You are on page 1of 39

DOCUMENT COVER SHEET

13 Aug 2009

ISSUED FOR APPROVAL

REV.

DATE

DESCRIPTION

B.C.PARK M.Y,JUNG
DGN

H.I.LEE

CHK

APP

CLIENT

GPCOEWG
GENERAL PEOPLES COMMITTEE
OF ELECTRICITY, WATER AND GAS

GECOL
GENERAL ELECTRIC
COMPANY OF LIBYA

PROJ. CONSULTANT

A R A B I AN C ON SU LT ING AND E NGIN EER ING S ERVICES C O.


PROJECT TITLE

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/2007)


DESIGNED
BY

B.C.
PARK

13 Aug
2009

CONTRACTOR

GESCO
CHECKED
BY
APPROVED
BY

13 Aug
M.Y.JUNG
2009
H.I.LEE

GLOBAL ELECTRICITY SERVICES CO.

13 Aug TITLE
2009

Fire Protection Commissioning Procedure


SCALE PROJ.NO.
DOCUMENT NO.
NO. OF SHT.
Cover Sheet
N/A
10026 142007-SR00-T-FPCP-5013
+38

REV.
A

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

TABLE OF CONTENTS

1.

OBJECTIVE

2.

ACCEPTANCE CRITERIA

3.

REFERENCE

4.

PREREQUISITES

5.

PREPARATION AND NOTES

6.

TEST EQUIPMENT

7.

TEST AND COMMISSIONING PROCEDURE

8.

TEST AND COMMISSIONING SCHEDULE

9.

APPPENDIX

Rev.
A

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

1.

Rev.
A

OBJECTIVE

The objective of this procedure is to provide guidelines to verify the Fire


Fighting System being tested, and to furnish the initial start-up procedure of
the fire fighting system except the fire alarm/ detection system.
The equipment and control devices on the system must meet functional
design requirements to demonstrate reliability and continuity of process.
The fire alarm and detection system will be tested by a separate test
procedure to be submitted later.

2. ACCEPTANCE CRITERIA
1. Acceptance noise level
85 dB (A) in one meter distance from the source of equipment.
2. Vibration
Acceptable field vibration limits shall meet the vibration severity attached in
appendix
3. Bearing temperature
Bearing temperature are as specified by the vendors technical manual, but
Not exceed 75C.

3.

REFERENCE

1. P & I diagram
142007-SR00-M-1089

P& ID Fire protection System

142007-SR00-M-FFS- 003

Water Spray/ Precaution System P&ID

142007-SR00-M-FFS-005

Water cooling/ foam system P & ID

142007-SR00-M-1059

Flow diagram fire detection system

142007-SR00-M- 1207

Fire pump house system General


Arrangement

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

2. Wiring diagram
Later

Fire pump controller

Later

Fire pump diesel engine

2. General arrangement drawing


EE44724/01

Electric driven water fire pump

E3955/01

Diesel driven water fire pump

4. PREREQUISITES

1. Raw water intake level is normal


2. All piping, manual valves and equipment installation is completed by erection
manual.
3. Associated electric power is available.
4. Associated instrument installation is completed and available to put into
service.
5. Deluge valves in each area are properly operational condition.
6. All spray nozzles have been installed in the spray water system.
7. Diesel oil in the fuel oil tank for diesel engine is normal level.

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

5. PRECAUTION AND NOTES

1. To protect personnel and the equipment:


Barriers, danger signs, tags, area restrictions, etc. should be used by
lockout & tag out procedure and permit to work system in accordance
with the commissioning plan.

2. Stop running pump if unusual noises develop, or if monitored parameters


exceed the design limits.

3. Stop running pump if unusual noise leakage of water is occurred and


closes the relating valves.
4. Communication is established between the test equipment and control
station.
5. Prior to test equipment, test area shall be cleaned.
6. Test running time shall be as specified by the manufacture or until
equipment temperatures stabilize.

6.

