Professional Documents
Culture Documents
SOLAR
COMPASS
April 2014
Quarterly update
on the Indian
solar market
Disclaimer
For further enquiries,
please contact:
info@bridgetoindia.com
BRIDGE TO INDIA Pvt. Ltd.
N-117, Panchsheel Park
New Delhi 110017
India
www.bridgetoindia.com
Glossary
AD Accelerated Depreciation
APPC Average Pooled Purchase Cost
CAPEX Capital Expenditure
CSP Concentrated Solar Power
DCR Domestic Content Requirement
EPC Engineering, Procurement and Construction
GBI Generation Based Incentive
IPP Independent Power Producer
LOI Letter of Intent
NSM Jawaharlal Nehru National Solar Mission
NTPC National Thermal Power Corporation
OPEX Operational expenditure
PPA Power Purchase Agreement
PV Photovoltaic
REC Renewable Energy Certificate
RPO Renewable Purchase Obligation
SECI Solar Energy Corporation of India
TANGEDCO Tamil Nadu Generation and Distribution Corporation
TNERC Tamil Nadu Electricity Regulatory Commission
VGF Viability Gap Funding
Executive Summary
a tepid start to 2014
The Indian solar market continues to rely heavily on policy driven projects
to meet capacity targets. Distributed generation market, constituting more
than 50% of total solar capacity in most countries around the world, has not
yet taken off in India primarily because of complex/ unviable open access
regulations, resistance from utilities and direct/indirect subsidies provided to
conventional power supply. Policy initiatives are (slowly) moving in the right
direction but to turn solar power into a true game changer, we need an urgent
overhaul of policy framework and transparent pricing of grid power.
Project Allocations
482 MW of PPAs
have been signed across
state policies and 750 MW
under the NSM in the
last quarter
The highlight of the last quarter (January 2014 March 2014) was allocation
of solar PV projects under batch one, phase two of National Solar Mission
(NSM). ACME, Azure Power and SunEdison emerged as the big winners with
100 MW each. Prominent players who missed out included Green Infra, Tata
Power, Mahindra Solar, Welspun (except for 5 MW), Renew Power and First
Solar amongst others. The bid levels were broadly as expected although quite
aggressive in our view. Our key takeaways and observations are as follows:
Domestic Content Requirement (DCR) has been a failure costing in
excess of M10 million/MW as local manufacturing has not gained anything
meaningful for the long-term. For the manufacturing sector to thrive,
we need investment in infrastructure, R&D, tax/labor reform and bigger
volumes.
Extremely competitive bidding means there will be too much pressure
on costs ie poor project quality. Although the Viability Gap Funding (VGF)
mechanism has been a relative success, a more performance focused
regime such as Generation Based Incentive (GBI) is far more favorable in
our view.
Considerable interest shown by foreign project developers and
Independent Power Producers (IPPs) is very welcome as it brings more
credibility to the market and hopefully, will result in much needed
international expertise in project execution and deliverability.
On the state policy front, 482 MW of new power purchase agreements
(PPAs) have been signed across four states in the last quarter - 42 MW in
Andhra Pradesh (against a target of 150 MW), 80 MW in Karnataka (after a
delay of six months), 110 MW in Uttar Pradesh (towards the tail end of the
preceding quarter) and 250 MW in Punjab. These projects are evenly split
between experienced and first time developers. A significant number of these
experienced players have in-house EPC capabilities, leaving lesser room for
pure-play EPC companies, which continue to struggle.
Another 300 MW of projects are expected to be allocated in UP after the
general elections in May. Madhya Pradesh expects to sign PPAs for 100 MW
solar PV projects in the ensuing quarter.
Capacity Addition
In the first quarter of 2014, India added just 89 MW of new capacity - the lowest
since Q3 2012. Out of this, 55 MW has come from three state level projects with
the balance 34 MW being primarily driven by captive or third party sale projects
relying on accelerated depreciation (AD) and Renewable Energy Certificate
(REC) incentives.
