ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN


No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
A-01 1 M' Pagar Sementara Dari Kayu Tinggi 2 m
- Dolken Kayu 8-10 / 400 cm Btg 1.2500 28,000.00 35,000.00
- Semen Portland Kg 2.5000 1,406.00 3,515.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Kayu balok terentang M3 0.0720 2,640,000.00 190,080.00
- Paku Biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Residu Kg 0.4000 8,100.00 3,240.00
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 269,315.90
Dibulatkan 269,316.00
A-02 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m
- Dolken Kayu 8-10 / 400 cm Btg 1.2500 28,000.00 35,000.00
- Semen Portland Kg 2.5000 1,406.00 3,515.00
- Seng Gelombang BJLS-30 Lbr 1.2000 62,900.00 75,480.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Kayu balok terentang M3 0.0720 2,640,000.00 190,080.00
- Paku Biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Meni Besi Kg 0.4500 30,400.00 13,680.00
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 355,235.90
Dibulatkan 355,236.00
A-03 1 M' Pagar SementaraKawat Duri Tinggi 1,80 m
- Dolken Kayu 8-10 / 400 cm Btg 1.0000 28,000.00 28,000.00
- Semen Portland Kg 2.0000 1,406.00 2,812.00
- Kawat Duri Kg 2.5000 63,500.00 158,750.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Paku Biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 222,842.90
Dibulatkan 222,843.00
A-04 1 M2 Pengukuran Dan Pasang Bouwplank
- Kayu kaso 5/7 M3 0.0120 1,870,500.00 22,446.00
- Paku Biasa 2" - 5" Kg 0.0200 23,400.00 468.00
- Kayu papan albasia M3 0.0070 2,071,700.00 14,501.90
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 49,265.90
Dibulatkan 49,266.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
A-05 1 M2 Pembuatan Kantor Sementara dgn Lantai Diplester
- Dolken Kayu 8-10 / 400 cm Btg 1.2500 28,000.00 35,000.00
- Kayu Balok terentang M3 0.1800 2,640,000.00 475,200.00
- Paku Biasa Kg 0.8500 23,400.00 19,890.00
- Besi Strip Kg 1.1000 26,800.00 29,480.00
- Semen Portland Kg 35.0000 1,406.00 49,210.00
- Pasir Pasang M3 0.1500 233,400.00 35,010.00
- Pasir beton M3 0.1000 255,400.00 25,540.00
- Koral Beton2/3 M3 0.1500 211,100.00 31,665.00
- Bata Merah Bh 30.0000 775.00 23,250.00
- Seng Plat m' 0.2500 15,815.00 3,953.75
- Kawat harmonika M2 2.0000 35,900.00 71,800.00
- Kaca Polos 3mm M2 0.0800 87,400.00 6,992.00
- Kunci Tanam Bh 0.1500 94,500.00 14,175.00
- Plywood 120 x 240 x 0,4 cm Lbr 0.0600 140,000.00 8,400.00
- Pekerja Oh 2.0000 42,000.00 84,000.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Tukang Batu Oh 1.0000 65,000.00 65,000.00
- Kepala Tukang Oh 0.3000 75,000.00 22,500.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 1,135,065.75
Dibulatkan 1,135,066.00
A-06 1 M2 Pembuatan Gudang Semen dan Alat-alat
- Dolken Kayu 8-10 / 400 cm Btg 1.7000 28,000.00 47,600.00
- Kayu balok terentang M3 0.2100 2,640,000.00 554,400.00
- Paku Biasa Kg 0.3000 23,400.00 7,020.00
- Semen Portland Kg 10.5000 1,406.00 14,763.00
- Pasir Beton M3 0.0300 255,400.00 7,662.00
- Koral Beton 2/3 M3 0.0500 211,100.00 10,555.00
- Seng Gelombang BJLS 30 Lbr 1.5000 62,900.00 94,350.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 927,350.00
Dibulatkan 927,350.00
A-07 1 M2 Pembuatan Bedeng Buruh
- Dolken Kayu 8-10 / 400 cm Btg 1.2500 28,000.00 35,000.00
- Kayu balok terentang M3 0.1860 2,640,000.00 491,040.00
- Paku Biasa Kg 0.3000 23,400.00 7,020.00
- Semen Portland Kg 18.0000 1,406.00 25,308.00
- Pasir Beton M3 0.0300 255,400.00 7,662.00
- Koral Beton 2/3 M3 0.0500 211,100.00 10,555.00
- Seng Gelombang BJLS 30 Lbr 1.5000 62,900.00 94,350.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 861,935.00
Dibulatkan 861,935.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
A-08 1 M2 Membersihkan Lapangan dan Perataan
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 8,200.00
Dibulatkan 8,200.00
A-09 1M2 Pembuatan Jalan Sementara
- Batu Belah 15/20 M3 0.1500 205,500.00 30,825.00
- Batu Pecah 5/7 M3 0.0900 196,000.00 17,640.00
- Pasir Pasang M3 0.0100 233,400.00 2,334.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 96,799.00
Dibulatkan 96,799.00
A-10 1 M3 Bongkaran Beton Bertulang
- Pekerja Oh 6.6670 42,000.00 280,014.00
- Mandor Oh 0.3330 80,000.00 26,640.00
Jumlah 306,654.00
Dibulatkan 306,654.00
A-11 1 M3 Bongkaran Dinding Tembok Bata Merah
- Pekerja Oh 6.6670 42,000.00 280,014.00
- Mandor Oh 0.0330 80,000.00 2,640.00
Jumlah 282,654.00
Dibulatkan 282,654.00
A-12 1 M Pagar beton Pracetak ( 5 x 50 x 213 ) cm
- Panel Beton Pracetak Lbr 0.9860 199,200.00 196,411.20
- Kolom Beton Pracetak Btg 0.5250 264,000.00 138,600.00
- Pasir Beton M3 0.0740 255,400.00 18,899.60
- Koral 2/3 M3 0.1460 211,100.00 30,820.60
- Semen abu - abu Kg 45.0000 1,406.00 63,270.00
- Pekerja Oh 0.3750 42,000.00 15,750.00
- Tukang Batu Oh 0.1250 65,000.00 8,125.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 474,296.40
Dibulatkan 474,296.00
A-13 1 M Pagar kawat ayam tiang besi L50.50.5, tinggi 1 m'
- Kawat ram ayam Lbr 0.4340 14,900.00 6,466.60
- Besi siku L 50.50.5 Kg 6.7860 18,300.00 124,183.80
- Besi pelat (1,2 x 3) mm Kg 0.0424 18,300.00 775.92
- Baut bh 4.0000 600.00 2,400.00
- Semen Portland Kg 2.5000 1,406.00 3,515.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Pekerja Oh 0.3750 42,000.00 15,750.00
- Tukang Batu Oh 0.1250 65,000.00 8,125.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 166,813.22
Dibulatkan 166,813.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
A-14 1 M2 Pagar BRC lengkap dengan tiang
- BRC lengkap dengan tiang Lbr 0.4340 171,300.00 74,344.20
- Semen Portland Kg 2.0000 1,406.00 2,812.00
- Kawat Duri Kg 2.5000 63,500.00 158,750.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Pekerja Oh 0.3750 42,000.00 15,750.00
- Tukang Batu Oh 0.1250 65,000.00 8,125.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 265,378.10
Dibulatkan 265,378.00
A-15 1 M2 Steiger Werk / perancah dari Bambu
- Bambu 6 - 10 (600) cm btng 1.0000 25,000.00 25,000.00
- Tali ijuk kg 0.2500 23,400.00 5,850.00
- Pekerja org 0.2500 42,000.00 10,500.00
- Tukang kayu org 0.0170 65,000.00 1,105.00
- Kepala tukang org 0.0020 75,000.00 150.00
- Mandor org 0.0130 80,000.00 1,040.00
Jumlah 43,645.00
Dibulatkan 43,645.00
A-16 1 M' Cerucuk Bambu
- Bambu 7 -10 (400) cm btng 1.2500 25,000.00 31,250.00
- Pekerja org 0.5000 42,000.00 21,000.00
- Mandor org 0.0250 80,000.00 2,000.00
Jumlah 54,250.00
Dibulatkan 54,250.00
B. ANALISA HARGA SATUAN PEKERJAAN TANAH
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
B-01 1 M3 Galian Tanah Biasa sedalam 1 m
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 20,000.00
Dibulatkan 20,000.00
B-02 1 M3 Galian Tanah Biasa Sedalam 2 m
- Pekerja Oh 0.5260 42,000.00 22,092.00
- Mandor Oh 0.0520 80,000.00 4,160.00
Jumlah 26,252.00
Dibulatkan 26,252.00
B-03 1 M3 Galian Tanah Biasa Sedalam 3 m
- Pekerja Oh 0.7350 42,000.00 30,870.00
- Mandor Oh 0.0730 80,000.00 5,840.00
Jumlah 36,710.00
Dibulatkan 36,710.00
B-04 1 M3 Galian Tanah Keras Sedalam 1 m
- Pekerja Oh 0.6250 42,000.00 26,250.00
- Mandor Oh 0.0620 80,000.00 4,960.00
Jumlah 31,210.00
Dibulatkan 31,210.00
B-05 1 M3 Galian Tanah Lumpur Sedalam 1 m
- Pekerja Oh 0.8230 42,000.00 34,566.00
- Mandor Oh 0.0830 80,000.00 6,640.00
Jumlah 41,206.00
Dibulatkan 41,206.00
B-06 1 M2 Pekerjaan Stripping Setinggi 10 cm
- Pekerja Oh 0.0500 42,000.00 2,100.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 2,500.00
Dibulatkan 2,500.00
B-07 1 M3 Pembuangan Tanah sejauh 150 m
- Pekerja Oh 0.5160 42,000.00 21,672.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 25,672.00
Dibulatkan 25,672.00
B-08 1 M3 Urugan Kembali
- Pekerja Oh 0.1920 42,000.00 8,064.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 9,584.00
Dibulatkan 9,584.00
B-09 1 M3 Pemadatan Tanah
- Pekerja Oh 0.5000 42,000.00 21,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 25,000.00
Dibulatkan 25,000.00
B-10 1 M3 Urugaan Pasir
- Pasir Urug M3 1.2000 175,300.00 210,360.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 223,760.00
Dibulatkan 223,760.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
B-11 1 M2 Pemasangan Lapisan Ijuk Tebal 10 cm
- Ijuk m2 1.2000 22,000.00 26,400.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 33,900.00
Dibulatkan 33,900.00
B-12 1 M3 Urugan Sirtu
- Sirtu M3 1.2000 203,500.00 244,200.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Mandor Oh 0.0250 80,000.00 2,000.00
Jumlah 256,700.00
Dibulatkan 256,700.00
B-13 1 M3 Urugan Tanah Pilihan
- Tanah urug pilihan M3 1.2000 89,200.00 107,040.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Mandor Oh 0.0250 80,000.00 2,000.00
Jumlah 119,540.00
Dibulatkan 119,540.00
B-14 1 M2 Pembuatan jalan sementara, tebal 25 cm
- Batu belah M3 0.2750 205,500.00 56,512.50
- Kerikil M3 0.0300 172,600.00 5,178.00
- Pasir Urug M3 0.0500 175,300.00 8,765.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Mandor Oh 0.1000 80,000.00 8,000.00
Jumlah 120,455.50
Dibulatkan 120,456.00
C. ANALISA HARGA SATUAN PEKERJAAN PONDASI
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
C-01 1 M3 Pasanag Pondasi batu Kali adk 1pc : 3 ps
- Batu Belah M3 1.1000 205,500.00 226,050.00
- Semen Portland Kg 202.0000 1,406.00 284,012.00
- Pasir Pasang M3 0.4850 233,400.00 113,199.00
- Pekerja Oh 1.5000 42,000.00 63,000.00
- Tukang Batu Oh 0.6000 65,000.00 39,000.00
- Kepala Tukang Oh 0.0600 75,000.00 4,500.00
- Mandor Oh 0.0750 80,000.00 6,000.00
Jumlah 735,761.00
Dibulatkan 735,761.00
C-02 1 M3 Pasang Pondasi Batu kali adk 1pc : 4ps
- Batu Belah M3 1.1000 205,500.00 226,050.00
- Semen Portland Kg 163.0000 1,406.00 229,178.00
- Pasir Pasang M3 0.5200 233,400.00 121,368.00
- Pekerja Oh 1.5000 42,000.00 63,000.00
- Tukang Batu Oh 0.6000 65,000.00 39,000.00
- Kepala Tukang Oh 0.0600 75,000.00 4,500.00
- Mandor Oh 0.0750 80,000.00 6,000.00
Jumlah 689,096.00
Dibulatkan 689,096.00
C-03 1 M3 Pasang Pondasi Batu kali adk 1pc : 5ps
- Batu Belah M3 1.1000 205,500.00 226,050.00
- Semen Portland Kg 136.0000 1,406.00 191,216.00
- Pasir Pasang M3 0.5440 233,400.00 126,969.60
- Pekerja Oh 1.5000 42,000.00 63,000.00
- Tukang Batu Oh 0.6000 65,000.00 39,000.00
- Kepala Tukang Oh 0.0600 75,000.00 4,500.00
- Mandor Oh 0.0750 80,000.00 6,000.00
Jumlah 656,735.60
Dibulatkan 656,736.00
C-04 1 M3 Pasang Pondasi Batu Kosong (aanstamping)
- Batu Belah M3 1.2000 205,500.00 246,600.00
- Pasir Urug M3 0.3000 175,300.00 52,590.00
- Pekerja Oh 0.7800 42,000.00 32,760.00
- Tukang Batu Oh 0.3900 65,000.00 25,350.00
- Kepala Tukang Oh 0.0390 75,000.00 2,925.00
- Mandor Oh 0.0390 80,000.00 3,120.00
Jumlah 363,345.00
Dibulatkan 363,345.00
C-05 1 M3 Beton siklop adk 1pc : 2ps : 3kr + 40 % Batu Belah dgn besi tulangan
- Besi Beton Kg 75.0000 16,500.00 1,237,500.00
- Semen Portland Kg 202.0000 1,406.00 284,012.00
- Pasir Beton m3 0.3200 255,400.00 81,728.00
- Koral Beton 2/3 m3 0.4900 211,100.00 103,439.00
- Kawat Beton Kg 0.8000 27,700.00 22,160.00
- Batu Belah m3 0.4500 205,500.00 92,475.00
- Pekerja Oh 3.0000 42,000.00 126,000.00
- Tukang Batu Oh 0.8500 65,000.00 55,250.00
- Kepala Tukang Oh 0.0850 75,000.00 6,375.00
- Mandor Oh 0.1500 80,000.00 12,000.00
Jumlah 2,020,939.00
Dibulatkan 2,020,939.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
C-06 1 M3 Pasang Pondasi Sumuran adk 1pc:2ps:3kr + 40 % Batu Belah (D= 1m)
- Batu Belah M3 0.4500 205,500.00 92,475.00
- Semen Portland Kg 280.0000 1,406.00 393,680.00
- Pasir Beton M3 0.4500 255,400.00 114,930.00
- Koral Beton M3 0.6700 211,100.00 141,437.00
- Pekerja Oh 2.3800 42,000.00 99,960.00
- Tukang Batu Oh 0.3000 65,000.00 19,500.00
- Kepala Tukang Oh 0.0300 75,000.00 2,250.00
- Mandor Oh 0.0800 80,000.00 6,400.00
Jumlah 870,632.00
Dibulatkan 870,632.00
C-07 1 M3 Pondasi siklop adk 1pc:2ps:3kr + 40 % Batu Belah
- Batu Belah M3 0.4500 205,500.00 92,475.00
- Semen Portland Kg 202.0000 1,406.00 284,012.00
- Pasir Beton M3 0.3200 255,400.00 81,728.00
- Koral Beton M3 0.4900 211,100.00 103,439.00
- Pekerja Oh 3.0000 42,000.00 126,000.00
- Tukang Batu Oh 0.8500 65,000.00 55,250.00
- Kepala Tukang Oh 0.0850 75,000.00 6,375.00
- Mandor Oh 0.1500 80,000.00 12,000.00
Jumlah 761,279.00
Dibulatkan 761,279.00
C-08 1 M' Pembuatan Tiang Pancang (40x40) cm, Beton Tulang
- Pasir Urug M3 0.0190 175,300.00 3,330.70
- Pasir Beton M3 0.0940 255,400.00 24,007.60
- Koral Beton M3 0.1500 211,100.00 31,665.00
- Semen Portland Kg 60.5000 1,406.00 85,063.00
- Besi Beton Kg 45.0000 16,500.00 742,500.00
- Kawat Beton Kg 0.9000 27,700.00 24,930.00
- Kayu balok terentang M3 0.0320 2,640,000.00 84,480.00
- Paku Kg 0.1200 23,400.00 2,808.00
- Minyak Bekisting Ltr 0.0900 55,000.00 4,950.00
- Plamir Tembok Kg 0.2400 25,000.00 6,000.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Batu Oh 0.6700 65,000.00 43,550.00
- Kepala Tukang Oh 0.0670 75,000.00 5,025.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 1,104,309.30
Dibulatkan 1,104,309.00
C-09 1 M' Pembuatan Tiang Pancang (35x35) cm, Beton Tulang
- Pasir Urug M3 0.0160 175,300.00 2,804.80
- Pasir Beton M3 0.0800 255,400.00 20,432.00
- Koral Beton M3 0.1250 211,100.00 26,387.50
- Semen Portland Kg 49.0000 1,406.00 68,894.00
- Besi Beton Kg 34.5000 16,500.00 569,250.00
- Kawat Beton Kg 0.7000 27,700.00 19,390.00
- Kayu balok terentang M3 0.0270 2,640,000.00 71,280.00
- Paku Kg 0.1200 23,400.00 2,808.00
- Minyak Bekisting Ltr 0.0900 55,000.00 4,950.00
- Plamir Tembok Kg 0.2000 25,000.00 5,000.00
- Pekerja Oh 0.8000 42,000.00 33,600.00
- Tukang Batu Oh 0.5000 65,000.00 32,500.00
- Kepala Tukang Oh 0.0500 75,000.00 3,750.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 864,246.30
Dibulatkan 864,246.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
C-10 1 M' Pembuatan Tiang Pancang f 40 cm, Beton Tulang
- Pasir Urug M3 0.0149 175,300.00 2,614.60
- Pasir Beton M3 0.0738 255,400.00 18,845.97
- Koral Beton M3 0.1178 211,100.00 24,857.03
- Semen Portland Kg 47.4925 1,406.00 66,774.46
- Besi Beton Kg 45.0000 16,500.00 742,500.00
- Kawat Beton Kg 0.9000 27,700.00 24,930.00
- Kayu balok terentang M3 0.0320 2,640,000.00 84,480.00
- Paku Kg 0.1200 23,400.00 2,808.00
- Minyak Bekisting Ltr 0.0900 55,000.00 4,950.00
- Plamir Tembok Kg 0.2400 25,000.00 6,000.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Batu Oh 0.6700 65,000.00 43,550.00
- Kepala Tukang Oh 0.0670 75,000.00 5,025.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 1,073,335.05
