CONSTRUCTION

FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
1







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2


CONTENTS

1. PROGRESS OF WORK
2. AREAS OF CONCERN
a) Engineering (Drawings)
3. CONSTRAINT
4. SITE AREA WISE PROGRESS ALONG WITH PHOTOGRAPHS
5. MANPOWER STATUS
6. PLAN FOR LATER HALF OF FEB12

7. MATERIAL RECIEVED AT SITE
























CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
3
PROGRESS OF WORK(CIVIL)





STG BUILDING
a) 2 Nos of Pile Cap Casting completed in A-A2 Bay.
b) 30 % Plinth beam work completed.
c) 20% Columns up to Mezzanine floor slab beam bottom completed.
d) Slab Casting of BC Bay 4.36m/4.85m slab (5 to 9 grid) completed.
e) 2 Nos of Pile cap chipping & PCC for pile cap completed in A-A2 Bay.
f) BFP 6 nos of foundation completed.
e) Reinforcement work for Slab 4.36m/4.85m slab (10to16 grid) work in progress.
STG
0%
50%
100%
150%
PLANNED ACHIEVED
STG







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
4
PROGRESS OF WORK(CIVIL)






BOILER-2
a) 5 Nos of pile cap casting work completed.
b) 5 Nos of Foundation bolt casting completed.
BOILER-3
a) 4 Nos of Pile for SA Fan completed.
BOILER-4
a) 39 Nos of Pile completed.
b) 4 Nos of Pile for SA fan completed.
BOILER-4
0
50
100
150
PLANNED ACHIEVED
BOILER-4









CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
5

PROGRESS OF WORK(CIVIL)



CHIMNEY-1

a) 25% slip form assembly completed.
CHIMNEY-1
0%
20%
40%
60%
80%
100%
120%
PLANNED ACHIEVED
CHIMNEY-1







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
6

PROGRESS OF WORK(CIVIL)








SECONDARY CRUSHER HOUSE
a) 4 of PCC for Pile caps completed.


SECONDARY CRUSHER HOUSE
0%
20%
40%
60%
80%
100%
120%
PLANNED ACHIEVED
SECONDARY CRUSHER
HOUSE








CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
7

PROGRESS OF WORK(CIVIL)





ESP-3

a) 4 Nos of foundation bolt casting completed.
ESP- 4

a) 2 Nos of foundation bolt casting completed.
ESP-3 & 4
100
90
PLANNED ACHIEVED
ESP-3 & 4








CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
8

PROGRESS OF WORK(CIVIL)







COOLING TOWER

a) 50 % cell wall casting work completed at basin.



COOLING TOWER
100%
75%
PLANNED ACHIEVED
COOLING TOWER







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK




AIS ROOM

a) 2 Nos of columns up to plinth beam bottom completed.
b) 30% plinth beam work completed.


AIS
0%
20%
40%
60%
80%
100%
120%
PLANNED ACHIEVED
AIS










CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK





CHP MCC ROOM
a) Balance 40% of plinth beam work comple
CHP MCC ROOM
0%
20%
40%
60%
80%
100%
120%
PLANNED ACHIEVED
CHP MCC ROOM








CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK





DM SHED

a) 11Nos of RCC for foundation completed.
b) 8 Nos of column upto plinth beam bottom completed.

DM SHED
0%
20%
40%
60%
80%
100%
120%
PLANNED ACHIEVED
DM SHED







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK





NEUTRALISATION PIT

a) Shuttering work for wall casting in progress.


N PIT
0%
50%
100%
150%
PLANNED ACHIEVED
N PIT










CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK




STACKER & RECLAIMER

a) 59 piles complete
STACKER & RECLAIMER
80
90
100
110
PLANNED ACHIEVED
STACKER & RECLAIMER








CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK




PRIMARY CRUSHER HOUSE

a) PCC for Pile Cap completed.
b) Pile Cap chipping completed.


PRIMARY CRUSHER HOUSE
0
50
100
150
PLANNED ACHIVED
PRIMARY CRUSHER
HOUSE







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK




ASH SILO

a) Pile cap casting work completed.
b) 4 nos of columns upto plinth beam bottom completed.


ASH SILO
0
50
100
150
PLANNED ACHIEVED
ASH SILO







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK





DM MCC ROOM

a) 19 Nos of PCC for foundation completed.
b) 12 Nos of RCC for the foundation completed

DM/MCC Room
85
90
95
100
105
PLANNED ACHIEVED
DM/MCC Room







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK







ESP MCC ROOM

a) 9 Nos of RCC for foundation completed.



