Computerized Project Management


Primavera 5.0
Case Study

Dr. Attia Gomaa


Industrial Engineering Professor & Consultant
Engineering Services - American University in Cairo (AUC)

2009

PM 5.0
Primavera 5.0 - Overview
Content:
• Computerized Project Management Overview
• How to install Primavera 5.0?
• Main Screens
• Data Gathering
• Data Entering
• Project Planning (ٍSchedule, Bar chart & PERT)
• Layouts & Reporting
• Case Study (Real Project)
• Updating
• Advanced options

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 2


Computerized Project Management
Overview

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 3


Computerized Project Management
Overview
Project Planning Packages:
Single project
• Primavera Project Planner - P3- 1996

• Primavera P5.0 – 2005  XP windows


Multi-Project
• Primavera P6.0 – 2006  Vista window
Enterprise Management
• Primavera P6.1 - 2007
Integration Management
Undo •Primavera P6.2 - 2008
Standard Information

Project Information Systems:


• Microsoft Project – MSP
Single project
• Time Line6 - TL6
• Expedition

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 4


Primavera P5.0
Enterprise Management = Multi-Project
Enterprise Level:
1) Organizational Breakdown Structure (OBS)  Managers
‫الهيكل التنظيمى للمؤسسة‬
2) Enterprise Project Structure (EPS)  Classification
)‫هيكل مشروعات المؤسسة (النوعية‬

3) Coding System  Standard IDs


4) Calendars  Working / Non-working days/hours
5) Resource List  Material, Labor, Non-labor

Project Level:
1) Work Breakdown Structure (WBS) – “Main Items”
2) Activity List (main activities … to … Details activities)
3) Resource Allocation
4) Planning  Analysis  Smoothing, leveling, crushing
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 5
Project Level: Systematic
Approach

Project
ProjectOverview
Overview

WBS Master Plan


WBS(main
(main items)
items) for WBS

Main
MainActivities
Activities Top

Action Plan for


Detailed
DetailedActivities
Activities each WP (design,
resource, cost,..)

Resource
ResourceAllocation
Allocation Middle

Detailed
Planning
PlanningAnalysis
Analysis Plans Operational

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 6


Project Planning Module:

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 7


Project Resources: (7 M)
• Manpower
• Machine Critical Resources Parameters:
• Materials • Limited (Available < Required)
• Method • Safety effect
• Management
• Cost effect
• Market
• Money

P3 P5
• Labor •Labor Time unit
• Equipment & Tools •Non-Labor Time unit

• Material •Material Physical unit

• Subcontractors

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 8


Work Breakdown Structure (WBS)- Main items:
IT Center
A000000

A100000 A200000 A300000


Lab #1 Lab #2 Lab #3

A210000 A220000 A230000


Design Procurement Construction

Activity ID:
For example:

1 2 3 4 5
Area Dept. Work type
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 9
WBS (Main Item) List

Work Description Responsibility


Phase Package
I- Design A110000
A210000
A310000
II- Procurement A120000
A220000
A320000
III- Construction A130000
A230000
A330000

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 10


For example
Master Plan (One Page Management)
Work Duration Budget Critical
Phase Package (week) ($1000) Resources
I- Design A110000 4 20 H/w Eng.:
A210000 5 25 Required: 10
A310000 3 15 Available: 6
II- Procurement A120000 2 200 xxx Mat.
A220000 3 300 (insufficient)
A320000 2 150 - 20%
III- Construction A130000 12 24 Welding groups:
A230000 15 32 Required: 8
A330000 11 22 Available: 5

Total Project A00000 24 800 H/w Eng.


Piping Mat.
Welding groups
Phase
I
II

III

1 -- -- -- -- --
20 24 Week
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 11
Main Outputs:
1) Network – Logic diagram – Flow chart – Sequence chart
PERT - Computerized

A B C

E
D

Activity Time
2) Bar Chart A

Time Chart B

GANTT Chart C

D
(Basic plan) E

1 2 3 4 5 6 7 Time

3) Resource Analysis (smoothing, leveling, crushing)


(Applicable plan ---- Available resource <= Required resources)
4) Target Plan (SMART) – Bar chart & Critcal Res. Plan& Budget plan
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 12
This is a simplified PERT chart for creating a small Web site.

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 13


How to install Primavera 5.0?

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 14


How to install Primavera 5.0?

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 15


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 16
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 17
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 18
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 19
Desktop Short Cut

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 20


Log in
1. Start Primavera by clicking the Primavera icon on the desktop or
clicking Start, Programs, Primavera, Project Management.

