You are on page 1of 147

Draft Report

System Impact Study Report


50 MW Felisa Solar Power Project
Prepared for:

Negros PH Solar Inc.


Barangay Felisa, Mansilingan, Bacolod City

By:

Power System Research and Consultancy Group

July, 2015

EXECUTIVE SUMMARY
This System Impact Study (SIS) is conducted for the 50 MW Felisa Solar
Power
Project of Negros Ph Solar Inc. (NPSI) in Brgy. Felisa Bacolod City. The
proposed
connection for this project is a direct connection to Bacolod 138 kV Substation.
The project currently has a 200 MW capacity endorsed by the Department of
Energy (DOE) over phases. The developers have since identified suitable land
sites and have made the requisite arrangements with the landowners for longterm leases. Various irradiation, flood, topography and soil studies have
already been conducted with positive results. In addition many of the local
and national approvals and permits have since been obtained including local
LGU endorsements. Technical layouts and routing plans have also been
identified and secured.
Currently there might be some anticipated
constraint
in
the
submarine
interconnection between Negros and Cebu islands due to various projects
being
planned for but many of which may not get implemented. In light of this
constraint
the capacity of the project was reduced to 50 MW for this current phase for
ease
of
implementation.
This project has been developed and structured to allow for a quick expansion
of another 60 MW in Phase II. The key milestone for this expansion would
be the alleviation of the potential congestion along the Cebu-Panay submarine
cable. This alleviation would be evident when either the submarine cable is
reinforced or when the various other projects included in the base data is formally
terminated.
In December 2014, Italy's Prysmian was awarded this US$111 million project by
the
NGCP for the design, supply, installation, and commissioning of a submarine

power
cable link to connect Negros and Panay islands in the Philippines. The CNP-1
cable
connection is the first stage of a larger development plan by NGCP, aimed
at
connecting the Cebu, Negros and Panay islands to each other and at
strengthening
the
country's power transmission network. The submarine cable link will be one of
the
main assets to play a core role in this plan as it will back up the existing 138 kV
oil
filled cable circuit, which is currently the only connection among the islands.
CNP-1 comprises of three HVAC (High Voltage Alternating Current) 230 kV
single
core cables with XLPE insulation and single wire armouring along a 22 km
submarine
route across the Guimaras Strait. As part of the complete system Prysmian will
also
supply and install underground cables for the land portions of the link and will
erect
the two Cable Terminal Stations (CTS) in Barotac Viejo on the Panay side and
in

Magalona on the Negros side. Delivery and commissioning is scheduled for the first
half of 2016. Phase II (60MW) of the solar plant will be implemented after CNP-1 is
commissioned.
In addition, in April 2015 NGCP announced plans to invest P1.6 billion to upgrade a
transmission facility in Cebu that forms part of a broader Visayan backbone project to
implement the Cebu substation 230 kilovolt (kV) upgrade project, this project
represents the second stage of the Cebu-Negros-Panay (CNP) 230 kV backbone project
further strengthening the grid in the Visayas. NGCPs CNP project is generally
intended to accommodate all additional capacity from new power plants that will be
built in the Visayas.
With the anticipated alleviation in congestion, NPSI will be implementing the 60 MW
Phase II expansion of this solar in the second half of 2016 and request that this be
recognized for planning purposes.

Description

Phase I

Phase II
(once CNP-1 is
completed or
when capacity
avails itself)

Size MW

50.00

60.00

Time Frame

2015/2016

2016/2017

TABLE OF CONTENTS
Executive Summary
Steady State
Stability
Frequency

Assessment

Short Circuit
Conclusion
1.

Background Information.................................................................................................10

2.

Study Assumptions........................................................................................................ 12
A.

Demand Forecast...................................................................................................12

B. Generation Expansions...............................................................................................12
C.

Transmission Expansions.......................................................................................14

D.

Grid Code Requirements........................................................................................15

3.

Proposed Connection Arrangement and System Modelling............................................19

4.

Load Flow Assessment..................................................................................................23


A.

Thermal Assessment - Adequacy in Normal Conditions (Peak Conditions)..............24

B. Thermal Assessment - Adequacy in Single Outage Conditions (Peak Conditions).......25


C.

Voltage Assessment in Normal Conditions (Peak)..................................................26

D.

Voltage Assessment in Single Outage Condition (Peak Conditions)........................27

5.

Fault Level Analysis.......................................................................................................28

6.

Stability Assessment......................................................................................................30

7.

Frequency Assessment..................................................................................................32

8.

Summary and Conclusions............................................................................................34

9.

Appendices

LIST OF TABLES
Table 1. Demand Projections for Visayas............................................................................
12
Table 2. Generator Capacity Additions for Visayas..............................................................
13
Table 3. Power Circuit Breaker Fault Duty Rating................................................................
15
Table 4. Requirements at Different Frequency Range.........................................................
17
Table 5. Lumped Generator Specifications..........................................................................
20
Table 6. Generator Transformer Data..................................................................................
21
Table 7. Transmission Line Data..........................................................................................
21
Table 8. Dynamics Data for 50 MW Lumped Generator Units.............................................
22
Table 9. Dynamics Data for the Electrical Controls..............................................................
23
Table 10. 2016 Thermal Assessment (Peak, Normal Loading)............................................
24
Table 11. 2021 Thermal Assessment (Peak, Normal Loading)............................................
24
Table 12. 2016 Thermal Assessment (Peak, N-1 Loading)..................................................
25
Table 13. 2021 Thermal Assessment (Peak, N-1 Loading)..................................................
25
Table 14. 2016 Voltage Assessment (Peak, Normal Loading).............................................
26
Table 15. 2021 Voltage Assessment (Peak, Normal Loading).............................................
26
Table 16. 2016 Voltage Assessment (Peak, N-1 Loading)...................................................
27
Table 17. 2021 Voltage Assessment (Peak, N-1 Loading)...................................................
28
Table 18. Short Circuit Rating of Selected Substations in the Grid......................................
29
Table 19. Short Circuit MVA at Power Plant S/S (Peak Loading).........................................
29

Table 20. Summary of Dynamic Stability Simulations with Power Plant...............................