Rajasthan: 20 MW project by Essel Mining (commissioned on time)
Madhya Pradesh: 25 MW project by EDF backed ACME
Andhra Pradesh: 10 MW renewable purchase obligation (RPO) project
by NTPC
As the REC market has failed to take off (around 6% of RECs managed to find
buyers on the Indian Energy Exchange in the first quarter of 2014), project
developers have moved away from selling power to local utilities at APPC
(typically M2.50-3.00/ kWh, $0.04-0.05/kWh) to finding private consumers with
tariffs in the range of M6 9/ kWh ($0.1-0.15/kWh). As an example, a 6 MW
project has been set up by a textile company for captive use and SunEdison
has set up an 18 MW solar park in Tamil Nadu. We expect this market to grow
rapidly as election fever subsides (reducing political pressure to keep tariff
increases low) and grid parity is attained across more states.
Distributed Generation
The rooftop market is slowly gaining momentum1 with Delhi and Kerala
(following on from Andhra Pradesh, Tamil Nadu) announcing net metering
policies in the last quarter (Delhi policy is still in draft stage). Keralas plan
of setting up 10,000 off-grid rooftop solar power plants by December 2014
appears to be well on track with around 6,000 sites already commissioned2.
At the central level, SECI continues to provide capital subsidies for rooftop
projects - it has allocated 25 MW till date and aims for a further 50 MW during
the year.
The policy support to the rooftop segment needs to be much bolder, especially
considering its future potential. Based on a study carried out by BRIDGE TO
INDIA for Greenpeace, Delhi alone has a rooftop solar potential for 2 GW3.
---------1 BRIDGE TO INDIA, along with Prayas, is working on a report on grid-connectivity issues for
distributed generation projects. This report is likely to be released in April 2014.
2 BRIDGE TO INDIA blog on the Kerala rooftop scheme, http://bit.ly/OzhHoS
3 Read our report: Rooftop Revolution: Unleashing Delhis Solar Potential
BRIDGE TO INDIA, 2014
2 Trends
2.1 Module Prices
In the last quarter (January 2014 March 2014), module prices have increased
2-3% in India (c-Si, Chinese). This increase has been driven by a rise in global
demand (especially in China). This development follows a 7-9% increase in
module prices in the last year that was driven mostly by the depreciation in the
Indian rupee. Since the second quarter of 2013, prices for thin film modules
have remained constant in dollar terms but have risen in Indian rupee terms.
Figure 2.1: Chinese C-Si and thin film module prices over
the last four quarters4
Figure 2.2: PV central inverter prices over the last four quarters5
2.3 Tariffs
The only new additions in tariffs bid for were under the Madhya Pradesh state
policy and the NSM. The tariffs in the Madhya Pradesh policy, although on
the lower side, are higher compared to the Karnataka phase II bidding even
though Madhya Pradesh has a better irradiation compared to Karnataka. The
average VGF bid for in the NSM, if seen in terms of tariff increase, translates to
an additional M1.05/kWh ($0.018/kWh) and M2.05/kWh ($0.034/kWh) under the
open and DCR categories respectively6.
Figure 2.3: Average tariffs across state policies in the last four quarters7 8
10
Policy Outlook
Karnataka Phase I
Madhya Pradesh
Rajasthan
SECI phase I
Allocation date
Apr-12
May-12
Mar-13
Apr-13
Allocated capacity
60 MW
225 MW
75 MW
5.5 MW
Delayed projects
42 MW
25 MW
55 MW
~1 MW
Scheduled date of
commissioning
Oct-13
Jun-13
Mar-14
Apr-14
Expected
commissioning
date
Q2 and Q3 of 2014
Q2 of 2014
Q3 of 2014
Q3 of 2014
Remarks
Penalties to be levied
only in cases where
the developer is not
able to justify the time
extension
Only a 20 MW project by
ESSEL Mining has been
commissioned in time
While 1 MW
projects have been
commissioned,
3.5 MW are expected
to be commissioned by
April 2014
A 25 MW project by
Moserbaer is still
pending completion
A 25 MW project by MK
solar energy has been
cancelled
* All details are based on information received from state authorities or project developers.
