0 HISE RISE TOWER


Start: Mon 3/16/15ID: 1
Finish: Fri 5/22/15 Dur: 50 days
Comp: 0%

1.1 MOBILIZATION ON SITE


Start: Mon 3/16/15ID: 2
Finish: Fri 3/20/15 Dur: 5 days
Comp: 0%

Page 1

Page 2

1.2 SITE PREPARATION


Start: Mon 3/23/15ID: 8
Finish: Tue 3/31/15Dur: 7 days
Comp: 0%

1.2.1 Clear and grub site


Start: Mon 3/23/15ID: 9
Finish: Mon 3/23/15Dur: 1 day
Res:

1.3 FOUNDATION
Start: Wed 4/1/15 ID: 16
Finish: Mon 4/20/15Dur: 14 days
Comp: 0%

1.3.1 Excavate foundations


Start: Wed 4/1/15 ID: 17
Finish: Wed 4/1/15 Dur: 1 day
Res:

1.4 BASEMENT
Start: Tue 4/21/15 ID: 31
Finish: Thu 4/23/15Dur: 3 days
Comp: 0%

Page 3

Page 4

1.2.2 Stone site access and temporary parking area


Start: Tue 3/24/15 ID: 10
Finish: Tue 3/24/15Dur: 1 day
Res:

1.2.3 Rough grade site (cut and fill)


Start: Wed 3/25/15ID: 11
Finish: Wed 3/25/15Dur: 1 day
Res:

1.3.2 Excavate elevator pit


Start: Thu 4/2/15 ID: 18
Finish: Thu 4/2/15 Dur: 1 day
Res:

1.3.3 Form column piers and spread foundations


Start: Fri 4/3/15 ID: 19
Finish: Fri 4/3/15 Dur: 1 day
Res:

1.4.1 column
Start: Tue 4/21/15 ID: 32
Finish: Tue 4/21/15Dur: 1 day
Res:

1.4.2 shear wall


Start: Wed 4/22/15ID: 33
Finish: Wed 4/22/15Dur: 1 day
Res:

1.5 FLOORS
Start: Fri 4/24/15 ID: 35
Finish: Mon 5/4/15 Dur: 7 days
Comp: 0%

1.5.1 STRUCTURE- form and pour concrete floors and roof and strip form
Start: Fri 4/24/15 ID: 36
Finish: Fri 4/24/15 Dur: 1 day
Res:

1.6 ROOFING
Start: Wed 5/6/15 ID: 43
Finish: Tue 5/12/15Dur: 5 days
Comp: 0%

Page 5

Page 6

1.2.4 Install storm drainage


Start: Thu 3/26/15 ID: 12
Finish: Thu 3/26/15Dur: 1 day
Res:

1.2.5 Install exterior fire line and building fire riser


Start: Fri 3/27/15 ID: 13
Finish: Fri 3/27/15 Dur: 1 day
Res:

1.3.4 Rough-in electric and plumbing in elevator


Start: Mon 4/6/15 ID: 20
Finish: Mon 4/6/15 Dur: 1 day
Res:

1.3.5 Form elevator pit wallS


Start: Tue 4/7/15 ID: 21
Finish: Tue 4/7/15 Dur: 1 day
Res:

1.4.3 slab
Start: Thu 4/23/15 ID: 34
Finish: Thu 4/23/15Dur: 1 day
Res:

1.5.2 ELEVATOR
Start: Mon 4/27/15ID: 37
Finish: Mon 4/27/15Dur: 1 day
Res:

1.5.3 CEILING
Start: Tue 4/28/15 ID: 38
Finish: Tue 4/28/15Dur: 1 day
Res:

1.6.1 Install flashing at parapet walls


Start: Wed 5/6/15 ID: 44
Finish: Wed 5/6/15 Dur: 1 day
Res:

1.6.2 Pour lightweight concrete roof fill


Start: Thu 5/7/15 ID: 45
Finish: Thu 5/7/15 Dur: 1 day
Res:

