You are on page 1of 2

Dok.

No

Rev

Project

PODOMORO INDUSTRIAL PARK

Subject

CONNECTING PIPE FLOW RATE IN INTAKE SYSTEM

Project Owner

2
2.1

PREPARED BY

dikei

CHECKED

APPROVED BY

Saiful

DATE

PT. SAMP

8-Oct-15

GENERAL
Project

: PODOMORO INDUSTRIAL PARK

Client

: PT. SAMP

Location

: Karawang, West of Java

Structure name

: CONNECTING PIPE FLOW RATE IN INTAKE SYSTEM

Unit measurement

: metric unit system

Comp. Software

: MS Excel

Calculation method

PUMP RATE DESIGN


GEOMETRIC DATA

100LPS

Vp?,Qp?

EL1 =
EL2 =

Water level in Tarum Barat River,


Center of connecting pipe level,
Inner Diameter of Connecting pipe
Gravity acceleration
Pumping out rate from tank

2.2.1

Conncecting pipe discharge capacity,

2.570 m'
0.50 m'
2
0.196 m
2
9.81 m/s
3
0.10 m /s

D=
A = 1/4 D2 =

Area of Connecting pipe

CALCULATION

+ 44.330

h = EL1 - EL2 =

Hight of river water above center of pipe,

2.2

+ 46.900

g=
Q2 =

Discharge velocity inside conncecting pipe

Vp = (2*g*h)1/2 =

Discharge volume inside conncecting pipe,

Qp = Vp * A =

Check for discharge capacity, Qp > Q1 :

1.394

1 of 2

>

0.10

7.10 m/s
3
1.394 m /s
(OK)

Dok. No

Rev

Project

PODOMORO INDUSTRIAL PARK

Subject

CONNECTING PIPE FLOW RATE IN INTAKE SYSTEM

2.2.2

PREPARED BY

dikei

CHECKED

APPROVED BY

Saiful

DATE

PT. SAMP

Project Owner

Pressure Head (water level) at the tank with constant discharge flow

z
2

using Bernoulli's equation in head form is follows :


where :
Pressure head 1

h1 =
z1 =

0.000 m

V12 / 2g =
z2 =

0.000 m

V22 / 2g = (Q2 / A)2 / 2g =

0.013 m

h2 = (h1 + z1 + V12 / 2g ) - ( z2 + V22 / 2g) =

2.557 m

Potensial/gravitational head 1
kinetic/velocity head 1
Potensial/gravitational head 2
kinetic/velocity head 2
Pressure head 2

2 of 2

2.570 m
0.000 m

8-Oct-15