Dibulatkan 1,073,335.00
C-11 1 M' Memancang Tiang Pancang Beton Tulang
- Crawler crane lengkap jam 0.1170 1,078,774.00 126,216.56
- Pekerja Oh 0.0400 42,000.00 1,680.00
- Mandor Oh 0.0020 80,000.00 160.00
Jumlah 128,056.56
Dibulatkan 128,057.00
C-12 1 Buah Memotong Tiang Pancang (40x40) cm Beton Tulang
- Pekerja jam 3.3200 42,000.00 139,440.00
- Kepala Tukang jam 0.0700 75,000.00 5,250.00
- Mandor jam 0.2000 80,000.00 16,000.00
- Alat bantu lot 0.3500 160,690.00 56,241.50
Jumlah 216,931.50
Dibulatkan 216,932.00
C-13 1 M' Menyambung Tiang Pancang Beton Bertulang
- Besi pelat kg 18.3700 14,100.00 259,017.00
- Besi beton kg 6.06 16,500.00 99,990.00
- Kawat las kg 2.20 23,600.00 51,920.00
- Tukang las org 1.00 65,000.00 65,000.00
- Pembantu tukang las org 2.0000 42,000.00 84,000.00
- Mandor org 0.2000 80,000.00 16,000.00
- Mesin las jam 2.0000 26,325.00 52,650.00
Jumlah 628,577.00
Dibulatkan 628,577.00
D. ANALISA HARGA SATUAN PEKERJAAN BETON
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
D-01 1 M3 Membuat Beton Tumbuk adk 1pc:3ps:5kr
- Semen Portland Kg 218.0000 1,406.00 306,508.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Batu Pecah Mesin 2/3 M3 0.8700 211,100.00 183,657.00
- Pekerja Oh 1.6500 42,000.00 69,300.00
- Tukang Batu Oh 0.2500 65,000.00 16,250.00
- Kepala Tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.0800 80,000.00 6,400.00
Jumlah 716,798.00
Dibulatkan 716,798.00
D-02 1 M3 Membuat Beton Tumbuk adk 1pc:3ps:6kr
- Semen Portland Kg 197.0000 1,406.00 276,982.00
- Pasir Beton M3 0.4700 255,400.00 120,038.00
- Batu Pecah Mesin 2/3 M3 0.9400 211,100.00 198,434.00
- Pekerja Oh 1.6500 42,000.00 69,300.00
- Tukang Batu Oh 0.2500 65,000.00 16,250.00
- Kepala Tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.0800 80,000.00 6,400.00
Jumlah 689,279.00
Dibulatkan 689,279.00
D-03 1 M3 Membuat Beton Tumbuk 1pc:2ps:3kr
- Semen Portland Kg 336.0000 1,406.00 472,416.00
- Pasir Beton M3 0.5400 255,400.00 137,916.00
- Batu Pecah Mesin 2/3 M3 0.8100 211,100.00 170,991.00
- Pekerja Oh 2.0000 42,000.00 84,000.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Kepala Tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 1.0000 80,000.00 80,000.00
Jumlah 970,698.00
Dibulatkan 970,698.00
D-04 1 M3 Membuat Tiang Pancang Beton Prestressed
- Semen Portland Kg 440.0000 1,406.00 618,640.00
- Pasir Beton M3 0.5000 255,400.00 127,700.00
- Batu Pecah Mesin 2/3 M3 0.8000 211,100.00 168,880.00
- Rapidrant Gln 2.4600 15,700.00 38,622.00
- Pekerja Oh 1.6500 42,000.00 69,300.00
- Tukang Batu Oh 0.2500 65,000.00 16,250.00
- Kepala Tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.0800 80,000.00 6,400.00
Jumlah 1,047,667.00
Dibulatkan 1,047,667.00
D-05 1 M3 Membuat Beton Tumbuk adk 1pc:2ps:4kr
- Semen Portland Kg 291.0000 1,406.00 409,146.00
- Pasir Beton M3 0.4700 255,400.00 120,038.00
- Batu Pecah Mesin 2/3 M3 0.9300 211,100.00 196,323.00
- Pekerja Oh 2.0000 42,000.00 84,000.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Kepala Tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 1.0000 80,000.00 80,000.00
Jumlah 914,882.00
Dibulatkan 914,882.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
D-06 1 M Memasang PVC Waterstop Lebar 200 mm
- Waterstop Lebar 200 mm M 1.0500 57,900.00 60,795.00
- Pekerja Oh 0.0500 42,000.00 2,100.00
- Tukang Batu Oh 0.0350 65,000.00 2,275.00
- Kepala Tukang Oh 0.0035 75,000.00 262.50
- Mandor Oh 0.0020 80,000.00 160.00
Jumlah 65,592.50
Dibulatkan 65,593.00
D-07 1 Kg Pembesian Dengan Besi Polos/ulir
- Besi Beton ( Polos / Ulir ) Kg 1.0500 16,500.00 17,325.00
- Kawat Beton Kg 0.0150 27,700.00 415.50
- Pekerja Oh 0.0070 42,000.00 294.00
- Tukang Besi Oh 0.0070 65,000.00 455.00
- Kepala Tukang Oh 0.0007 75,000.00 52.50
- Mandor Oh 0.0003 80,000.00 24.00
Jumlah 18,566.00
Dibulatkan 18,566.00
D-08 1 M2 Pasang Bekesting Untuk Pondasi
- Kayu papan terentang M3 0.0400 2,850,000.00 114,000.00
- Paku Biasa 2" - 5" Kg 0.3000 23,400.00 7,020.00
- Minyak Bekisting Ltr 55,000.00 -
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Kayu Oh 0.2600 65,000.00 16,900.00
- Kepala Tukang Oh 0.0260 75,000.00 1,950.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 152,870.00
Dibulatkan 152,870.00
D-09 1 M2 Pasang Bekisting Untuk Sloof
- Kayu papan terentang M3 0.0450 2,850,000.00 128,250.00
- Paku Biasa 2" - 5" Kg 0.3000 23,400.00 7,020.00
- Minyak Bekisting Ltr 55,000.00 -
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Kayu Oh 0.2600 65,000.00 16,900.00
- Kepala Tukang Oh 0.0260 75,000.00 1,950.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 167,120.00
Dibulatkan 167,120.00
D-10 1 M2 Pasang Bekesting Untuk Kolom
- Kayu papan terentang M3 0.0400 2,850,000.00 114,000.00
- Paku Biasa 2" - 5" Kg 0.4000 23,400.00 9,360.00
- Minyak Bekisting Ltr 55,000.00 -
- Kayu balok terentang M3 0.0150 2,640,000.00 39,600.00
- MultiPlek 9 mm 120 x 240 Lbr 0.3500 151,100.00 52,885.00
- Dolken -8-10/4m Btg 2.0000 28,000.00 56,000.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Kayu Oh 0.3300 65,000.00 21,450.00
- Kepala Tukang Oh 0.0330 75,000.00 2,475.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 308,850.00
Dibulatkan 308,850.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
D-11 1 M2 Pasang Bekesting Untuk Balok
- Kayu papan terentang M3 0.0400 2,850,000.00 114,000.00
- Paku Biasa 2" - 5" Kg 0.4000 23,400.00 9,360.00
- Minyak Bekisting Ltr 55,000.00 -
- Kayu balok terentang M3 0.0180 2,640,000.00 47,520.00
- MultiPlek 9 mm 120 x 240 Lbr 0.3500 151,100.00 52,885.00
- Dolken -8-10/4m Btg 2.0000 28,000.00 56,000.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Kayu Oh 0.3300 65,000.00 21,450.00
- Kepala Tukang Oh 0.0330 75,000.00 2,475.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 316,770.00
Dibulatkan 316,770.00
D-12 1 M2 Pasang Bekesting Untuk Lantai
- Kayu papan terentang M3 0.0400 2,850,000.00 114,000.00
- Paku Biasa 2" - 5" Kg 0.4000 23,400.00 9,360.00
- Minyak Bekisting Ltr 0.2000 55,000.00 11,000.00
- Kayu balok terentang M3 0.0150 2,640,000.00 39,600.00
- MultiPlek 9 mm 120 x 240 Lbr 0.3500 151,100.00 52,885.00
- Dolken -8-10/4m Btg 6.0000 28,000.00 168,000.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Kayu Oh 0.3300 65,000.00 21,450.00
- Kepala Tukang Oh 0.0330 75,000.00 2,475.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 431,850.00
Dibulatkan 431,850.00
D-13 1 M2 Pasang Bekesting Untuk Tangga
- Kayu papan terentang M3 0.0300 2,850,000.00 85,500.00
- Paku Biasa 2" - 5" Kg 0.4000 23,400.00 9,360.00
- Minyak Bekisting Ltr 0.1500 55,000.00 8,250.00
- Kayu balok terentang M3 0.0150 2,640,000.00 39,600.00
- MultiPlek 9 mm 120 x 240 Lbr 0.3500 151,100.00 52,885.00
- Dolken -8-10/4m Btg 2.0000 28,000.00 56,000.00
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Kayu Oh 0.3300 65,000.00 21,450.00
- Kepala Tukang Oh 0.0330 75,000.00 2,475.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 289,440.00
Dibulatkan 289,440.00
D-14 1 M3 Membuat Beton Cor Mutu K-225
- Semen Portland Kg 388.0000 1,406.00 545,528.00
- Pasir Beton m3 0.6500 255,400.00 166,010.00
- Koral Beton 2/3 M3 0.6500 211,100.00 137,215.00
- Air ltr 215.0000 3.00 645.00
- Pekerja Oh 6.0000 42,000.00 252,000.00
- Tukang Batu Oh 1.0000 65,000.00 65,000.00
- Kepala Tukang Oh 0.1000 75,000.00 7,500.00
- Mandor Oh 0.3000 80,000.00 24,000.00
Jumlah 1,197,898.00
Dibulatkan 1,197,898.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
D-15 1 M3 Membuat Beton Cor Mutu K-275
- Semen Portland Kg 400.0000 1,406.00 562,400.00
- Pasir Beton M3 0.4000 255,400.00 102,160.00
- Koral Beton 2/3 M3 0.8200 211,100.00 173,102.00
- Air ltr 215.0000 3.00 645.00
- Pekerja Oh 6.0000 42,000.00 252,000.00
- Tukang Batu Oh 1.0000 65,000.00 65,000.00
- Kepala Tukang Oh 0.1000 75,000.00 7,500.00
- Mandor Oh 0.3000 80,000.00 24,000.00
Jumlah 1,186,807.00
Dibulatkan 1,186,807.00
D-16 1 M3 Pondasi Beton Tulang (150 kg besi + bekisting)
- Kayu papan terentang M3 0.2000 2,850,000.00 570,000.00
- Paku Biasa 2" - 5" Kg 1.5000 23,400.00 35,100.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 150.0000 16,500.00 2,475,000.00
- Kawat Beton Kg 2.2500 27,700.00 62,325.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Pekerja Oh 3.9000 42,000.00 163,800.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 1.0400 65,000.00 67,600.00
- Tukang Besi Oh 1.0500 65,000.00 68,250.00
- Kepala Tukang Oh 0.2450 75,000.00 18,375.00
- Mandor Oh 0.1650 80,000.00 13,200.00
Jumlah 4,248,004.00
Dibulatkan 4,248,004.00
D-17 1 M3 Sloof Beton Tulang (200 kg besi + bekisting)
- Kayu papan terentang M3 0.2700 2,850,000.00 769,500.00
- Paku Biasa 2" - 5" Kg 2.0000 23,400.00 46,800.00
- Minyak Bekisting Ltr 0.6000 55,000.00 33,000.00
- Besi Beton Kg 200.0000 16,500.00 3,300,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Pekerja Oh 4.8500 42,000.00 203,700.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 1.5600 65,000.00 101,400.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.3310 75,000.00 24,825.00
- Mandor Oh 0.1700 80,000.00 13,600.00
Jumlah 5,441,279.00
Dibulatkan 5,441,279.00
D-17r1 1 M3 Sloof Beton Tulang 15/20 (150 kg besi + bekisting)
- Kayu papan terentang M3 0.2700 2,850,000.00 769,500.00
- Paku Biasa 2" - 5" Kg 2.0000 23,400.00 46,800.00
- Minyak Bekisting Ltr 0.6000 55,000.00 33,000.00
- Besi Beton Kg 150.0000 16,500.00 2,475,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Pekerja Oh 4.8500 42,000.00 203,700.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 1.5600 65,000.00 101,400.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.3310 75,000.00 24,825.00
- Mandor Oh 0.1700 80,000.00 13,600.00
Jumlah 4,616,279.00
Dibulatkan 4,616,279.00
D-17r2 1 M3 Sloof Beton Tulang 15/20 (180 kg besi + bekisting) 4dia. 12 ring 8-15
- Kayu papan terentang M3 0.2700 2,850,000.00 769,500.00
- Paku Biasa 2" - 5" Kg 2.0000 23,400.00 46,800.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 180.0000 16,500.00 2,970,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Pekerja Oh 4.8500 42,000.00 203,700.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 1.5600 65,000.00 101,400.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.3310 75,000.00 24,825.00
- Mandor Oh 0.1700 80,000.00 13,600.00
Jumlah 5,078,279.00
Dibulatkan 5,078,279.00
1 M3 Sloof Beton Tulang 20/30 (150 kg besi + bekisting) Struktur bertingkat 4dia.16 8-15
- Kayu papan terentang M3 0.2700 2,850,000.00 769,500.00
- Paku Biasa 2" - 5" Kg 2.0000 23,400.00 46,800.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 150.0000 16,500.00 2,475,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Pekerja Oh 4.8500 42,000.00 203,700.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 1.5600 65,000.00 101,400.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.3310 75,000.00 24,825.00
- Mandor Oh 0.1700 80,000.00 13,600.00
Jumlah 4,583,279.00
Dibulatkan 4,583,279.00
1 M3 Sloof Beton Tulang 20/30 (200 kg besi + bekisting) Struktur bertingkat 6dia.16 8-15
- Kayu papan terentang M3 0.2700 2,850,000.00 769,500.00
- Paku Biasa 2" - 5" Kg 2.0000 23,400.00 46,800.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 200.0000 16,500.00 3,300,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Pekerja Oh 4.8500 42,000.00 203,700.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 1.5600 65,000.00 101,400.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.3310 75,000.00 24,825.00
- Mandor Oh 0.1700 80,000.00 13,600.00
Jumlah 5,408,279.00
Dibulatkan 5,408,279.00
1 M3 Sloof Beton Tulang 20/40 (240 kg besi + bekisting) Struktur bertingkat
- Kayu papan terentang M3 0.2700 2,850,000.00 769,500.00
- Paku Biasa 2" - 5" Kg 2.0000 23,400.00 46,800.00
- Minyak Bekisting Ltr 0.6000 55,000.00 33,000.00
- Besi Beton Kg 240.0000 16,500.00 3,960,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Pekerja Oh 4.8500 42,000.00 203,700.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 1.5600 65,000.00 101,400.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.3310 75,000.00 24,825.00
- Mandor Oh 0.1700 80,000.00 13,600.00
Jumlah 6,101,279.00
Dibulatkan 6,101,279.00
D-18 1 M3 Kolom Beton Tulang (120 kg besi + bekisting)
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 2.0000 55,000.00 110,000.00
- Besi Beton Kg 120.0000 16,500.00 1,980,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- Plywood Tebal 9 mm Lbr 3.5000 235,000.00 822,500.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 6,646,664.00
Dibulatkan 6,646,664.00
D-18r 1 M3 Kolom Beton Tulang 20/20 (140 kg besi + bekisting) 4dia. 12 8-15
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 140.0000 16,500.00 2,310,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 6,573,014.00
Dibulatkan 6,573,014.00
1 M3 Kolom Beton Tulang 15/20 (180 kg besi + bekisting) 4dia.12 8-15
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 180.0000 16,500.00 2,970,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 7,233,014.00
Dibulatkan 7,233,014.00
1 M3 Kolom Beton Tulang Praktis 12/12 (175 kg besi + bekisting)
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 175.0000 16,500.00 2,887,500.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 2,640,000.00 -
- MultiPlek 9 mm 120 x 240 Lbr 151,100.00 -
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 6,225,664.00
Dibulatkan 6,225,664.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
1 M3 Kolom Beton Tulang Praktis 12/12 (210 kg besi + bekisting)
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 210.0000 16,500.00 3,465,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 2,640,000.00 -
- MultiPlek 9 mm 120 x 240 Lbr 151,100.00 -
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 6,803,164.00
Dibulatkan 6,803,164.00
1 M3 Kolom Beton Tulang Praktis 12/12 (260 kg besi + bekisting) 4dia.10 8-15
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 260.0000 16,500.00 4,290,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 2,640,000.00 -
- MultiPlek 9 mm 120 x 240 Lbr 151,100.00 -
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 7,628,164.00
Dibulatkan 7,628,164.00
1 M3 Kolom Beton Tulang 20/20 (210 kg besi + bekisting) Struktur bertingkat 4dia.16 8-15
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 210.0000 16,500.00 3,465,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 7,728,014.00
Dibulatkan 7,728,014.00