31

LIST OF FIGURES
Figure 1. Generation Capacity Additions in Visayas............................................................
13
Figure 2. Transmission Expansion Projects in Visayas........................................................
14
Figure 3. Low Voltage Withstand Capability Requirement for Large Photovoltaic
Systems 18
Figure 4. Connection Scheme for the Project.......................................................................
19
Figure 5. Geographic Location of the Project.......................................................................
20
Figure 6. Equivalent Model of the Grid in the Vicinity of the Project......................................
22
Figure 7. Frequency Assessment, 2016 Peak Base Case....................................................
33
Figure 8. Frequency Assessment, 2021 Peak Base Case....................................................
33

EXECUTIVE SUMMARY
This System Impact Study (SIS) is conducted for the 50 MW Felisa Solar
Power
Project of Negros Ph Solar Inc. (NPSI) in Brgy. Felisa Bacolod City. The
proposed
connection for this project is a direct connection to Bacolod 138 kV Substation.
The project currently has a 200 MW capacity endorsed by the Department of
Energy (DOE) over phases. The developers have since identified suitable land
sites and have made the requisite arrangements with the landowners for longterm leases. Various irradiation, flood, topography and soil studies have
already been conducted with positive results. In addition many of the local
and national approvals and permits have since been obtained including local
LGU endorsements. Technical layouts and routing plans have also been
identified and secured.
Currently there might be some anticipated
constraint
in
the
submarine
interconnection between Negros and Cebu islands due to various projects
being
planned for but many of which may not get implemented. In light of this
constraint
the capacity of the project was reduced to 50 MW for this current phase for
ease
of
implementation.
This project has been developed and structured to allow for a quick expansion
of another 60 MW in Phase II. The key milestone for this expansion would
be the alleviation of the potential congestion along the Cebu-Panay submarine
cable. This alleviation would be evident when either the submarine cable is
reinforced or when the various other projects included in the base data is formally
terminated.
In December 2014, Italy's Prysmian was awarded this US$111 million project by
the
NGCP for the design, supply, installation, and commissioning of a submarine

power
cable link to connect Negros and Panay islands in the Philippines. The CNP-1
cable
connection is the first stage of a larger development plan by NGCP, aimed
at
connecting the Cebu, Negros and Panay islands to each other and at
strengthening
the
country's power transmission network. The submarine cable link will be one of
the
main assets to play a core role in this plan as it will back up the existing 138 kV
oil
filled cable circuit, which is currently the only connection among the islands.
CNP-1 comprises of three HVAC (High Voltage Alternating Current) 230 kV
single
core cables with XLPE insulation and single wire armouring along a 22 km
submarine
route across the Guimaras Strait. As part of the complete system Prysmian will
also
supply and install underground cables for the land portions of the link and will
erect
the two Cable Terminal Stations (CTS) in Barotac Viejo on the Panay side and
in

Magalona on the Negros side. Delivery and commissioning is scheduled for the
first half of 2016. Phase II (60MW) of the solar plant will be implemented after
CNP-1 is commissioned.
In addition, in April 2015 NGCP announced plans to invest P1.6 billion to
upgrade
a
transmission facility in Cebu that forms part of a broader Visayan backbone
project
to
implement the Cebu substation 230 kilovolt (kV) upgrade project, this project
represents the second stage of the Cebu-Negros-Panay (CNP) 230 kV backbone
project
further strengthening the grid in the Visayas. NGCPs CNP project is
generally
intended to accommodate all additional capacity from new power plants that
will
be
built in the Visayas.
With the anticipated alleviation in congestion, NPSI will be implementing the 60
MW Phase II expansion of this solar in the second half of 2016 and request
that this be recognized for planning purposes.

Description

Phase I

Phase II
(once CNP-1 is
completed or
when capacity
avails itself)

Size MW

50.00

60.00

Time Frame

2015/2016

2016/2017

This study was performed in accordance with the Philippines Grid Code (PGC)
and NGCP requirements. The purposes of this study are as follows:

1. Analyze the steady-state, stability, and short circuit conditions of the grid
with
the project;
2. Determine any upgrades to the transmission system that would be
required to
mitigate any adverse impacts that the project could otherwise pose on
the
reliability and operating characteristics of the transmission system
in
accordance with the PGC, NGCP standards and generally accepted
international transmission utility practices;
3. Determine any upgrades required to mitigate any degradation to
transmission
transfer capability; and
4. Determine any upgrades required to mitigate any degradation to
system
dynamic stability.
The primary area of concern of this study is the area around NGCPs
Bacolod Substation. Generated power from the proposed power plant will be
transmitted to Visayas grid through this substation.
In addition to the standard requirements of the PGC, the ERC had issued
Resolution
No. 7 Series of 2013 imposing new requirements for intermittent power plants
such
as
this project.
This proposed power plant should comply with those
requirements,
compliance thereto should be demonstrated by field tests during testing
and
commissioning.

STEADY STATE
Steady state thermal and voltage analyses were conducted to examine the
comparative
system performance with and without the proposed project. The baseline
performance
is based on the system without the proposed project. System performance
was
reevaluated with the project and compared with the baseline system. This
approach
exposes the impact of the project on the system utilizing the criteria set by the
PGC.
Steady state analysis was evaluated using a scenario where power plants at
close
proximity to the project were dispatched to its maximum feasible levels for years
2016
and 2021. Peak load for 2016 and 2021 were respectively, 1,854.8 MW and
2,279.5
MW. Simulation at this dispatch scenario enabled the examination of the
transmission
system to reliably operate with the proposed project integrated to the system.
Based on the steady state results the projects connection to the grid poses
no
significant adverse impact on the reliability and operating characteristics of
Visayas
grid. There was no significant voltage or thermal violations of reliability
criteria
associated with the entry of the project considering its priority dispatch
incentive
under the RE Law.

STABILITY
This evaluation consisted of application of faults on the system with the project
using peak base cases. The dynamic stability of the system during and after

these faulted conditions should conform to the requirements of the PGC. In


addition, voltage, frequency and power fluctuations or oscillations should
dampen within the prescribed period. Machine angle should also exhibit
acceptable coherence.
In all tested fault conditions the project would pose no significant adverse
impact on the stability of the system.

FREQUENCY ASSESSMENT
Frequency assessment showed that the system frequency will not drop as low as
59.4 Hz with the outage of the proposed power plant. Automatic Load
Dropping is not expected during this loss-of-generation scenario.

SHORT CIRCUIT
Short-circuit analysis was conducted to determine the impact of the project on
the existing fault current levels in all substations. In this study, it was assumed
that fault duty of the circuit breakers installed in the system are as follows:

Volage Level
<69 kV
>69kV <138 kV
>230 kV

Rated Short
Circuit
Current (kA)
25
31.5
40

Simulation results indicate that the entry of the proposed project will not result
to fault levels beyond the fault duties of the existing circuit breakers.

CONCLUSION
This study revealed that the addition of NPSIs Phase I, the 50 MW Felisa Solar
Power Project has no significant impact on the reliability, stability and
operating characteristics of the Visayas power transmission system.
The proposed power plant could be safely and reliably integrated to Visayas
grid. Phase II 60 MW of NPSI project will be implemented once CNP-1 is
commissioned or when there is capacity in the grid when other projects are do
not materialize.

The results of the stability simulation indicated acceptable


response
of
the
system
parameters with the proposed facility integrated, damping mostly
within the first ten
(10) seconds after the application of fault. The summary of
dynamic stability simulations is shown in Table 20 for scenarios
with the power plant.