2. Type a Login Name <admin> and a Password <admin>, and then


click OK.

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 21


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 22
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 23
Main Screen Overview
1) Title bar
2) Menu bar 4) Navigation bar

3) Directory bar
5) Status bar

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 24


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 25
Primavera 5.0 Overview

Oracle Database

Relationship between Primavera components.


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 26
Data Gathering

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 27


Main Information:
I- Enterprise Data: “Long term”
• Organizational Breakdown Structure (OBS)
• Enterprise Breakdown Structure (EBS)
• Calendar List (Working & Non-working days)
• Activity Codes
• Cost Accounts (Cost Centers)
• Resource roles
• Resource List (Labor, Non-labor, Materials)

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 28


1) Organizational Breakdown Structure (OBS)

XYZ Manager (Top Manager)


Cairo Manager: Top

- IT Manager
- MIS Manager
- Network Manager Middle

Alex Manager:
- IT Manager
Operational
- MIS Manager

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 29


2) Enterprise Project Structure (EPS)
ID Name Responsible Manager
ITP IT Projects IT Manager
- Hard Ware Projects
- Soft Ware Projects
- Installation Projects
- Maintenance Projects

MIS MIS Projects IT Manager

NWP Network Projects IT Manager

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 30


3) Calendars (Working & Nonworking)

Global: Company wide


Standard 5 days

Add Holidays
10 Jan 2009

Resource: --
Supplier, Vendor, Consultant, third party

Project: ---
Customer calendar
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 31
4) Activity Codes:
Global:
Code Value Description
HW Hard Ware Activities
SW Soft Ware Activities
SR Server Activities
GA General Activates
EPS:
-----
Project:
-----

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 32


5) Cost Accounts (Cost Centers)
“Budget work break structure”

ID Name
IT IT Cost Account
ITD IT Design
ITH IT H/w
ITS IT S/w

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 33


6) Resource Role: “Policy”

Role ID: ITC Role Name: IT Crew

Description:
‫هى الدور الوظيفى للمورد والمهارات‬
• Engineer
‫المطلوبة لهذا الدور وتستخدم عند عمل‬
• Technician
‫التخطيط المبدئى للمشروع‬
• Helper
• Tool Box
Rate type: Price / unit
• Price / unit $ 100 /hour
• Price / unit 2 $ 120 /hour
• Price / unit 3
•Price / unit 4
•Price / unit 5

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 34


7) Resource List
Resource type: Labor Non-Labor Material

Global:
Resource Resource Resource Unit/day Maximum Role
ID name type units/day
HWE H/w Eng. Labor 8 Hour 8 ITC

SWE S/w Eng. Labor 8 Hour 8 ITC

MAT Total Material $1000 - -


Materials

Project:
----
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 35
Enterprise Information Systematic
Approach

Project
Project
Master Plan for WBS
(Target plan)
WBS
WBS(main
(mainitems)
items)
(Monthly to Annual)
Milestones
Milestones Top

Main
MainActivities
Activities
Action Plan for each WP
(design, resource, cost,..)
(Weekly to Monthly) Main
Main Steps
Steps Middle

Detailed Plans
(Daily to Weekly)
Details
Details Operational

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 36


Main Information:

II- Project Data:


1. Project name & description
2. Work Breakdown Structure (WBS)
3. Activity list (ID, description, duration)
4. Activity relations (Predecessor, SS, SF, FS, FF)
5. Resource Assignments (allocation)
6. Resource Availability (Maximum limits)
7. Work Products & Documents
8. Notebook

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 37


1) Project name & description
- EPS: IT Projects
- Project ID: AUCIT
- Project Name: AUC IT Center
- Planned Start: 01 / 01 / 09
- Must finish by: ---- (Max. 2 Month)

- Responsible Manager (OBS): IT Manager


- Rate type: Price / unit
- Project Architect: No

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 38


2) Work Breakdown Structure (WBS)

ID Name
- SR Server room

- L1 Lab #1

- L2 Lab #2

- L3 Lab #3

- GA General Activities

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 39


3) Activity List Original duration
- SR Server room (Day)
- SRHW Server H/w activities 2
- SRSW Server S/w activities 2

- L1 Lab #1
- L1HW Lab #1 H/w activities 10
- L1SW Lab #1 S/w activities 6

- L2 Lab #2
- L2HW Lab #2 H/w activities 10
- L2SW Lab #2 S/w activities 6

- L3 Lab #3
- L3HW Lab #3 H/w activities 10
- L3SW Lab #3 S/w activities 6

- GA General Activities
- GASR Survey activities 2
- GADS Design activities 5
- GAMB Mob.& Preparation 1
- GAST Setup & testing activities 2
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 40
4) Activity Relations Original duration Predecessors
- SR Server room (Day)
- SRHW Server H/w activities 2 GAMB FS=0
- SRSW Server S/w activities 2 SRHW FS=0

