Professional Documents
Culture Documents
Transmittal
Date:
Section:
To:
From:
Subject:
We are
submitting:
Date
1201 006
Dan Latta
Hollyann Walker
Amanda Elsayed, Jerry Autry, Brandon Krahn, Shane OBrien
Beam Project Technical Report
Memorandum
Design Package
Problem Set
Report - Draft
Report - Final
Extra Credit
Description
Beam Project Technical Report
1
Beam Project Technical Report
Prepared for:
XLIX Engineering Design Firm
9201 University City Blvd
Charlotte, NC 28223
Introduction to Engineering Practice and Principles I
ENGR 1201-006
Prepared by: Team 1
Jerry Autry, Brandon Krahn, Amanda Elsayed, Shane OBrien
Date Submitted:
11/24/2015
I have neither given nor received any unauthorized help on this assignment, nor witnessed any
violation of the UNC Charlotte Code of Academic Integrity.
2
Table of Contents
Abstract... 3
Introduction..... 3
Background Information..... 3
Figure 1: Beam Support Styles...4
Figure 1: Typical Beam Shapes..4
Figure 3: Deflection of a beam...5
Methods and Procedure.. 5
Figure 4: Structural Beam Design Requirements.......................................................6
Figure 5: Amandas Beam Design.....7
Figure 6: Brandons Beam Design.....7
Figure 7: Shanes Beam Design.....8
Figure 8: Treys Beam Design.......8
Figure 9: Example Beam Calculator..9
Table 1: Beam Design Decision Matrix.....9
Figure 10: Team 1s Beam11
Observations and Results.......12
Table 2: Standards for Each Team....12
Table 3: Beam Requirements....12
Table 4: Calculated Specifications of the Beam...12
Figure 11: Beam for Team 1.13
Figure 12: Beam under Load.14
Figure 13: Test Data Sheet14
Table 5: Test Data for Beam by Team 1...15
Table 6: Calculated Vs Experimental Results...15
Table 7: Percent Difference...15
Discussion..16
Conclusion and Recommendations....17
References..18
3
Abstract
For the Beam Design Project, Team 1 was assigned with designing and building a beam within
certain constraints and resources. This project was assigned to introduce 1201 students to
working within a team to design and build a product, and also be able to analyze the results.
Resources to build the beam were limited to only basswood obtained from 1201 lumber yard,
clamps, hobby knife, tools, and Elmers Carpenters Wood Glue from the Discovery Box. Each
team member did intensive research about simply, supported beams before designing individual
beams. After each member designed three different beams and selected the best one out of the
three, the team as a whole selected the best beam to be constructed and tested. After the beam was
build, it was brought to class to be tested in which the load indicated by the problem statement
was applied. The beam supported the load that was given and the deflection was within the
constraints. Upon testing, Team 1 analyzed the beam results and discussed what these successful
results meant. It is recommended to use a thick wed and flanges when constructing an I-Beam, as
presented with the results of Team 1s beam. It was also recommended to add glue and stabilizers
with caution as it could lead to an increase in mass, thus skewing the efficiency ratio. After full
completion of this project, Team 1 further realized the effectiveness of a well-organized team and
that good engineering judgement is needed in the design process, as not everything that passes on
paper will succeed under real circumstances.
Introduction
A unique beam, number 150803, was constructed of basswood obtained from 1201 lumber yard.
This beam was required to support a load of 350lb f in a center-loaded, simply-supported
configuration (x-axis). The y-axis load of this beam was also required to support 200 lb f. The
length of this beam was required to be 24 in., while the length span was 21in. The beam was
expected to carry the required load within a minimum deflection of 0.05 in. and maximum of
0.235 in. when tested. In order for the beam to be tested, the composite cross-section was
required to be symmetrical about the centroid axis and be designed in a standard I-beam, H-beam,
or a hollow box beam configuration. The cross-section dimensions of the beam were not to
exceed 2 x 2. The mass of the beam could not exceed the maximum mass requirement of 240 g.
Moreover, the cost to construct the beam could not exceed $10.50, which included the cost of the
wood and $0.50 per glue joint. Teams were also required to provide a Bill of Materials for the
cost of the final design. All wood used to construct this unique beam, was obtained from the 1201
Lumber Yard, which had limited sizes and quantities. Construction of the beam was completed
using the given supplies and tools, which included: clamps, hobby knife, tools, and Elmers
Carpenters Wood Glue from the Discovery Box. Calculations were completed for the basswood
beam assuming values for physical material properties which included the modulus of elasticity
(1.46 x 106 psi) and density (28lbm/ft3).
Background Information
Beams are typically horizontal structures, which are used to hold and support vertical loads.