AREAS TO BE PROTECTED BY FIRE PROTECTION SYSTEM

1) Indoor hydrants
CTG Building
Electrical control Building
Water Treatment Plant Building
Air Compressor Building
All others building
2) Outdoor hydrants
Chemical Dosing Shelter
LFO unloading bay
Fuel gas treatment Area
All other building and areas

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

3)

4)

Rev.
A

Automatic CO2 System


Gas turbine unit
Fuel gas skid
Corresponding Power control Center

Fixed Low expansion foam system


LFO Storage Tank

5)

Automatic water spray system


All oil filled transformers
Cable Cellar area in Electrical Control Building
LFO Storage tank

6) (Mobile and Portable fire Extinguisher)


Class A Class B Class C-

7.

Office Areas
Fuel Oil and Gas handling skid
Control, Electrical, Switchgear and battery room

TEST AND COMMISSIONING PROCEDURE


1) General Item
a. Prior to the commissioning test run, the system is to be checked,
and then the test run of raw/ water fire fighting pump and the water
flushing of the fire fighting system are to be executed in
accordance with the commissioning checklist attached herewith.
b. Before initial starting electric sequence and interlock test are to be
execute according to the documents issued for construction.
c. During the commissioning, adjustment of the limit switches are to be
executed if required.
d. The fire water pipes are to be flushed by back flow from the fire
water line and the flushing water is discharged to intake raw/ water
through the hose valves around the water fire fighting pump.

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

e. The ring main header of the fire fighting system should be flushed
using the fire water pump.
f.

Record measured values on the record sheet and / or logging


sheet while equipment is running.

2) Specification
a. Electric Motor driven fire water pump

Supplier
Number of pump
Type

Capacity
Model
Motor rated
Speed

SPP Pumps Limited


1 set
Horizontal Thru-Stream
(FM & or UL)- Axial Split Case
568 m/hr
SPP0 TD-20E
199.5 KW
2950 rpm

b. Electric Motor driven Jockey pump

Supplier
Number of pump
Type
Capacity

SPP Pumps Limited


1 set
Centrifugal, Horizontal
20m/hr

c. Desiel engine driven fire water pump


a) Pump
Supplier
Type

SPP Pumps Limited


Horizontal Thru- Stream
(FM & or UL)- Axial Split Case
SPP- TE20D
1 set
568 m/hr
2350 rpm,diesel

Model
Number of Pump
Capacity
Speed

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

b) Gear
Type
Model
Ratio
c)

Later
Later
Later

Engine
Manufacturer
Type
Model
Cylinder number
Aspiration
Governor Later
Fuel oil pump disch. Flow
Coolant flow rate
Coolant oper. Pressure
Lubrication type
Lube oil flow
Starter motor
Battery capacity
Low idle speed
Rated speed

3) Installation

Later
Later
Later
Later
Later
Later
Later
Later
Later
Later
Later
Later
Later
Later

check

Refer to installation checklist:

attachment 1

4) Pre- commissioning check


Refer to pre- commissioning check list:

attachment 2

5) Schedule of outstanding works


The outstanding works from the pre- commissioning check should be
listed up on the punch list attachment in appendix.

6) Commissioning check and system flushing works


Refer to commissioning checklist: attachment 3

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

8.

Rev.
A

TEST AND COMMISSIONING SCHEDULE

The actual test date will be informed to GECOL engineer in advance before test
based on the attached commissioning schedule.

9.

APPENDIX

1)

2)

3)

P & I Diagram
142007-SR00-M-1089

Fire protection System

142007-SR00-M-FFS-003

Water spray system

142007-SR00-M-FFS-005

Water cooling/ foam system

142007-SR00-M-1059

Flow diagram fire detection system

142007-SR00-M-1207

Fire pump house system General


Arrangement

Wiring diagram
Later

Fire pump controller

Later

Fire pump diesel engine

General Arrangement drawing


EE44724/01

Electric driven water fire pump

E3955/01

Diesel driven water fire pump

4)

Engine running test record sheet

5)

Pump running test record sheet

6)

Punch list

7)

Commissioning Schedule
8

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

ATTACHMENT 1

INSTALLATION CHECK LIST


MECHANICAL
ELECTRICAL
INSRUMENT

Rev.
A

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

TITLE: INSTALLATION CHECK LIST


SYSTEM
: FIRE FIGHTING SYSTEM
EQUIPMENT
JOB DESCRIPTION

NO.
1

Check the raw water fire fighting pump/engine, indoor hydrants


combined foam/ water hydrant, outdoor hydrants and automatic
water spray system have been installed as per the attached
P & I diagram.