Table 20. Summary of Dynamic Stability Simulations with


Power Plant

Status of
Grid
2016 Base

Applied Fault

Case

2021

Base

Case

Normal

Normal

Delayed

Delayed

Clearing

Clearing

Clearing

Clearing

BUS FAULTS
1. Bus Fault at NPHS_HI 138 kV Bus (3)
2. Bus Fault at BACOLOD 138 kV Bus
(237500)

Stable
Stable

3. Bus Fault at EBMAG1 138 kV Bus (237800)


4. Bus Fault at EBMAG2 138 kV Bus (237801)

Stable
Stable

Stable
Stable

Stable
Stable

Stable

Stable

Stable

Stable

Stable

Stable

Stable
Stable

5. Bus Fault at KABANKAL 138 kV Bus (237400)


6. Bus Fault at MAB HI 138 kV Bus (237300)

Stable
Stable

Stable
Stable

Stable
Stable

Stable

Stable

7. Bus Fault at AMLAN SP 138 kV Bus (237201)


8. Bus Fault at DINGLE 138 kV Bus (247200)

Stable
Stable

Stable

Stable
Stable

Stable

Stable

Stable

Stable

Stable

Stable

Stable

LINE FAULTS
1. Fault at Solar Hi-Bacolod 138 kV Line with
Tripping

Stable

Stable
Stable

Stable

2. Fault at Bacolod-EBMAG1 138 kV Line with


Tripping

Stable

Stable
Stable

Stable

3. Fault at Bacolod-EBMAG2 138 kV Line with


Tripping

Stable

Stable
Stable

Stable

4. Fault at Bacolod-Kabankalan

138 kV Line with

Tripping

Stable
Stable

Stable
Stable

Stable
Stable

Stable
Stable

Stable

Stable

Stable
Stable

Stable
Stable

Stable

Stable

Stable
Stable

Stable
Stable

5. Fault at Bacolod 138/69 kV Transformer (T2) with


Tripping

System Impact Study for Negros Ph Solar Inc.s


Page 31
50 MW Felisa Solar Power Project

6. Fault at Bacolod-BRGS TAP

69 kV Line with

Tripping
7. Fault at Bacolod 138/69 kV Transformer (T1) with
Tripping

8. Fault at Kabankalan-Mabinay HI 138 kV Line with


Tripping
9. Fault at Amlan HI-Mabinay HI 138 kV Line with
Tripping

7. FREQUENCY ASSESSMENT
Frequency assessment evaluates if the loss of the proposed power
plant
will
not
cause
the frequency to drop below 59.4 Hz frequency limit set by PGC.
For
2016
and
2021
base cases, the frequency will not fall as low as 59.4 Hz. The
outage
of
the
proposed
power plant will not result to Automatic Load Dropping (ALD). Figure
7 and Figure
8 shows the results of frequency assessments for 2016 and 2021 base cases
respectively.

System Impact Study for Negros Ph Solar Inc.s


Page 32

50 MW Felisa Solar Power Project

Figure 7. Frequency Assessment, 2016 Peak Base Case

Figure 8. Frequency Assessment, 2021 Peak Base Case


System Impact Study for Negros Ph Solar Inc.s
Page 33
50 MW Felisa Solar Power Project

1. BACKGROUND INFORMATION
Negros Ph Solar Inc. (NPSI) has embarked on developing this project by
committing
significant resources and time to identify and secure key project specifics to
ensure
project viability prior to applying for the various government permits and
approvals.
This project has been under-development for the last 6 months with the proper
site selection and technical evaluation and local stakeholders engagement and
relationship building being developed to ensure project viability. The initial
findings are very optimistic. Necessary government permits were already
secured.
This approach allows all the stakeholders, DOE, NGCP, Landowners, LGUs,
etc. to have better comfort and visibility that our Service Contract will crystalize
into a real project and not remain in development for years.
NPSI is a wholly owned Filipino corporation and was set up to fully focus on
developing the Philippine Solar market. The founder Ms. Maricel Montfort, a
highly successful native of Cadiz and currently residing in Bacolod and Manila, is
a long-standing citizen who has had extensive working experience abroad and
has returned back to the Philippines to take an active part in improving the
lives of the local Filipinos through various infrastructure projects. Ms. Montfort
is currently active with several large infrastructure and social developments
throughout the Philippines. These include medical facilities, orphanages,
water-treatment/purification projects and land & property investments. Being
a very successful business lady, she is able to fully fund the professional and

proper development of these projects.


NPSI has identified Bacolod City as a suitable site for the Solar project. Bacolod
has a stable climate with adequate sunlight throughout the year and minimal risk
of heavy typhoons or flooding. Land is plentiful and the local government
agencies are supportive of such an initiative.
NPSI has been actively developing the project for the last 6 months and
focused
on
securing the right land location and negotiating with the landowners to ensure
terms
and conditions and commercially viable for the project. NPSI has actively
engaged
the
local LGUs and have planned for CSR activities for the area once the project
moves
ahead.

System Impact Study for Negros Ph Solar Inc.s


Page 10
50 MW Felisa Solar Power Project

Land Status:
a) Identified and secured approximately 150 hectares with the landowners.
Many
of the landowners are prominent local business people with good local
standing.
Land Options have been signed for most of them and the rest will be
complete
shortly and landowners are backing this project fully. NPSI has very
good
relationships with all the landowners. In total NPSI aims to
secure
approximately 280 hectares to build up to 200 MW.
b) NPSI had engaged professionals to conduct
Irradiation Studies
Flood studies
Topographical surveys
Soil studies
Connection routing and
Plant layout design
The site has ideal road access and is relatively flat with little flood risk.
The lands will not be an inconvenience any inhabitants. The
landlords have committed to ensure the site will be problem free and we
will engage their local individuals where possible.
c) The lands identified are outside the CARP jurisdiction and we have
obtained
proper legal advice as well as advice from the local LGUs on the
proper
procedure to ensure that the site is Solar ready. This has already been
factored
in our evaluation.
d) The land titles have also been checked for any risk of foreclosure

or
encumbrances being attached.
e) NPSI has also ensured that there are no sensitive or endangered trees on
the
site and will not need any special approval or process.
This project proposes to connect to the grid through a direct connection to
Bacolod 138 kV Substation. Direct connection had been preferred by
NGCP to avoid complicating the grid backbone protection system.

System Impact Study for Negros Ph Solar Inc.s


Page 11
50 MW Felisa Solar Power Project

The proposed connection would involve construction of approximately 3.5


km 138 kV transmission line, a take-off substation at the power plant site
and modifications at a bay in Bacolod Substation to accommodate
entry of the proposed power plant. Conductors for this line should be
795 MCM ACSR equipped with appropriate communication facility to
convey revenue meter reading to NGCPs Bacolod Substation.

2. STUDY ASSUMPTIONS
A. DEMAND FORECAST
Based on the 2013 Transmission Development Plan (TDP), there would
relatively be a significant increase in demand in Visayas Grid. Table
1 shows the demand projections for the entire grid. Of greater interest
for this proposed project is the demand in Negros Island where the
proposed facility will be injecting its power to the grid. Bacolod
Substation will be the main corridor of this project.

