SEGUIMIENTO DEL PROYECTO

FINANCIA

: ASOCIACION CIVIL NEOANDINA

OBRA

: CONSTRUCCION DE LA LOSA MULTIDEPORTIVA - MULTIUSO DE TINYASH

CONTRATISTA

: JHOTAS CONSULTORES & CONSTRUCTORES SRL

RESIDENTE

: ING. JHONNY HUAMAN GIRALDO

SUPERVISOR :

: ING. LEO LA BORDA

UBICACIN

: DISTRITO DE INDEPENDENCIA, PROVINCIA DE HUARAZ, DPTO DE ANCASH

Fuente: El Grupo
MESES
AVANCE
MENSUAL
PROGRAMADO ACUMULADO
AVANCE
REAL

MENSUAL
ACUMULADO

06-02-12
0.00%
0.00%

29-02-12
56.67%
56.67%

31-03-12
40.26%
96.93%

06-04-12
3.07%
100.00%

0.00%
0.00%

65.66%
65.66%

28.28%
93.94%

6.06%
100.00%

LEYENDA
CURVA DE AVANCE PROG.
CURVA DE AVANCE REAL