TASK

EARLIEST START DUE DATE


1.Determine social needs
30-Sep-14
28-Jan-15
2.Evaluate current curriculum
30-Sep-14
28-Jan-15
3.Obtain potential employee views
30-Sep-14
10-Mar-15
4.Obtain opinions from experts in the field
30-Sep-14
10-Mar-15
5.Obtain learner background
Jul-14
10-Mar-15
6.Research technological influences and developments
Sep-14 1st May 2015
7.Identify trends in health care and education facilities
Sep-14 1st May 2015
8.Formulate outcomes
Nov-14 1st May 2015
9.Formulate teaching strategies
Nov-14 1st May 2015
10.Formulate assessment methods
Nov-14 1st May 2015
11.Compile formal document
03-May-15 15-May-15
12.Print & Submit 1st draft to faculty
20-May 30-May-15
13.Evaluation(internal)
1st June 2015
14.Apply changes
12-Jul-15
15.Print and re-submit for approval(internal)
20-Jul-15
16.Submit to statutory bodies
30-Jul-15
17.Review comments from statutory body
03-Aug-15
18.Apply changes
28-Aug-15
25-Sep-15
19.Submission of final document
27-Sep-15
30-Sep-15

TYPE
sequential
parallel
parallel
parallel
sequential
parallel
sequential
sequential
sequential
sequential
sequential
sequential
sequential
sequential
sequential
sequential
sequential
sequential
sequential

DEPENDENT ON
2
na
na
na
2
na
6
2
8
9
all
11
12
13
14
15
16
17
18