Table 1. Demand Projections for Visayas

Source: 2013 Transmission Development Plan

B. GENERATION EXPANSIONS
Based on the Department of Energys list of proposed generators,
the
2013
Transmission Development Plan identified the grid reinforcements needed
to cater the incoming generators. The status of generator development
are classified by the Department of Energy as Committed,

Indicative and Prospective. The generators considered in the study


is shown in Figure 1, corresponding table is shown in Table 2.

System Impact Study for Negros Ph Solar Inc.s


Page 12
50 MW Felisa Solar Power Project

Figure 1. Generation Capacity Additions in Visayas


Table 2. Generator Capacity Additions for Visayas

System Impact Study for Negros Ph Solar Inc.s


Page 13
50 MW Felisa Solar Power Project

C. TRANSMISSION EXPANSIONS
Major developments in Negros island included in the 2013 TDP are as follows:
1. Negros-Panay Interconnection Uprating
2. Negros V Transmission Line Project
3. Visayas Substation Expansion I (Kabangkalan 1 x 50 MVA)
4. Visayas Substation Reliability I (Amlan 1 x 50 MVA, Bacolod 1 x 100
MVA
and Cadiz 1 x 50 MVA)
These proposed developments shown in Figure 2 as well as generation expansions
were included in the base cases and were considered in the assessments.

Figure 2. Transmission Expansion Projects in Visayas

System Impact Study for Negros Ph Solar Inc.s


Page 14
50 MW Felisa Solar Power Project

D. GRID CODE REQUIREMENTS


The proposed projects performance was evaluated based on the criteria set
by
the
Philippine Grid Code, utilizing grid dispatch scenario where power plants near
the
project were set at maximum dispatch to reflect the worst impact of the project
to
the
grid. Steady state voltage and thermal analyses examined system performance
without
the proposed project in order to establish a baseline data. System performance
was
re-evaluated with the project and compared with the previous baseline
performance
to
demonstrate the impact of the project on area transmission reliability.
The voltage limits adopted in this study were in compliance with the PGC
which
requires that during normal and single outage contingency conditions, the
voltage
should be within the range of 0.95 to 1.05 per unit. For the thermal limits,
normal
thermal ratings shall not be violated under all-lines-in and single outage
contingency
conditions. The steady state analysis was performed with both pre-contingency
and
post-contingency solution parameters that allow adjustment of load tapchanging
transformers (LTCs), static var devices (SVDs) including switched capacitors
and
phase angle regulators (PARs).
For short circuit studies, resulting three phase fault should not exceed the levels
shown in Table 3. These ratings are the standard fault duty rating of circuit
breakers connected to the grid.
Table 3. Power Circuit Breaker Fault Duty

Rating
Rated Short Circuit
Current
Voltage Level
<69 kV

(kA)
25

>69kV <138 kV

31.5

>230 kV

40

Stability analysis evaluated the impact of the project on transmission


system
performance during the occurrence of disturbances or faults. The application of
faults
established transmission system reliability performance under stressed
transfer
conditions observing known stability limits. The stability criteria applied
for
evaluation in the system is the PGC provision under Section 5.3.4.1 which
requires:

System Impact Study for Negros Ph Solar Inc.s


Page 15
50 MW Felisa Solar Power Project

1. The Grid remains stable after any Single Outage Contingency for all
forecasted
Load conditions; and
2. The Grid remains controllable after a Multiple Outage Contingency. In
the
case of Grid separation, no total blackout should occur in any Island Grid.

In this study however, only stability under single outage contingency conditions
were evaluated.
Applied faults were cleared (normal clearing) in compliance with the
requirements of the PGC Section 4.5.2.3 as follows:
1. 85 ms for 500 kV;
2. 100 ms for 230 kV and 138 kV; and
3. 120 ms for voltages less than 138 kV
Delayed clearing were simulated in accordance with the requirements of the
PGC which states:
The circuit breaker fail protection shall be designed to initiate
the
tripping
of
all the necessary electrically-adjacent circuit breakers and to
interrupt
the
fault
current within the next 50 milliseconds, in the event that the
primary
protection
system fails to interrupt the fault current within the prescribed
Fault
Clearance
Time
In addition to the standard PGC requirements, the Energy Regulatory
Commission
(ERC) had issued Resolution No. 7 series of 2013 entitled Resolution Adopting
and
Approving Addendum to Amendment No. 1 of the Philippine Grid Code,
Establishing
the Connection and Operational Requirements for Variable Renewable Energy
(VRE)
Generating Facilities.
Under Article II Section 2 of this addendum,
additional
requirements for large photovoltaic generation systems were prescribed as
follows:
1.) Section 2.1 - Generating Unit Power Output

2.) Section 2.2 - Frequency Withstand Capability


3.) Section 2.3 - Reactive Power Capability
4.) Section 2.4 - Performance During Network Disturbances
5.) Section 2.5 - Voltage Control System
6.) Section 2.6 - Active Power Control System; and
7.) Section 2.7 - Power Quality

System Impact Study for Negros Ph Solar Inc.s


Page 16
50 MW Felisa Solar Power Project

Generating Limit Power Output


The proposed power plant should continuously supply active and reactive
power
depending on the availability of primary source within the frequency range of
59.760.3 Hz. It should be capable of interchanging reactive power at connection
point
within 5% voltage variation. Outside this range and up to 10% voltage
variation,
a reduction in active and/or reactive power may be allowed up to 5% of the
generators
declared data.
Frequency Withstand Capability
Table 4 shows the allowable power plant frequency response.

Table 4. Requirements at Different Frequency Range

Reactive Power Capability


The proposed power plant should be capable of supplying reactive power output
at its connection point, within the limits of 0.95 pf lag and 0.95 pf lead.

System Impact Study for Negros Ph Solar Inc.s


Page 17
50 MW Felisa Solar Power Project

Performance during Network Disturbances


The allowable voltage ride-through for the power plant is shown in Figure 3.

Figure 3. Low Voltage Withstand Capability Requirement for Large


Photovoltaic
Systems
Voltage Control System
The proposed power plant shall be capable of contributing voltage control
by continuous regulation of the reactive power supplied to the grid under
power factor control mode wherein power factor is maintained at the
connection point or voltage control mode wherein voltage at the high voltage
busbar of the proposed power plant is maintained at a constant set-point.
Active Power Control System
The proposed power plant shall be capable of active power control to operate
under

free active power production (no active power control) or under active
power
constraint.

System Impact Study for Negros Ph Solar Inc.s


Page 18
50 MW Felisa Solar Power Project

Power Quality
With the proposed power plant connected to the system and under normal
operating state, the Flicker Severity and Total Harmonic Distortion at the
connection point shall not exceed the values prescribed by the PGC
The proposed power plant will demonstrate compliance with these
requirements through testing to be conducted pursuant to Section 3.2.3.