1 M3 Kolom Beton Tulang 20/30 (230 kg besi + bekisting) Struktur bertingkat 6dia.16 +2dia.12, 8-15
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 230.0000 16,500.00 3,795,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 8,058,014.00
Dibulatkan 8,058,014.00
1 M3 Kolom Beton Tulang 20/40 (250 kg besi + bekisting) Struktur bertingkat
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 2.0000 55,000.00 110,000.00
- Besi Beton Kg 250.0000 16,500.00 4,125,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 8,498,014.00
Dibulatkan 8,498,014.00
1 M3 Kolom Beton Tulang 30/30 (175 kg besi + bekisting) Struktur bertingkat 8dia.16, 8-15
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 175.0000 16,500.00 2,887,500.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 7,150,514.00
Dibulatkan 7,150,514.00
1 M3 Kolom Beton Tulang 30/30 (210 kg besi + bekisting) Struktur bertingkat 10dia.16, 8-15
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 210.0000 16,500.00 3,465,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 7,728,014.00
Dibulatkan 7,728,014.00
1 M3 Kolom Beton Tulang 30/40 (200 kg besi + bekisting) Struktur bertingkat
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 2.0000 55,000.00 110,000.00
- Besi Beton Kg 200.0000 16,500.00 3,300,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 7,673,014.00
Dibulatkan 7,673,014.00
D-19 1 M3 Kolom Beton Tulang (140 kg besi + bekisting)
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 2.0000 55,000.00 110,000.00
- Besi Beton Kg 140.0000 16,500.00 2,310,000.00
- Kawat Beton Kg 2.1000 27,700.00 58,170.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 6,691,324.00
Dibulatkan 6,691,324.00
D-20 1 M3 Kolom Beton Tulang (150 kg besi + bekisting)
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 2.0000 55,000.00 110,000.00
- Besi Beton Kg 150.0000 16,500.00 2,475,000.00
- Kawat Beton Kg 2.4000 27,700.00 66,480.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 6,864,634.00
Dibulatkan 6,864,634.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
D-21 1 M3 Kolom Beton Tulang (180 kg besi + bekisting)
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 2.0000 55,000.00 110,000.00
- Besi Beton Kg 180.0000 16,500.00 2,970,000.00
- Kawat Beton Kg 2.7000 27,700.00 74,790.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 7,367,944.00
Dibulatkan 7,367,944.00
D-22 1 M3 Kolom Beton Tulang (200 kg besi + bekisting)
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 2.0000 55,000.00 110,000.00
- Besi Beton Kg 200.0000 16,500.00 3,300,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 7,706,254.00
Dibulatkan 7,706,254.00
D-23 1 M3 Kolom Beton Tulang (250 kg besi + bekisting)
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 2.0000 55,000.00 110,000.00
- Besi Beton Kg 250.0000 16,500.00 4,125,000.00
- Kawat Beton Kg 3.7500 27,700.00 103,875.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 8,552,029.00
Dibulatkan 8,552,029.00
D-24 1 M3 Kolom Beton Tulang (300 kg besi + bekisting)
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 2.0000 55,000.00 110,000.00
- Besi Beton Kg 300.0000 16,500.00 4,950,000.00
- Kawat Beton Kg 4.5000 27,700.00 124,650.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1500 2,640,000.00 396,000.00
- MultiPlek 9 mm 120 x 240 Lbr 3.5000 151,100.00 528,850.00
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 9,397,804.00
Dibulatkan 9,397,804.00
D-25 1 M3 Balok Beton Tulang (120 kg besi + bekisting)
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 1.6000 55,000.00 88,000.00
- Besi Beton Kg 120.0000 16,500.00 1,980,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 5,693,859.00
Dibulatkan 5,693,859.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
D-26 1 M3 Balok Beton Tulang 15/20 (150 kg besi + bekisting)
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 1.6000 55,000.00 88,000.00
- Besi Beton Kg 150.0000 16,500.00 2,475,000.00
- Kawat Beton Kg 2.2500 27,700.00 62,325.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 6,201,324.00
Dibulatkan 6,201,324.00
D-26 1 M3 Balok Beton Tulang 15/20 (180 kg besi + bekisting) 4dia. 12, 8-15
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 180.0000 16,500.00 2,970,000.00
- Kawat Beton Kg 2.2500 27,700.00 62,325.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 6,608,324.00
Dibulatkan 6,608,324.00
1 M3 Balok Beton Tulang 15/20 sofi-sofi, ring balk + balok poratl (180 kg besi + bekisting) 4dia. 12, 8-15
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 180.0000 16,500.00 2,970,000.00
- Kawat Beton Kg 2.2500 27,700.00 62,325.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 6,608,324.00
Dibulatkan 6,608,324.00
1 M3 Balok Beton Tulang 15/30 (190 kg besi + bekisting) Struktur bertingkat 4dia. 16, 8-15
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 190.0000 16,500.00 3,135,000.00
- Kawat Beton Kg 2.2500 27,700.00 62,325.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 6,773,324.00
Dibulatkan 6,773,324.00
D-27 1 M3 Balok Beton Tulang 20/40 (200 kg besi + bekisting) Struktur bertingkat 7dia.16+2dia.12, 8-15
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 200.0000 16,500.00 3,300,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 6,959,099.00
Dibulatkan 6,959,099.00
1 M3 Balok Beton Tulang 20/30 (200 kg besi + bekisting) Struktur bertingkat 6dia. 16, 8-15
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 200.0000 16,500.00 3,300,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 6,959,099.00
Dibulatkan 6,959,099.00
1 M3 Balok Beton Tulang 20/30 (175 kg besi + bekisting) Struktur bertingkat 5dia. 16, 8-15
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 55,000.00 -
Besi Beton Kg 175.0000 16,500.00 2,887,500.00
- Kawat Beton Kg 3.0000 55,000.00 165,000.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
Jumlah 6,628,499.00
Dibulatkan 6,628,499.00
1 M3 Balok Beton Tulang 25/55 (140 kg besi + bekisting) Struktur bertingkat 8dia.16 +2dia.12, 8-15
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 140.0000 16,500.00 2,310,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 5,969,099.00
Dibulatkan 5,969,099.00
1 M3 Balok Beton Tulang 30/60 (110 kg besi + bekisting) Struktur bertingkat 8dia.16 +2dia.12, 8-15
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 110.0000 16,500.00 1,815,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 5,474,099.00
Dibulatkan 5,474,099.00
1 M3 Balok Beton Lintel 11/11 (300 kg besi + bekisting) 4dia.10 8-15
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 300.0000 16,500.00 4,950,000.00
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 2,640,000.00 -
- MultiPlek 9 mm 120 x 240 Lbr 151,100.00 -
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 8,288,164.00
Dibulatkan 8,288,164.00
1 M3 Balok Beton Lintel 11/15 (234 kg besi + bekisting) 4dia.10 8-15
- Kayu papan terentang M3 0.4000 2,850,000.00 1,140,000.00
- Paku Biasa 2" - 5" Kg 4.0000 23,400.00 93,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 234.0000 16,500.00 3,861,000.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
- Kawat Beton Kg 1.8000 27,700.00 49,860.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 2,640,000.00 -
- MultiPlek 9 mm 120 x 240 Lbr 151,100.00 -
- Dolken -8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 42,000.00 306,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 3.3000 65,000.00 214,500.00
- Tukang Besi Oh 2.1000 65,000.00 136,500.00
- Kepala Tukang Oh 0.5700 75,000.00 42,750.00
- Mandor Oh 0.2500 80,000.00 20,000.00
Jumlah 7,199,164.00
Dibulatkan 7,199,164.00
D-28 1 M3 Balok Beton Tulang (230 kg besi + bekisting)
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 1.6000 55,000.00 88,000.00
- Besi Beton Kg 230.0000 16,500.00 3,795,000.00
- Kawat Beton Kg 3.4500 27,700.00 95,565.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1400 2,640,000.00 369,600.00
- MultiPlek 9 mm 120 x 240 Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 16.0000 28,000.00 448,000.00
- Pekerja Oh 5.9600 42,000.00 250,320.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.8000 65,000.00 182,000.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4550 75,000.00 34,125.00
- Mandor Oh 0.2080 80,000.00 16,640.00
Jumlah 7,554,564.00
Dibulatkan 7,554,564.00
D-29 1 M3 Tangga Beton Tulang (200 kg besi + bekisting)
- Kayu papan terentang M3 0.2500 2,850,000.00 712,500.00
- Paku Biasa 2" - 5" Kg 3.0000 23,400.00 70,200.00
- Minyak Bekisting Ltr 1.2000 55,000.00 66,000.00
- Besi Beton Kg 200.0000 16,500.00 3,300,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1050 2,640,000.00 277,200.00
- Plywood Tebal 9 mm Lbr 2.5000 151,100.00 377,750.00
- Dolken -8-10/4m Btg 14.0000 28,000.00 392,000.00
- Pekerja Oh 5.6000 42,000.00 235,200.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.3000 65,000.00 149,500.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.4050 75,000.00 30,375.00
- Mandor Oh 0.2020 80,000.00 16,160.00
Jumlah 6,575,339.00
Dibulatkan 6,575,339.00
D-30 1 M3 Pelat Lantai Beton Tulang T= 10 cm (90 kg besi + bekisting)
- Beton tulang ad. 1Pc : 2Ps : 3Kr M3 1.0000 914,882.00 914,882.00
- Pasang Bekisting untuk lantai M2 10.0000 431,850.00 4,318,500.00
- Besi Beton Polos Kg 90.0000 18,566.00 1,670,940.00
Jumlah 6,904,322.00
Dibulatkan 6,904,322.00
1 M3 Lisplang Beton Tulang T= 8 cm (77,5 kg besi + bekisting)
- Beton tulang ad. 1Pc : 2Ps : 3Kr M3 1.0000 914,882.00 914,882.00
- Pasang Bekisting untuk lantai M2 10.0000 431,850.00 4,318,500.00
- Besi Beton Polos Kg 77.5000 18,566.00 1,438,865.00
Jumlah 6,672,247.00
Dibulatkan 6,672,247.00
D-31 1 M3 Pelat Lantai Beton Tulang T= 12 cm (110 kg besi + bekisting) dia.8-12,5
- Beton bertulang ad. 1Pc : 2Ps : 3Kr M3 1.0000 914,882.00 914,882.00
- Pasang Bekisting untuk lantai M2 8.3300 431,850.00 3,597,310.50
- Besi Beton Polos Kg 110.0000 18,566.00 2,042,260.00
Jumlah 6,554,452.50
Dibulatkan 6,554,453.00
1 M3 Pelat Lantai Beton Tulang T= 12 cm (130 kg besi + bekisting) dia.10-20
- Beton bertulang ad. 1Pc : 2Ps : 3Kr M3 1.0000 914,882.00 914,882.00
- Pasang Bekisting untuk lantai M2 8.3300 431,850.00 3,597,310.50
- Besi Beton Polos Kg 130.0000 18,566.00 2,413,580.00
Jumlah 6,925,772.50
Dibulatkan 6,925,773.00
D-32 1 M3 Pelat Lantai Beton Tulang T= 12 cm (130 kg besi + bekisting)
- Beton bertulang ad. 1Pc : 2Ps : 3Kr M3 1.0000 914,882.00 914,882.00
- Pasang Bekisting untuk lantai M2 8.3300 431,850.00 3,597,310.50
- Besi Beton Polos Kg 130.0000 18,566.00 2,413,580.00
Jumlah 6,925,772.50
Dibulatkan 6,925,773.00
D-33 1 M3 Pelat Lantai Beton Tulang T= 15 cm (90 kg besi + bekisting)
- Beton bertulang ad. 1Pc : 2Ps : 3Kr M3 1.0000 914,882.00 914,882.00
- Pasang Bekisting untuk lantai M2 6.6700 431,850.00 2,880,439.50
- Besi Beton Polos Kg 90.0000 18,566.00 1,670,940.00
Jumlah 5,466,261.50
Dibulatkan 5,466,262.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
D-34 1 M3 Pelat Lantai Beton Tulang T= 15 cm (115 kg besi + bekisting)
- Beton bertulang ad. 1Pc : 2Ps : 3Kr M3 1.0000 914,882.00 914,882.00
- Pasang Bekisting untuk lantai M2 6.6700 431,850.00 2,880,439.50
- Besi Beton Polos Kg 115.0000 18,566.00 2,135,090.00
Jumlah 5,930,411.50
Dibulatkan 5,930,412.00
D-35 1 M' Kolom Praktis Beton Tulang (11x11) cm
- Kayu papan terentang M3 0.0020 2,850,000.00 5,700.00
- Paku Biasa 2" - 5" Kg 0.0100 23,400.00 234.00
- Besi Beton Polos Kg 3.0000 16,500.00 49,500.00
- Kawat Beton Kg 0.0450 27,700.00 1,246.50
- Semen Portland Kg 4.0000 1,406.00 5,624.00
- Pasir Beton M3 0.0060 255,400.00 1,532.40
- Koral Beton M3 0.0090 211,100.00 1,899.90
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang Batu Oh 0.0200 65,000.00 1,300.00
- Tukang Kayu Oh 0.0200 65,000.00 1,300.00
- Tukang Besi Oh 0.0200 65,000.00 1,300.00
- Kepala Tukang Oh 0.0060 75,000.00 450.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 72,846.80
Dibulatkan 72,847.00
D-36 1 M' Ring Balok Beton Tulang (10x15) cm
- Kayu papan terentang M3 0.0030 2,850,000.00 8,550.00
- Paku Biasa 2" - 5" Kg 0.0200 23,400.00 468.00
- Besi Beton Polos Kg 3.6000 16,500.00 59,400.00
- Kawat Beton Kg 0.0500 27,700.00 1,385.00
- Semen Portland Kg 5.5000 1,406.00 7,733.00
- Pasir Beton M3 0.0090 255,400.00 2,298.60
- Koral Beton M3 0.0150 211,100.00 3,166.50
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Batu Oh 0.0330 65,000.00 2,145.00
- Tukang Kayu Oh 0.0330 65,000.00 2,145.00
- Tukang Besi Oh 0.0330 65,000.00 2,145.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 94,786.10
Dibulatkan 94,786.00
D-37 1 M2 Pasang Bekesting Untuk Dinding
- Kayu papan terentang M3 0.0300 2,850,000.00 85,500.00
- Paku Biasa 2" - 5" Kg 0.4000 1,406.00 562.40
- Minyak Bekisting Ltr 0.2000 55,000.00 11,000.00
- Kayu balok terentang M3 0.0200 2,640,000.00 52,800.00
- Plywood Tebal 9 mm Lbr 0.3500 151,100.00 52,885.00
- Dolken -8-10/4m Btg 3.0000 28,000.00 84,000.00
- Formite/spacer Buah 4.0000 2,500.00 10,000.00
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Kayu Oh 0.0330 65,000.00 2,145.00
- Kepala Tukang Oh 0.0330 75,000.00 2,475.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 315,287.40
Dibulatkan 315,287.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
D-38 1 M3 Pelat Beton Tulang (150 kg besi + bekisting)
- Kayu papan terentang M3 0.3200 2,850,000.00 912,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 1.6000 55,000.00 88,000.00
- Besi Beton Kg 150.0000 16,500.00 2,475,000.00
- Kawat Beton Kg 2.2500 27,700.00 62,325.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1200 2,640,000.00 316,800.00
- Plywood Tebal 9 mm Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 32.0000 28,000.00 896,000.00
- Pekerja Oh 5.3000 42,000.00 222,600.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 1.3000 65,000.00 84,500.00
- Tukang Besi Oh 1.0500 65,000.00 68,250.00
- Kepala Tukang Oh 0.2650 75,000.00 19,875.00
- Mandor Oh 0.2650 80,000.00 21,200.00
Jumlah 6,438,864.00
Dibulatkan 6,438,864.00
D-39 1 M3 Dinding Beton Tulang (150 kg besi + bekisting)
- Kayu papan terentang M3 0.2400 2,850,000.00 684,000.00
- Paku Biasa 2" - 5" Kg 3.2000 23,400.00 74,880.00
- Minyak Bekisting Ltr 1.6000 55,000.00 88,000.00
- Besi Beton Kg 150.0000 16,500.00 2,475,000.00
- Kawat Beton Kg 2.2500 27,700.00 62,325.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
- Kayu Balok Terentang M3 0.1600 2,640,000.00 422,400.00
