3 Submitting the shop drawing for approval 4 Approval of shop drawings - Duct layout 5 Approval of GA drawings - Ambiator, 40 K 6 Technical Submittals Approvals 7 Site Mobilization 8 Placing Internal PO Material deliveries 9 Duct materials 10 Insulation materials 11 VCD's and Fire dampers 12 Air Washers / Ambiator 13 Split AC units 14 Copper pipes, drain pipes & Insulation tubes 15 Propeller fans 16 Supply of Jet Nozzles & jet diffusers 17 Control panels Erection Works 18 Insulation of Duct 19 Duct and support installation 20 VCD's and fire dampers 21 Air Washers / Ambiator installation 22 Split AC units piping, testing & commissioning 23 Exhaust fans installation 24 Jet Nozzles & jet diffusers installation 25 Control panels 26 Cable laying & termination 27 Drain pipe installation 28 Testing & commissioning 29 Snag list and Handing Over