- L1 Lab #1
- L1HW Lab #1 H/w activities 10 SRSW SS1-FF1
- L1SW Lab #1 S/w activities 6 L1HW SS3-FF2

- L2 Lab #2
- L2HW Lab #2 H/w activities 10 SRSW SS1-FF1
- L2SW Lab #2 S/w activities 6 L2HW SS3-FF2

- L3 Lab #3
- L3HW Lab #3 H/w activities 10 SRSW SS1-FF1
- L3SW Lab #3 S/w activities 6 L3HW SS3-FF2

- GA General Activities
- GASR Survey activities 2 - -
- GADS Design activities 5 GASR FS=0
- GAMB Mob.& Preparation 1 GADS FS=0
- GAST Setup & testing activities 2 L1SW,2SW,3SW FS=0
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 41
5) Resource allocation HWE /day SWE /day Mat
- SR Server room
- SRHW Server H/w activities 2 -
- SRSW Server S/w activities - 2

- L1 Lab #1
- L1HW Lab #1 H/w activities 3 -
- L1SW Lab #1 S/w activities - 4

- L2 Lab #2
- L2HW Lab #2 H/w activities 3 -
- L2SW Lab #2 S/w activities - 4

- L3 Lab #3
- L3HW Lab #3 H/w activities 3 -
- L3SW Lab #3 S/w activities - 4

- GA General Activities
- GASR Survey activities 1 1
- GADS Design activities 2 2
- GAMB Mob.& Preparation 1 1
- GAST Setup & testing activities 1 1
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 42
6) Resource Availability
Resource Resource Resource Unit/day Maximum Required
ID name type units/day units/day
HWE H/w Eng. Labor 8 Hour 8*4=32 ?

SWE S/w Eng. Labor 8 Hour 8*4=32 ?

Duration (day) ? ?

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 43


7) Work Products & Documents

GADS Design activities:


• Drawings Approved
• Detailed Design Specification In Progress

GAMB Mob.& Preparation


• General Documents In Progress

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 44


8) Notebook

GAMB Mob.& Preparation

• Contractor will send the equipment & tools


specification for review and approval before it
is shipped.

‫مفكرة النشاط عبارة عن المالحظات الخاصة بالنشاط أو التعليقات أو رسم‬


‫توضيحى أو صورة أو ملف فيديو حيث يمكن إضافة جميع هذه البيانات من خالل‬
. ‫مفكرة النشاط‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 45


Updating ‫مشروع‬++‫يانات لا‬++‫حديث ب‬++‫ت‬
ID Orig. Dur. Actual Start Actual Finish Remaining Dur.

Lab #1

L1HW 10 18-Jan-09 30-Jan-09 0

L1SW 6 26-Jan-09 5

General Activities:

GASR 2 03-Jan-09 04-Jan-09 0

GADS 5 05-Jan-09 10-Jan-09 0

GAMB 1 12-Jan-09 12-Jan-09 0

Server Room:

SRHW 2 15-Jan-09 17-Jan-09 0

SRSW 2 16-Jan-09 18-Jan-09 0


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 46
Main Screens & Data Entering

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 47


Gantt Chart ‫ ثم‬Show in Bottom ‫ ثم نختار‬Layout ‫لتقسيم الشاشة نضغط‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 48


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 49
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 50
Resource/Cost Usage Profile ‫تكلفة‬++‫ لا‬/ ‫موارد‬++‫منحنى لا‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 51


Resource/Cost Usage Spreadsheet ‫تكلفة‬++‫ لا‬/ ‫موارد‬++‫دول لا‬+‫ج‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 52


Activity Usage Profile ‫ألنشطة‬+‫تكلفة ل‬++‫ لا‬/ ‫موارد‬++‫منحنى لا‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 53


Activity Usage Spreadsheet ‫ألنشطة‬+‫موارد ل‬++‫دول لا‬+‫ج‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 54


Resource leveling ‫موارد‬++‫موازنة لا‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 55


‫‪Preserve Scheduled Early and Late Dates‬‬
‫هذا االختيار يحفظ التواريخ المبكرة والمتأخرة المحسوبة من الشبكة قبل عمل الموازنة‬
‫ولعمل مقارنة بين تواريخ األنشطة قبل وبعد ال ‪ Leveling‬من شاشة األنشطة‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪56‬‬


