Tango Skiff 14 Building Log

Date Task Hours


6/24/2009 Cut out and laminated Transom 1.5
6/26/2009 Cut out and scarfed sides together 3.5
6/27/2009 Cut out hull bottoms and scarfed / sanded transom 3
6/28/2009 Sanded scarf joints 1
7/1/2009 Stitched hull together 6.5
7/3/2009 Cut out bulkheads and seats 3.5
7/3/2009 Cut out parts to build jig 1
7/4/2009 Setup boat in jig 2
7/5/2009 Spot glued 80% of hull 4
7/9/2009 Finished spot gluing 1
7/12/2009 Installed Bulkheads and Transom 4
7/13/2009 Finished gluing Bulkheads 2
7/14/2009 Filleting hull 2
7/16/2009 Filleting hull 1
9/17/2009 Started Fiberglass Taping 1
9/18/2009 Continued Taping 1.5
9/22/2009 Continued Taping 1.5
9/25/2009 Continued Taping 1
9/29/2009 Continued Taping 3
10/5/2009 Continued Taping 1
10/11/2009 Sanded inside of hull 1
10/17/2009 Filled around seams with thickened epoxy 2.5
10/18/2009 Sanded tape seams 1.5
10/20/2009 Epoxied entire inside of hull 2
10/21/2009 Started fitting and gluing inside rails 1.5
10/22/2009 Finished gluing inside rails 1
10/23/2009 Scraped / sanded inside of hull 2
10/24/2009 Made from and rear brackets 4
10/25/2009 Sanded inside of hull 2
10/28/2009 Faired inside of hull 2
10/29/2009 Marked and cut out holes for seat hatches 2
11/1/2009 Worked on rear of transom 1.5
11/2/2009 Worked on rear of transom 1
11/3/2009 Worked on rear of transom 1
11/5/2009 Sanded inside of hull and fit seats 6.5
11/7/2009 Faired inside of hull and started sealing seats 1.5
11/8/2009 Sealed seats 1
11/9/2009 Worked on installing rear seat 1.5
11/10/2009 Worked on installing middle seat 1.5
11/11/2009 Worked on installing front seat 2
11/12/2009 Filleted seats 1
11/15/2009 Sanding 2
11/18/2009 Sanding / taping seats 3
11/19/2009 Blended in seat tape lines 3
11/28/2009 Flipped hull / faired outside of hull 2
11/29/2009 Sanding and fairing outside of hull 1
11/30/2009 Finished getting hull ready for glass 1
12/1/2009 Glassed outside of hull 5.5
12/3/2009 Taped under seats and filleted compartments 3
12/5/2009 Scraped hull 1
12/8/2009 Sanded hull and under seats / faired hull 5
12/10/2009 Sanding and refairing of hull 2.5
12/14/2009 Sanded outside of hull 3
12/15/2009 Faired under seats 1
12/29/2009 Sanded under seats 3
12/30/2009 Sanded hull / flipped boat / laminated 1 outside rail 1.5
12/31/2009 Laminated second outside rail 1
1/1/2010 Sanded / shaped / filled rails 2
1/2/2010 Sanded / filled rails 1
1/3/2010 Finished rails / glassed bow and transom brackets 2
1/4/2010 Glassed transom 2
1/5/2010 2nd coat epoxy on transom 1
1/7/2010 Sanded brackets at bow and transom 2
1/9/2010 Sanding 1.5
1/10/2010 Drilled drain hole / fabricated gas tank bracket 1
1/11/2010 Cut out and installed motor mounts 2
1/12/2010 Finished motor mounts 1
1/13/2010 Sanded inside of hull and hung motor 3
1/14/2010 Rounded transom and fit motor 0.5
1/16/2010 Faired inside of hull again 1
2/7/2009 Sanded interior and transom 4
2/14/2010 Sanded interior 1.5
2/20/2010 Sanded interior 1.5
2/22/2010 Sanded interior 1
2/23/2009 Washed for primer 2
2/25/2010 Primed rails and interior 3
2/26/2010 Primed interior 1
3/4/2010 Sanded primer 1
3/6/2010 Washed primer to get ready for spot putty 1
3/7/2010 Spot puttied rails and inside / sanded / reprimed 2
3/10/2010 Sanded primer for final interior paint 1
3/11/2010 Washed primer / taped boat for 1st topcoat 2
3/13/2010 1st topcoat of white on rails and interior 3
3/17/2010 Sanded topcoat for 2nd coat 1
3/18/2010 2nd topcoat on rails and interior 3
3/23/2010 Flipped hull / primed outside of hull 1.5
3/25/2010 Sanded / washed / painted outside of hull 2
3/26/2010 Touch-up hull paint from tape lines 1.5
3/27/2010 Sanded for 2nd topcoat on outside of hull 2
3/28/2010 2nd topcoat on outside of hull 3
3/29/2010 Removed tape cleaned some bleed through 1
3/31/2010 Touch-up paint on rails 1
4/6/2010 Hull on trailer / installed cleats / 1st seat varnish 5
4/8/2010 Motor mounted / 2nd coat of varnish on seats 2
4/9/2010 3rd coat of varnish on seats 1
4/10/2010 4th coat of varnish on seats 1
4/11/2010 Installed compartments and rod holders 2
4/16/2010 Installed boat numbers 0.5

TOTAL HOURS: 195