1.7 LANDSCAPE
Start: Wed 5/13/15ID: 49
Finish: Fri 5/15/15 Dur: 3 days
Comp: 0%

1.7.1 Pour concrete driveway and sidewalks


Start: Wed 5/13/15ID: 50
Finish: Wed 5/13/15Dur: 1 day
Res:
Page 7

1.8 ROADS
Start: Mon 5/18/15ID: 53
Finish: Fri 5/22/15 Dur: 5 days
Res:

Page 8

1.2.6 Perform final site grading


Start: Mon 3/30/15ID: 14
Finish: Mon 3/30/15Dur: 1 day
Res:

1.2.7 Erect building batter boards and layout building


Start: Tue 3/31/15 ID: 15
Finish: Tue 3/31/15Dur: 1 day
Res:

1.3.6 Set reinforcing and anchor bolts


Start: Wed 4/8/15 ID: 22
Finish: Wed 4/8/15 Dur: 1 day
Res:

1.3.7 Pour column piers and foundations


Start: Thu 4/9/15 ID: 23
Finish: Thu 4/9/15 Dur: 1 day
Res:

1.3.8 Pour concrete elevator walls


Start: Fri 4/10/15 ID: 24
Finish: Fri 4/10/15 Dur: 1 day
Res:

1.5.4 TOILET
Start: Wed 4/29/15ID: 39
Finish: Wed 4/29/15Dur: 1 day
Res:

1.5.5 MECH. ROOM


Start: Thu 4/30/15 ID: 40
Finish: Thu 4/30/15Dur: 1 day
Res:

1.5.6 ELECT. ROOM


Start: Fri 5/1/15 ID: 41
Finish: Fri 5/1/15 Dur: 1 day
Res:

1.6.3 Install seamless roofing material


Start: Fri 5/8/15 ID: 46
Finish: Fri 5/8/15 Dur: 1 day
Res:

1.6.4 Spread stone ballast on seamless roof


Start: Mon 5/11/15ID: 47
Finish: Mon 5/11/15Dur: 1 day
Res:

1.6.5 Set rooftop equipment


Start: Tue 5/12/15 ID: 48
Finish: Tue 5/12/15Dur: 1 day
Res:

1.7.2 Install boundary wall perimeter


Start: Thu 5/14/15 ID: 51
Finish: Thu 5/14/15Dur: 1 day
Res:

1.7.3 Sod and complete plantings


Start: Fri 5/15/15 ID: 52
Finish: Fri 5/15/15 Dur: 1 day
Res:
Page 9

Page 10

1.3.9 Cure elevator wall concrete


Start: Mon 4/13/15ID: 25
Finish: Mon 4/13/15Dur: 1 day
Res:

1.3.10 Cure piers and foundations


Start: Tue 4/14/15 ID: 26
Finish: Tue 4/14/15Dur: 1 day
Res:

1.5.7 EXTERIOR
Start: Mon 5/4/15 ID: 42
Finish: Mon 5/4/15 Dur: 1 day
Res:

Page 11

1.3.11 Strip wall forms


Start: Wed 4/15/15ID: 27
Finish: Wed 4/15/15Dur: 1 day
Res:

Page 12

1.3.11 Strip column piers and foundation forms


Start: Thu 4/16/15 ID: 28
Finish: Thu 4/16/15Dur: 1 day
Res:

1.3.12 Install pneumatic tube in elevator pit


Start: Fri 4/17/15 ID: 29
Finish: Fri 4/17/15 Dur: 1 day
Res:

Page 13

1.3.13 Prepare and pour concrete floor in ele


Start: Mon 4/20/15ID: 30
Finish: Mon 4/20/15Dur: 1 day
Res:

Page 14

Page 15

Page 16

Project: WBSchart1
Date: Sat 3/21/15

Critical

Summary

Critical External

Noncritical

Critical Inserted

External

Critical Milestone

Inserted

Project Summary

Milestone

Critical Marked

Highlighted Critical

Critical Summary

Marked

Highlighted Noncritical