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 57
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 58
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 59
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 60
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 61
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 62
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 63
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 64
1) Organizational Breakdown Structure (OBS)

XYZ Manager (Top Manager)


Cairo Manager: Top

- IT Manager
- MIS Manager
- Network Manager Middle

Alex Manager:
- IT Manager
Operational
- MIS Manager

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 65


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 66
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 67
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 68
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 69
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 70
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 71
2) Enterprise Project Structure (EPS)
IT Projects
- Hard Ware Projects
- Soft Ware Projects
- Installation Projects
- Maintenance Projects

MIS Manager
-
-

Network Manager

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 72


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 73
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 74
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 75
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 76
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 77
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 78
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 79
3) Calendars (Working & Nonworking)

Global: Company wide


Standard 5 days

Resource: --
Supplier, Vendor, Consultant, third party

Project: ---
Customer calendar
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 80
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 81
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 82
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 83
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 84
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 85
• Cost Accounts (Cost Centers)

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 86


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 87
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 88
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 89
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 90
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 91
4) Activity Codes:
Global:
Code Value Description
HW Hard Ware Activities
SW Soft Ware Activities
SR Server Activities
GA General Activates
EPS:
-----
Project:
-----

1 2 3 4
WBS Main Activities
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 92
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 93
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 94
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 95
Resources (Labor, Non-labor, Materials)

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 96


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 97
5) Cost Accounts (Cost Centers)
“Budget work break structure”

IT IT Cost Account
ITD IT Design
ITH IT H/w
ITS IT S/w

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 98


6) Resource Role: “Policy”

Role ID: ITC Role Name: IT Crew

Description:
‫هى الدور الوظيفى للمورد والمهارات‬
• Engineer
‫المطلوبة لهذا الدور وتستخدم عند عمل‬
• Technician
‫التخطيط المبدئى للمشروع‬
• Helper
• Tool Box
Rate type: Price / unit
• Price / unit $ 100 /hour
• Price / unit 2 $ 120 /hour
• Price / unit 3
•Price / unit 4
•Price / unit 5

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 99


7) Resource List
Resource type: Labor Non-Labor Material

Global:
Resource Resource Resource Unit/day Maximum Role
ID name type units/day
HWE H/w Eng. Labor 8 Hour 8 ITC

SWE S/w Eng. Labor 8 Hour 8 ITC

Project:
----
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 100
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 101
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 102
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 103
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 104
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 105
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 106
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 107
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 108
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 109
Enterprise Information Systematic
Approach

Project
Project
Master Plan for WBS
(Target plan)
WBS
WBS(main
(mainitems)
items)
(Monthly to Annual)
Milestones
Milestones Top

Main
Main Steps
Steps
Action Plan for each WP
(design, resource, cost,..)
(Weekly to Monthly) Main
MainActivities
Activities Middle

Detailed Plans
(Daily to Weekly)
Detailed
DetailedActivities
Activities Operational

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 110


Main Information:

II- Project Data:

1. Project name & description

2. Work Breakdown Structure (WBS)

3. Activity list (ID, description, duration)

4. Activity relations (Predecessor, SS, SF, FS, FF)

5. Resource Assignments (allocation)

6. Work Products & Documents

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 111


1) Project name & description
- EPS: IT Projects
- Project ID: AUCIT
- Project Name: AUC IT Center
- Planned Start: 01 / 01 / 09
- Must finish by: ---- (Max. 2 Month)

- Responsible Manager (OBS): IT Manager


- Rate type: Price / unit
- Project Architect: No

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 112


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 113
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 114
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 115
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 116
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 117
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 118
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 119
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 120
2) Work Breakdown Structure (WBS)
- SR Server room

- L1 Lab #1

- L2 Lab #2

- L3 Lab #3

- GA
Activity Codes: General Activities
1 2 3 4
WBS Work type

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 121


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 122
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 123
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 124
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 125
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 126
3) Activity List Original duration
- SR Server room (Day)
- SRHW Server H/w activities 2
- SRSW Server S/w activities 2

- L1 Lab #1
- L1HW Lab #1 H/w activities 10
- L1SW Lab #1 S/w activities 6

- L2 Lab #2
- L2HW Lab #2 H/w activities 10
- L2SW Lab #2 S/w activities 6

- L3 Lab #3
- L3HW Lab #3 H/w activities 10
- L3SW Lab #3 S/w activities 6

- GA General Activities
- GASR Survey activities 2
- GADS Design activities 5
- GAMB Mob.& Preparation 1
- GAST Setup & testing activities 2
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 127
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 128
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 129
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 130
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 131
4) Activity Relations Original duration Predecessors
- SR Server room (Day)
- SRHW Server H/w activities 2 GAMB FS=0
- SRSW Server S/w activities 2 SRHW FS=0