3. PROPOSED

CONNECTION

ARRANGEMENT

AND

SYSTEM
MODELLING
In Figure 4 is shown the proposed connection for the project. This connection
consists
of 138 kV transmission line directly connected to Bacolod 138 kV Substation.
The
project will be equipped with a take-off substation at the power plant site
connected
to a main bay at Bacolod Substation. The projects geographic location is
shown
in
Figure 5.
Proposed Power Plant

Figure 4. Connection Scheme for the Project


System Impact Study for Negros Ph Solar Inc.s
Page 19
50 MW Felisa Solar Power Project

3.5 km 138 kV transmission line

Take-off Substation

Figure 5. Geographic Location of the Project

The technical specifications used to model the proposed connection assets


of NPSI solar power plant project are shown in Table 5 to Table 7.
Table 5. Lumped Generator Specifications
Power
Capability
(MW)
Pmax Pmin
50

Reactive Capability at
Full Dispatch (MVAR)
Qmax
0

Qmin
0

Remarks

R Source X Source
0

99999

Refer to PSS/E
PV Modelling
Guide

System Impact Study for Negros Ph Solar Inc.s


Page 20
50 MW Felisa Solar Power Project

Table 6. Generator Transformer

Description

Tap Ratio

Grid
Transformers

22/138
D/Y

Present MVA
Tap
R (pu)
Tap
Rating Steps

Center

65

X (pu)
based on
System
MVA

0.178620

Table 7. Transmission Line Data


Line Name

Type

NPSI take-off 138 kV, 795


MCM
138
kV
km
tapping
ACSR

Length

Rate
(MVA)
196

3.5

R (pu)

0.001580
0.002290

X (pu)

0.008740

B (pu)

The grid model or base cases used in this study for years 2016 and 2021 were
provided by NGCP. Both base cases were derived from the Transmission
Development Plan and considered transmission line and generator expansion
plans for the period covered. The scenario represented was peak loading
condition, maximizing dispatch of power plants in the vicinity of the project.
Off-peak scenarios were not considered in the assessment since the proposed
power plant is not expected to operate during off-peak.
To reflect the priority dispatch scenario in the model, dispatch of
conventional synchronous machines in Negros and Panay areas were
slightly reduced. In actual application, these conventional plants dispatch
will vary due to the intermittence of the proposed power plant. Power plants
with adjusted dispatch are as follows:
1.) Palinpinon Geothermal Power Plant (Negros)
2.) Nasulo Geothermal Power Plant (Negros)
3.) PGPP (Negros)
4.) Palm Thermal (Panay)
5.) PEDC Power Plant (Panay)

Equivalent model of the grid in the vicinity of the project is shown in Figure 6.

System Impact Study for Negros Ph Solar Inc.s

Page 21
50 MW Felisa Solar Power Project

Prop
osed
50
MW
Solar
Powe
r
Plant

Figure 6. Equivalent Model of the Grid in the Vicinity of the Project

The 50 MW generator was modeled as lumped unit using PVGU1 in the

dynamic stability study while the electrical controls was modelled as


PVEU1. Parameters for the models are shown in Table 8 and Table 9
respectively. Other system dynamics data were provided by NGCP.

Table 8. Dynamics Data for 50 MW Lumped Generator Units

System Impact Study for Negros Ph Solar Inc.s


Page 22
50 MW Felisa Solar Power Project

Table 9. Dynamics Data for the Electrical Controls

4. LOAD FLOW ASSESSMENT


The results of the simulation for thermal adequacy are presented in Sections 4.A.
and
4.B. while that for the voltages are shown in Sections 4.C. and 4.D.
Under normal loading conditions, considering the priority dispatch of
intermittent
RE
Generators, thermal loading of elements in the grid will remain within PGC
required
limits.
The number of grid loading violations during single-outage
contingency
conditions essentially remained the same for major transmission line elements.
Voltages at other monitored substations during normal and contingency

conditions remained within the prescribed limits of the Philippine Grid Code.

System Impact Study for Negros Ph Solar Inc.s


Page 23
50 MW Felisa Solar Power Project

A. THERMAL ASSESSMENT - ADEQUACY IN NORMAL CONDITIONS


(PEAK CONDITIONS)
The results of the simulations are given in Table 10 and Table 11 for the 2016
and 2021 base cases respectively.
Table 10. 2016 Thermal Assessment (Peak, Normal Loading)
Peak Load Condition
Monitored Element

MVA
Rating

Solar Hi-Bacolod 138 kV


196.00
25.97
2 Samboan-Pondol 138 kV
108.0
4
3 Pondol-Amlan 138 kV
196.00
47.58
4 Amlan Hi-Amlan SP
196.0
0
5 Amlan-Mabinay 138 kV
196.00
12.61
6 Kabankalan-Bacolod 138 kV
196.0
0
7 Bacolod-E. B. Magalona 138 kV L1
14.44
7.37
8 Bacolod-E. B. Magalona 138
392.0
kV
L2
0
9 EB Magalona-Barotac Viejo 138 kV
44.02
40.76
10 Barotac Viejo-Dingle 138 kV
196.0
11 Barotac Viejo-Concepcion 138 kV0
90.28
23.03

Without
Silay Solar
MVA
%
%
N/A
84.9
1
84.72

78.59
43.22

132.9
215.33

67.82
7.82

With
Silay Solar
MVA
50.90

93.26

86.5
1

24.71

77.9
3

10.31

10.2
0

10.6
4
196.00

5.43
20.20

34.5
6
108.00

8.82
49.57

45.90

47.4
0
392.00

24.18
95.44

24.35

6.20

Table 11. 2021 Thermal Assessment (Peak, Normal Loading)


Peak Load Condition
Monitored Element

MVA
Rating

Without
Silay Solar

With
Silay Solar

29.2
5

MVA
1
2
3
4
5
6
7
8
kV
9
10
11

Solar Hi-Bacolod 138 kV


196.00
25.99
Samboan-Pondol 138 kV
108.0
4
Pondol-Amlan 138 kV
196.00
45.45
Amlan Hi-Amlan SP
196.0
0
Amlan-Mabinay 138 kV
196.00
11.19
Kabankalan-Bacolod 138 kV
196.0
0
Bacolod-E. B. Magalona 138 kV L1
27.58
14.07
Bacolod-E. B. Magalona 138
392.0
L2
0
EB Magalona-Barotac Viejo 138 kV
47.02
43.54
Barotac Viejo-Dingle 138 kV
196.0
Barotac Viejo-Concepcion 138 kV0
82.69
21.09