However, they can be vertical members of a structure that withstand horizontal loads such as a
wall withstanding the force of wind. Beams have different names depending on where they are
being used. Roof, building, and bridge construction have their own respective names for beams,
depending on where and how they are placed and the loads which act upon them. The load is a
force which is placed on a beam and can be different depending on how and where the load is
applied. Single point loads act at a specific spot on the beam and the force is concentrated at that
particular point. Distributed loads act along a span of the beam, and are either uniformly or
4
variably distributed. Static loads remain the same over time while a dynamic load changes as it
travels across the beam.
Beam theory is the prediction of the reaction a beam will have to a specific load and the different
beam configurations that have an effect on the beams reaction. These different styles of beam
configuration include simple, continuous, cantilever, end-supported cantilever, combination, and
fixed, however, only a simple supported beam was tested. This means that the beam is rested on
two points near the ends of the beam. An example of these beam styles can be seen in Figure 1
below.
b h3
12
where b
The moment of inertia for a hollow box beam is found with the equation:
bo ho
12
bh
- i i
12
where bo is the base of the outer box, ho is the height of the outer box, bi is the base of the inner
box, and hi is the height of the inner box
bo ho3
12
The calculations for an I-beams moment of inertia is completed with the equation:
2(
bi hi3
12
where bo is the base of the entire beam, ho is the height of the entire beam, bi is the
base minus the width of the web (vertical section), and h i is the height minus 2x the width of the
flanges (horizontal sections).
b1 h 13
For an H-beam, the moment of inertia is found with the equation: 2(
12
b2 h23
12
where b1 is the base of the flange (horizontal section), h 1 is the height of the flange, b2 is the base
of the web (vertical section), and h2 is the height of the web.
3
Once the moment of inertia is found, it can be plugged into the equation:
PL
48 EI
where
is the deflection, L is the length of the beam, E is the modulus of elasticity which is the resistance
to bending of the specific material used (in this case, basswood), and I is the moment of inertia.
Figure 3 below shows the deflection of a beam, and aids in understanding where each
measurement originates.
M =( V )( D) where V is the
60%
30%
30%
100%
Evaluatio
n Criteria
X-Axis
Deflectio
n
Efficiency
Ratio
Cost
Total
Alternatives
Treys I Beam
Brandons I
Beam
Ratin
Scor
g
e
Ratin
g
Scor
e
1.5
0.6
2
5.1
1.2
3.3
Amandas I
Beam
Scor
Ratin e
g
4
2.4
1.5
0.6
2
4.5
Shanes I
Beam
Ratin
Scor
g
e
4
2.4
1.5
1.5
0.6
0.6
4.5
The following calculations were utilized in the mathematical analysis of the beam dimensions
that were ultimately decided upon. Although all beams passed the requirements, Shanes beam
utilized the sturdiest materials, and was chosen to be built by team 1 based on this. These
calculations are representative of the dimensions of his beam.
Cross Sectional area (A):
A= ( ( B )( H ) )((BT w )( H w ))
A= ( ( 1. ) ( 1.875. ) )((1.0.3125.)(1.25.))
A=1.016 2
Volume (V):
V =( A )(l)
10
3
V =24.375
V=
( A)(l)
1728 3
V=
(1.016 )(24.)
1728 3
V =0.014 ft 3
Mass (m):
For mass in (lbm):
m=(V )( D)
m=(0.014 ft 3 ) 28
lbm
ft 3
m=0.395 lb m
For mass in (g)
m=( 0.014 ft 3 ) 28
lbm
ft 3
(453.592 g)
m=179.153 g
Moment of inertia about x-axis (Ix)
3
( )(
)
(1.)(1.875.)
) ( 1.25. )
I =(
)( ( 1.0.3125.
)
12
12
3
( BT w )( H w )
BH
I x=
12
12
3
I x =0.437 4
Moment of inertia about y-axis (Iy)
)(
(T f ) ( B )
( H w ) ( T w)
I y =2
+
12
12
)(
(0.3125.) ( 1. )
( 1.25. ) ( 0.3125. )
I y =2
+
12
12
11
4
I y =0.055
P x L3
x=
48 E I x
21.
3
(350 lb f )
x =
x =0.106
Deflection about y-axis (y)
3
P L
y= y
48 E I y
21.
3
(200 lb f )
y =
y =0.478
Cost ($)
12
350
200
240
0.05
0.235
10.50
21
24
13
These requirements were used to design and build the beam that Team 1 used. The dimensions,
along with the calculated specifications of this beam are included in Table 4 below.
Table 4. Calculated Specifications of the Beam
Value
1
0.3125
1.875
1.25
0.3125
1.016
24.375
0.014
0.395
179.153
0.437
0.055
0.106
0.478
8.32
A cross-sectional view of the beam used by Team 1 can be seen in Figure 11 below.
14
15
16
179.153
Calculated Deflection
0.106
and
supports
supports
175
185
Tested Deflection
0.147
After seeing that Team 1s beam passed, the grade received was based upon
the efficiency ratio of their beam. This can be found by the following
equation.
Efficiency Ratio=
The efficiency ratio for Team 1 came out to be 1.297, which resulted in a
grade of 90.