11
Tamil Nadu
Andhra Pradesh
Madhya Pradesh
phase II
NSM
Allocation date
Jun 2013
Jun 2013
Feb 2014
Feb 2014
LOIs signed
708 MW
600 MW
100 MW
750 MW
PPAs signed as on
March 2014
180 MW
(138 MW in Q4 2013 and
42 MW in Q1 2014)
750 MW
PPAs expected to be
signed in the next
quarter
No clarity
100 MW
100 MW
Remarks
19 companies had
participated in the bid
Himgiri Energy
Ventures quoted
the lowest tariff of
M6.475/kWh ($0.11/
kWh), followed by
Today homes and
infrastructure M6.48/
kWh($0.11/kWh)
Renew Power managed
to secure a 30 MW
project at a tariff of
M6.97/kWh ($0.12/kWh)
Leading project
developers that did not
win any projects include
Azure, Acme, IL&FS,
Sunedison, Essel
infraprojects, Welspun
and Solairedirect
Prominent developers
which were allotted
projects include Acme
(100 MW), Welspun (5
MW), Azure (100 MW),
Sunedison (100 MW),
Solairedirect(20 MW),
IL&FS (40 MW)
More than half of the
projects chose their
location as Rajasthan
(~360 MW). Surprisingly
the second most
preferred location was
Madhya Pradesh ( ~200
MW) instead of Gujarat
(~50 MW)
The average bid under
the open category
was M10.1 million/
MW ($0.17 million/
MW) and DCR category
was M20.1 million /MW
($0.33 million/MW)
TATA power rejected a
partial allocation under
the DCR category (had
bid for 40 MW but was
offered part allocation
of 25 MW)
12
Punjab
Uttar Pradesh
Karnataka
Andhra Pradesh
Allocation date
Jun-13
Jun-13
Jul-13
Jun-13
PPAs signed as
on March 2014
250 MW
110 MW
80 MW
180 MW
Expected date
of procurement
for projects
Q4 of 2014 and
Q1 of 2015
Q4 of 2014 and
Q1 of 2015
Q1 of 2015
Q4 of 2014 and
Q1 of 2015
Expected date
of procurement
for projects
April September
2014
April September
2014
Ongoing
Remarks
42 MW PPAs signed
in the current quarter.
Out of the 180 MW, a
70 MW project is by a
JV between Premier
Solar and New
Generation Power
(USA)
13
SECI phase II
Allocation date
Jul-13
Dec-13
PPAs signed as
on March 2014
11.3 MW
8.75 MW
Q3 and Q4 of 2014
Expected date
of procurement
for projects
Q1 of 2015
Ongoing
Expected date
of procurement
for projects
Remarks
Uttar Pradesh
Karnataka
phase III
SECI phase IV
Haryana
Uttarakhand
Expected allocation
date
Q3 of 2014
Q3 of 2014
2014
2014
2014
Expected allocation
capacity
300 MW
50 MW
50 MW
50 MW
50 MW
Expected PPA
signing date
Q1 of 2015
Q1 of 2015
Not known
Not known
Not known
Expected
commissioning date
Q2 of 2016
Q2 and Q3 of 2016
Not known
Not known
Not known
14
Projects Outlook
15
Despite our best efforts, the solar PV landscape in India is usually difficult
to forecast due to policy uncertainties. In the figure, we have depicted our
quarterly projections over various editions benchmarked against actual
capacity additions. In certain quarters our projections have been close, while
on certain occasions, we have been wrong with significant margins. The
rationale behind the misjudged predictions has been mentioned in the table.
Having learnt from our misjudgments in the past, our endeavor is to do better
in the future.
Historically, we have found that projects for parity with or without
REC benefits tend to exceed our expectations, projects under the NSM are
usually on target and projects under various state policies are inevitably
behind schedule even though we have been fairly pessimistic about them to
begin with.
16
Policy
RPO projects
State Policies
17
Acme, Azure Power and SunEdison get the biggest share of the NSM
How will financing of NSM projects work?
Indias subsidy scheme for de-centralized solar to stay subdued in 2014
as well
National Solar Mission to miss capacity targets for the year by
a significant margin
Market analysis
Thought leadership
10,000
Average dedicated
readership for
each published
report
Our Reports
The India Solar
Compass
(quarterly)
India Solar
Decision Briefs
(bi-annual)
India Solar
Policy Briefs
More than
12,000
printed copies
of publications
distributed at
events
IndiaSolarHomes.com
Weekly Newsletter
contact@bridgetoindia.com