ESP/MCC ROOM
0
50
100
150
PLANNED ACHIEVED
ESP/MCC ROOM







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK (MECHANICAL)





ESP-1

a) Balance tie beam erection completed
b) Balance bracing erection completed.
c) Balance Pre ssembly work of casing completed.
d) 30 % staircase erection work completed.
ESP-2
a) 18 columns erected.

ESP-1
85
90
95
100
105
PLANNED ACHIEVED
ESP-1









CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PROGRESS OF WORK (MECHANICAL)






BOILER-1

a) Preassembly work all columns(2nd Tier completed).
b) 10% erection of Tie beams completed.
c) 5% erection of bracing completed.
BOILER-1
0
50
100
150
PLANNED ACHIEVED
BOILER-1







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

AREA OF CONCERN

ENGINEERING


a) Civil drawing

1. AIS Building - Drawing for Slab.

2. STG Building - Drawing for 14 m Slab.

3. DM/MCC Room - Drawing for trench, equipment foundation & Slab.

4. Cooling Tower - Drawing for 3.85 m fore bay slab & other complete .
Drawing other list of cooling tower drawings.

5. ESP MCC Room - Drawing for Slab.

6. Primary Crusher House - Drawing for plinth beam.

7. Secondary Crusher House - Drawing for plinth beam.

8. Secondary Screen House - Pile cap & Tie beam.

9. DM Shed - Equipment foundation drawing & drawings above plinth level.


b) Mechanical drawing

1.All drawing for pressure parts(Boiler 1).
2. Coal Bunker.
3. Ducting PA,SA,APH to ESP,ESP to ID Fan,ID Fan to chimney.
4. Integral & Non Integral piping with supports.


MateriaI ducting material required.







CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2


CONSTRAINTS

M/s Ahluwalia Contracts (I) Ltd.


1.Requirement of 250 more workers
2. Requirement of more areawise Supervisors/Engineers.
3. Requirement of scaffolding,shuttering materials.



M/s V D Swami Pvt. Ltd.

1.IBR clearance for erection of pressure parts has to be expedite.
2. 210 Ton Crane readiness for further erection .
3.Activities in ESP-1 & Boiler-1 needs to speedup.


Thermax Instrumentation Ltd.

1. Area Lighting is to be improved.
2. Drinking Water facilities ,labour camp & site is to be regularised.



















CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

MANPOWER
















0
100
200
300
400
500
600
700
800
900
1000
Manpower Status
Manpower Status









CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

PLAN FOR LATER HALF OF FEBRUARY


1.STG Building Balance Pile Cap casting of BC bay,balance
Columns upto mezanine floor slab beam bottom
balance plinth beam work of BC bay , slab(4.36m)
casting upto 16 grid(BC bay),9.60m Slab casting upto
8 grid and pile cap casting(A-A2 bay) upto 4 th grid.
TG Deck-1 casting.


2.Boiler-2,3,4 Balance piling work for fan foundations.

3.Boiler-2 - complete civil work.

4.ESP-3 & ESP-4 Balance civil work.

5.Cooling Tower Basin Cell wall casting.

6.Neutralisation Pit Wall casting.

7.DM Shed Plinth Beam.

8.DM MCC Room Plinth Beam.

9.ESP MCC Room Columns upto plinth beam bottom.

10.Ash Silo Plinth Beam.

11.Primary Crusher House Pile cap casting.










CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2


PLAN FOR LATER HALF OF FEBRUARY


12.Chimney-1 Slip form assembly work.

13.Chimney-2 Complete piling work.

14.Stacker & Reclaimer Piling Work.



MECHANICAL

1.Boiler-1 Erection of columns(2 nd Tier) & erection of tie
Beams,APH module preassembly.

2.ESP-1 Erection of casing,nozzle preassembly

3.ESP-2 Balance Tie beams,bracings & structural alignment.

4.Boiler-2- Preassembly of Columns.

5.DM Tank Bottom plate & shell fabrication.















CONSTRUCTION
FORTNIGHTLY
PROGRESS REPORT

3x32 MW
CPP,GIL,BHARUCH

PROGRESS
MONTH.
Page
FEBRUARY
FEBRUARY
(1.2.12 TO 16.2.12)
2

MATERIAL RECIEVED AT SITE


1.STEEL Upto 31 st Jan12 -TMT Bar 2094 MT.
- From 1-16 Feb12 - TMT Bar 25 MT.


2. CEMENT BAGS - Upto 31 st Jan12- 49120 Bags.
- From 1-16 Feb12- Bags 10620 Bags.
- Loose Cement - - Upto 31 st Jan12- 1629 MT.
- Loose Cement -From 1-16 Feb12- 230 MT.



3.PLANT MATERIAL - Upto 31 st Jan12-3006 MT.
- From 1-16 Feb12- 1270 MT.