- L1 Lab #1
- L1HW Lab #1 H/w activities 10 SRSW SS1-FF1
- L1SW Lab #1 S/w activities 6 L1HW SS3-FF2

- L2 Lab #2
- L2HW Lab #2 H/w activities 10 SRSW SS1-FF1
- L2SW Lab #2 S/w activities 6 L2HW SS3-FF2

- L3 Lab #3
- L3HW Lab #3 H/w activities 10 SRSW SS1-FF1
- L3SW Lab #3 S/w activities 6 L3HW SS3-FF2

- GA General Activities
- GASR Survey activities 2 - -
- GADS Design activities 5 GASR FS=0
- GAMB Mob.& Preparation 1 GADS FS=0
- GAST Setup & testing activities 2 L1SW,2SW,3SW FS=0
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 132
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 133
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 134
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 135
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 136
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 137
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 138
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 139
‫عند الضغط المزدوج بالماوس على الخط الممثل للعالقة‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪140‬‬


Trace Logic

‫األنشطة السابقة والالحقة للنشاط المختار‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 141


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 142
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 143
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 144
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 145
5) Resource allocation HWE /day SWE /day
- SR Server room
- SRHW Server H/w activities 2 -
- SRSW Server S/w activities - 2

- L1 Lab #1
- L1HW Lab #1 H/w activities 3 -
- L1SW Lab #1 S/w activities - 4

- L2 Lab #2
- L2HW Lab #2 H/w activities 3 -
- L2SW Lab #2 S/w activities - 4

- L3 Lab #3
- L3HW Lab #3 H/w activities 3 -
- L3SW Lab #3 S/w activities - 4

- GA General Activities
- GASR Survey activities 1 1
- GADS Design activities 2 2
- GAMB Mob.& Preparation 1 1
- GAST Setup & testing activities 1 1
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 146
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 147
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 148
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 149
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 150
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 151
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 152
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 153
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 154
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 155
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 156
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 157
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 158
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 159
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 160
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 161
Resource Analysis
Resource Resource Resource Unit/day Maximum Required
ID name type units/day units/day
HWE H/w Eng. Labor 8 Hour 8*4=32 72 = 8*9

SWE S/w Eng. Labor 8 Hour 8*4=32 96 = 8*12

Duration (day) 45 25

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 162


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 163
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 164
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 165
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 166
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 167
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 168
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 169
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 170
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 171
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 172
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 173
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 174
7) Work Products & Documents

GADS Design activities:


• Drawings Approved
• Detailed Design Specification In Progress

GAMB Mob.& Preparation


• General Documents In Progress

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 175


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 176
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 177
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 178
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 179
8) Notebook

GAMB Mob.& Preparation

• Contractor will send the equipment & tools


specification for review and approval before it
is shipped.

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 180


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 181
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 182
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 183
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 184
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 185
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 186
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 187
‫ت‪++‬حديث ب‪++‬يانات لا‪++‬مشر‪+‬وع ‪Updating‬‬
‫لا‪++‬مشروعات لا‪++‬مسته‪+‬دفة ‪Baselines‬‬
‫قبل تحديث بيانات المشروع البد من حفظ نسخة من المشروع األصلى تسمى ‪Baselines‬‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪188‬‬


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 189
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 190
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 191
‫تحديث بيانات األنشطة من شاشة التفاصيل‬
‫بعد بدء المشروع نقوم بتسجيل تقدم األعمال بصفة دورية حتى تاريخ تحديث‬
‫البيانات ‪ Data Date‬وقبل تحديث البيانات يجب أوال تحديد نوع النسبة المئوية‬
‫التى يتم حساب تقدم النشاط على أساسها‪.‬‬
‫‪Duration:‬‬
‫نختار هذا النوع من النسب المئوية عندما يكون‬
‫تقدم أعمال النشاط يمكن حسابه عن طريق مدة التنفيذ المتبقية ‪Remaining Duration‬‬
‫‪Duration % = {(Original Duration – Remaining Duration)/Original Duration} x100‬‬

‫‪Unit:‬‬
‫نختار هذا النوع من النسب المئوية عندما يكون‬
‫تقدم أعمال النشاط يمكن حسابه عن طريق الموارد المخصصة لهذا النشاط‬
‫‪Unit % = (Actual Units / At Completion Units) x 100‬‬
‫‪Physical:‬‬
‫نختار هذا النوع من النسب عندما يكون‬
‫تقدم األعمال النشاط أسهل عن طريق التقدير الشخصى‪.‬‬
‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪192‬‬
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 193
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 194
Status

Remaining Actual started


duration date
Duration % = {(Original Duration – Remaining Duration)/Original Duration} x100
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 195
Updating ‫مشروع‬++‫يانات لا‬++‫حديث ب‬++‫ت‬
ID Orig. Dur. Actual Start Actual Finish Remaining Dur.

