SEPTEMBER 2014 Supplier Evaluation KOLTE PATIL DEVELOPRS LIMITED MONTHLY MATERIAL QUALITY AUDIT REPORT
MONTH / YEAR Sep-14 PERIOD 01.09.2014 TO 30.09.2014 PAGE 1 OF 1 QA/418 SR NO MATERIAL SUPLLIER NET INSPECTED QUANTITY UNIT INSPECTION FREQUENCY NET ACCEPTED QUANTITY NET REJECTED QUANTITY % ACCPTANCE ACCEPTANCE / REJECTION ROOT CAUSE CORRECTIVE / PREVENTIVE ACTION PLAN % QUALITY ASSURANCE RATING QUALITY PERFORMANAN CE GRADING Remark 1 Cover block Mentone Concrete 8600 NOS Per Lot 8600.00 0.00 100.00 NA NA 100.00 A 2 8 mm steel Bhuleshwar steel 2280.00 KG Per Lot 2280.00 0.00 100.00 NA NA 100.00 A 3 10 mm steel Bhuleshwar steel 0.00 KG Per Lot 0.00 0.00 #DIV/0! NA NA #DIV/0! A 4 12 mm steel Bhuleshwar steel 420.00 KG Per Lot 420.00 0.00 100.00 NA NA 100.00 A 5 16 mm steel Bhuleshwar steel 1420.00 KG Per Lot 1420.00 0.00 100.00 NA NA 100.00 A 6 20 mm steel Bhuleshwar steel 5300.00 KG Per Lot 5300.00 0.00 100.00 NA NA 100.00 _ 7 25 mm steel Bhuleshwar steel 0.00 KG Per Lot 0.00 0.00 #DIV/0! NA NA #DIV/0! _ 8 32 mm steel Bhuleshwar steel 0.00 KG Per Lot 0.00 0.00 #DIV/0! NA NA #DIV/0! A 9 Cement C. S. Raghoji 314.00 BAG Per Lot 314.00 0.00 100.00 NA NA 100.00 A 10 Crush sand Sai Stone Crusher 1148.00 CFT Per Lot 1148.00 0.00 100.00 NA NA 100.00 A 11 4" Fly ash brick Ash Concepts 6226.00 NOS Per Lot 6226.00 40.00 99.36 NA NA 99.36 A 11 Binding wire Bhagyalaxmi Enterprises 1604.00 KG Per Lot 1604.00 40.00 97.51 NA NA 97.51 A 10 Concrete :-M15 Sai RMC 0.00 m3 Per Transit / Sampling basis 0.00 0.00 #DIV/0! NA NA #DIV/0! _ 11 Concrete :-M20 Sai RMC 0.00 m3 Per Transit / Sampling basis 0.00 0.00 #DIV/0! NA NA #DIV/0! A 12 Concrete :-M25 Sai RMC 386.00 m3 Per Transit / Sampling basis 386.00 0.00 100.00 NA NA 100.00 A 13 Concrete :-M30 Sai RMC 0.00 m3 Per Transit / Sampling basis 0.00 0.00 #DIV/0! NA NA #DIV/0! _
SR NO DESCRIPTION NAME DESIGNATION SIGNATURE REMARKS QUALITY PERFORMANANC E GRADING
1 PREPARED BY
SR NO % QA RATING QUALITY PERFORMNANCE GRADING
2 APPROVED BY
QAQC MANAGER
A 90-100 EXCELLENT
B 80-89 GOOD
C 60-79 AVERAGE
D 50-59 BELOW AVERAGE
QAQC MANAGER E < 50 POOR
CONTRACTOR EVALUATION QUALITY RATING ACHIEVED BY SUPPLIER 0 20 40 60 80 100 120 QUALITY ASSURANCE RATING % QUALITY ASSURANCE RATING S T E E L
1 6
M M
S T E E L
1 2
M M
S T E E L
8
M M
S T E E L
2 0
M M
C O V E R
B L O C K
Contractor Evaluation
KOLTE PATIL DEVELOPERS LTD CONTRACTOR EVALUATION ON BASIS OF QUALITY OF WORK
MONTH : August-2014 QA/424 PROJECT CONTRACTOR NAME ACTIVITY NC TYPE (MAJOR / MINOR) OCCURANCE OF NON CONFIRMATIVE( 40%) CLOSURE OF NON CONFIRMATIVE (30%) DOCUMENTA TION(20%) HOUSEKEEPING / CURING (10%) NET QUALITY RATING ACHIEVED(100%) STARGAZE MAZUKA CONSTRUCTION RCC NO 40 30 15 8 93 STARGAZE PAR HITEK RCC 1 20 20 20 20 80 STARGAZE ORIENT INFRASTRUCTURE RCC MINOR 40 25 15 10 90
Remarks - % Closure of NC Marks Documentation Marks House Keeping Marks