After completing a project, it is helpful to know how far off your results are
from what you calculated them to be. To find this, the percent difference
equation is used, which is demonstrated below.
| ActualTheoretical|
Difference=
Theoretical
x 100
The percent difference from the data gained through this experiment is found in Table 7 below.
Table 7. Percent Difference
|175179.153|
Difference ( mass ) =
179.153
x 100 =2.31
|0.1470.106|
Difference ( deflection ) =
0.106
x 100 =27.89
The data for the percent difference in the table above comes from Table 6. Due to there being two
different values for the actual mass of the beam, the mass before gluing was used to find percent
error since the calculated mass of beam includes only the wood.
Discussion
17
After acquiring the needed sections of wood to construct the beam designed by Team 1, the wood
pieces were weighed to find the mass of the raw wood. This mass came out to be 175 grams,
about four grams less than the calculated mass. After constructing the beam by gluing the sections
together in an I beam style, and the addition of stabilizers at both ends of the beam, the total
mass came out to be 185 grams. Upon testing the beam by applying 350 pounds of force in a
center loaded, simply supported style, the beam deflected 0.147 inches, which was within the
constraints of the deflection being greater than 0.05 inches and less than 0.235 inches. Although
the beam passed the test, the results achieved are not exactly what was predicted by Team 1s
calculations. The raw weight of the basswood used to construct the beam measure about four
grams less than what was calculated by Team 1. This shows that the density of the wood is not as
high as assumed, and therefore led to the conclusion that the wood used was not as strong as
indicated by the calculations. Upon testing, this assumption was further confirmed by the beam
deflecting more than predicted. However, the beam still passed well within constraints due to
Team 1 designing it to be able to pass with a safety factor of two. Because the beam was built
following the assumptions that the density was 28 lbm/ft3 and that the modules of elasticity was
1.46 x 106 psi, it could have failed testing if the safety factor had not been included in the original
design.
For the beam built by Team 1, the I beam style was used. This is done by gluing three sections
of wood into an I shape, as shown in Figure 6 above. Other options for the construction of the
beam was the H beam style and the hollow box beam style. The I was chosen due to costing
less and weighing less than a hollow box beam, while also having about the same defection
characteristics. The H beam was never considered due to being much weaker than the other two
options. Other options included choosing which beam to design out of the ones proposed by each
member of Team 1. The beam that was chosen was not completely based off of the decision
matrix, but instead off of good engineering judgement. Knowing that a beam built with a narrow
web would most likely fail under real testing conditions (even though it passes on paper), the
beam chosen by Team 1 was the one with the thickest web and flanges. This greatly increased
stability, and is what most likely allowed Team 1 to be successful in the beam testing. Because of
the results achieved, it is shown that the beam built by Team 1 easily passed the requirements set
upon its design. This demonstrates that Team 1 understands the process behind designing and
producing a simple beam to meet specific weight and deflection requirements. Since the beam
passed testing, it automatically received a grade of 80, but due to its efficiency ratio, 10 bonus
points was achieved. Team 1 realized that if the beam weighed 2 grams less, the beam would have
passed with a score of 100 due to a better efficiency ratio. For future classes, it is recommended
that an I beam is used. This is because they (I beam) can be designed to have nearly the same
deflection as a sturdier box beam but as a much lower weight and cost, which contributes to a
greater efficiency ratio. However, in designing an I beam, it is highly recommended that the
thickest flanges and web is used for max stability, as was demonstrated in Team 1s beam.
Conclusion and Recommendations
Team 1 was given the task of analyzing and designing a beam to support a load with a minimum
and maximum amount of deflection. Task definition to completion of assembly took two weeks
time to complete, with the initial stages of the project demanding the most thought and time.
Starting with a project plan, each member was required to develop individual designs, which then
were taken into consideration for final team design. Team 1 decided upon an I beam design,
which was then assembled six days prior to testing. During testing, the beam handled the
specified load well within the maximum allowable deflection. The beam was successful for a few
reasons, as a significant amount of time was spent in analyzing various I beam configurations
18
until a quality balance was found between the determining factors. The benefit of the addition of
torsional end supports, with regards to aiding in the beams passing success or if they strictly just
added weight, remains unknown. Speculation has been drawn that they merely added weight to
the beam, and that the beam could have handled the center loaded weight regardless. However,
there is no mathematical or scientific evidence in support of either side. The recommendations
for future applications of beam design is to utilize the I-beam design with significant work to be
placed in further engineering analysis. It is also recommended to use the strongest (thickest)
materials possible that allows the cost to be within the constraints.
19
References
1201 Faculty, "Beam Theory" (Pre-class readings, ENGR 1201 Moodle Site, UNC Charlotte,
Charlotte, NC, accessed November 22, 2015).
1201 Faculty, The Design Process (Pre-class readings, ENGR 1201 Moodle Site, UNC
Charlotte, Charlotte, NC, accessed November 23, 2015).