- Plywood Tebal 9 mm Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 24.0000 28,000.00 672,000.00
- Pekerja Oh 5.6000 42,000.00 235,200.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 2.6400 65,000.00 171,600.00
- Tukang Besi Oh 1.0500 65,000.00 68,250.00
- Kepala Tukang Oh 0.4000 75,000.00 30,000.00
- Mandor Oh 0.1930 80,000.00 15,440.00
Jumlah 6,196,529.00
Dibulatkan 6,196,529.00
D-40 1 M3 Dinding Beton Tulang (200 kg besi + bekisting)
- Kayu papan terentang M3 0.2500 2,850,000.00 712,500.00
- Paku Biasa 2" - 5" Kg 3.0000 23,400.00 70,200.00
- Minyak Bekisting Ltr 1.2000 55,000.00 66,000.00
- Besi Beton Kg 200.0000 16,500.00 3,300,000.00
- Kawat Beton Kg 3.0000 27,700.00 83,100.00
- Semen Portland Kg 323.0000 1,406.00 454,138.00
- Pasir Beton M3 0.5200 255,400.00 132,808.00
- Koral Beton 2/3 M3 0.7800 211,100.00 164,658.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
- Kayu Balok Terentang M3 0.1050 2,640,000.00 277,200.00
- Plywood Tebal 9 mm Lbr 2.8000 151,100.00 423,080.00
- Dolken -8-10/4m Btg 14.0000 28,000.00 392,000.00
- Pekerja Oh 5.6500 42,000.00 237,300.00
- Tukang Batu Oh 0.3500 65,000.00 22,750.00
- Tukang Kayu Oh 1.5600 65,000.00 101,400.00
- Tukang Besi Oh 1.4000 65,000.00 91,000.00
- Kepala Tukang Oh 0.3230 75,000.00 24,225.00
- Mandor Oh 0.2830 80,000.00 22,640.00
Jumlah 6,574,999.00
Dibulatkan 6,574,999.00
D-41 1 M3 Membuat Beton Cor Mutu K-300
- Semen Portland Kg 413.0000 1,406.00 580,678.00
- Pasir Beton M3 0.4256 255,400.00 108,704.63
- Koral Beton 2/3 M3 0.6807 211,100.00 143,688.73
- Pekerja Oh 1.6500 42,000.00 69,300.00
- Tukang Batu Oh 0.2750 65,000.00 17,875.00
- Kepala Tukang Oh 0.0280 75,000.00 2,100.00
- Mandor Oh 0.0830 80,000.00 6,640.00
Jumlah 928,986.36
Dibulatkan 928,986.00
D-42 1 M3 Membuat Beton Cor Mutu K-200
- Semen Portland Kg 352.0000 1,406.00 494,912.00
- Pasir Beton M3 0.4569 255,400.00 116,685.88
- Koral Beton 2/3 M3 0.6873 211,100.00 145,096.07
- Pekerja Oh 1.6500 42,000.00 69,300.00
- Tukang Batu Oh 0.2750 65,000.00 17,875.00
- Kepala Tukang Oh 0.0280 75,000.00 2,100.00
- Mandor Oh 0.0830 80,000.00 6,640.00
Jumlah 852,608.94
Dibulatkan 852,609.00
D-43 1 M3 Membuat Beton Cor Mutu K-250
- Semen Portland Kg 384.0000 1,406.00 539,904.00
- Pasir Beton M3 0.4325 255,400.00 110,460.50
- Koral Beton 2/3 M3 0.6927 211,100.00 146,221.93
- Pekerja Oh 1.6500 42,000.00 69,300.00
- Tukang Batu Oh 0.2750 65,000.00 17,875.00
- Kepala Tukang Oh 0.0280 75,000.00 2,100.00
- Mandor Oh 0.0830 80,000.00 6,640.00
Jumlah 892,501.43
Dibulatkan 892,501.00
E. ANALISA HARGA SATUAN PEKERJAAN DINDING
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-01 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 3ps
- Bata Merah Bh 140.0000 775.00 108,500.00
- Semen Portland Kg 32.9500 1,406.00 46,327.70
- Pasir Pasang M3 0.0910 233,400.00 21,239.40
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 220,267.10
Dibulatkan 220,267.00
E-02 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 4ps
- Bata Merah Bh 140.0000 775.00 108,500.00
- Semen Portland Kg 26.5500 1,406.00 37,329.30
- Pasir Pasang M3 0.0930 233,400.00 21,706.20
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 211,735.50
Dibulatkan 211,736.00
E-03 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 5ps
- Bata Merah Bh 140.0000 775.00 108,500.00
- Semen Portland Kg 22.2000 1,406.00 31,213.20
- Pasir Pasang M3 0.1020 233,400.00 23,806.80
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 207,720.00
Dibulatkan 207,720.00
E-04 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 3ps
- Bata Merah Bh 70.0000 775.00 54,250.00
- Semen Portland Kg 14.3700 1,406.00 20,204.22
- Pasir Pasang M3 0.0400 233,400.00 9,336.00
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 105,680.22
Dibulatkan 105,680.00
E-05 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 4ps
- Bata Merah Bh 70.0000 775.00 54,250.00
- Semen Portland Kg 11.5000 1,406.00 16,169.00
- Pasir Pasang M3 0.0430 233,400.00 10,036.20
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 102,345.20
Dibulatkan 102,345.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-06 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 5ps
- Bata Merah Bh 70.0000 775.00 54,250.00
- Semen Portland Kg 9.6800 1,406.00 13,610.08
- Pasir Pasang M3 0.0450 233,400.00 10,503.00
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 100,253.08
Dibulatkan 100,253.00
E-07 1 M2 Pasang Dinding Roster Beton 20 x 20 adk 1pc : 3ps
- Roster / Terawang Bh 36.0000 14,800.00 532,800.00
- Semen Portland Kg 12.8000 1,406.00 17,996.80
- Pasir Pasang M3 0.0350 233,400.00 8,169.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 580,015.80
Dibulatkan 580,016.00
E-08 1 M2 Pasang Dinding Roster Beton 20 x 20 adk 1pc : 4ps
- Roster / Terawang Bh 36.0000 14,800.00 532,800.00
- Semen Portland Kg 11.0000 1,406.00 15,466.00
- Pasir Pasang M3 0.0350 233,400.00 8,169.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 577,485.00
Dibulatkan 577,485.00
E-09 1 M2 Pasang Dinding Roster/terawng (12 x 11 x 24) cm
- Roster / Terawang Bh 36.0000 14,800.00 532,800.00
- Semen Portland Kg 12.8000 1,406.00 17,996.80
- Pasir Pasang M3 0.0350 233,400.00 8,169.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 580,015.80
Dibulatkan 580,016.00
E-10 1 M2 Pasang Dinding Batako Besar Pres uk. 8x20x30 adk. 1pc:4ps
- Batako bh 13.0000 2,400.00 31,200.00
- PC kg 12.0000 1,406.00 16,872.00
- Pasir Pasang M3 0.0380 233,400.00 8,869.20
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 46,791.20
Dibulatkan 46,791.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-11 1 M2 Pasang Dinding hollowblock (HB-20)
- HB-20 Bh 12.5000 5,000.00 62,500.00
- PC (50 kg) Kg 13.5000 1,406.00 18,981.00
- Pasir Pasang m3 0.0480 233,400.00 11,203.20
- Besi angkur f 8 mm Kg 1.9500 16,500.00 32,175.00
- Pekerja Oh 0.3500 42,000.00 14,700.00
- Tukang Batu Oh 0.1500 65,000.00 9,750.00
- Kepala Tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0170 80,000.00 1,360.00
Jumlah 151,794.20
Dibulatkan 151,794.00
E-12 1 M2 Pasang Dinding hollowblock (HB-15)
- HB-15 Bh 12.5000 4,000.00 50,000.00
- PC (50 kg) Kg 10.4500 1,406.00 14,692.70
- Pasir Pasang m3 0.0380 233,400.00 8,869.20
- Besi angkur f 8 mm Kg 1.9500 16,500.00 32,175.00
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Batu Oh 0.1200 65,000.00 7,800.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 129,076.90
Dibulatkan 129,077.00
E-13 1 M2 Pasang Dinding hollowblock (HB-10)
- HB-10 Bh 12.5000 3,000.00 37,500.00
- PC (50 kg) Kg 7.5000 1,406.00 10,545.00
- Pasir Pasang m3 0.0270 233,400.00 6,301.80
- Besi angkur f 8 mm Kg 1.9500 16,500.00 32,175.00
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Batu Oh 0.1200 65,000.00 7,800.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 109,861.80
Dibulatkan 109,862.00
E-14 1 M2 Pasang Dinding Conblock (CB-20)
- CB-20 Bh 12.5000 5,000.00 62,500.00
- PC (50 kg) Kg 14.0500 1,406.00 19,754.30
- Pasir beton M3 0.0040 255,400.00 1,021.60
- Pasir Pasang M3 0.0420 233,400.00 9,802.80
- Besi angkur f 8 mm Kg 3.8700 16,500.00 63,855.00
- Paku Biasa 2" - 5" kg 0.0060 23,400.00 140.40
- Kayu terentang M3 0.0010 2,850,000.00 2,850.00
- Kawat beton kg 0.0300 27,700.00 831.00
- Koral beton M3 0.0050 211,100.00 1,055.50
- Pekerja Oh 0.3700 42,000.00 15,540.00
- Tukang Batu Oh 0.1570 65,000.00 10,205.00
- Tukang Besi Oh 0.0070 75,000.00 525.00
- Kepala Tukang Oh 0.0164 75,000.00 1,230.00
- Mandor Oh 0.0185 80,000.00 1,480.00
Jumlah 190,790.60
Dibulatkan 190,791.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-15 1 M2 Pasang Dinding Conblock (CB-15)
- CB-15 Bh 12.5000 4,000.00 50,000.00
- PC (50 kg) Kg 10.4600 1,406.00 14,706.76
- Pasir beton M3 0.0030 255,400.00 766.20
- Pasir Pasang M3 0.0320 233,400.00 7,468.80
- Besi angkur f 8 mm Kg 0.8700 16,500.00 14,355.00
- Paku Biasa 2" - 5" kg 0.0040 23,400.00 93.60
- Kayu terentang M3 0.0010 2,850,000.00 2,850.00
- Kawat beton kg 0.0200 27,700.00 554.00
- Koral beton M3 0.0040 211,100.00 844.40
- Pekerja Oh 0.3400 42,000.00 14,280.00
- Tukang Batu Oh 0.1300 65,000.00 8,450.00
- Tukang Besi Oh 0.0070 75,000.00 525.00
- Kepala Tukang Oh 0.0137 75,000.00 1,027.50
- Mandor Oh 0.0170 80,000.00 1,360.00
Jumlah 117,281.26
Dibulatkan 117,281.00
E-16 1 M2 Pasang Dinding Conblock (CB-10)
- CB-10 Bh 12.5000 3,000.00 37,500.00
- PC (50 kg) Kg 10.4600 1,406.00 14,706.76
- Pasir beton M3 0.0030 255,400.00 766.20
- Pasir Pasang M3 0.0320 233,400.00 7,468.80
- Besi angkur f 8 mm Kg 0.8700 16,500.00 14,355.00
- Paku Biasa 2" - 5" kg 0.0040 23,400.00 93.60
- Kayu terentang M3 0.0010 2,850,000.00 2,850.00
- Kawat beton kg 0.0200 27,700.00 554.00
- Koral beton M3 0.0040 211,100.00 844.40
- Pekerja Oh 0.3400 42,000.00 14,280.00
- Tukang Batu Oh 0.1300 65,000.00 8,450.00
- Tukang Besi Oh 0.0070 75,000.00 525.00
- Kepala Tukang Oh 0.0137 75,000.00 1,027.50
- Mandor Oh 0.0170 80,000.00 1,360.00
Jumlah 104,781.26
Dibulatkan 104,781.00
E-17 1 M2 Dinding Keramik Corak 10 x 20 cm Setara Mulia
- Keramik Corak 10 x 20 cm m2 1.0000 56,000.00 56,000.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 108,782.30
Dibulatkan 108,782.00
E-18 1 M2 Dinding Keramik polos 10 x 20 cm Setara Mulia
- Keramik 10 x 20 cm m2 1.0000 54,500.00 54,500.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 107,282.30
Dibulatkan 107,282.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-19 1 M2 Dinding Keramik corak 20 x 20 cm setara Mulia
- Keramik 20 x 20 cm m2 1.0000 62,500.00 62,500.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 115,282.30
Dibulatkan 115,282.00
E-20 1 M2 Dinding Keramik polos 20 x 20 cm Setara Mulia
- Keramik 20 x 20 cm m2 1.0000 54,500.00 54,500.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 107,282.30
Dibulatkan 107,282.00
E-21 1 M2 Dinding Keramik polos 20 x 25 cm Setara Mulia
- Keramik 20 x 25 cm m2 1.0000 54,500.00 54,500.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 107,282.30
Dibulatkan 107,282.00
E-22 1 M2 Dinding Keramik Corak 20 x 25 cm Setara Mulia
- Keramik corak 20 x 25 cm m2 1.0000 62,500.00 62,500.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 115,282.30
Dibulatkan 115,282.00
E-23 1 M2 Dinding Keramik Polos 30 x 30 cm Setara Mulia
- Keramik polos 30 x 30 cm m2 1.0000 53,000.00 53,000.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 105,782.30
Dibulatkan 105,782.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-24 1 M2 Dinding Keramik Corak 30 x 30 cm Setara Mulia
- Keramik corak 30 x 30 cm m2 1.0000 58,000.00 58,000.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 110,782.30
Dibulatkan 110,782.00
E-25 1 M2 Dinding Keramik Polos 40 x 40 cm Setara Mulia
- Keramik polos 40 x 40 cm m2 1.0000 56,800.00 56,800.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 109,582.30
Dibulatkan 109,582.00
E-26 1 M2 Dinding Keramik Corak 40 x 40 cm Setara Mulia
- Keramik corak 40 x 40 cm m2 1.0000 65,500.00 65,500.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 118,282.30
Dibulatkan 118,282.00
E-27 1 M2 Dinding Keramik Corak 10 x 20 cm Setara Roman
- Keramik Corak 10 x 20 cm m2 1.0000 72,200.00 72,200.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 124,982.30
Dibulatkan 124,982.00
E-28 1 M2 Dinding Keramik polos 10 x 20 cm Setara Roman
- Keramik 10 x 20 cm m2 1.0000 64,400.00 64,400.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 117,182.30
Dibulatkan 117,182.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-29 1 M2 Dinding Keramik corak 20 x 20 cm setara Roman
- Keramik 20 x 20 cm m2 1.0000 75,200.00 75,200.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 127,982.30
Dibulatkan 127,982.00
E-30 1 M2 Dinding Keramik polos 20 x 20 cm Setara Roman
- Keramik 20 x 20 cm m2 1.0000 64,400.00 64,400.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 117,182.30
Dibulatkan 117,182.00
E-31 1 M2 Dinding Keramik polos 20 x 25 cm Setara Roman
- Keramik 20 x 25 cm m2 1.0000 72,900.00 72,900.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 125,682.30
Dibulatkan 125,682.00
E-32 1 M2 Dinding Keramik Corak 20 x 25 cm Setara Roman
- Keramik corak 20 x 25 cm m2 1.0000 75,200.00 75,200.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 127,982.30
Dibulatkan 127,982.00
E-33 1 M2 Dinding Keramik Polos 30 x 30 cm Setara Roman
- Keramik polos 30 x 30 cm m2 1.0000 68,900.00 68,900.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 121,682.30
Dibulatkan 121,682.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-34 1 M2 Dinding Keramik Corak 30 x 30 cm Setara Roman
- Keramik corak 30 x 30 cm m2 1.0000 76,600.00 76,600.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 129,382.30
Dibulatkan 129,382.00
E-35 1 M2 Dinding Keramik Polos 40 x 40 cm Setara Roman
- Keramik polos 40 x 40 cm m2 1.0000 72,500.00 72,500.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 125,282.30
Dibulatkan 125,282.00
E-36 1 M2 Dinding Keramik Corak 40 x 40 cm Setara Roman
- Keramik corak 40 x 40 cm m2 1.0000 77,000.00 77,000.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 129,782.30
Dibulatkan 129,782.00
E-37 1 M2 Dinding Marmer
- Marmer M2 1.0200 550,000.00 561,000.00
- Paku pancing 60 x 230 Bh 2.0000 900.00 1,800.00
- Semen abu-abu Kg 12.4400 1,406.00 17,490.64
- Pasir pasang M3 0.0250 233,400.00 5,835.00
- Semen warna Kg 1.5000 15,700.00 23,550.00
- Pekerja Oh 0.7200 42,000.00 30,240.00
- Tukang batu Oh 0.6500 65,000.00 42,250.00
- Kepala tukang Oh 0.0650 75,000.00 4,875.00
- Mandor Oh 0.0350 80,000.00 2,800.00
Jumlah 689,840.64
Dibulatkan 689,841.00
E-38 1 M2 Dinding Batu Tempel Hitam
- Batu tempel hitam M2 1.0500 96,600.00 101,430.00
- Semen abu-abu Kg 11.7500 1,406.00 16,520.50
- Pasir pasang M3 0.0350 233,400.00 8,169.00
- Pekerja Oh 0.6200 42,000.00 26,040.00
- Tukang batu Oh 0.3500 65,000.00 22,750.00
- Kepala tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 179,934.50
Dibulatkan 179,935.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-39 1 M2 Dinding Porselen (11 x 11) cm
- Porselen M2 1.0000 63,300.00 63,300.00
- Semen abu-abu Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0180 233,400.00 4,201.20
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.1875 42,000.00 7,875.00
- Tukang batu Oh 0.3750 65,000.00 24,375.00
- Kepala tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0188 80,000.00 1,504.00
Jumlah 116,082.30
Dibulatkan 116,082.00
E-40 1 M2 Wall paper
- Wall paper M2 1.0500 55,700.00 58,485.00
- Lem Kg 0.2500 35,700.00 8,925.00
