoided; instead, apparently inconsistent provisions
should be reconciled whenever possible as parts of a
coordinated and harmonious whole.
4.