Lab #1

L1HW 10 18-Jan-09 30-Jan-09 0

L1SW 6 26-Jan-09 5

General Activities:

GASR 2 03-Jan-09 04-Jan-09 0

GADS 5 05-Jan-09 10-Jan-09 0

GAMB 1 12-Jan-09 12-Jan-09 0

Server Room:

SRHW 2 15-Jan-09 17-Jan-09 0

SRSW 2 16-Jan-09 18-Jan-09 0


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 196
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 197
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 198
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 199
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 200
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 201
Advanced options

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 202


Create a New File

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 203


‫‪Create a New File‬‬

‫من خالل هذه الشاشة نحدد إذا كنا نرغب فى استخدام بر‪s‬نامج‬
‫‪Methodology Manager‬‬

‫نقوم من خالله بتصميم نماذج مختلفة ألنواع المشروعات نستفيد‬


‫بها بعد ذلك عند إنشاء مشروع جديد‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪204‬‬


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 205
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 206
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 207
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 208
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 209
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 210
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 211
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 212
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 213
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 214
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 215
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 216
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 217
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 218
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 219
Advanced
Activity Options

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 220


Group

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 221


Filters

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 222


Activity Types

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 223


‫‪Activity Types‬‬
‫‪Task Dependent‬‬
‫يقوم البرنامج بحساب تواريخ النشاط طبقا للتقويم المخصص للنشاط نختار هذا‬
‫النوع إذا لم نكن نخطط لتحديد مورد لهذا النشاط أ‪s‬و أن الموارد المخصصة لهذا‬
‫النشاط البد أن تتم حساباتها طبقا للتقويم المخصص لألنشطة‪.‬‬

‫‪Resource Dependent‬‬
‫يقوم ا‪s‬لبرنامج بحساب تواريخ النشاط طبقا لل‪s‬تقويم المخصص لل‪s‬موارد نختار هذا‬
‫النوع عند وجود موارد حاكمة أى تتحكم فى مدة وتواريخ النشاط‪.‬‬

‫‪Level Of Effort‬‬
‫هذا النوع من األنشطة يتم تحديد مدة تنفيذه طبقا لألنشطة المرتبطة به ويستخدم‬
‫لمعرفة تاريخ بداية ونهاية ونسبة تنفيذ مجموعة من األنشطة والمثال التالى يوضح‬
‫هذا النوع من النشاط حيث تم ربط بدايته ببداية أول نشاط فى المجموعة وربط‬
‫‪.‬نهايته بنهاية آخر نشاط فى المجموعة‬

‫‪Level Of Effort‬‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪224‬‬


‫‪Milestone‬‬

‫تعنىكلمة ‪ Milestone‬أهدافمرحلية وأصل الكلمة مكونمنمقطعين‪Mile‬‬


‫وتعنى ميل وكلمة ‪ Stone‬تعنى حجر حيث كان عمال الطرق فى أمريكا يقومون‬
‫بوضع حجر كل ميل لقياس اإلنجاز‪.‬‬

‫للتعبير عن بداية أو نهاية األحداث المهمة بالمشروع ‪ Milestone‬ويستخدم ال‬


‫مثل نهاية أعمال األساسات أو بداية أعمال الشبكات‪.‬‬

‫وال‪ Milestone‬هو حدث ليس له مدة تنفيذ ونسبة إنجاز إما صفر أو ‪% 100‬‬

‫ويوجد نوعانمن ال‪ Milestone‬هما ‪ Start Milestone‬و ‪Finish Milestone‬‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪225‬‬


Duration Types

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 226


‫‪Duration Types‬‬
‫‪Fixed Duration and Units‬‬
‫مدة النشاط وكمية الموارد ثابتة ويتغير طبقا لهذه معدل الموارد لكل وحدة زمنية‪.‬‬