- Pekerja Oh 0.3500 42,000.00 14,700.00
- Tukang batu Oh 0.1750 65,000.00 11,375.00
- Kepala tukang Oh 0.0170 75,000.00 1,275.00
- Mandor Oh 0.0020 80,000.00 160.00
Jumlah 94,920.00
Dibulatkan 94,920.00
E-41 1 M2 Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kamper Medan
- Kayu Balok Kamper Medan M3 0.0280 5,692,600.00 159,392.80
- Paku Biasa 2" - 5" Kg 0.1500 23,800.00 3,570.00
- Lem Kayu Ltr 0.5600 23,900.00 13,384.00
- Teakwood 120 x 240 x 0,4 cm Lbr 0.8600 131,700.00 113,262.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang Kayu Oh 0.4500 65,000.00 29,250.00
- Kepala Tukang Oh 0.0450 75,000.00 3,375.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 329,173.80
Dibulatkan 329,174.00
E-42 1 M2 Dinding Pemisah Plywood Rangkap, Rangka Kayu Kamper Medan
- Kayu Balok Kamper Medan M3 0.0280 5,692,600.00 159,392.80
- Paku Biasa 2" - 5" Kg 0.1500 23,800.00 3,570.00
- Lem Kayu Ltr 0.5600 23,900.00 13,384.00
- Plywood 120 x 240 x 9 mm Lbr 0.8600 235,000.00 202,100.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang Kayu Oh 0.6000 65,000.00 39,000.00
- Kepala Tukang Oh 0.0600 75,000.00 4,500.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 431,146.80
Dibulatkan 431,147.00
E-43 1 M2 Dinding Pemisah Triplek 4 mm Rangkap, Rangka Kayu Kamper Medan
- Kayu Balok Kamper Medan M3 0.0280 5,692,600.00 159,392.80
- Paku Biasa 2" - 5" Kg 0.1500 23,800.00 3,570.00
- Lem Kayu Ltr 0.5600 23,900.00 13,384.00
- Triplek (120x240x0,4) cm Lbr 0.8600 64,400.00 55,384.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang Kayu Oh 0.6000 65,000.00 39,000.00
- Kepala Tukang Oh 0.0600 75,000.00 4,500.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 284,430.80
Dibulatkan 284,431.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-44 1 M2 Dinding Pemisah GRC t = 4 mm + rangka besi hollow
- Hollow 4/4 Zincromate Btg 0.4150 29,200.00 12,118.00
- Hollow 2/4 Zincromate Btg 0.1500 22,600.00 3,390.00
- GRC ( 120 x 240 x 4 ) mm Lbr 0.3640 67,500.00 24,570.00
- Paku GRC kg 0.1100 35,000.00 3,850.00
- Ramset / dina bolt Bh 4.0000 7,200.00 28,800.00
- Cotton plaster Bh 0.0720 23,900.00 1,720.80
- Compoun Zak 0.1250 75,000.00 9,375.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 92,048.80
Dibulatkan 92,049.00
E-44 1 M2 Dinding Pemisah Gypsum t = 4 mm + rangka besi hollow
- Hollow 4/4 Zincromate Btg 0.4150 29,200.00 12,118.00
- Hollow 2/4 Zincromate Btg 0.1500 22,600.00 3,390.00
- Gypsum Lbr 0.3640 79,800.00 29,047.20
- Paku GRC kg 0.1100 35,000.00 3,850.00
- Ramset / dina bolt Bh 4.0000 7,200.00 28,800.00
- Cotton plaster Bh 0.0720 23,900.00 1,720.80
- Compoun Zak 0.1250 75,000.00 9,375.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 96,526.00
Dibulatkan 96,526.00
E-45 1 M2 Dinding Pemisah Plywood t = 4 mm + rangka besi hollow
- Hollow 4/4 Zincromate Btg 0.4150 29,200.00 12,118.00
- Hollow 2/4 Zincromate Btg 0.1500 22,600.00 3,390.00
- Plywood 120 x 240, 9 mm Lbr 0.3640 235,000.00 85,540.00
- Paku kg 0.1100 23,800.00 2,618.00
- Ramset / dina bolt Bh 4.0000 7,200.00 28,800.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 140,691.00
Dibulatkan 140,691.00
E-46 1 M2 Dinding Pemisah teakwood t = 4 mm + rangka besi hollow
- Hollow 4/4 Zincromate Btg 0.4150 29,200.00 12,118.00
- Hollow 2/4 Zincromate Btg 0.1500 22,600.00 3,390.00
- Teakwood ( 120 x 240 x 4 ) mm Lbr 0.3640 131,700.00 47,938.80
- Paku kg 0.1100 23,800.00 2,618.00
- Ramset / dina bolt Bh 4.0000 7,200.00 28,800.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 103,089.80
Dibulatkan 103,090.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
E-47 1 M2 Pasang Dinding Glass Block 20 x 20 adk 1pc : 4ps
- Glass block 20 x 20 Bh 36.0000 22,000.00 792,000.00
- Semen Portland Kg 11.0000 1,406.00 15,466.00
- Pasir Pasang M3 0.0350 233,400.00 8,169.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 836,685.00
Dibulatkan 836,685.00
E-48 1 M2 Pasang Dinding anyaman bambu, rangka kayu
- Bilik bambu M2 1.5000 22,700.00 34,050.00
- Kayu kaso 5/7 M3 0.0140 3,356,800.00 46,995.20
- Paku Kg 0.0112 23,800.00 266.56
- List kayu 2/4 m3 0.0030 5,280,000.00 15,840.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Batu Oh 0.0500 65,000.00 3,250.00
- Kepala Tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0020 80,000.00 160.00
Jumlah 105,136.76
Dibulatkan 105,137.00
F. ANALISA HARGA SATUAN PEKERJAAN PLESTERAN
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
F-01 1 M2 Plesteran adk. 1pc : 2ps Tebal 15 mm
- Semen Portland Kg 8.5200 1,406.00 11,979.12
- Pasir Pasang M3 0.0170 233,400.00 3,967.80
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang Batu Oh 0.1500 65,000.00 9,750.00
- Kepala Tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 36,021.92
Dibulatkan 36,022.00
F-02 1 M2 Plesteran adk. 1pc : 3ps Tebal 15 mm
- Semen Portland Kg 6.4800 1,406.00 9,110.88
- Pasir Pasang M3 0.0190 233,400.00 4,434.60
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang Batu Oh 0.1500 65,000.00 9,750.00
- Kepala Tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 33,620.48
Dibulatkan 33,620.00
F-03 1 M2 Plesteran adk. 1pc : 4ps Tebal 15 mm
- Semen Portland Kg 5.2000 1,406.00 7,311.20
- Pasir Pasang M3 0.0200 233,400.00 4,668.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang Batu Oh 0.1500 65,000.00 9,750.00
- Kepala Tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 32,054.20
Dibulatkan 32,054.00
F-04 1 M2 Plesteran adk. 1pc : 3ps Tebal 20 mm
- Semen Portland Kg 10.8000 1,406.00 15,184.80
- Pasir Pasang M3 0.0260 233,400.00 6,068.40
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 47,253.20
Dibulatkan 47,253.00
F-05 1 M2 Plesteran adk. 1pc : 4ps Tebal 20 mm
- Semen Portland Kg 8.6800 1,406.00 12,204.08
- Pasir Pasang M3 0.0280 233,400.00 6,535.20
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 44,739.28
Dibulatkan 44,739.00
F-06 1 M2 Plesteran adk. 1pc:5ps tebal 20 mm
- Semen Portland Kg 7.2900 1,406.00 10,249.74
- Pasir Pasang M3 0.0260 233,400.00 6,068.40
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 42,318.14
Dibulatkan 42,318.00
1 M2 Plesteran adk. 1pc:5ps tebal 15 mm + Acian
- Semen Portland Kg 4.3200 1,406.00 6,073.92
- Pasir Pasang M3 0.0220 233,400.00 5,134.80
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang Batu Oh 0.1500 65,000.00 9,750.00
- Kepala Tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 31,283.72
Dibulatkan 31,284.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
F-07 1 M2 Berapen adk. 1pc : 5ps Tebal 15 mm
- Semen Portland Kg 5.6700 1,406.00 7,972.02
- Pasir Pasang M3 0.0230 233,400.00 5,368.20
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang Batu Oh 0.0700 65,000.00 4,550.00
- Kepala Tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 25,355.22
Dibulatkan 25,355.00
F-08 1 M2 Plesteran Beton adk. 1pc : 2ps Tebal 15 mm
- Semen Portland Kg 9.3000 1,406.00 13,075.80
- Pasir Pasang M3 0.0180 233,400.00 4,201.20
- Pekerja Oh 0.2600 42,000.00 10,920.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0130 80,000.00 1,040.00
Jumlah 43,737.00
Dibulatkan 43,737.00
F-09 1 M2 Plesteran Beton adk. 1pc : 3ps Tebal 15 mm
- Semen Portland Kg 7.0700 1,406.00 9,940.42
- Pasir Pasang M3 0.0210 233,400.00 4,901.40
- Pekerja Oh 0.2600 42,000.00 10,920.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0130 80,000.00 1,040.00
Jumlah 41,301.82
Dibulatkan 41,302.00
F-10 1 M2 Plesteran Skoning adk. 1pc : 2ps, tebal 10mm
- Semen Portland Kg 0.5000 1,406.00 703.00
- Pasir Pasang M3 0.0130 233,400.00 3,034.20
- Pekerja Oh 0.0800 42,000.00 3,360.00
- Tukang Batu Oh 0.4000 65,000.00 26,000.00
- Kepala Tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0040 80,000.00 320.00
Jumlah 36,417.20
Dibulatkan 36,417.00
F-11 1 M2 Acian Plesteran
- Semen Portland Kg 4.0000 1,406.00 5,624.00
- Pekerja Oh 0.1430 42,000.00 6,006.00
- Tukang batu Oh 0.1070 65,000.00 6,955.00
- Kepala Tukang Oh 0.0105 75,000.00 787.50
- Mandor Oh 0.0105 80,000.00 840.00
Jumlah 20,212.50
Dibulatkan 20,213.00
F-12 1 M2 Plesteran Siar adk. 1pc : 2ps batu belah
- Semen Portland Kg 6.3400 1,406.00 8,914.04
- Pasir Pasang M3 0.0120 233,400.00 2,800.80
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Batu Oh 0.1500 65,000.00 9,750.00
- Kepala Tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 36,389.84
Dibulatkan 36,390.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
F-13 1 M2 Plesteran Siar adk. 1pc : 2ps dinding bata merah
- Semen Portland Kg 4.3200 1,406.00 6,073.92
- Semen Portland M3 0.0160 233,400.00 3,734.40
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang Batu Oh 0.0700 65,000.00 4,550.00
- Kepala Tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 21,823.32
Dibulatkan 21,823.00
G. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
G-01 1 M2 Pasang Atap Genteng Palentong
- Genteng palentong Bh 25.0000 1,900.00 47,500.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.0750 65,000.00 4,875.00
- Kepala tukang Oh 0.0080 75,000.00 600.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 59,915.00
Dibulatkan 59,915.00
G-02 1 M2 Pasang Genteng Bubung Palentong
- Genteng bubung palentong Bh 5.0000 6,000.00 30,000.00
- Semen Portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0320 233,400.00 7,468.80
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Tukang kayu Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0020 80,000.00 160.00
Jumlah 80,176.80
Dibulatkan 80,177.00
G-03 1 M2 Pasang Roof Light Fibreglass ( 180 x 90 ) cm
- Roof light fibreglass Lbr 0.6000 100,000.00 60,000.00
- Paku biasa " - 1" Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0670 65,000.00 4,355.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 72,510.00
Dibulatkan 72,510.00
G-04 1 M2 Pasang Atap Asbes Gelombang ( 3,00 x 1,05 m ) x 4 mm
- Asbes gelombang Lbr 0.3500 80,000.00 28,000.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0700 65,000.00 4,550.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 42,371.00
Dibulatkan 42,371.00
G-05 1 M2 Pasang Atap Asbes Gelombang ( 2,70 x 1,05 m ) x 4 mm
- Asbes gelombang Lbr 0.4200 73,300.00 30,786.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0700 65,000.00 4,550.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 45,157.00
Dibulatkan 45,157.00
G-06 1 M2 Pasang Atap Asbes Gelombang ( 2,40 x 1,05 m ) x 4 mm
- Asbes gelombang Lbr 0.4400 65,900.00 28,996.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0670 65,000.00 4,355.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 43,172.00
Dibulatkan 43,172.00
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
G-07 1 M2 Pasang Atap Asbes Gelombang ( 2,10 x 1,05 m ) x 4 mm
- Asbes gelombang Lbr 0.5100 58,500.00 29,835.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0670 65,000.00 4,355.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 44,011.00
Dibulatkan 44,011.00
G-08 1 M2 Pasang Atap Asbes Gelombang ( 1,50 x 1,05 m ) x 4 mm
- Asbes gelombang Lbr 0.8000 42,300.00 33,840.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0670 65,000.00 4,355.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 48,016.00
Dibulatkan 48,016.00
G-09 1 M Pasang Nok Stel Gelombang 1,05 m
- Nok stel gelombang Lbr 2.1000 38,100.00 80,010.00
- Paku sekrup 3,5" Bh 6.0000 800.00 4,800.00
- Pekerja Oh 0.0840 42,000.00 3,528.00
- Tukang kayu Oh 0.1250 65,000.00 8,125.00
- Kepala tukang Oh 0.0130 75,000.00 975.00
- Mandor Oh 0.0040 80,000.00 320.00
Jumlah 97,758.00
Dibulatkan 97,758.00
G-10 1 M2 Pasang Atap Genteng Beton
- Genteng beton bh 11.0000 8,500.00 93,500.00
- Paku biasa 2" - 5" Kg 0.0300 23,400.00 702.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang kayu Oh 0.1000 65,000.00 6,500.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 110,652.00
Dibulatkan 110,652.00
G-11 1 M2 Pasang Atap Genteng Murando Natural
- Genteng murando natural bh 18.0000 2,700.00 48,600.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.0750 65,000.00 4,875.00
- Kepala tukang Oh 0.0080 75,000.00 600.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 61,015.00
Dibulatkan 61,015.00
G-12 1 M2 Pasang Atap Genteng Murando Glazur
- Genteng murando glazur bh 18.0000 4,000.00 72,000.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.0750 65,000.00 4,875.00
- Kepala tukang Oh 0.0080 75,000.00 600.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 84,415.00
Dibulatkan 84,415.00
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
G-13 1 M2 Pasang Atap Genteng Metal
- Genteng metal m2 1.0200 203,100.00 207,162.00
- Paku biasa 2" - 5" Kg 0.2000 23,400.00 4,680.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang kayu Oh 0.1000 65,000.00 6,500.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0010 80,000.00 80.00
Jumlah 227,572.00
Dibulatkan 227,572.00
G-14 1 M Pasang Nok Genteng Beton
- Nok genteng beton Bh 3.5000 10,500.00 36,750.00
- Paku biasa 2" - 5" Kg 0.0500 23,400.00 1,170.00
- Semen abu-abu Kg 10.8000 1,406.00 15,184.80
- Pasir pasang M3 0.0320 233,400.00 7,468.80
- Semen warna Kg 1.0000 15,700.00 15,700.00
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Tukang kayu Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 109,173.60
Dibulatkan 109,174.00
G-15 1 M Pasang Nok Genteng Metal
- Nok genteng metal Lbr 1.1000 138,500.00 152,350.00
- Paku biasa " - 1" Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang kayu Oh 0.1500 65,000.00 9,750.00
- Kepala tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0130 80,000.00 1,040.00
Jumlah 175,955.00
Dibulatkan 175,955.00
G-16 1 M2 Pasang Atap Seng Gelombang
- Seng gelombang 180x80, 5mm Lbr 0.7000 83,100.00 58,170.00
- Paku biasa " - 1" Kg 0.0200 23,800.00 476.00
- Pekerja Oh 0.1200 42,000.00 5,040.00
- Tukang kayu Oh 0.0600 65,000.00 3,900.00
- Kepala tukang Oh 0.0060 75,000.00 450.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 68,516.00
Dibulatkan 68,516.00
G-17 1 M2 Pasang Atap Nok Seng
- Seng plat 3" x 6" BJLS 30 Lbr 0.3000 37,500.00 11,250.00
- Paku biasa " - 1" Kg 0.0400 23,800.00 952.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.0700 65,000.00 4,550.00
- Kepala tukang Oh 0.0080 75,000.00 600.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 24,132.00
Dibulatkan 24,132.00
G-18 1 M2 Pasang Alluminium Foil / Sisalation
- Sisalation / alluminium foil M2 1.0500 19,600.00 20,580.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 31,145.00
Dibulatkan 31,145.00