Check all pipings and valves including post indicator valves,


deluge valves, safety valves, strainer, spray nozzles and flow
meter have been installed as per the attached P& I diagram.

Check all instrument ( gauge, switch, controller and transmitter)


have been installed as per the attached P & I diagram.

Check the diesel engine / fire pump control panel have been
installed as per electrical drawing.

THE ABOVE SUBJECT IN THIS SHEET HAS BEEN


CERTIFIED BY BELOW AUTHORITIES

PREPARED BY:

DATE:
HDEC/ VENDOR

REVIEWED BY:

DATE:
HDEC COMM'G

APPROVED BY:

DATE:
GECOL/ ACESCO

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

ATTACHMENT 2

PRE- COMMISSIONING CHECK LIST


RAW WATER FIRE FIGHTING SYSTEM
WATER SPRAY SYSTEM

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

TITLE: PRE- COMMISSIONING CHECK LIST


SYSTEM
: FIRE FIGHTING SYSTEM
EQUIPMENT : RAW WATER FIRE PUMP
NO.
1

JOB DESCRIPTION
DIESEL ENGINE TEST
1. Preparation Check
a. Mount the engine and fasten in place.
b. Align the engine with the pump. And disconnect the
coupling/ shaft between the engine and pump.
c. Install the fuel supply and the return lines.
d. Check to see if the fuel tank has been filled.
e. fill engine cooling system with pro- mixture of 50% treated
water and 50% coolant
coolant.
f. Inspect/ or install the air filter. Repair or replace the air
filter if damanged or missing. Do not allow air filter to be
obstructed; poor performance or engine damage may
occur.
g. Install the exhaust system. Do not allow exhaust system
piping to cause any stress on the engine. Do not exceed
backpressure limits.
h. Install wiring between the automatic engine control and
the engine terminal strip.
i. Install batteries and battery cables to the battery main
battery contactors. Batteries should be charged 24 hrs
j. Install the water conduits. Do not allow plumbing to cause
any stress on the heat exchanger or aftercooler.
k. Check for damaged or missing exhaust blankets.
Repair or replace if necessary.
l. Fill the engine with crankcase oil.
m. Connect the jacket water heater to the pump motor AC
outlet. The jacket water heater is thermostatically controlled.
Do not connect the jacket water heater if the engine is not
filled with coolant: this may cause the heating element to
over heat and burn out.
n. To prevent bearing damage during initial start-up,
pre lubricate the engine at low rpm.

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

TITLE: PRE- COMMISSIONING CHECK LIST


SYSTEM
: FIRE FIGHTING SYSTEM
EQUIPMENT : RAW WATER FIRE PUMP
NO.

JOB DESCRIPTION
ENGINE START
a. Manual start and stop
a) Place the selector switch in " Manual" mode
- Observe the pilot light comes "On".
- Observe the run soleniod engages, and a clicking sound is heard.
b) Lifts and holds manual crank toggle switch.
c) Check the engine starts, and the engine speed is reached the
the factory -set speed without the engine idling and without a
warm up period
period.
d) Release the manual crank toggle switch.
-Observe the pilot light turns " Off" indicating that the alternator
is functioning and the batteries are being charged.
e) During the diesel engine is running. The followings should be
checked.
- Leaks:
Check for leaks. Verify the coolant hose. The fuel supply and
the return lines or any where else around the engine.
- Oil pressure:
Normal reading is between 55 and 88 psi ( 3.75 and 5.4 bar.)
- Jacket water temperature:
The jacket water temperature should normally remain in the
green sector. If the pointer enters the orange sector, the engine
is over heating and engine damage may occur.
- Engine speed:
Normal reading for the tachometer is the factory preset speed.
b. Remote Start and stop
a) Place the selector switch in " Auto " mode.
b) Push the " Remote" push button in central control room.
- Observe the pilot light comes " on "
- Observe the run selenoid engages, and a clicking sound is
heard .
c) Check the engine start cranking automatically.

