Professional Documents
Culture Documents
Department
Responsibility/Role
File Name 27636992.doc
Revision
Document Generation Date 15/01/2010 09:51:00
Date Modified 1/15/2010 09:51:00 AM
Last Changed by
Status
Concept
In this topic, you will perform batch simulations.
Additional Information
Procedure
Step Action
1. Begin by navigating to the Batch Replan page.
Step Action
2. Use the Organizations page to select an instance:organization.
Step Action
3. Find organization TST:M1 TST:Seattle Manufacturing.
Step Action
4. Click the TST:M1 TST:Seattle Manufacturing list item.
Step Action
5. Click the OK button.
or Press [Alt+O].
Step Action
6. Click the Plans tab.
Step Action
7. Use the Navigator page, Plans tab to view and act on results from the
material/capacity plan.
Step Action
8. Click the Plans tree item.
Step Action
9. Click the Const-Date (Constrained Plan - Demand Due Date) tree item.
Step Action
10. Click the Plan menu.
Step Action
11. Click the Batch Replan menu.
Step Action
12. Use the Note page to view the concurrent request ID of the batch replan.
Step Action
13. Click the OK button.
or Press [Alt+O].
Step Action
14. You have successfully performed batch simulations.
End of Procedure.