80- 100 % 30 Excellent 20 Excellent 10 1.Occurance of NC- 01 Mark deducted for Minor NC & 3 Marks Deducted 60 - 79 % 25 Good 15 Good 8 for Major NC 50- 59 % 20 Average 10 Average 6 2. Frequency of Contractor evaluation is 25 - 49 % 15 Below Average 5 Below Average 4 < 25 % 10 Poor 0 Poor 2 PREPARED BY : REVIEWED BY : CONTRACTOR EVALUATION 70 75 80 85 90 95 MAZUKA CONSTRUCTION PAR HITEK ORIENT INFRASTRUCTURE Series1 QUALITY RATING ACHIEVED BY CONTRACTOR
KOLTE PATIL DEVELOPERS LTD NC SUMMARY SEPTEMBER MONTH PROJECT : STARGAZE BAVDHAN MONTH :SEPT-2014 QA/421 NAME OF CONTRACTOR BUILDING SCOPE OF WORK OCCURANCE CLOSED % OF CLOSER MAJOR NC MINOR NC MAJOR NC MINOR NC PAR HITECH RCC 1 _ 1 _ 100 MAZUKA CONSTRUCTION RCC _ _ _ _ NA ORIENT INFRA RCC _ 1 _ 1 NA
_ _ _ _ NA
_ _ _ _ NA
_ _ _ _ NA
_ _ _ _ NA PREPARED BY : REVIEWED BY : MATERIAL TEST SUMMARY 0 2 4 6 8 10 12 A BLDG 28 DAYS SET OF Cube B BLDG 28 DAYS SET OF Cube STEEL CEMENT FLY ASH BRICK COVER BLOCK PASS FAIL REJECT MATERIAL LIST Sr. No. Date Building Challan No. Vehicle No. Supplier Name Grade Qty. Remark 1 13-Sep-14 A 3720 MH - 14 CP - 7225 Sai Rmc M - 25 1.5 M3 Rejection due intial setting 2 16-Sep-14 A 3761 MH - 14 CP-7225 Sai Rmc M - 25 1.5 M3 Rejection due intial setting 3 16-Sep-14 B 3826 MH -12 FZ - 7023 Sai Rmc M - 25 1.5 M3 Rejection due intial setting 4 16-Sep-14 B 3828 MH -14 CP - 7225 Sai Rmc M - 25 1.00 M3 Rejection due intial setting 5 18-Sep-14 B 3398 MH - 12 FZ - 7024 Sai Rmc M - 25 0.50 M3 Rejection due intial setting 6 20-Sep-14 A 3972 MH -14 CP - 3221 Sai Rmc M - 25 3.00 M3 Rejection due intial setting 7 22-Sep-14 B 4002 MH -12 FZ - 7023 Sai Rmc M - 25 2.00 M3 Rejection due initial setting 8 26-Sep-14 A 4201 MH -14 CP - 3227 Sai Rmc M - 25 1.5 M3 Rejection due initial setting
GOOD PRACTISES Preventive & Corrective Action Root Cause Analysis Quality Control at Site. B Building lift wall Shuttering Work B Building Retaining wall casting Shuttering oil,cover,alignment Column Cover Proper supporting Tray for concrete Quality Control at Site. A Building . Proper Curing Crystallization water proofing to lift wall 450mm layer backfilling vibro roller Quality Control at Site. CLUB HOUSE Construction joint treatment Plinth beam curing Proper Supporting Perforated pipe Material Testing Slump Test Of RMC Concrete. (Slump 125mm) Proper Cube Casting Of RMC Concrete
Compressive Strength Test Of Concrete Cube. Root Cause Analysis ROOT CAUSE ANALYSIS RCA : 01
PROJECT NAME : STARGAZE, BAVDHAN Description of Issue / lapses: Lower Cube results
Cause Identified : 1. Lower cube results.
Root Cause Identified: 1. Ingredient mixing. 2. Water cement ratio. 3. Sampling & cube casting. Corrective Action taken : a. NDT test- Found ok.
Preventive Action taken : A. Training & awareness given to RCC contractor. B. One day workshop on concrete ingredient mixing,sampling,cube casting.
Lower cube results due to improper cube casting EVIDENCES Improvement After Instructions MOCK-UP / DEMOs Location : STARGAZE, CLUB HOUSE Contractor- par hitech.
Concrete mixing good practice Water & Admixture mixing Weigh batcher calibration Sandwich mixing of ingredients Cleaning of cube mould Oiling of cube mould Cube mould validation Sampling Cube casting step wise procedure Sampling Layer 1 Layer 2 Layer 3 Finishing Cube casting step wise procedure