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

TITLE: PRE- COMMISSIONG CHECK LIST


SYSTEM
: FIRE FIGHTING SYSTEM
EQUIPMENT : RAW WATER FIRE PUMP
NO.

JOB DESCRIPTION
d) Check the engine speed is reached the factory set speed.
e) Observe the starter motor to the stop cranking has been
actuated by electronic switch.
f) After running of diesel engine observe the pilot light turns" Off"
indicating that the alternator is functioning and the batteries are
being charged .
g) Stop the engine.
c Verifying the overspeed test switch
c.
a) Start the engine by manual
b) Check the engine speed is kept at rated speed.
c) Hold the overspeed testing switch in the "up" position until the
the engine shuts down.
d) Check the engine shuts down immediately with overspeed
alarm.
e) Push the "Over speed reset" button on the control panel
f) Restart the engine.

FIRE PUMP TEST


1) Chek the oil level of right angle gear unit is normal in oil level
gage.
2) Rotate the pump shaft by hand to make sure the pump is free
and the impeller are correctly positioned.
3) Make sure that the shaft adjusting nut is properly locked into
position
4) Be sure the driver has been properly lubricated in accordance
with the instruction furnished with the driver.
5) Checked the driver rotation. Remember the pump must be
disconnected from the driver before checking. The driver must
rotate Counter Clockwise when looking down from the top of
the driver.
6) Check all connection to the driver and control equipment.
7) Check all piping connection are tight.

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

TITLE: PRE- COMMISSIONING CHECK LIST


SYSTEM
: WATER SPRAY SYSTEM
EQUIPMENT : DELUGE VALVE
NO.

1
2
3

JOB DESCRIPTION
8) Check all anchor bolts for tightness.
9) Check all bolting and tubing connection for tightness.
( driver mounting bolts, flanged coupling bolts, seal housing cover
bolts, seal piping, etc.)
10) On the pumps equipment with packing box, make sure the
glands nuts are only finger tight and do not tighen packing gland
before starting. Check the cooling water inlet and outlet lines.
Connect the coupling /drive shaft bet, the engine and pump.
The system is full of water up to the automatic deluge valve clapper
clapper.
The main gate valves, installed upstream of the automatic deluge
valve ,are open.
Automatic deluge valve unit condition.
1) Deluge valve is closed, full of water in pressure under the clapper.
2) Clapper is blocked in " closed position" by the water pressure
in the control head.
3) The actuator or solenoid valve and the emergency release valve
to be closed.
4) System water pressure to be shown on pressure gage.
5) Alarm valve is closed.
6) Angle discharge valve for drain is closed.
7) Water flow pressure switch not transmit signal to the Control
panels.
The water spray nozzles switch are in standby.
PREPARED BY:

DATE:
HDEC/ VENDOR

REVIEWED BY:

DATE:
HDECCOMM'G

APPROVED BY:

DATE:
GECOL/ ACESCO

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

ATTACHMENT 3

COMMISSIONING CHECK LIST


RAW WATER FIRE PUMP
SYSTEM FLUSHING & SYSTEM FILL-UP WATER
WATER SPRAY SYSTEM

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

TITLE: COMMISSIONING CHECK LIST


SYSTEM
: FIRE FIGHTING SYSTEM
EQUIPMENT : RAW WATER FIRE PUMP
NO.

JOB DESCRIPTION

PUMP TEST RUN


1) Preparation
a. Check the engine no load test has been completed.
b. Check the coupling / drive shaft has been connected.
c. Check the safety pressure valve located on the pump discharge
line is set in the factory.
d. Check the following valve are closed.
-pump discharge valve AA003 to system
-fire
fire water ring header PIV valves AA001
AA001.
e. Open pump discharge valve AA004going to flow meter CF701
2) Start the raw water fire pump by manual at diesel engine
control panel momentary.
-Check the direction of pump rotation, any noise and vibration.
3) Restart the raw water fire fighting pump by manual.
4) After the fire pump is started with the engine satisfactory, adjust
the pump discharge pressure, if necessary. And check any
abnormal conditions.
5) Check complete pump and engine for leaks, loose connection
or improper operation.
6) If possible, the fire pump should be left running for approximately
30 minutes on the initial start-up. This will allow the bearing,
packing or seals, and other parts to " Run- in" and reduce the
possibility of trouble on the future starts.
7) During the pump and engine test all operation data should be
be checked and recorded.
8) Stop the engine by manual.

