Professional Documents
Culture Documents
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
Task Name
Dec 26, '99
Jan 2, '00
Jan 9, '00
Jan 16, '00
Jan 23, '00
Jan 30, '00
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Three-story Office Building (76,000 square feet)
General Conditions
G.C. General Management
Receive notice to proceed and sign contract
G.C. Project Management,G.C. General Management[25%]
Submit bond and insurance documents
G.C. Project Management[25%],G.C. Scheduler
Prepare and submit project schedule
G.C. General Management[10%],G.C. Project Management
Prepare and submit schedule of values
G.C. Project Management[50%],G.C. Procurement[50%]
Obtain building permits
G.C. Project Management[50%],G.C. Procurem
Submit preliminary shop drawings
Submit monthly requests for payment
Long Lead Procurement
Steel Erection Contractor Management
Submit shop drawings and order long lead items - steel
Submit shop drawings and order long lead items - roofing
Submit shop drawings and order long lead items - elevator
Submit shop drawings and order long lead items - plumbing
Submit shop drawings and order long lead items - electric
Submit shop drawings and order long lead items - HVAC
St
Detail, fabricate and deliver steel
Mobilize on Site
Install temporary power
Install temporary water service
Set up site office
Set line and grade benchmarks
Prepare site - lay down yard and temporary fencing
Site Grading and Utilities
Clear and grub site
Stone site access and temporary parking area
Rough grade site (cut and fill)
Install storm drainage
Install exterior fire line and building fire riser
Perform final site grading
Erect building batter boards and layout building
Foundations
Excavate foundations
Electric Contractor
Plumbing Contractor
G.C. Superintendent,G.C. Labor Crew[10%]
G.C. Survey Crew
Site Grading Contractor,G.C. Labor Crew[10%]
Site Grading Contractor
Site Grading Contractor
Site Grading
Si
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 1
ID
Task Name
Dec 26, '99
S
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
Jan 2, '00
S M T
Jan 9, '00
S M T
Si
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 2
ID
Task Name
Dec 26, '99
S
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
Jan 2, '00
S M T
Jan 9, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 3
ID
Task Name
Dec 26, '99
S
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
Jan 2, '00
S M T
Jan 9, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 4
ID
133
134
135
136
137
138
139
140
141
142
143
144
145
Task Name
Dec 26, '99
Jan 2, '00
S S M T W T
Install hard tile flooring in common areas
Clean hard tile floors
Remove debris from building and do final clean-up
Substantial completion date
Complete Final Inspections
Complete elevator inspection and certification
Perform architect's inspection
Perform local building agency inspection
Perform Fire Marshal's inspection
Complete punch list items from all inspections
Obtain certificate of occupancy
Issue final completion documents including warranties
Issue final request for payment
Jan 9, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 5
Feb 6, '00
S M T
Mar 5, '00
S M T
0%],G.C. Procurement[50%]
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 6
Feb 6, '00
S M T
Mar 5, '00
S M T
Plumbing Contractor,E
St
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 7
Feb 6, '00
S M T
Mar 5, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 8
Feb 6, '00
S M T
Mar 5, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 9
Feb 6, '00
S M T
Mar 5, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 10
ar 19, '00
T
Apr 2, '00
S M T
Apr 9, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 11
ar 19, '00
T
Apr 2, '00
S M T
Apr 9, '00
S M T
St
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 12
ar 19, '00
T
Apr 2, '00
S M T
Apr 9, '00
S M T
Ma
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 13
ar 19, '00
T
Apr 2, '00
S M T
Apr 9, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 14
ar 19, '00
T
Apr 2, '00
S M T
Apr 9, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 15
May 7, '00
S M T
Jun 4, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 16
May 7, '00
S M T
Jun 4, '00
S M T
Steel Erec
G.
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 17
May 7, '00
S M T
Jun 4, '00
S M T
G.
