FUTURE BOONE COUNTY ROAD CONSTRUCTION PROJECTS - STATUS REPORT

Road/Name

Design

Right-of-Way

Utilities

Construction

Notes

1) I-75/KY 536 Interchange

Underway

$ 8,930,000 - 2016

$5,200,000 - 2017

$19,740,000 - 2018
$ 2,340,000 - 2021

R-O-W
Changed to 2016

2) Add Auxiliary Lanes on I-75


from Mt Zion Road to U.S. 42

Underway

$ 4,300,000 - 2016

$ 800,000 - 2017

$17,600,000 - 2018

R-O-W
Changed to 2016

3) I-75/KY 338 Interchange

Underway

$20,950,000 - 2016

$6,240,000 - 2017

$31,710,000 - 2018
$24,340,000 - 2021

R-O-W
Changed to 2016

4) KY 536 (Mt. Zion Road)


(From I-75 to Old Union Road)

Underway

Underway

$4,060,000 - 2015

$28,730,000 - 2017

No Construction $
in 2-Year Budget

5) Access Road from KY 237


to Lim aburg Road Opposite
Gateway Boulevard

Underway

Airport Owned

County Project
Bid in 2015

6) Construct Lanes to U.S. 42


& Hopeful Church Road

Underway

$ 1,750,000 - 2016

$ 150,000 - 2016

$ 2,500,000 - 2016

Construct Left Turning Lanes

7) Southbound Entrance Ram p


off I-75/Mall Road Interchange

Underway

250,000 - 2015

50,000 - 2015

$ 1,500,000 - 2015

Build Ram p to Connect to


an Existing Entrance Ram p

8) Hicks Pike, Rice Pike &


U.S. 42 Intersection

Underway

750,000 - 2015

$ 600,000 - 2015

$ 2,750,000 - 2016

Im prove Safety and Grade


of Intersection

9) Cam p Ernst Road from


Rogers Lane to KY 18

Com pleted

Com pleted

Underway

Final Construction in 2015

10) Pleasant Valley Road from


Valley View Drive to Rogers Ln.

Underway

$10,300,000 - 2015

$1,120,000 - 2016

$20,560,000 - 2017

R-O-W Start Soon


No Construction $
in 2-Year Budget

11) Add Lanes to W orldwide


Boulevard & KY 237

Underway

$ 1,000,000 - 2015

$ 500,000 - 2016

$ 3,000,000 - 2017

Add Left Turn Lanes on


W orldwide Blvd. & Thru
Lanes on KY 237

12) Extension of W endell Ford


Boulevard to Aero Parkway

Underway

N/A

$ 2,576,717 - 2015

Airport Road Project

N/A

Com pleted

N/A

224,343 - 2015

Road/Name

Design

13) Reconstruct Intersection


of Longbranch Road & Cam p
Ernst Road

Underway

50,000 - 2015

$ 112,000 - 2015

14) Geom etric Reconstruction


of Frogtown Road Near
Triple Crown Boulevard

$120,000 - 2016

200,000 - 2017

$ 120,000 - 2017

$ 1,200,000 - 2018

Add Left Turn Lane on


Frogtown & Im prove
Site Distance

15) Two Lane Extension of


Veterans W ay Between KY 18
& KY 237

Underway

Underway

N/A

$ 1,640,000 - 2015

County Project

16) Replace W oolper Creek


Bridge

Underway

Underway

Underway

$ 3,250,000 - 2015

17) Total Replacem ent of


Richardson Road Bridge

$500,000 - 2021

$ 2,000,000 - 2021

$ 500,000 - 2021

$ 3,000,000 - 2021

Project Years Away

18) Add Sidewalk & Realign


Intersection of Idlewild Rd.
and Jefferson Street

Underway

Underway

Part of Construction

150,000 - 2015

May Need Additional Funds

19) Add Sidewalk on South


Side of Frogtown Rd. from
U.S. 42 to W ar Adm iral Dr.

Underway

17,000

N/A

262,333 - 2016

County Project Using


TAP Funds

KPC/vlm
2/20/15

Right-of-Way

Utilities

Construction
524,640 - 2016

Notes
Includes W idening of
Longbranch Road