FLOW MEASURING TEST


1) Preparation
a. Close the pump outlet valve AA003.
b. Open the valve AA005.

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

TITLE: COMMISSIONING CHECK LIST


SYSTEM
: FIRE FIGHTING SYSTEM
EQUIPMENT : RAW WATER FIRE PUMP
NO.

JOB DESCRIPTION
2) Start the raw water fire pump by manual at local and
purge the flow meter CF701.
4) Take the pump discharge pressure gage reading.
5) Stop the raw water fire pump manual after reading the
pump discharge flow.

SYSTEM FLUSHING AND SYSTEM FILL-UP WATER


Note: Check hydrostatic test of all fire water ring main and
branches line had been completed
completed.
1) Perparation ( Check the follows valve are closed)
a. Fill the system with raw water as follows.
- inlet valve of all outdoor hydrants.
- inlet valve of all in/ outdoor deluge valves for water spray
system.
- Isolating valve of all indoor water and foam/water hydrants.
b. Check the following valves are opened.
- All post indicator valves located in underground.
- Isolating valve of indoor water hydrants.
2) Execute the flushing after confirming that all water system has
been filled up with water.
a. Outdoor hydrants
- Open the valve of outdoor hydrants one by one until clean water
comes out.
b. Indoor hydrants
-Connect the fire hose at the indoor water hydrants.
- Open the hydrants inlet valve one by one until clean water
comes out.
c. Restore and normalize the fire fighting system.

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

TITLE: COMMISSIONING CHECK LIST


SYSTEM
EQUIPMENT
NO.
1

: WATER SPRAY SYSTEM


: DELUGE VALVE
JOB DESCRIPTION

TEST OPERATION OF DELUGE VALVE


The actual test of deluge valve will be limited to the outdoor
transformer except for the cable Cellar area in Electrical Control
building and LFO Storage tank.
1) Manual Test for Transformers
a. Select the trasformer to be tested.
b. Check the system pressure is maintained at 8.45 bar
c Open the manual valve of manual emergency station on
c.
on deluge valve to be checked.
d. Check the following
a) Pressure switch is closed and zone lamp of fire
alarm control panel is on.
b) Buzzer of control panel make sound.
c) Deluge valve is opened
d) Water discharge to transformer
e. Check the system pressure is maintaine by the fire water
pumps.
f. Close the manual valve of manual emergency station on the
deluge valve.
g. Observe the deluge valve is closed and the alarm on the fire
alarm control panel is " OFF".
h. Test all deluge valves for transformer as per the above test
procedure one by one. If possible.
2) Automatic test for Transformer
a. Select the transformer to be tested .
b. Check the system pressure is maintained at 8.45 bar by fire
water pump.
c. Actuate the heat detector around the transformer by heat
push the emergency release button of manual operating
box.

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

TITLE: COMMISSIONING CHECK LIST


SYSTEM
EQUIPMENT

: WATER SPRAY SYSTEM


: DELUGE VALVE

NO.

JOB DESCRIPTION
d. Check the followings
a) Solenoid/ actuator valve is opened.
b) Pressure switch is closed and zone lamp of fire alarm
control panel is on.
c) buzzer of control panel makes sound.
d) Deluge valve is opened
- Water discharge to transformer
e. Reset the fire alarm on the fire alarm control panel and
check the solenoid /actuator valve is closed and then deluge
valve is closed.

Test the deluge valves for all transformer as per the above
test procedure one by one. If possible.

THE ABOVE SUBJECT IN THIS SHEET HAS BEEN CERTIFIED


BY BELOW AUTHOURITIES.

PREPARED BY:

DATE:
HDEC/ VENDOR

REVIEWED BY:

DATE:
HDEC COMM'G

APPROVED BY:

DATE:
GECOL/ ACESCO

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

8.