%
%

MVA

N/A

50.94

69.6
0
69.45

64.42
35.43

89.09

82.6
7

97.6
96.03

49.84
3.08

21.93

75.0
5

6.37
196.00

3.25
27.08

13.82

10.5
5

42.8
2
108.00

10.92
47.90

44.35

11.0
3

27.6
7
392.00

14.12
82.62

21.08

13.9
8

System Impact Study for Negros Ph Solar Inc.s


Page 24
50 MW Felisa Solar Power Project

B. THERMAL ASSESSMENT - ADEQUACY IN SINGLE OUTAGE


CONDITIONS (PEAK CONDITIONS)
Thermal N-1 adequacy assessments are given in and Table 12 and Table 13
for 2016 and 2021 base cases. The quantity of grid loading violations during
this contingency conditions essentially remained the same.
Table 12. 2016 Thermal Assessment (Peak, N-1 Loading)
Peak Load Condition
Monitored Element

Solar Hi-Bacolod 138 kV

MVA
Rating

196.00

Without
Silay Solar
MVA
%
%
N/A

With
Silay Solar
MVA
50.97

2
3
4
5
6
7
8
kV
9
10
11

26.01
Samboan-Pondol 138 kV
108.0
4
Pondol-Amlan 138 kV
196.00
92.57
Amlan Hi-Amlan SP
196.0
0
Amlan-Mabinay 138 kV
196.00
33.40
Kabankalan-Bacolod 138 kV
196.0
0
Bacolod-E. B. Magalona 138 kV L1
57.49
29.33
Bacolod-E. B. Magalona 138
392.0
L2
0
EB Magalona-Barotac Viejo 138 kV
69.33
64.19
Barotac Viejo-Dingle 138 kV
196.0
Barotac Viejo-Concepcion 138 kV0
180.17
45.96

165.9
6
164.93

153.61
84.15

212.7
855.29

108.56
28.21

51.1
4
196.00

26.09
85.03

64.9
3
108.00

16.56
98.30

94.7
5
392.00

48.34
190.35

181.44

168.9
6

65.46

118.6
5

43.38

31.4
5

91.02

13.9
5

48.56

59.4
4

Table 13. 2021 Thermal Assessment (Peak, N-1 Loading)


Peak Load Condition
Monitored Element

1
2
3
4
5
6
7
8
kV
9
10
11

MVA
Rating

Solar Hi-Bacolod 138 kV


196.00
26.09
Samboan-Pondol 138 kV
108.0
4
Pondol-Amlan 138 kV
196.00
88.37
Amlan Hi-Amlan SP
196.0
0
Amlan-Mabinay 138 kV
196.00
31.33
Kabankalan-Bacolod 138 kV
196.0
0
Bacolod-E. B. Magalona 138 kV L1
27.58
52.95
Bacolod-E. B. Magalona 138
392.0
L2
0
EB Magalona-Barotac Viejo 138 kV
47.02
98.89
Barotac Viejo-Dingle 138 kV
196.0
Barotac Viejo-Concepcion 138 kV0
82.69
41.80

Without
Silay Solar
MVA
%
%
N/A
136.0
1
135.04

125.89
68.90

176.6
282.25

90.11
41.96

82.6
5
196.00

42.17
103.25

71.3
9
108.00
101.4
4
392.00

18.21
109.71
51.76
163.85

With
Silay Solar
MVA
50.94

89.09

161.4
5

21.93

114.3
4

52.68

30.9
8

101.58

18.3
6

41.80

51.7
0

System Impact Study for Negros Ph Solar Inc.s


Page 25
50 MW Felisa Solar Power Project

C. VOLTAGE ASSESSMENT IN NORMAL CONDITIONS (PEAK)


Voltage assessment conducted on the system indicated that the entry of the
project will not result to voltage violations in the grid. Table 14 and Table 15
present the results of voltage assessment for the 2016 and 2021 base cases
respectively.
Table 14. 2016 Voltage Assessment (Peak, Normal Loading)
Peak Load Condition
Monitored Substations

3 [NPHS_HI 138.000]
227601 COLON138.00
227700 SAMBOAN
136.85
235500 BACOLOD 69.000
235501 BACOLOD
1.0196
237100 PONDOL 138.00
237101 PONDOL
138.23
237200 AMLAN HI 138.00
237201 AMLAN SP
137.78
237300 MAB HI
138.00
237400 KABANKAL
139.08
237500 BACOLOD 138.00
237800 EBMAG1
140.94
237801 EBMAG2 138.00
247100 BTC VIEJ
140.99
247200 DINGLE 138.00
247700 CNCPCION
141.37

Without
Silay Solar
(kV)
(p.u.)
N/A

With
Silay Solar
(kV)
(p.u.)
1.0142 139.95

136.8
0
138.00

0.9913
137.31

0.9950

136.6
6
0.9917

70.4
6
69.000
70.35
138.4
8
138.00

1.0212
70.46

1.0212

70.3
5

1.0035
138.48

1.0035

138.2
3
1.0017

137.9
9
138.00

0.9999
137.99

0.9999

137.7
8
0.9984

138.8
6
138.00

1.0062
139.35

1.0098

138.5
8
1.0078

140.1
8
138.00

1.0158
140.90

1.0210

139.9
7
1.0213

141.0
6
138.00

1.0222
141.20

1.0232

140.9
1
1.0217

140.0
3
138.00

1.0147
141.51

1.0254

139.8
5
1.0244

Table 15. 2021 Voltage Assessment (Peak, Normal Loading)


Peak Load Condition
Monitored Substations

Without
Silay Solar
(kV)
(p.u.)
N/A

3 [NPHS_HI 138.000]
227601 COLON138.00
227700 SAMBOAN
136.87
235500 BACOLOD 69.000

With
Silay Solar
(kV)
(p.u.)
1.0055 138.75

1.009
3
138.00

139.28
0.9987

138.9
1
0.9918

1.007
4

69.51

1.007
4
138.00

69.5
1
1.0033

1.004
4
138.46

69.3
0
1.0003

1.003
3
138.00

138.4
6
0.9991

1.000
3
137.88

138.0
4
0.9963

0.999
1
138.00

137.8
8
1.0032

0.996
3
138.44

137.4
9
0.9999

1.005
2
138.00

138.7
2
1.0084

1.001
9
139.16

138.2
6
1.0056

1.018
3
138.00

140.5
3
1.0215

1.016
4
140.97

140.2
6
1.0197

1.023
3
138.00

141.2
2
1.0107

1.021
6
139.48

140.9
8
1.0098

1.033
0

142.5
5

1.032
0

142.4
2

137.82

69.3
0

System Impact Study for Negros Ph Solar Inc.s


Page 26
50 MW Felisa Solar Power Project

235501 BACOLOD 69.000


237100 PONDOL
138.04
237101 PONDOL 138.00
237200 AMLAN HI
137.49
237201 AMLAN SP 138.00
237300 MAB HI
137.99
237400 KABANKAL 138.00
237500 BACOLOD
138.77
237800 EBMAG1 138.00
237801 EBMAG2
140.72
247100 BTC VIEJ 138.00
247200 DINGLE
139.35
247700 CNCPCION 138.00

D.