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
G-19 1 M2 Pasang Atap Alluminium Natural
- Atap Alumunium Natural USR 26 Lbr 1.0500 140,600.00 147,630.00
- Paku hak panjang 15 cm Kg 0.0200 20,000.00 400.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.7500 65,000.00 48,750.00
- Kepala tukang Oh 0.0080 75,000.00 600.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 204,160.00
Dibulatkan 204,160.00
G-20 1 M2 Pasang Atap Alluminium warna
- Atap Alumunium Warna USR 26 Lbr 1.0500 164,700.00 172,935.00
- Paku hak panjang 15 cm Kg 0.0200 20,000.00 400.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.7500 65,000.00 48,750.00
- Kepala tukang Oh 0.0080 75,000.00 600.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 229,465.00
Dibulatkan 229,465.00
G-21 1 M2 Pasang Nok Alluminium
- Nok standar M2 1.2000 75,000.00 90,000.00
- Paku hak panjang 15 cm Kg 0.0400 20,000.00 800.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 1.0000 65,000.00 65,000.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 161,550.00
Dibulatkan 161,550.00
G-22 1 M' Pasang Lisplank GRC ukuran 30 cm
- GRC M2 0.3300 67,500.00 22,275.00
- Paku GRC kg 0.0500 35,000.00 1,750.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 43,125.00
Dibulatkan 43,125.00
G-21 1 M' Pasang Nok Pinggir
- Nok Genteng Pinggir M' 4.0000 4,000.00 16,000.00
- Paku biasa 2" - 5" Kg 0.0526 20,000.00 1,052.00
- Pekerja Oh 0.0840 42,000.00 3,528.00
- Tukang kayu Oh 0.1250 65,000.00 8,125.00
- Kepala tukang Oh 0.0130 75,000.00 975.00
- Mandor Oh 0.0040 80,000.00 320.00
Jumlah 30,000.00
Dibulatkan 30,000.00
H. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANGIT-LANGIT
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
H-01 1 M2 Langit-langit Asbes ( 1,00 x 1,00 ) m, tebal 5 mm
- Pelat asbes tebal 4 mm m2 1.1000 22,500.00 24,750.00
- Paku seng Kg 0.0100 23,800.00 238.00
- Pekerja Oh 0.0300 42,000.00 1,260.00
- Tukang kayu Oh 0.0700 65,000.00 4,550.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0015 80,000.00 120.00
Jumlah 31,443.00
Dibulatkan 31,443.00
H-02 1 M2 Langit-langit Asbes ( 1,00 x 1,00 ) m, tebal 3,5 mm
- Pelat asbes tebal 3,5 mm Lbr 1.1000 19,500.00 21,450.00
- Paku seng Kg 0.0100 23,800.00 238.00
- Pekerja Oh 0.0300 42,000.00 1,260.00
- Tukang kayu Oh 0.0700 65,000.00 4,550.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0015 80,000.00 120.00
Jumlah 28,143.00
Dibulatkan 28,143.00
H-03 1 M2 Langit-langit Akustik ( 60 x 120 ) cm
- Akustik 600 x 1200 Lbr 1.5000 132,800.00 199,200.00
- Paku Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang kayu Oh 0.1000 65,000.00 6,500.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 210,400.00
Dibulatkan 210,400.00
H-04 1 M2 Langit-langit Akustik ( 60 x 120 ) cm + Rangka Alluminium
- Profil Alluminium "T" M 3.6000 12,200.00 43,920.00
- Kawat f 4 mm Kg 0.1500 28,200.00 4,230.00
- Ramset / dina bolt Bh 1.0500 7,200.00 7,560.00
- Akustik 600 x 1200 Lbr 1.5000 132,800.00 199,200.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0500 75,000.00 3,750.00
- Mandor Oh 0.0075 80,000.00 600.00
Jumlah 298,060.00
Dibulatkan 298,060.00
H-05 1 M2 Langit-langit teakwood (60 x 120) cm, t = 4 mm + rangka kayu borneo super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Teakwood 120 cm x 240 cm x 0,4 cm Lbr 0.3900 131,700.00 51,363.00
- Pekerja Oh 0.2700 42,000.00 11,340.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 154,907.00
Dibulatkan 154,907.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
H-06 1 M2 Langit-langit Teakwood 3 mm + Rangka Kayu Borneo Super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Teakwood (120 x 240x 0,3) cm Lbr 0.3900 129,100.00 50,349.00
- Pekerja Oh 0.2700 42,000.00 11,340.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 153,893.00
Dibulatkan 153,893.00
H-07 1 M2 Langit-langit Triplek 4 mm + Rangka Kayu Borneo Super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,800.00 1,428.00
- Triplek 120 cm x 240 cm x 0,4 cm Lbr 0.3900 64,400.00 25,116.00
- Pekerja Oh 0.2700 42,000.00 11,340.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 128,684.00
Dibulatkan 128,684.00
H-08 1 M2 Langit-langit Gypsum Board, tebal 9 mm + rangka besi hollow
- Hollow 4/4 Zincromate Btg 0.4150 29,200.00 12,118.00
- Hollow 2/4 Zincromate Btg 0.1500 22,600.00 3,390.00
- Gypsum board ( 120 x 240 x 9 ) mm Lbr 0.3640 79,800.00 29,047.20
- Paku gypsum kg 0.1100 17,500.00 1,925.00
- Ramset / dina bolt Bh 4.0000 7,200.00 28,800.00
- Cotton plaster Bh 0.0720 15,000.00 1,080.00
- Compoun Zak 0.1250 75,000.00 9,375.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 93,960.20
Dibulatkan 93,960.00
H-09 1 M2 Langit-langit GRC t = 4 mm + rangka besi hollow
- Hollow 4/4 Zincromate Btg 0.4150 29,200.00 12,118.00
- Hollow 2/4 Zincromate Btg 0.1500 22,600.00 3,390.00
- GRC ( 120 x 240 x 4 ) mm Lbr 0.3640 67,500.00 24,570.00
- Paku GRC kg 0.1100 35,000.00 3,850.00
- Ramset / dina bolt Bh 4.0000 7,200.00 28,800.00
- Cotton plaster Bh 0.0720 15,000.00 1,080.00
- Compoun Zak 0.1250 75,000.00 9,375.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 91,408.00
Dibulatkan 91,408.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
H-10 1 M2 Langit-langit gypsum t = 9 mm + Rangka Kayu Borneo Super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,800.00 1,428.00
- Gypsum board ( 120 x 240 x 9 ) mm Lbr 0.3900 79,800.00 31,122.00
- Paku sekrup kg 0.1100 17,500.00 1,925.00
- Pekerja Oh 0.2700 42,000.00 11,340.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 136,615.00
Dibulatkan 136,615.00
H-11 1 M2 Langit-langit GRC t = 4 mm + Rangka Kayu Borneo Super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,800.00 1,428.00
- GRC ( 120 x 240 x 4 ) mm Lbr 0.3900 67,500.00 26,325.00
- Paku GRC kg 0.1100 35,000.00 3,850.00
- Pekerja Oh 0.2700 42,000.00 11,340.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 133,743.00
Dibulatkan 133,743.00
H-12 1 M List Langit-langit Kayu Profil 10 cm
- List Kayu profil M 1.0500 29,400.00 30,870.00
- Paku Kg 0.0100 23,800.00 238.00
- Pekerja Oh 0.0500 42,000.00 2,100.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 37,073.00
Dibulatkan 37,073.00
H-13 1 M List Langit-langit Gypsum 10 cm
- List gypsum M 1.0500 8,500.00 8,925.00
- Tepung gypsum Kg 0.1500 12,500.00 1,875.00
- Pekerja Oh 0.0500 42,000.00 2,100.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 16,765.00
Dibulatkan 16,765.00
H-12 1 M List Langit-langit Kayu 1/4 cm
- List Kayu profil M 1.0500 1,500.00 1,575.00
- Paku Kg 0.0100 23,800.00 238.00
- Pekerja Oh 0.0434 42,000.00 1,822.80
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 7,500.80
Dibulatkan 7,500.00
I. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN
DINDING
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
I-01 1 M2 Lantai Ubin Granito ukuran 40 x 40 cm Setara Essenza
- Granito 40 x 40 cm m2 1.0500 345,000.00 362,250.00
- Semen portland Kg 9.8000 1,406.00 13,778.80
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 1.3000 15,700.00 20,410.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 421,656.90
Dibulatkan 421,657.00
I-02 1 M2 Lantai Ubin Granito ukuran 30 x 30 cm Setara Essenza
- Granito 30 x 30 cm m2 1.0500 322,800.00 338,940.00
- Semen portland Kg 10.0000 1,406.00 14,060.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 1.5000 15,700.00 23,550.00
- Pekerja Oh 0.2600 42,000.00 10,920.00
- Tukang batu Oh 0.1250 65,000.00 8,125.00
- Kepala tukang Oh 0.0125 75,000.00 937.50
- Mandor Oh 0.0130 80,000.00 1,040.00
Jumlah 402,590.60
Dibulatkan 402,591.00
I-03 1 M Plint Ubin Granito ukuran 10 x 40 cm Setara Essenza
- Plint granito 10 x 40 cm Bh 2.6500 27,600.00 73,140.00
- Semen portland Kg 1.2000 1,406.00 1,687.20
- Pasir pasang M3 0.0030 233,400.00 700.20
- Semen warna Kg 0.1000 15,700.00 1,570.00
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang batu Oh 0.0300 65,000.00 1,950.00
- Kepala tukang Oh 0.0030 75,000.00 225.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 82,032.40
Dibulatkan 82,032.00
I-04 1 M Plint Ubin Granito ukuran 10 x 30 cm Setara Essenza
- Plint granito 10 x 30 cm Bh 3.3300 25,900.00 86,247.00
- Semen portland Kg 1.6500 1,406.00 2,319.90
- Pasir pasang M3 0.0032 233,400.00 746.88
- Semen warna Kg 0.1000 15,700.00 1,570.00
- Pekerja Oh 0.0900 42,000.00 3,780.00
- Tukang batu Oh 0.0900 65,000.00 5,850.00
- Kepala tukang Oh 0.0090 75,000.00 675.00
- Mandor Oh 0.0045 80,000.00 360.00
Jumlah 101,548.78
Dibulatkan 101,549.00
I-05 1 M2 Lantai Keramik Corak 10 x 20 cm setara Mulia
- Keramik corak 10 x 20 cm m2 1.0000 56,000.00 56,000.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 92,670.20
Dibulatkan 92,670.00
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
I-06 1 M2 Lantai Keramik corak 20 x 20 cm setara Mulia
- Keramik corak 20 x 20 cm m2 1.0000 62,500.00 62,500.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 99,170.20
Dibulatkan 99,170.00
I-07 1 M2 Lantai Keramik polos 30 x 30 cm setara Mulia
- Keramik polos 30 x 30 cm m2 1.0000 53,000.00 53,000.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 89,670.20
Dibulatkan 89,670.00
I-08 1 M2 Lantai Keramik corak 30 x 30 cm Setara Mulia
- Keramik corak 30 x 30 cm m2 1.0000 58,000.00 58,000.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 94,670.20
Dibulatkan 94,670.00
I-09 1 M2 Lantai Keramik polos 40 x 40 cm Setara Mulia
- Keramik polos 40 x 40 cm m2 1.0000 56,800.00 56,800.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 93,470.20
Dibulatkan 93,470.00
I-10 1 M2 Lantai Keramik corak 40 x 40 cm Setara Mulia
- Keramik corak 40 x 40 cm m2 1.0000 65,500.00 65,500.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 102,170.20
Dibulatkan 102,170.00
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
I-11 1 M2 Lantai Keramik Corak 10 x 20 cm setara Roman
- Keramik corak 10 x 20 cm m2 1.0000 72,200.00 72,200.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 108,870.20
Dibulatkan 108,870.00
I-12 1 M2 Lantai Keramik corak 20 x 20 cm setara Roman
- Keramik corak 20 x 20 cm m2 1.0000 75,200.00 75,200.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 111,870.20
Dibulatkan 111,870.00
I-13 1 M2 Lantai Keramik polos 30 x 30 cm setara Roman
- Keramik polos 30 x 30 cm m2 1.0000 68,900.00 68,900.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 105,570.20
Dibulatkan 105,570.00
I-14 1 M2 Lantai Keramik corak 30 x 30 cm Setara Roman
- Keramik corak 30 x 30 cm M2 1.0000 76,600.00 76,600.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 113,270.20
Dibulatkan 113,270.00
I-15 1 M2 Lantai Keramik polos 40 x 40 cm setara Roman
- Keramik polos 40 x 40 cm m2 1.0000 72,500.00 72,500.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 109,170.20
Dibulatkan 109,170.00
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
I-16 1 M2 Lantai Keramik corak 40 x 40 cm Setara Roman
- Keramik corak 40 x 40 cm m2 1.0000 77,000.00 77,000.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 113,670.20
Dibulatkan 113,670.00
I-17 1 M2 Lantai Marmer
- Marmer m2 1.0600 550,000.00 583,000.00
- Semen portland Kg 8.1900 1,406.00 11,515.14
- Pasir pasang M3 0.0450 233,400.00 10,503.00
- Semen warna Kg 0.6500 15,700.00 10,205.00
- Pekerja Oh 0.7000 42,000.00 29,400.00
- Tukang batu Oh 0.3500 65,000.00 22,750.00
- Kepala tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 0.0350 80,000.00 2,800.00
Jumlah 672,798.14
Dibulatkan 672,798.00
I-18 1 M2 Lantai Parquet Jati
- Parquet jati M2 1.0500 375,400.00 394,170.00
- Lem vinyl Kg 0.6000 44,000.00 26,400.00
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang Oh 0.3500 65,000.00 22,750.00
- Kepala tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 0.0325 80,000.00 2,600.00
Jumlah 475,845.00
Dibulatkan 475,845.00
I-19 1 M Plint Keramik ukuran (10 x 40) cm
- Plint keramik (10 x 40) cm Bh 2.6500 4,000.00 10,600.00
- Semen portland Kg 1.2000 1,406.00 1,687.20
- Pasir pasang M3 0.0030 233,400.00 700.20
- Semen warna Kg 0.1000 15,700.00 1,570.00
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang batu Oh 0.0300 65,000.00 1,950.00
- Kepala tukang Oh 0.0030 75,000.00 225.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 19,492.40
Dibulatkan 19,492.00
I-20 1 M Plint Keramik ukuran (10 x 30) cm
- Plint keramik (10 x 30) cm Bh 3.5000 3,500.00 12,250.00
- Semen portland Kg 1.6500 1,406.00 2,319.90
- Pasir pasang M3 0.0032 233,400.00 746.88
- Semen warna Kg 0.1000 15,700.00 1,570.00
- Pekerja Oh 0.0900 42,000.00 3,780.00
- Tukang batu Oh 0.0900 65,000.00 5,850.00
- Kepala tukang Oh 0.0090 75,000.00 675.00
- Mandor Oh 0.0045 80,000.00 360.00
Jumlah 27,551.78
Dibulatkan 27,552.00
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
I-21 1 M' Plint kayu kamper Samarinda (2 x 10) cm
- Papan kayu kamper samarinda M3 0.0024 8,724,300.00 20,938.32
- Paku Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.1200 42,000.00 5,040.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 36,348.32
Dibulatkan 36,348.00
I-22 1 M' Plint keramik ukuran (10 x 20) cm
- Plint keramik Bh 5.3000 3,000.00 15,900.00
- Semen abu-abu Kg 1.1400 1,406.00 1,602.84
- Pasir pasang M3 0.0030 233,400.00 700.20
- Semen warna Kg 0.0250 15,700.00 392.50
- Pekerja Oh 0.0900 42,000.00 3,780.00
- Tukang batu Oh 0.0900 65,000.00 5,850.00
- Kepala tukang Oh 0.0090 75,000.00 675.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 29,300.54
Dibulatkan 29,301.00
I-23 1 M2 Lantai karpet
- Karpet M2 1.0500 353,500.00 371,175.00
- Lem Kg 0.3500 35,700.00 12,495.00
- Pekerja Oh 0.1700 42,000.00 7,140.00
- Tukang batu Oh 0.1700 65,000.00 11,050.00
- Kepala tukang Oh 0.0170 75,000.00 1,275.00
- Mandor Oh 0.0085 80,000.00 680.00
Jumlah 403,815.00
Dibulatkan 403,815.00
I-24 1 M2 Paving block natural 8 cm
- Paving block natural M2 1.050 81,100.00 85,155.00
- Pasir pasang Kg 0.100 233,400.00 23,340.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.00250 80,000.00 200.00
Jumlah 153,570.00
Dibulatkan 153,570.00
I-25 1 M2 Paving block warna 8 cm
- Paving block warna M2 1.050 108,600.00 114,030.00
- Pasir pasang Kg 0.100 233,400.00 23,340.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.00250 80,000.00 200.00
Jumlah 182,445.00
Dibulatkan 182,445.00
I-26 1 M2 Paving block natural 6 cm
- Paving block natural M2 1.050 76,000.00 79,800.00
- Pasir pasang Kg 0.100 233,400.00 23,340.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.00250 80,000.00 200.00