Rev.
A

TEST AND COMMISSIONING SCHEDULE

The actual test date will be informed to GECOL engineer in advance before test
based on the attached commissioning schedule.

9.

APPENDIX

1)

2)

3)

P & I Diagram
142007-SR00-M-1089

Fire protection System

142007-SR00-M-003

Water spray system

142007-SR00-M-FFS-005

Water cooling/ foam system

142007-SR00-M-1059

Flow diagram fire detection system

142007-SR00-M-1207

Fire pump house system General


Arrangement

Wiring diagram
Later

Fire pump controller

Later

Fire pump diesel engine

General Arrangement drawing


EE44724/01

Electric driven water fire pump

E3955/01

Diesel driven water fire pump

4)

Engine running test record sheet

5)

Pump running test record sheet

6)

Punch list

7)

Commissioning Schedule
8

Project :
Quote Ref. :

Libia - HDCE
SC 080527

Type:
Pump Model:
Pump Op. Speed:
Impeller Dia.:
Curve No.:
Market :

Horizontal Thru-Stream (FM and/or UL) - Axial Split Case


SPP - TD20E
2950 RPM, 50 Hz Electric
314.4
mm
TD20E-C2950/2G-A1
FM/UL/ULC Listed Fire Pump

Page No : 1

Customer :

Silvani Antincendi spa


Via Bancora e Rimoldi, 47
22070 Guanzate (CO)

Date :

26 May 2008

Item :
Impeller No.:
Liquid:
Temperature:
Viscosity:
Density:
Your Ref. :

Electric pump
Water
20
C
1.01 cSt
998.2 kg/m

D1-340.0 mm, D6-240.0 mm

Rated Flow

568.1 m/h

Rated Head

150

100 m

Imp. Dia.

314.4 mm

Rated Power Required

199.5 kW

Head - m

Rated NPSH Required

100

77.6 %

NFPA Limits:
140% Head at shutoff

140 m

65% Head at 150%


flow
Flow at 150%

D1

50

4.7 m

Rated Efficiency

65 m
852.2 m/h

Head at 150

D6

74.3 m

Power Req. at 150%

215.8 kW

NPSH Req. at 150%

5.8 m

NPSH - m

8
6
4
2

Power - kW

Efficiency at 150%

200
150
100
50

79.9 %

Peak Power

216 kW
126.6 m

Closed Valve Pressure


Approval

FM

Comments
NPSH REQUIRED at centreline of
impeller. Add 0.5m to Laboratory
NPSH curve for field applications

500

1,000
Flow - m/h

Flow
(m/h)

Head
(m)

Pump Efficiency
(%)

Power Required
(kW)

NPSH Required
(m)

0.0
128.1

126.6
120.6

0.0
30.8

130.3
136.6

256.2

115.3

52.7

152.7

3.7

384.2
512.3

109.9
103.4

66.5
75.1

172.8
192.2

4.0
4.5

640.4

94.9

79.9

207.2

4.9

768.5
896.6

83.6
68.6

81.4
78.1

215.2
214.5

5.3
6.3

1024.6

49.0

66.7

204.9

SPP Pumps Limited - RAPID v8.06 - 1st August 2007.

Project :
Quote Ref. :

Libia - HDCE
SC 080527

Type:
Pump Model:
Pump Op. Speed:
Impeller Dia.:
Curve No.:
Market :

Horizontal Thru-Stream (FM and/or UL) - Axial Split Case


SPP - TE20D
2350 RPM, Diesel
364.6
mm
TE20D-C2350/1S-A1
FM/UL/ULC Listed Fire Pump

Page No : 2

Customer :

Silvani Antincendi spa


Via Bancora e Rimoldi, 47
22070 Guanzate (CO)

Date :

26 May 2008

Item :
Impeller No.:
Liquid:
Temperature:
Viscosity:
Density:
Your Ref. :

Diesel pump
Water
20
C
1.01 cSt
998.2 kg/m

D1-378.0 mm, D3-320.0 mm

Rated Flow
Rated Head

150

568.1 m/h
100 m

Imp. Dia.

