STANDARD CHECKLIST:: SYSTEM COMMISSIONING

STATION: NTPC /RhSTPP-II (2 x 500 Mw) ; UNIT: _____


PLANT ITEM:

WALL DE SLAGGERS

SHEET

1 OF 2

Date -

Name of the system: ___________________ Plant area: ________________________


System Drawing No: __________________ Manufacturers Name:__________________
Location :
SN

_____________________ Serial No: ________________________


ACTIVITY

1.

General conditions satisfy the site standing Instructions listed in


the Plant Item Commissioning Essential Pre-requisites (SCL MS
1/1).

2.

The nameplate legend agrees with the approved NTPC Plant


Nomenclature and is clearly visible, securely fixed, durable and
correlates with remote labels.

3.

The installation is complete and correct in accordance with the


latest drawings.

4.

Access for adjustments, maintenance and repairs is satisfactory.

Check the blower number with reference to the location drawing to


ensure the installation of correct blower in correct location

Check the perpendicularity of wall sleeve and swivel type (90 deg +
30 ) (Certificate from erection personnel to be obtained)

Check the accessibility for hand crank and the switch box
assembly.

Check that the soot blower piping adjacent to the blower is


supported on boiler steel and is not likely to foul with structural
steel when the boiler expansion will take place

STATUS
Yes / No

SCL REF: M/VOL II /SEC C-F02

NTPC

RIHAND

STATION: NTPC /RhSTPP-II (2 x 500 Mw); UNIT:


SN

SHEET 2 OF 2

ACTIVITY

The rotary and traverse gear boxes are thoroughly flushed and
filled with the recommended lubricant.

10

Check that the lubrication of the linkages is properly carried out.

11

Check that the stop nuts are in place on the guide rods.

12

Check that the drain holes in the motor frames point downwards
and are open.

13

The SBV head valve is serviced for proper opening and closing.

14

Check that the blower, before starting or at the end of its operation
is in the correct parking position.

15

Check that a minimum clearance of 1mm is maintained between


the drive screw and SBV head valve stem. (to ensure tight valve
seating).

16

Check the refractory filling in the seal box is done.


SCL REF: M/VOL II /SEC- F02

Remarks: -

STATUS
Yes / No

Name
Agency
NTPC-Erection
NTPC-Commissioning

Signature

Date