VOLTAGE ASSESSMENT

(PEAK

IN

SINGLE OUTAGE CONDITION

CONDITIONS)
Results of voltage assessment during contingency conditions are shown in
Table
16
and Table 17 for the 2016 and 2021 base cases respectively. No deviations from
the
PGC prescribed limits are expected upon the entry of the proposed project to the
grid.
Table 16. 2016 Voltage Assessment (Peak, N-1 Loading)
Peak Load Condition
Monitored Substations

Without
Silay Solar

With
Silay Solar

Min

Max

1.0043

Max
1.0242
0.995
8
0.9694

1.0326

1.030
4
1.0006

1.0069

1.006
6
0.9874

1.0032

1.002
8
0.9874

1.0141
0.9972

1.0208

1.012
5

1.0235
0.9995

1.0277

1.024
2
0.9974

0.994
1
138.00

1.0270
1.0060

1.0277

1.027
3
1.0046

1.004
5
138.00

1.021
0
1.0149

1.003
3
1.0282

1.020
3
1.0140

3 [NPHS_HI 138.000]
227601 COLON138.00
227700 SAMBOAN
1.0035
235500 BACOLOD 69.000
235501 BACOLOD
1.0304

N/A
0.975
4
138.00

0.9971
0.9743

0.997
0
69.000

1.0326
0.9970

237100 PONDOL 138.00


237101 PONDOL
1.0067
237200 AMLAN HI 138.00
237201 AMLAN SP
1.0028
237300 MAB HI
138.00
237400 KABANKAL
0.9939
237500 BACOLOD 138.00
237800 EBMAG1
1.0287
237801 EBMAG2 138.00
247100 BTC VIEJ
1.0276

0.989
9
138.00

1.0068
0.9889

0.988
9
138.00

1.0032
0.9889

0.994
3
138.00
1.019
0.992
7
138.00

Min
0.9961

System Impact Study for Negros Ph Solar Inc.s


Page 27
50 MW Felisa Solar Power Project

247200 DINGLE 138.00


247700 CNCPCION
1.0280

Table 17. 2021 Voltage Assessment (Peak, N-1 Loading)


Peak Load Condition
Monitored Substations

Without
Silay Solar
Min
Max

3 [NPHS_HI 138.000]
227601 COLON138.00

0.999
9

1.0132

With
Silay Solar
Min
Max
0.9612 1.0155
1.010
7

227700 SAMBOAN
1.0028
235500 BACOLOD 69.000
235501 BACOLOD
1.0195
237100 PONDOL 138.00
237101 PONDOL
1.0046
237200 AMLAN HI 138.00
237201 AMLAN SP
1.0003
237300 MAB HI
138.00
237400 KABANKAL
1.0125
237500 BACOLOD 138.00
237800 EBMAG1
1.0262
237801 EBMAG2 138.00
247100 BTC VIEJ
1.0275
247200 DINGLE 138.00
247700 CNCPCION
1.0355

138.00 0.982
0.96
1.0245
4
69.000 0.964

1.0042

0.9716

1.0245

1.019
5
0.9574

1.0067

1.004
6
0.9853

1.0027

1.000
3
0.9853

1.0153

1.007
5
0.9777

0.988
8
138.00

1.0067
0.9879

0.987
9
138.00

1.0027
0.9879

0.980
5
138.00

1.01
0.9801

0.967
5
138.00

1.0199
0.9901

1.0279

1.015
5
0.9866

0.968
9
138.00

1.0287
1.0054

1.0301

1.025
9
1.0046

0.994
1
138.00

1.0168
1.0221

1.0371

1.015
4
1.0217

5. FAULT LEVEL ANALYSIS


The fault current assessment determined the fault level at various
buses/substations in the grid in the vicinity of the proposed power plant. The
entry of the proposed project would not result to fault current exceeding the
allowable levels. The resulting short circuit currents are shown in Table 18.
Table 19 shows the short circuit MVA at the power plant high voltage
substation.

System Impact Study for Negros Ph Solar Inc.s

Page 28
50 MW Felisa Solar Power Project

Table 18. Short Circuit Rating of Selected Substations in the Grid


Peak Load Condition
Substation

3 [NPHS_HI 138.000]
237500 [BACOLOD
138.00]
235501 [BACOLOD
10,200.30
235500 [BACOLOD
237800 [EBMAG169.000]
6,472.00
237801 [EBMAG2 138.00]
247100 [BTC VIEJ
10,599.50
247700 [CNCPCION 138.00]
247200 [DINGLE
11,179.00
237400 [KABANKAL 138.00]
237300 [MAB HI
5,559.60
237200 [AMLAN HI 138.00]
237201 [AMLAN SP
8,111.80
237100 [PONDOL 138.00]
227700 [SAMBOAN
7,273.00
227601 [COLON138.00]

Without
With
Silay Solar
Silay Solar
2016
2021
2016
2021
N/A
13,807.40 N/A
13,540.00
8,279.20 8,143.70
8,009.8
0
69.000]
10,118.20
9,956.30
9,779.30
10,118.2 9,956.30
9,779.3
0138.00] 6,700.40 6,613.40 6,730.80
0
9,896.8 9,761.90
9,658.5
0
0
138.00]
10,450.30
10,307.70
10,218.90
9,917.1 9,806.70
9,773.7
0
0
138.00]
10,987.80
10,858.90
10,780.30
5,771.0 5,701.80
5,578.9
0
0
138.00]
5,737.40 5,679.60 5,712.20
8,287.9
0
138.00]

8,227.60
8,111.8
0
8,287.90 8,227.60 8,279.20

7,434.4
0
138.00]

7,379.90
7,266.5
0
7,453.70 7,388.90 7,448.20

20,813.6 20,750.50
0
22,803.90

22,552.8
0

Table 19. Short Circuit MVA at Power Plant S/S (Peak Loading)
Short Circuit MVA and X/R
at Solar 69kV Bus
Peak Load Condition
2016
2021
MVA
X/R
MVA
X/R
1,650.15 4.8616 1,618.19 4.43667

System Impact Study for Negros Ph Solar Inc.s


Page 29
50 MW Felisa Solar Power Project

6. STABILITY ASSESSMENT
Stability analysis assessed the impact of the project to the transient
stability
performance of the grid. The analysis was based on the assumptions and
methodology
described in the previous sections. The stability plots are included in the
Appendices.
The 3-phase faults were applied on transmission line segments followed
by tripping/outage of the segments at normal and delayed clearing times.
The segments where faults were applied are as follows:
1. Fault at Solar Hi-Bacolod 138 kV Line with Tripping
2. Fault at Bacolod-EBMAG1 138 kV Line with Tripping
3. Fault at Bacolod-EBMAG2 138 kV Line with Tripping
4. Fault at Bacolod-Kabankalan 138 kV Line with Tripping
5. Fault at Bacolod 138/69 kV Transformer (T2) with Tripping
6. Fault at Bacolod-BRGS TAP