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 18
May 7, '00
S M T
Jun 4, '00
S M T
El
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 19
May 7, '00
S M T
Jun 4, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 20
8, '00
W
Jul 2, '00
S M T
Jul 9, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 21
Aug 6, '
S
8, '00
W
Jul 2, '00
S M T
Jul 9, '00
S M T
Aug 6, '
S
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 22
8, '00
W
Jul 2, '00
S M T
Jul 9, '00
S M T
Aug 6, '
S
Dr
Masonry Contractor
Ti
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 23
8, '00
W
Jul 2, '00
S M T
Jul 9, '00
S M T
Aug 6, '
S
Elevator Contractor
HVAC Contractor
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 24
8, '00
W
Jul 2, '00
S M T
Jul 9, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 25
Aug 6, '
S
Aug 6, '00
S M T
Sep 3, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 26
Aug 6, '00
S M T
Sep 3, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 27
Aug 6, '00
S M T
Sep 3, '00
S M T
g Contractor[33%],Electric Contractor[33%]
C. Concrete Crew
G.C. Labor Crew[10%]
G.C. Labor Crew
Plumbing Contractor
Ro
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 28
Aug 6, '00
S M T
Sep 3, '00
S M T
ntractor
Elevator Contractor
Elevator Contractor
Electric Contractor
HVAC Contractor
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 29
Aug 6, '00
S M T
Sep 3, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 30
0
T
Oct 1, '00
S M T
Oct 8, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 31
Nov 5, '00
S M
0
T
Oct 1, '00
S M T
Oct 8, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 32
Nov 5, '00
S M
0
T
Oct 1, '00
S M T
Oct 8, '00
S M T
Nov 5, '00
S M
Drywall Contractor
Masonry Contractor
Roofing Contractor
Tile Contractor
M
Tile Contractor[50%]
Roofing Contr
Dr
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 33
0
T
Oct 1, '00
S M T
Oct 8, '00
S M T
Nov 5, '00
S M
El
Pl
El
HV
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 34
0
T
Oct 1, '00
S M T
Oct 8, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 35
Nov 5, '00
S M
Nov 5, '00
M T
Dec 3, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 36
Nov 5, '00
M T
Dec 3, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 37
Nov 5, '00
M T
Dec 3, '00
S M T
actor
g Contractor
Masonry Contractor[50%]
Roofing Contractor
Roofing Contractor
Roofing Contractor
Roofing Contractor
HVAC Contractor
Window Contractor
Window Contractor
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 38
Nov 5, '00
M T
Dec 3, '00
S M T
Pa
Dr
Plumbing Contractor
HVAC Contractor
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 39
Nov 5, '00
M T
Dec 3, '00
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 40
Jan 7, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 41
Feb 4, '01
S M T
Jan 7, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 42
Feb 4, '01
S M T
Jan 7, '01
S M T
Feb 4, '01
S M T
Drywall Contractor
G.C. Finish Carpenter Crew
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 43
Jan 7, '01
S M T
Feb 4, '01
S M T
Electric Contractor
HVAC Contractor
Ca
Pa
Plumbing Contractor
Plumbing Contractor
Electric Contractor
Electric Contractor
Electr
Electric Contractor
AC Contractor
HVAC Contractor
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 44
Jan 7, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 45
Feb 4, '01
S M T
eb 4, '01
T
Mar 4, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 46
eb 4, '01
T
Mar 4, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 47
eb 4, '01
T
Mar 4, '01
S M T
er Crew
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 48
eb 4, '01
T
Drywall Contractor
Drywall Contractor
Painting Contractor
G.C. Finish Carpenter
Landscape Contractor
Plumbing Contractor
Electric Contractor
Electric Contractor
HVAC Contractor
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 49
eb 4, '01
T
Mar 4, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 50
Apr 1, '01
S M T
Apr 8, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 51
May 6, '01
S M T
Apr 1, '01
S M T
Apr 8, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 52
May 6, '01
S M T
Apr 1, '01
S M T
Apr 8, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 53
May 6, '01
S M T
Apr 1, '01
S M T
Apr 8, '01
S M T
Carpet Contractor
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 54
May 6, '01
S M T
Apr 1, '01
S M T
Apr 8, '01
S M T
May 6, '01
S M T
Elevator Contractor
G.C. Superintendent[50%],G.C. Project Management[50%]
G.C. Project Management[50%],G.C. Superintendent[50%]
G.C. Superintendent[50%],G.C. Project Management[50%]
G.C. Superintendent[11%],G.C. Labor Crew[11%],Plumbing Contrac
G.C. Project Management
G.C. Project Management
G.C. Project Management[33%],G.C. Accounting[33%],G
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 55
, '01
W
Jun 3, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 56
Jun 24,
S
, '01
W
Jun 3, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 57
Jun 24,
S
, '01
W
Jun 3, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 58
Jun 24,
S
, '01
W
Jun 3, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 59
Jun 24,
S
, '01
W
Jun 3, '01
S M T
Task
Inactive Task
Manual Summary
Split
Inactive Milestone
Start-only
Milestone
Inactive Milestone
Finish-only
Summary
Inactive Summary
External Tasks
Project Summary
Manual Task
External Milestone
External Tasks
Duration-only
Progress
External Milestone
Deadline
Page 60
Jun 24,
S