1 PLUMBING FIXTURES ( Install Only ) 15

( 1 March : 15 March ) ( 1 March : 15 March ) ( 1 March : 15 March ) ( 1 March : 15 March ) ( 1 March : 15 March )
2
UNIVERSAL ACCESSORIES: ( Paper & Soap
Dispenser , Hand Dryers , etc )
( Install Only )
15
( 15 March : 31 March ) ( 15 March : 31 March ) ( 15 March : 31 March ) ( 15 March : 31 March ) ( 15 March : 31 March )
3 DRAINAGE SYSTEM
3.1
ABOVE GROUND & UNDER GROUND
DRAINAGE PIPING SYSTEM
(VERTICAL & HORIZONTAL)
15
( 19 January : 2 February ) ( 19 January : 2 February ) ( 2 February : 16 February ) ( 2 February : 16 February ) ( 2 February : 16 February )
Supply, install, connect and test UPVC PIPE,
waste and vent (vertical & horizontal) above
ground and under ground piping system
3.2
Plumbing Accessories ( Clean Out , Roof Vent
Cap , Floor Drain , Roof Drain , .. etc )
7
( 8 February : 15 February ) ( 8 February : 15 February ) ( 20 February : 28 February ) ( 20 February : 28 February ) ( 20 February : 28 February )
4 WATER SUPPLY SYSTEM
4.1
ABOVE GROUND & UNDER GROUND WATER
SUPPLY PIPING SYSTEM (VERTICAL &
HORIZONTAL)
4.1.1
Supply, install, connect, and test poly-proplyene
(PN-10) (vertical & horizontal) above ground
and under ground cold water supply piping
systems
15
( 19 January : 2 February ) ( 19 January : 2 February ) ( 2 February : 16 February ) ( 2 February : 16 February ) ( 2 February : 16 February )
4.1..2 VALVES & ELECTRIC WATER HEATER 7
( 8 February : 15 February ) ( 8 February : 15 February ) ( 20 February : 28 February ) ( 20 February : 28 February ) ( 20 February : 28 February )
EPS Building Utility Building Guard Room
Waste Storage
Building
PROJECT TITEL: SAMSUNG ELECTRONICS FACTORY - PLUMBING NETWORK WORKS
Time Schedule For Plumbing network Samsung Project
SECTION
NO.
ITEM
NO.
DESCRIPTION
No. of
days
Main Production
Building



PLUMBING (3) 1 of 1 Rev.0