364.6 mm

Rated Power Required

204.4 kW

Head - m

Rated NPSH Required


Rated Efficiency
NFPA Limits:
140% Head at shutoff

100

65% Head at 150%


flow
Flow at 150%

50
D3

D1

4.1 m
76.1 %
140.8 m
65.4 m
852.2 m/h

Head at 150
Power Req. at 150%

83 m
231 kW

NPSH Req. at 150%

NPSH - m

Peak Power

Closed Valve Pressure

Power - kW

Efficiency at 150%

250
200
150
100
50

Approval

5.1 m
83.4 %
236.3 kW
120 m
FM/UL

Add 2% Cooling

Comments
NPSH REQUIRED at centreline of
impeller. Add 0.5m to Laboratory
NPSH curve for field applications

500

1,000
Flow - m/h

Flow
(m/h)

Head
(m)

Pump Efficiency
(%)

Power Required
(kW)

NPSH Required
(m)

0.0
172.9

120.0
113.6

0.0
36.6

136.8
146.1

345.8

108.9

59.9

171.1

518.7
691.6

102.8
93.8

73.5
80.8

197.7
218.7

4.0
4.4

864.4

82.0

83.4

231.6

5.2

1037.3
1210.2

67.8
49.5

81.1
69.9

236.3
233.5

6.3
7.8

1383.1

23.3

39.5

222.0

250.

SPP Pumps Limited - RAPID v8.06 - 1st August 2007.

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/ 2007)


TITLE: Fire Protection Commissioning Procedure

Rev.
A

DIESEL ENGINE RUNNING TEST SHEET


Time(Min)
Items

Unit

Speed

rpm

Lube oil pressure

bar

Lube oil temp.

Vibration

Noise

dB

Fueltanklevel

mm

Runninghour

hr

10

20

30

PUMP RUNNING TEST RECORD


EQUIPMENT NAME
PUMP CAPACITY
PUMP MAKER
PUMP SPEED
PUMP SERIAL NO.

SYSTEM
MOTOR MAKER

(V)

MOTOR SPEC.

(KW)

(A)

INSUL. CLASS

(rpm)

MOTOR SPEED

(m3/hr)

MOTOR SERIAL NO.

AMBIENT TEMP. (C)


VIBRATION (1/1000mm)

INSUL.. RESISTANCE
BEARING TEMP. WINDING TEMP

Item Suct Disch


/
Pr
pr
Time (mbar) (bar)

rpm

Volt Amp
(V) (A)

HORIZONTAL
1

VERTICAL
1

AXIAL
4

Design
Value
Before
Start

:
:
:
:
:
:
:

NOISE (dB)
PUMP

MOTOR
Y

NOISE
NOISE LEVEL ACCEPTABLE CRITERIA 85 dB

THE ABOVE SUBJECT IN THIS SHEET HAS BEEN


CERTIFIED BY BELOW AUTHOURITIES.

PREPARED BY:

REVIEWED BY:

APROVED BY:

DATE:
HDEC/ VENDOR
DATE:
HDEC COMMG
DATE:
GECOL/ ACESCO

dB

PUNCH LIST
SHEET:

SYSTEM:
NO.

DESCRIPTION

RAISED BY

HYUNDAI
RESPONSIBLE
PERSON

COMPLETION
DATE

RELEASED BY

OF

REMARKS

SARIR 3X250MW GAS TURBINE PROJECT, LIBYA (14/2007)


FIRE PROTECTION COMMISSIONING PROCEDURE

Duration (Days)
1

Activities
A. INSTALLATION CHECK
1) MECHANICAL

2) ELECTRICAL/ I&C

B. PRE-COMMISSIONG CHECK
1) RAW WATER FIRE PUMP
AND DIESEL ENGINE
2) WATER SPRAY DELUGE
VALVE

C. COMMISSIONING CHECK
1) RAW WATER FIRE PUMP
2) SYSTEM FLUSHING &
SYSTEM FILL-UP WATER
3) ACTUAL TEST OF DELUGE
VALVE OF OUTDOOR
TRANSFORMER

10

11

12

13

14

15