‫‪Fixed Unit/Time‬‬
‫معدل الموارد لكل وحدة زمنية ثاب ًتا ويتم تغيير مدة النشاط‬
‫وكمية المورد طبقا لتوا فر هذا المعدل لكل وحدة زمنية ونستخدم هذا النوع فى حالة‬
‫وجود مورد له معدل إنتاجية محدد‪.‬‬

‫‪Fixed Duration and unit / time‬‬


‫مدة النشاط ثابتة ويتغير طبقا لهذه المدة كمية الموارد ونستخدم‬
‫هذا النوع فى حالة أن النشاط البد اال نتهاء منه خالل فترة محددة بغض النظر عن‬
‫معدل إنتاجية الموارد أو كميتها حيث البد من توفير هذه المعدالت طبقا لمدة النشاط‪.‬‬
‫‪Fixed Unit‬‬
‫كمية المورد ثابتة وتتغير مدة النشاط أو معدل المورد لكل‬
‫وحدة زمنية ونستخدم هذا النوع فى حالة عقد من النو ع ‪ Lump sum‬حيث إن‬
‫الكميات والتكلفة تكون ثابتة وال تتغير‪.‬‬
‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪227‬‬
Customize
activity details

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 228


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 229
‫نضيف المالحظات أو التعليقات الخاصة بالنشاط فى هذا الجزء من الشاشة‬

‫إلدراج صورة أو رسم تفصيلى بالمفكرة‬

‫لربط المفكرة بملف أو بموقع إنترنت نضغط‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪230‬‬


‫‪Steps‬‬

‫ونفرض أن لدينا نشاط خرسانة مسلحة ونريد تقسيم هذا النشاط إلى نجارة وحدادة وصب‪:‬‬
‫النجارة ‪%40‬الحدادة ‪%40‬الصب ‪%20‬‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪231‬‬


‫ عند بداية‬Complete ‫نضغط‬
‫النشاط وعمل متابعة له أمام‬
‫الخطوة المنتهية‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 232


Work Products and Documents‫ت‬+‫مستندا‬++‫اموس لا‬++‫ق‬

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 233


Constraints

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 234


‫‪Start on or after‬‬
‫يستخدم هذا القيد لجعل النشاط ال يبدأ قبل تاريخ محدد‬
‫‪Start on or before‬‬
‫يستخدم هذا القيد لجعل النشاط ال يبدأ بعد تاريخ محدد‬
‫‪Start On‬‬
‫هذا القيد يجعل تاريخ البداية المبكرة مساويا لتاريخ البداية المتأخرة مساويا لتاريخ القيد‪.‬‬
‫‪Finish on or after‬‬
‫يستخدم هذا القيد لجعل النشاط ال ينتهى قبل تاريخ معين هو تاريخ القيد‪.‬‬
‫‪Finish on or before‬‬
‫هذا القيد يحدد آخر تاريخ يمكن للنشاط أن ينتهى فيه‬
‫‪Finish on‬‬
‫هذا القيد يجعل تاريخ النهاية المبكرة مساويا لتاريخ النهاية المتأخرة مساويا لتاريخ القيد‪.‬‬
‫‪Mandatory start‬‬
‫هذا القيد يجعل تاريخ البداية المبكرة مساويا لتاريخ البداية المتأخرة مساويا لتاريخ‬
‫القيد وفى حالة تعارض تاريخ القيد مع منطق الشبكة يتم إهمال منطق الشبكة‬
‫واحترام تاريخ القيد‪.‬‬
‫‪Mandatory finish‬‬
‫هذا القيد يجعل تاريخ النهاية المبكرة مساويا لتاريخ النهاية المتأخرة مساويا لتاريخ‬
‫القيد وفى حالة تعارض تاريخ القيد مع منطق الشبكة يتم إهمال منطق الشبكة‬
‫‪As late as possible‬‬ ‫‪.‬واحترام تاريخ القيد‬
‫يستخدم هذا القيد لجعل النشاط يبدأ متأخ ًرا بقدر اإلمكان وذلك دون التأثير على‬
‫األنشطة الالحقة له أى أنه يجعل فترة السماح الحرة ‪ Free Float‬مساوية للصفر‬
‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪235‬‬
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 236
‫مصر‪+‬وفات لا‪++‬مشروع ‪Expenses‬‬
‫المصروفات الخاصة بالمشروع وغير مرتبطة بالموارد مثل‬
‫المصروفات اإلدارية وتكاليف التدريب واال نتقاالت ‪...‬إلخ‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪237‬‬


