FORM 10
Regulation 60 (5)
‘THE PUBLIC PROCUREMENT AND DISPOSAL OF PUBLIC ASSETS ACT. 2003
RECORD OF MINUTES OF PRE-BID MEETING
Procurement Reference Number
Code of Procuring and | Suppies/WVorksiNon-consullancy senices | Financial year | Sequence number
Disposing
Entity
NWSCIG Works 20T2015 60775
Particulars of Procurement
Subject of procurement Kinawataka Pre-Treatment Plant and Lifting Station
Location of Pre-bid Meeting National Water and Sewerage Corporation International resource Center,
Bugolobi, Kampala
Date and time of Meeting 30 November 2015, 10.00 am EAT
Record of Pre-bid Meeting Minutes
‘Question asked
Response giveniClarifcations
The level/content of H2S in the bio filters
was not specified in the tender documents
and this is very key as it has to be
considered during the design stage.
In the tender documents, you indicated that
a softcopy of the Geo-Technical site
investigation report and Design report and
of the B.0.Qs can be provided upon request.
Could we please have them
The level of HeS Is specified as below
Description | Units
Design Data
[ mgim? 40
Hs:
This falls under the table volume 2B,
Employers specific Requirements; “Process”
on page 18 of 23,
The geotechnical reports and Design Reports
as well as soft copies of the BOQs are
available at the procurement department for
bidders upon request.
Has the client designated a specific place
for dumping excavated material from site.
Tt is the responsibility of the Contractor to
identify and secure permits from relevant
authorities for places proposed for dumping
excavated material.
In the Bid Data Sheet, tem 16.3: i was
indicated that “the Bidder shall submit with
its bid, evidence that it will be represented
by an’ Agent in the country.” What did u
mean by this?
The Bidder shall_not submit with its bid,
evidence that it will be represented by an Agent
in the country.Will the bidder obtain exemption from
domestic taxes such as sales tax, VAT and
Customs duties on equipment imported for
the execution of Project and construction
items specified in Bills of Quantities
The bidder shall bear and pay all taxes, duties,
levies and charges assessed on the Contractor
its Subcontractors or their employees by all
municipal, state or national government
authorities in connection with the Facilities in
and outside of the country where the Site i
located. The Contractor shall bear and prompt!
pay;
(2) All customs and import duties for the}
Plant specified in Price Schedule No. 1; and
(b) Other domestic taxes such as, sales tax and
value added tax (VAT) on the Plant specified in
Price Schedules No. 1 and No. 2.
Will the arrangement of Electricity and
Water required for execution of the
construction activities be the Employer's
responsibilty or the Bidder
Supply of Electricity and water arrangement
during execution of the construction activities
will be the Contractor's responsibility.
Tn Volume 2 — Part 28, Employer's specific
requirements — item 1.11 says the piling and
foundation design will be done by the
contractor where as in volume 3 — Bills of
Quantities - Item 1.1.12 says piling and
foundation design will be provided by the
employer.
In addition, the scope of the piling and
foundation works is not defined for
measurement and payment purposes in the
Bills of Quantities. Please clarify on this
The bid security in the amount of 600,000
Euros as stated in the Bid Data Sheet, ITB
49.1 (Vol.1 Section II of the provided tender
documents), is in our opinion too high.
Please confirm or clarify on this
These works are to be executed by the
Contractor. Please note, that the piling works
include as well the design, which is intended to
be completed in the 2 months mobilization
phase. Kindly study the _ submitted
"Geotechnical Report’. Below is a table
indicating the provisional scope of the piling
and foundation works for measurement
purposes. Piles will be CFA piles as specified in
the specific requirements for Civil works;
General; Design and Surveys; Foundation and
Bored Pile Design, pg. 6 of 45 in the attached
document.
The general specification under General
requirements (1.3.7.5) is general information
but not all requirements are relevant in this
scenario as the piles will be CFA piles
We confirm that the bid security is 500,000
Euros as stated in the Bid Data Sheet, ITB
49.1 (Vol.1 Section Il of the provided tender
documents)
Twas mentioned in the Bid Data Sheet that
the prices shall be quoted by the bidder in
the schedules, entirely in Ugandan shillings
and the currency of the bill of quantity is
mentioned in Euro, Please clarify
The prices that should be quoted by the bidder
in the schedules should be entirely in Euros.
Iry,-It was mentioned in the consultant Design | The Pre-treatment sewage pipeline (600mm
report that our scope of works includes | diameter and 4.5km long) as described is not
construction of a pretreatment sewage | part of the scope of works. This is already
pipeline with 500mm diameter and 4.5km | being executed by a different contractor under
long, but it was not mentioned in the bills of | a different project.
quantities or bid documents, Please clarify if
itis included in our scope of work or not.
Pilings quantities
Please note that this cut out of the table has now been included in the revised BOQs under
the sheet for Civil Works (tab colored red) sub-heading Earthworks and Piled Foundations
and wordings highlighted red
Price schedule N° 4.2.1
Earth Works and Piled Foundations
Item Description Qty. | Unit
Uni Total
Price Price
EURO | EURO
Mobilisation/Demobilisation of complete
equipment’ machinery necessary for
4.2.1.1 | driling/casting/load testing of 600mm 1| 15. 0.00
diameter piles in reinforced concrete to a
depth of up to 40m below ground
Construction of diam 600mm conerete
4.2.1.12 | Piles including driling works, borehole
stabilisation, concrete filing and 2,500) m OO
reinforcement
4.21.14 | Culting back of pile heads 15 | me 0.00 |
4.2.1.16 | Pile load testing for each pile constructed TI Is. 0.00 |
‘Conorete testing of conorete test cubes
(after 7 days, 14 days and 28 days) of,
4.2.1.16 | each batch of pile concrete by an 100 | No 0.00
independent approved institution as
ordered by the Engineer
‘Any other items necessary to complete the ane 0.00
Contractor's obligations l
424.17
Certification of minutes as a true record of the proceedings of the meeting:
Name Kas ture 4S6fae7
Posit
ion: Chairperson of the meeting
Signature:
Date: A 19 fa i?
Record of pre-bid meeting to be sent to all bidders who purchased or were issued with the
bidding documents.