Jumlah 148,215.00
Dibulatkan 148,215.00
No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
I-27 1 M2 Paving block warna 6 cm
- Paving block warna M2 1.050 86,000.00 90,300.00
- Pasir pasang Kg 0.100 233,400.00 23,340.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.00250 80,000.00 200.00
Jumlah 158,715.00
Dibulatkan 158,715.00
I-28 1 M2 Grass Block 20 x 20
- Grass block Bh 26.250 9,700.00 254,625.00
- Pasir pasang Kg 0.100 233,400.00 23,340.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.00250 80,000.00 200.00
Jumlah 323,040.00
Dibulatkan 323,040.00
I-29 1 M2 Grass Block 30 x 30
- Grass block Bh 11.670 22,500.00 262,575.00
- Pasir pasang Kg 0.100 233,400.00 23,340.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.00250 80,000.00 200.00
Jumlah 330,990.00
Dibulatkan 330,990.00
J. ANALISA HARGA SATUAN PEKERJAAN KAYU
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
J-01 1 M3 Kusen Pintu & jendela kayu Kamper Samarinda
- Kayu Balok Kamper Samarinda m3 1.2000 8,633,700.00 10,360,440.00
- Pekerja Oh 6.0000 42,000.00 252,000.00
- Tukang Kayu Oh 18.0000 65,000.00 1,170,000.00
- Kepala Tukang Oh 2.0000 75,000.00 150,000.00
- Mandor Oh 0.3000 80,000.00 24,000.00
Jumlah 11,956,440.00
Dibulatkan 11,956,440.00
J-02 1 M3 Kusen Pintu & jendela kayu Kamper Medan/Kruing
- Kayu Balok Kamper Medan M3 1.2000 5,692,600.00 6,831,120.00
- Pekerja Oh 6.0000 42,000.00 252,000.00
- Tukang Kayu Oh 18.0000 65,000.00 1,170,000.00
- Kepala Tukang Oh 2.0000 75,000.00 150,000.00
- Mandor Oh 0.3000 80,000.00 24,000.00
Jumlah 8,427,120.00
Dibulatkan 8,427,120.00
J-03 1 M3 Kusen Pintu & jendela kayu Borneo Super
- Kayu Borneo Balok Super M3 1.2000 5,280,000.00 6,336,000.00
- Pekerja Oh 6.0000 42,000.00 252,000.00
- Tukang Kayu Oh 18.0000 65,000.00 1,170,000.00
- Kepala Tukang Oh 2.0000 75,000.00 150,000.00
- Mandor Oh 0.3000 80,000.00 24,000.00
Jumlah 7,932,000.00
Dibulatkan 7,932,000.00
J-04 1 M2 Pintu Panel Kayu Kamper Samarinda
- Kayu Papan Kamper Samarinda M3 0.0400 8,633,700.00 345,348.00
- Paku Biasa 2" - 5" Kg 0.0500 23,400.00 1,170.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 2.5000 65,000.00 162,500.00
- Kepala Tukang Oh 0.2500 75,000.00 18,750.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 573,768.00
Dibulatkan 573,768.00
J-05 1 M2 Pintu Panel Kayu Kamper Medan/Kruing
- Kayu Papan Kamper Medan M3 0.0400 5,692,600.00 227,704.00
- Paku Biasa 2" - 5" Kg 0.0500 23,400.00 1,170.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 2.5000 65,000.00 162,500.00
- Kepala Tukang Oh 0.2500 75,000.00 18,750.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 456,124.00
Dibulatkan 456,124.00
J-06 1 M2 Pintu & Jendela Kaca Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0350 5,692,600.00 199,241.00
- Pekerja Oh 0.8000 42,000.00 33,600.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 381,041.00
Dibulatkan 381,041.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
J-07 1 M2 Pintu & Jendela Kaca Kayu Borneo
- Kayu Papan Borneo Super M3 0.0350 5,595,800.00 195,853.00
- Pekerja Oh 0.8000 42,000.00 33,600.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 377,653.00
Dibulatkan 377,653.00
J-08 1 M2 Pintu & Jendela Jalusi Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0640 5,692,600.00 364,326.40
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 3.0000 65,000.00 195,000.00
- Kepala Tukang Oh 0.3000 75,000.00 22,500.00
- Mandor Oh 0.5000 80,000.00 40,000.00
Jumlah 663,826.40
Dibulatkan 663,826.00
J-09 1 M2 Pintu Triplek Rangkap, Rangka Tertutup Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0196 5,692,600.00 111,574.96
- Paku Biasa " - 1" Kg 0.0300 23,800.00 714.00
- Lem Kayu Ltr 0.3000 23,900.00 7,170.00
- Triplek 120 x 240 x 0,4 cm Lbr 1.0000 64,400.00 64,400.00
- Pekerja Oh 0.6000 42,000.00 25,200.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 356,458.96
Dibulatkan 356,459.00
J-10 1 M2 Jalusi Mati Kusen Kayu kamper Medan
- Kayu Papan Kamper Medan M3 0.0600 5,692,600.00 341,556.00
- Paku Biasa " - 1" Kg 0.1500 23,800.00 3,570.00
- Pekerja Oh 0.5000 42,000.00 21,000.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0250 80,000.00 2,000.00
Jumlah 513,126.00
Dibulatkan 513,126.00
J-11 1 M2 Pintu Triplek Rangkap, Rangka Kayu Borneo Super
- Kayu Papan Borneo Super M3 0.0196 5,595,800.00 109,677.68
- Paku Biasa " - 1" Kg 0.0300 23,800.00 714.00
- Lem Kayu Ltr 0.3000 23,900.00 7,170.00
- Triplek 120 x 240 x 0,4 cm Lbr 1.0000 64,400.00 64,400.00
- Pekerja Oh 0.6000 42,000.00 25,200.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 354,561.68
Dibulatkan 354,562.00
J-12 1 M2 Pintu Teakwood Rangkap, rangka Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0196 5,692,600.00 111,574.96
- Paku Biasa " - 1" Kg 0.3000 23,800.00 7,140.00
- Lem Kayu Ltr 0.3000 23,900.00 7,170.00
- Teakwood 4 mm Lbr 1.0000 131,700.00 131,700.00
- Pekerja Oh 0.6000 42,000.00 25,200.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 430,184.96
Dibulatkan 430,185.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
J-13 1 M2 Pintu Triplek & Formika, Rangka Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0196 5,692,600.00 111,574.96
- Paku Biasa " - 1" Kg 0.3000 23,800.00 7,140.00
- Lem Kayu Ltr 0.8000 23,900.00 19,120.00
- Triplek 120 x 240 x 0,4 cm Lbr 1.0000 64,400.00 64,400.00
- Formica 3" x 6" Lbr 0.5000 132,900.00 66,450.00
- Pekerja Oh 0.8000 42,000.00 33,600.00
- Tukang Kayu Oh 2.5000 65,000.00 162,500.00
- Kepala Tukang Oh 0.2500 75,000.00 18,750.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 486,734.96
Dibulatkan 486,735.00
J-14 1 M2 Pintu Teakwood & Formika, Rangka Kayu Kamper Medan (dipolitur)
- Kayu Papan Kamper Medan M3 0.0196 5,692,600.00 111,574.96
- Paku Biasa " - 1" Kg 0.3000 23,800.00 7,140.00
- Lem Kayu Ltr 0.8000 23,900.00 19,120.00
- Teakwood 120 x 240 x 0,4 cm Lbr 1.0000 131,700.00 131,700.00
- Formica 4" x 8" Lbr 0.5000 238,100.00 119,050.00
- Pekerja Oh 0.8000 42,000.00 33,600.00
- Tukang Kayu Oh 2.5000 65,000.00 162,500.00
- Kepala Tukang Oh 0.2500 75,000.00 18,750.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 606,634.96
Dibulatkan 606,635.00
J-15 1 M3 Kuda-kuda Kayu Kamper Medan
- Kayu Balok Kamper Medan M3 1.1000 5,692,600.00 6,261,860.00
- Besi Strip Kg 15.0000 26,800.00 402,000.00
- Paku Biasa 2" - 5" Kg 0.8000 23,800.00 19,040.00
- Pekerja Oh 4.0000 42,000.00 168,000.00
- Tukang Kayu Oh 12.0000 65,000.00 780,000.00
- Kepala Tukang Oh 1.2000 75,000.00 90,000.00
- Mandor Oh 0.2000 80,000.00 16,000.00
Jumlah 7,736,900.00
Dibulatkan 7,736,900.00
J-16 1 M3 Kuda-kuda Kayu Borneo Super
- Kayu balok Borneo super M3 1.1000 5,280,000.00 5,808,000.00
- Besi Strip Kg 15.0000 26,800.00 402,000.00
- Paku Biasa 2" - 5" Kg 0.8000 23,800.00 19,040.00
- Pekerja Oh 4.0000 42,000.00 168,000.00
- Tukang Kayu Oh 12.0000 65,000.00 780,000.00
- Kepala Tukang Oh 1.2000 75,000.00 90,000.00
- Mandor Oh 0.2000 80,000.00 16,000.00
Jumlah 7,283,040.00
Dibulatkan 7,283,040.00
J-17 1 M2 Kaso + Reng Genteng Plentong Kayu Borneo Super
- Kayu balok Borneo super m3 0.0120 5,280,000.00 63,360.00
- Paku Biasa 2" - 5" Kg 0.1500 23,800.00 3,570.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 78,780.00
Dibulatkan 78,780.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
J-18 1 M2 Kaso + Reng Genteng Beton Kayu Borneo Super
- Kayu balok Borneo super M3 0.0140 5,280,000.00 73,920.00
- Paku Biasa 2" - 5" Kg 0.1500 23,800.00 3,570.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 89,340.00
Dibulatkan 89,340.00
J-19 1 M' Lisplang uk (3x20)cm, Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0072 5,823,400.00 41,928.48
- Paku Biasa 2" - 5" Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 62,218.48
Dibulatkan 62,218.00
J-20 1 M' Lisplang uk (3x30)cm, Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0110 5,692,600.00 62,618.60
- Paku Biasa 2" - 5" Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.1100 42,000.00 4,620.00
- Tukang Kayu Oh 0.2200 65,000.00 14,300.00
- Kepala Tukang Oh 0.0220 75,000.00 1,650.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 84,778.60
Dibulatkan 84,779.00
J-21 1 M List Plafond + kayu Profil 10 cm
- Kayu Profil 10 cm M' 1.0500 29,400.00 30,870.00
- Pekerja Oh 0.0210 42,000.00 882.00
- Tukang Kayu Oh 0.0210 65,000.00 1,365.00
- Kepala Tukang Oh 0.0020 75,000.00 150.00
- Mandor Oh 0.0010 80,000.00 80.00
Jumlah 33,347.00
Dibulatkan 33,347.00
J-22 7,26 M2 Kusen Partisi Dobel Triplek
- Kayu balok borneo super M3 0.1050 5,280,000.00 554,400.00
- Triplek 120 x 240 x 0,4 cm Lbr 5.0000 64,400.00 322,000.00
- Paku 1 s/d 3 cm Kg 2.0000 23,800.00 47,600.00
- Ampelas Lbr 2.0000 5,000.00 10,000.00
- Engsel Bh 4.0000 21,000.00 84,000.00
- Slot Bh 4.0000 31,500.00 126,000.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Kayu terampil Oh 1.3000 65,000.00 84,500.00
- Kepala Tukang kayu Oh 0.1300 75,000.00 9,750.00
- Mandor Oh 0.0130 80,000.00 1,040.00
Jumlah 1,251,890.00
1 M2 Pekerjaan partisi 172,436.64
Dibulatkan 172,437.00
J-23 1 M2 Rangka Langit-langit (1,00 x 1,00) m, Kayu borneo super
- Kayu Borneo super m 0.0120 2,640,000.00 31,680.00
Paku 5 s.d. 7 cm kg 0.1000 23,800.00 2,380.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang Kayu Oh 0.2500 65,000.00 16,250.00
- Kepala Tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.0750 80,000.00 6,000.00
Jumlah 64,485.00
Dibulatkan 64,485.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
J-24 1 M2 Rangka langit-langit ( 0,50 x 1,00 ) m, Kayu Borneo Super
- Kayu Balok Borneo Super m3 0.0154 2,640,000.00 40,656.00
- Paku Biasa 2" - 5" kg 0.2000 23,800.00 4,760.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang Kayu Oh 0.3000 65,000.00 19,500.00
- Kepala Tukang Oh 0.0300 75,000.00 2,250.00
- Mandor Oh 0.0750 80,000.00 6,000.00
Jumlah 79,466.00
Dibulatkan 79,466.00
J-25 1 M' Reuter Kayu kamper Medan
- Kayu kamper Medan m 0.0040 2,640,000.00 10,560.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 29,660.00
Dibulatkan 29,660.00
J-26 1 M3 Gording kayu kelas II
- Balok kayu m 1.1000 5,692,600.00 6,261,860.00
- Besi Strip Kg 15.0000 26,800.00 402,000.00
- Paku Biasa 2" - 5" Kg 3.0000 23,800.00 71,400.00
- Pekerja Oh 2.4000 42,000.00 100,800.00
- Tukang Kayu Oh 7.2000 65,000.00 468,000.00
- Kepala Tukang Oh 0.7200 75,000.00 54,000.00
- Mandor Oh 0.1200 80,000.00 9,600.00
Jumlah 7,367,660.00
Dibulatkan 7,367,660.00
J-27 1 M2 Dinding bilik, rangka kayu borneo
- Bilik bambu m2 1.1000 22,700.00 24,970.00
- Kaso 5/7 m3 0.0140 2,640,000.00 36,960.00
- Paku Biasa 2" - 5" Kg 0.0120 23,800.00 285.60
- List kayu 2/4 m3 0.0030 10,000.00 30.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.0500 65,000.00 3,250.00
- Kepala Tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 70,470.60
Dibulatkan 70,471.00
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
K-01 1 Kg Besi profil
- Besi profil WF Kg 1.1000 24,000.00 26,400.00
- Meni besi Kg 0.0800 30,400.00 2,432.00
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang besi Oh 0.0060 65,000.00 390.00
- Kepala tukang Oh 0.0060 75,000.00 450.00
- Mandor Oh 0.0003 80,000.00 24.00
Jumlah 32,216.00
Dibulatkan 32,216.00
K-02 1 Kg Perakitan baja
- Solar m' 0.0100 7,150.0000 71.50
- Minyak pelumas m' 0.0010 55,000.0000 55.00
- Sewa alat jam 0.0080 100,000.0000 800.00
- Pekerja Oh 0.0010 42,000.0000 42.00
- Tukang besi Oh 0.00001 65,000.0000 0.65
- Kepala tukang Oh 0.00001 75,000.0000 0.75
- Mandor Oh 0.00005 80,000.0000 4.00
Jumlah 973.90
Dibulatkan 974.00
K-03 1 Cm Pengelasan dengan las listrik
- kawat las kg 0.0400 23,600.00 944.00
- Solar ltr 0.0300 7,150.00 214.50
- Minyak pelumas ltr 0.0040 55,000.00 220.00
- Sewa alat jam 0.0170 100,000.00 1,700.00
- Pekerja org 0.0040 42,000.00 168.00
- Tukang org 0.0020 65,000.00 130.00
- Kepala Tukang org 0.0002 75,000.00 15.00
- Mandor org 0.0002 80,000.00 16.00
Jumlah 2,463.50
Dibulatkan 2,464.00
K-04 1 m2 Pintu Rolling Door
- Rolling door M2 1.0000 306,600.00 306,600.00
- Pekerja Oh 1.0500 42,000.00 44,100.00
- Tukang besi Oh 1.5000 65,000.00 97,500.00
- Kepala tukang Oh 0.1050 75,000.00 7,875.00
- Mandor Oh 0.0052 80,000.00 416.00
Jumlah 456,491.00
Dibulatkan 456,491.00
K-05 1 m2 Pintu Alluminium Natural
- Pintu alluminium natural m2 1.0000 211,800.00 211,800.00
- Pekerja Oh 1.0500 42,000.00 44,100.00
- Tukang besi Oh 1.0500 65,000.00 68,250.00
- Kepala tukang Oh 0.1050 75,000.00 7,875.00
- Mandor Oh 0.0052 80,000.00 416.00
Jumlah 332,441.00
Dibulatkan 332,441.00
K. ANALISA HARGA SATUAN PEKERJAAN PENUTUP BESI & ALLUMINIUM
Page 61 K
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
K-06 1 m2 Terali Besi
- Besi strip 2 x 3 m' 11.5000 5,500.00 63,250.00
- Pekerja Oh 1.2000 42,000.00 50,400.00
- Tukang las Oh 1.2000 65,000.00 78,000.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0006 80,000.00 48.00
Jumlah 192,598.00
Dibulatkan 192,598.00
K-07 1 m2 Kawat Harmonika 4 cm
- Kawat harmonika M2 1.1000 35,900.00 39,490.00
- Paku biasa " - 1" kg 0.0200 23,800.00 476.00
- Papan kayu kamper M2 0.0018 5,692,600.00 10,246.68
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.1000 65,000.00 6,500.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 62,062.68
Dibulatkan 62,063.00
K-08 1 m' Talang Datar, Seng BJLS 28 lebar 90 cm
- Seng plat 3' x 6' BJLS 30 m' 1.0500 20,801.00 21,841.05
- Paku biasa " - 1" Kg 0.0150 23,800.00 357.00
- Kayu papan borneo super M3 0.0096 5,595,800.00 53,719.68
- Flincote / meni besi Kg 0.2500 30,400.00 7,600.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.0013 80,000.00 104.00
Jumlah 117,796.73
Dibulatkan 117,797.00
K-09 1 m' Talang Miring, Seng BJLS 28 lebar 90 cm
- Seng plat 3' x 6' BJLS 30 m' 1.0500 20,801.00 21,841.05
- Paku biasa " - 1" Kg 0.0150 23,800.00 357.00
- Kayu papan borneo super M3 0.0190 5,595,800.00 106,320.20
- Flincote / meni besi Kg 0.3000 30,400.00 9,120.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.0013 80,000.00 100.00
Jumlah 174,013.25
Dibulatkan 174,013.00
K-10 1 m' Talang 1/2 lingkaran D-15 cm, seng pelat BJLS 28 lebar 90 cm
- Seng plat 3' x 6' BJLS 30 m' 1.0500 20,801.00 21,841.05
- Paku biasa " - 1" Kg 0.1000 23,800.00 2,380.00
- Kayu papan borneo super kg 0.0190 5,595,800.00 106,320.20
- Besi strip Kg 0.5000 26,800.00 13,400.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.3000 65,000.00 19,500.00
- Kepala tukang Oh 0.0300 75,000.00 2,250.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 172,631.25