69 kV Line with Tripping

7. Fault at Bacolod 138/69 kV Transformer (T1) with Tripping


8. Fault at Kabankalan-Mabinay HI 138 kV Line with Tripping
9. Fault at Amlan HI-Mabinay HI 138 kV Line with Tripping

Bus faults applied to the system are as follows:


1. Bus Fault at NPHS_HI 138 kV Bus (3)
2. Bus Fault at BACOLOD 138 kV Bus (237500)
3. Bus Fault at EBMAG1 138 kV Bus (237800)
4. Bus Fault at EBMAG2 138 kV Bus (237801)
5. Bus Fault at KABANKAL 138 kV Bus (237400)
6. Bus Fault at MAB HI 138 kV Bus (237300)
7. Bus Fault at AMLAN SP 138 kV Bus (237201)
8. Bus Fault at DINGLE 138 kV Bus (247200)

These three phase faults were later isolated at normal and delayed clearing times.
As a stability criteria, for the transient stability assessment, parameters namely,
machine angle, bus voltages, bus frequency and generator power swing during
and after the system disturbance should have acceptable damping and
coherence.
System Impact Study for Negros Ph Solar Inc.s
Page 30
50 MW Felisa Solar Power Project

The results of the stability simulation indicated acceptable


response
of
the
system
parameters with the proposed facility integrated, damping mostly
within the first ten
(10) seconds after the application of fault. The summary of
dynamic stability simulations is shown in Table 20 for scenarios
with the power plant.

Table 20. Summary of Dynamic Stability Simulations with


Power Plant
Status of
Grid
Applied Fault

2016 Base
Case

2021

Base

Case

Normal

Normal

Delayed

Delayed

Clearing

Clearing

Clearing

Clearing

BUS FAULTS
1. Bus Fault at NPHS_HI 138 kV Bus (3)
2. Bus Fault at BACOLOD 138 kV Bus
(237500)

Stable
Stable

Stable
Stable

Stable
Stable

Stable

Stable

3. Bus Fault at EBMAG1 138 kV Bus (237800)


4. Bus Fault at EBMAG2 138 kV Bus (237801)

Stable
Stable

5. Bus Fault at KABANKAL 138 kV Bus (237400)


6. Bus Fault at MAB HI 138 kV Bus (237300)

Stable
Stable
Stable

Stable

Stable
Stable

Stable

Stable

Stable

Stable

Stable

Stable
Stable
Stable

7. Bus Fault at AMLAN SP 138 kV Bus (237201)


8. Bus Fault at DINGLE 138 kV Bus (247200)

Stable
Stable

Stable

Stable
Stable

Stable

Stable

Stable

Stable

Stable

Stable

Stable

LINE FAULTS
1. Fault at Solar Hi-Bacolod 138 kV Line with
Tripping

Stable

Stable
Stable

Stable

2. Fault at Bacolod-EBMAG1 138 kV Line with


Tripping

Stable

Stable
Stable

Stable

3. Fault at Bacolod-EBMAG2 138 kV Line with


Tripping

Stable

Stable
Stable

Stable

4. Fault at Bacolod-Kabankalan

138 kV Line with

Tripping

Stable
Stable

Stable
Stable

Stable
Stable

Stable
Stable

Stable

Stable

Stable
Stable

Stable
Stable

Stable

Stable

Stable
Stable

Stable
Stable

5. Fault at Bacolod 138/69 kV Transformer (T2) with


Tripping

System Impact Study for Negros Ph Solar Inc.s


Page 31
50 MW Felisa Solar Power Project

6. Fault at Bacolod-BRGS TAP

69 kV Line with

Tripping
7. Fault at Bacolod 138/69 kV Transformer (T1) with
Tripping

8. Fault at Kabankalan-Mabinay HI 138 kV Line with


Tripping
9. Fault at Amlan HI-Mabinay HI 138 kV Line with
Tripping

7. FREQUENCY ASSESSMENT
Frequency assessment evaluates if the loss of the proposed power
plant
will
not
cause
the frequency to drop below 59.4 Hz frequency limit set by PGC.
For
2016
and
2021
base cases, the frequency will not fall as low as 59.4 Hz. The
outage
of
the
proposed
power plant will not result to Automatic Load Dropping (ALD). Figure
7 and Figure
8 shows the results of frequency assessments for 2016 and 2021 base cases
respectively.

System Impact Study for Negros Ph Solar Inc.s


Page 32

50 MW Felisa Solar Power Project

Figure 7. Frequency Assessment, 2016 Peak Base Case

Figure 8. Frequency Assessment, 2021 Peak Base Case


System Impact Study for Negros Ph Solar Inc.s
Page 33
50 MW Felisa Solar Power Project

8. SUMMARY AND CONCLUSIONS


This study was conducted to assess the impact of the proposed 50 MW Felisa
Solar
Power Project on the reliability, stability and operating characteristics of the
Visayas
Grid. Steady state, stability and short-circuit conditions were analyzed.
Proposed
connection for this project is a direct connection to Bacolod 138 kV Substation.
Steady state assessment with the project in-service showed no significant
voltage or thermal violations of reliability criteria. Considering the priority
dispatch of intermittent RE Generators, thermal loading of elements in the grid
will remain within PGC required limits.
Short circuit analyses concluded that the project did not alter adversely the
short circuit duties of the baseline system.
Transient stability assessment simulated a set of faults. None of the faults
tested showed unstable response of the system with the project integrated.
Frequency assessment showed that the system frequency will not drop as low as
59.4 Hz with the outage of the proposed power plant. Automatic Load
Dropping is not expected during this loss-of-generation scenario.
As a general conclusion, this System Impact Study revealed that the addition of
NPSIs
first project phase, the 50 MW Felisa Solar Power Project has no significant
system

impact to the stability, reliability, and operating characteristics of the Visayas


Grid.
The proposed project could be safely and reliably integrated to Visayas.
Subsequent
phases of the project will be implemented upon NGCPs reinforcement of
the
submarine interconnection.

System Impact Study for Negros Ph Solar Inc.s


Page 34
50 MW Felisa Solar Power Project

APPENDICES

Appendix A
2016 Bus Fault Normal Clearing

Appendix C
2016 Line Fault Normal Clearing

Appendix D
2016 Line Fault Delayed Clearing

Appendix E
2021 Bus Fault Normal Clearing

Appendix F
2021 Bus Fault Delayed Clearing

Appendix G
2021 Line Fault Normal Clearing

Appendix H
2021 Line Fault Delayed Clearing

Appendix I
Power Flow Plots

2016 Peak Base Case, Normal Loading, Without the Proposed Plant

2016 Peak Base Case, Normal Loading, With the Proposed Plant

2021 Peak Base Case, Normal Loading, Without the Proposed Plant

2021 Peak Base Case, Normal Loading, With the Proposed Plant

You might also like