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 238
‫نحدد طريقة توزيع ال ‪ Expense‬على مدة النشاط‬
‫من خانة ‪Accrual Type‬‬
‫وهى إما أن تكون كل التكاليف محملة على بداية النشاط أو‬
‫موزعة بالتساوى على مدة تنفيذ النشاط أو محملة على‬
‫نهاية النشاط‪.‬‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪239‬‬


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 240
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 241
Customize
project details

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 242


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 243
File

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 244


File

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 245


File

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 246


File

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 247


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 248
File

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 249


Import & Export
Options

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 250


File

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 251


Edit

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 252


Edit

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 253


Edit

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 254


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 255
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 256
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 257
Advance Project
Options

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 258


PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 259
Access Mode
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 260
‫‪Exclusive‬‬
‫المستخدم الحالى فقط هو الذى يستطيع التعديل فى البرنامج وبقية‬
‫المستخدمين يمكنهم الدخول للقراءة فقط ولكن ال يمكنهم التعديل‬

‫‪Shared‬‬
‫المستخدم الحالى يمكنه الدخول والتعديل فى المشروع وبقية‬
‫المستخدمين أيضا يمكنهم الدخول والتعديل فى المشر‪s‬وع‬

‫‪Read Only‬‬
‫يمكنك فتح المشروع ولكن للقراءة فقط وال يمكنك التعديل فيه‬

‫‪PM 5.0‬‬ ‫‪Computerized Project Management - Primavera 5.0 - 2009‬‬ ‫‪261‬‬


Edit

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 262


Edit

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 263


Edit

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 264


Tools

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 265


Admin Options

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 266


Admin

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 267


Admin

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 268


Admin

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 269


Admin

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 270


Admin

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 271


Admin

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 272


Admin

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 273


Admin

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 274


Admin

PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 275


Key Terms
• Organizational Breakdown Structure (OBS) ‫تنظيمى‬++‫هيكل لا‬++‫اموس لا‬++‫ق‬
• Enterprise Project Structure (EPS) ‫مؤسسة‬++‫هيكلمشروعات لا‬
• Work Breakdown Structure (WBS) ‫لمشروع‬ŽŽ‫اموسهيكل ا‬ŽŽ‫ق‬
• Activity Codes ‫ألنشطة‬+‫كواد ا‬+‫اموس أ‬++‫ق‬
• Work Products and Documents )‫لمرجعية‬ŽŽ‫تا‬Ž‫لمستندا‬ŽŽ‫ت(ا‬+‫مستندا‬++‫اموس لا‬++‫ق‬
• Project Codes ‫مشروعات‬++‫كواد لا‬+‫اموس أ‬++‫ق‬
• Project Tracking ‫مشروعات‬++‫ة لا‬+‫متابع‬
• Cost Account ‫تكلفة‬++‫سابات لا‬+‫اموس ح‬++‫ق‬
• Cost Breakdown Structure ‫تكلفة‬++‫هيكل لا‬
• Constraints ‫قيود‬++‫لا‬
• Resource allocation ‫شاط‬+‫كل ن‬++‫خاصة ب‬++‫موارد لا‬++‫حديد لا‬++‫ت‬
• Notebook Items ‫نشاط‬++‫ا‬++‫ب‬
‫خاصة ل‬++‫مفكرة لا‬++‫لا‬
• Updating ‫مشروع‬++‫يانات لا‬++‫حديث ب‬++‫ت‬
• Baselines ‫دفة‬+‫مسته‬++‫مشروعات لا‬++‫لا‬
• Layout ‫نموذج‬++‫لا‬
• Expenses ‫مشروع‬++‫مصروفات لا‬
• Earned Value ‫مستحقة‬++‫قيمة لا‬++‫ياس لا‬++‫ق‬
• Global Changes ‫شاملة‬++‫ت لا‬+‫تغييرا‬++‫لا‬
• Risk Management ‫مخاطر‬++‫إدارة لا‬
• Export ‫مشروعات‬++‫يانات لا‬++‫صدير ب‬++‫ت‬
• Import ‫مشروعات‬++‫يانات لا‬++‫ستيراد ب‬+‫ا‬
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 276
Thank you for your attention!

Discussion

Suggestions Comments

Questions
For More Information:
Dr. Attia Hussien Gomaa
Industrial Engineering Professor & Consultant
Tel: 0122738497 attiagomaa@yahoo.com
‫اللهم يا عالم يا عليم نسألك أن تتقبل هذا العلم إبتغاء مرضاتك وأن تجعله علما ينتفع به – اللهم أمين – نسألكم الدعاء‬
PM 5.0 Computerized Project Management - Primavera 5.0 - 2009 277