Dibulatkan 172,631.00
Page 62 K
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
K-11 1 m' Pasang kusen pintu/jendela alluminium natural 4"
- Alumunium profil natural 4" m' 1.1000 151,100.00 166,210.00
- Skrup fixer bh 2.0000 250.00 500.00
- Sealant m' 1.0000 7,500.00 7,500.00
- Pekerja Oh 0.0430 42,000.00 1,806.00
- Tukang kayu Oh 0.0430 65,000.00 2,795.00
- Kepala tukang Oh 0.0043 75,000.00 322.50
- Mandor Oh 0.0021 80,000.00 168.00
Jumlah 179,301.50
Dibulatkan 179,302.00
K-12 1 m' Pasang kusen pintu/jendela alluminium warna 4"
- Alumunium profil warna 4" m' 1.1000 163,000.00 179,300.00
- Skrup fixer bh 2.0000 250.00 500.00
- Sealant m' 1.0000 7,500.00 7,500.00
- Pekerja Oh 0.0430 42,000.00 1,806.00
- Tukang kayu Oh 0.0430 65,000.00 2,795.00
- Kepala tukang Oh 0.0043 75,000.00 322.50
- Mandor Oh 0.0021 80,000.00 168.00
Jumlah 192,391.50
Dibulatkan 192,392.00
K-13 1 m' Pasang kusen pintu/jendela alluminium natural 3"
- Alumunium profil natural 3" m' 1.1000 81,000.00 89,100.00
- Skrup fixer bh 2.0000 250.00 500.00
- Sealant m' 1.0000 7,500.00 7,500.00
- Pekerja Oh 0.0430 42,000.00 1,806.00
- Tukang kayu Oh 0.0430 65,000.00 2,795.00
- Kepala tukang Oh 0.0043 75,000.00 322.50
- Mandor Oh 0.0021 80,000.00 168.00
Jumlah 102,191.50
Dibulatkan 102,192.00
K-14 1 m' Pasang kusen pintu/jendela alluminium warna 3"
- Alumunium profil warna 3" m' 1.1000 102,000.00 112,200.00
- Skrup fixer bh 2.0000 250.00 500.00
- Sealant m' 1.0000 7,500.00 7,500.00
- Pekerja Oh 0.0430 42,000.00 1,806.00
- Tukang kayu Oh 0.0430 65,000.00 2,795.00
- Kepala tukang Oh 0.0043 75,000.00 322.50
- Mandor Oh 0.0021 80,000.00 168.00
Jumlah 125,291.50
Dibulatkan 125,292.00
K-15 1 m2 Pintu alluminium strip lebar 8 cm
- Alumunium profil 4" natural m' 4.4000 151,100.00 664,840.00
- Alumunium strip 6mm m2 1.0500 171,800.00 180,390.00
- Pekerja Oh 0.0850 42,000.00 3,570.00
- Tukang kayu Oh 0.0850 65,000.00 5,525.00
- Kepala tukang Oh 0.0085 75,000.00 637.50
- Mandor Oh 0.0042 80,000.00 336.00
Jumlah 855,298.50
Dibulatkan 855,299.00
Page 63 K
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
K-16 1 m2 Pintu/jendela kaca rangka alluminium natural 4"
- Alumunium profil natural 4" m' 4.4000 151,100.00 664,840.00
- Profil alluminium T m' 4.5000 12,200.00 54,900.00
- Sealant tube 0.2700 7,500.00 2,025.00
- Pekerja Oh 0.0850 42,000.00 3,570.00
- Tukang kayu Oh 0.0850 65,000.00 5,525.00
- Kepala tukang Oh 0.0085 75,000.00 637.50
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 731,897.50
Dibulatkan 731,898.00
K-17 1 m2 Pintu/jendela kaca rangka alluminium warna 4"
- Alumunium profil warna 4" m' 4.4000 163,000.00 717,200.00
- Profil alluminium T m' 4.5000 12,200.00 54,900.00
- Sealant tube 0.2700 7,500.00 2,025.00
- Pekerja Oh 0.0850 42,000.00 3,570.00
- Tukang kayu Oh 0.0850 65,000.00 5,525.00
- Kepala tukang Oh 0.0085 75,000.00 637.50
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 784,257.50
Dibulatkan 784,258.00
K-18 1 m2 Jendela nako & teralis (10 klips)
- Jendela nako (rangka + kaca 5 mm) m2 1.1000 300,000.00 330,000.00
- Paku skrup 1cm - 2,5cm bh 10.0000 250.00 2,500.00
- Besi strip m' 7.0000 5,500.00 38,500.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang kayu Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0010 80,000.00 80.00
Jumlah 393,980.00
Dibulatkan 393,980.00
K-19 1 m2 Pintu pelat baja tebal 2mm rangkap, rangka baja siku
- Besi siku L 30.30.3 Kg 15.0000 24,000.00 360,000.00
- Baja pelat Kg 32.8000 24,000.00 787,200.00
- kawat las Kg 0.0500 23,600.00 1,180.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang kayu Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0010 80,000.00 80.00
Jumlah 1,171,360.00
Dibulatkan 1,171,360.00
K-20 1 m2 Rangka jendela besi square tube (5 x 5) cm
- Besi square tube M 4.7600 7,300.00 34,748.00
- Besi lis kaca (1 x 1) cm Kg 4.5220 24,000.00 108,528.00
- Pengelasan Cm 20.0000 2,464.00 49,280.00
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang kayu Oh 0.6500 65,000.00 42,250.00
- Kepala tukang Oh 0.0650 75,000.00 4,875.00
- Mandor Oh 0.0320 80,000.00 2,560.00
Jumlah 269,541.00
Dibulatkan 269,541.00
Page 64 K
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
K-21 1 m2 Pintu lipat (folding door) bahan besi
- Pintu lipat M2 1.0000 501,700.00 501,700.00
- Pekerja Oh 1.0500 42,000.00 44,100.00
- Tukang kayu Oh 1.0500 65,000.00 68,250.00
- Kepala tukang Oh 0.1050 75,000.00 7,875.00
- Mandor Oh 0.0052 80,000.00 416.00
Jumlah 622,341.00
Dibulatkan 622,341.00
K-22 1 m2 Tirai (venetions blinds and vertical blinds)
- Tirai M2 1.0000 537,300.00 537,300.00
- Pekerja Oh 0.3500 42,000.00 14,700.00
- Tukang kayu Oh 0.3500 65,000.00 22,750.00
- Kepala tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 0.0018 80,000.00 144.00
Jumlah 577,519.00
Dibulatkan 577,519.00
Page 65 K
K(2) Analisa Biaya Konstruksi Pekerjaan Kusen Alumunium
1 1 UNIT Pasang partisi Alumunium, Daun partisi Multiplek rangka kayu Kamper
Bahan 7.6200 m' Kusen Alumunium Natural Uk 4" + upah 20% 181,320.00 1,381,658.40
1.3500 lbr Multiplek 9 mm 151,100.00 203,985.00
0.0300 m3 Kayu papan kamper medan 5,823,400.00 174,702.00
11.7000 m' List kayu profil 1 cm 8,900.00 104,130.00
0.1000 kg Paku biasa " - 1" 23,800.00 2,380.00
0.2500 kg Lem putih FOX 23,900.00 5,975.00
4.0000 bh Grendel jendela 2" 5,500.00 22,000.00
2.0000 bh Handle partisi 33,000.00 66,000.00
1.5400 m2 Cat kayu 39,790.00 61,276.60
4.8600 m2 Cat tembok 17,608.00 85,574.88
Jumlah I 2,107,681.88
Tenaga 0.3000 Oh Pekerja Terampil 42,000.00 12,600.00
1.3000 Oh Tukang kayu Terampil 65,000.00 84,500.00
0.1300 Oh Kepla Tukang Kayu 75,000.00 9,750.00
0.0130 Oh Mandor 80,000.00 1,040.00
Jumlah II 107,890.00
Jumlah I + II 2,215,571.88
2 1 UNIT Pek. Kusen Jendela Alumunium uk. 2 X 1,50 M' ( 3 lubang ) dgn 2 Daun Jendela
Bahan 12.0000 m' Profil aluminium 4" natural + upah 20% 181,320.00 2,175,840.00
5.4000 m' Profil daun jendela alm. + upah 20% 118,560.00 640,224.00
1.8100 m2 Kaca polos 5 mm 111,000.00 200,910.00
2.0000 ps Engsel jendela 3" 15,000.00 30,000.00
2.0000 bh Slot Handle jendela 33,000.00 66,000.00
2.0000 bh Hak Kait angin jendela biasa 7,100.00 14,200.00
0.0000 ls Acesories ( 5 % ) 150,848.70 150,848.70
3,278,022.700
3 1 UNIT Pek. Kusen Pintu Jendela Alumunium uk. 2,2 X 2,70 M' ( 2 lb. Jendela + 1 lb. Pintu )
Bahan 14.1000 m' Profil aluminium 4" natural + upah 20% 181,320.00 2,556,612.00
2.7000 m' Profil daun jendela alm. + upah 20% 118,560.00 320,112.00
1.6500 m2 Kaca polos 5 mm 111,000.00 183,150.00
1.6800 m2 Daun pintu panel Multiplek 9 mm 356,459.00 598,851.12
rangka ky. Kamper Medan/Kruing
1.0000 ps Engsel jendela 3" 15,000.00 15,000.00
1.0000 bh Slot Handle jendela 33,000.00 33,000.00
2.0000 bh Hak Kait angin jendela biasa 7,100.00 14,200.00
1.5000 ps Engsel pintu 4" 21,000.00 31,500.00
1.0000 bh Grendel pintu 2" 5,500.00 5,500.00
1.0000 bh Kunci tanam 2 slaagh (Royal) 126,500.00 126,500.00
0.0000 ls Acesories ( 5 % ) 152,993.70 152,993.70
4,037,418.820
4 1 UNIT Pekerjaan Kusen Pintu Alumunium uk. 0,8 X 2,70 M'
Bahan 7.0000 m' Profil aluminium 4" natural + upah 20% 181,320.00 1,269,240.00
0.3700 m2 Kaca polos 5 mm 111,000.00 41,070.00
1.6800 m2 Daun pintu panel Multiplek 9 mm 356,459.00 598,851.12
rangka ky. Kamper Medan/Kruing
1.5000 ps Engsel pintu 4" 21,000.00 31,500.00
1.0000 bh Grendel pintu 2" 5,500.00 5,500.00
1.0000 bh Kunci tanam 2 slaagh (Royal) 126,500.00 126,500.00
0.0000 ls Acesories ( 5 % ) 95,458.06 95,458.06
2,168,119.176
5 1 UNIT Pek. Kusen Jendela Alumunium uk. 2,65 X 1,50 M' ( 4 lubang ) dgn 2 Daun Jendela
Bahan 15.4500 m' Profil aluminium 4" natural + upah 20% 181,320.00 2,801,394.00
5.4000 m' Profil daun jendela alm. + upah 20% 118,560.00 640,224.00
2.5500 m2 Kaca polos 5 mm 111,000.00 283,050.00
2.0000 ps Engsel jendela 3" 15,000.00 30,000.00
2.0000 bh Slot Handle jendela 33,000.00 66,000.00
2.0000 bh Hak Kait angin jendela biasa 7,100.00 14,200.00
0.0000 ls Acesories ( 5 % ) 186,233.40 186,233.40
4,021,101.400
Page 66 K (2)
6 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk. 2,85 X 2,70 M' ( 3 lb. Jendela + 1 lb. Pintu )
Bahan 17.5500 m' Profil aluminium 4" natural + upah 20% 181,320.00 3,182,166.00
5.4000 m' Profil daun jendela alm. + upah 20% 118,560.00 640,224.00
2.4000 m2 Kaca polos 5 mm 111,000.00 266,400.00
1.6800 m2 Daun pintu panel Multiplek 9 mm 356,459.00 598,851.12
rangka ky. Kamper Medan/Kruing
2.0000 ps Engsel jendela 3" 15,000.00 30,000.00
2.0000 bh Slot Handle jendela 33,000.00 66,000.00
2.0000 bh Hak Kait angin jendela biasa 7,100.00 14,200.00
1.5000 ps Engsel pintu 4" 21,000.00 31,500.00
1.0000 bh Grendel pintu 2" 5,500.00 5,500.00
1.0000 bh Kunci tanam 2 slaagh (Royal) 126,500.00 126,500.00
0.0000 ls Acesories ( 5 % ) 204,439.50 204,439.50
5,165,780.620
7 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,30 X 2,80 M' ( 2 Daun Pintu )
Bahan 8.9000 m' Profil aluminium 4" natural + upah 20% 181,320.00 1,613,748.00
0.6500 m2 Kaca polos 5 mm 111,000.00 72,150.00
2.7300 m2 Daun pintu panel Multiplek 9 mm 356,459.00 973,133.07
rangka ky. Kamper Medan/Kruing
1.5000 ps Engsel pintu 4" 21,000.00 31,500.00
1.0000 ps spagnolet tanam 51,600.00 51,600.00
1.0000 bh Kunci tanam 2 slaagh (Royal) 126,500.00 126,500.00
0.0000 ls Acesories ( 5 % ) 132,951.55 132,951.55
3,001,582.624
8 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,50 X 2,70 M' ( 2 Daun Pintu )
Bahan 8.8000 m' Profil aluminium 4" natural + upah 20% 181,320.00 1,595,616.00
0.7000 m2 Kaca polos 5 mm 111,000.00 77,700.00
2.9400 m2 Daun pintu panel Multiplek 9 mm 356,459.00 1,047,989.46
rangka ky. Kamper Medan/Kruing
1.5000 ps Engsel pintu 4" 21,000.00 31,500.00
1.0000 ps spagnolet tanam 51,600.00 51,600.00
1.0000 bh Kunci tanam 2 slaagh (Royal) 126,500.00 126,500.00
0.0000 ls Acesories ( 5 % ) 136,065.27 136,065.27
3,066,970.733
9 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk.1,55 X 2,70 M' ( 1 lb. Jendela + 1 lb. Pintu )
Bahan 10.7500 m' Profil aluminium 4" natural + upah 20% 181,320.00 1,949,190.00
1.0700 m2 Kaca polos 5 mm 111,000.00 118,770.00
1.6800 m2 Daun pintu panel Multiplek 9 mm 356,459.00 598,851.12
rangka ky. Kamper Medan/Kruing
1.5000 ps Engsel pintu 4" 21,000.00 31,500.00
1.0000 ps spagnolet tanam 51,600.00 51,600.00
1.0000 bh Kunci tanam 2 slaagh (Royal) 126,500.00 126,500.00
0.0000 ls Acesories ( 5 % ) 133,340.56 133,340.56
3,009,751.676
10 1 UNIT Pekerjaan Jalusi Alumunium Sofi-sofi
Bahan 5.1000 m' Profil aluminium 4" natural + upah 20% 181,320.00 924,732.00
8.0000 m2 Jalusi Alm 35,000.00 280,000.00
0.0000 ls Acesories ( 5 % ) 60,236.60 60,236.60
1,264,968.600
11 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 1 lubang ) uk. 0,70 x 0,60 m
Bahan 4.0000 m' Profil aluminium 4" natural + upah 20% 181,320.00 725,280.00
0.2400 m2 Kaca polos 5 mm 111,000.00 26,640.00
0.0000 ls Acesories ( 5 % ) 37,596.00 37,596.00
789,516.000
12 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 2 lubang ) uk. 1,35 x 0,60 m
Bahan 4.5000 m' Profil aluminium 4" natural + upah 20% 181,320.00 815,940.00
0.4800 m2 Kaca polos 5 mm 111,000.00 53,280.00
0.0000 ls Acesories ( 5 % ) 43,461.00 43,461.00
912,681.000
Page 67 K (2)
13 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 3 lubang ) uk. 2,00 x 0,60 m
Bahan 6.4000 m' Profil aluminium 4" natural + upah 20% 181,320.00 1,160,448.00
0.7200 m2 Kaca polos 5 mm 111,000.00 79,920.00
0.0000 ls Acesories ( 5 % ) 62,018.40 62,018.40
1,302,386.400
14 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 4 lubang ) uk. 2,65 x 0,60 m
Bahan 8.3000 m' Profil aluminium 4" natural + upah 20% 181,320.00 1,504,956.00
0.9600 m2 Kaca polos 5 mm 111,000.00 106,560.00
0.0000 ls Acesories ( 5 % ) 80,575.80 80,575.80
1,692,091.800
Page 68 K (2)
L. ANALISA HARGA SATUAN PEKERJAAN KUNCI & KACA
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
L-01 1 Buah Pasang Kunci Tanam 2 slaag
- Kunci tanam Bh 1.0000 335,900.00 335,900.00
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang kayu Oh 0.6000 65,000.00 39,000.00
- Kepala tukang Oh 0.0600 75,000.00 4,500.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 382,160.00
Dibulatkan 382,160.00
L-02 1 Buah Pasang Kunci Tanam Biasa
- Kunci tanam biasa Bh 1.0000 165,300.00 165,300.00
- Pekerja Oh 0.0100 42,000.00 420.00
- Tukang kayu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 199,370.00
Dibulatkan 199,370.00
L-03 1 Buah Pasang Kunci Tanam Kamar Mandi
- Kunci tanam km mandi Bh 1.0000 94,500.00 94,500.00
- Pekerja Oh 0.0050 42,000.00 210.00
- Tukang kayu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 127,785.00
Dibulatkan 127,785.00
L-04 1 Buah Pasang Engsel Pintu
- Engsel pintu Bh 1.0000 21,000.00 21,000.00
- Pekerja Oh 0.0150 42,000.00 630.00
- Tukang kayu Oh 0.1500 65,000.00 9,750.00
- Kepala tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0008 80,000.00 64.00
Jumlah 32,569.00
Dibulatkan 32,569.00
L-05 1 Buah Pasang Engsel Jendela Kupu-kupu
- Engsel jendela Bh 1.0000 15,000.00 15,000.00
- Pekerja Oh 0.0100 42,000.00 420.00
- Tukang kayu Oh 0.1000 65,000.00 6,500.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0005 80,000.00 40.00
Jumlah 22,710.00
Dibulatkan 22,710.00
L-06 1 Buah Pasang Kait Angin
- Kait angin Bh 1.0000 3,550.00 3,550.00
- Pekerja Oh 0.0150 42,000.00 630.00
- Tukang kayu Oh 0.1500 65,000.00 9,750.00
- Kepala tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0008 80,000.00 64.00
Jumlah 15,119.00
Dibulatkan 15,119.00
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
L-07 1 Buah Pasang Door Closer
- Door closer Bh 1.0000 420,000.00 420,000.00
- Pekerja Oh 0.0500 42,000.00 2,100.00
- Tukang kayu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0500 75,000.00 3,750.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 458,550.00
Dibulatkan 458,550.00
L-08 1 Buah Pasang Pegangan Pintu / Door Holder
- Door holder Bh 1.0000 205,400.00 205,400.00
- Pekerja Oh 0.0500 42,000.00 2,100.00
- Tukang kayu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0500 75,000.00 3,750.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 243,950.00
Dibulatkan 243,950.00
L-09 1 M2 Pasang Kaca , tebal 3 mm
- Kaca M2 1.1000 87,400.00 96,140.00
- Pekerja Oh 0.0150 42,000.00 630.00
- Tukang kayu Oh 0.1500 65,000.00 9,750.00
- Kepala tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0008 80,000.00 60.00
Jumlah 107,705.00
Dibulatkan 107,705.00
L-10 1 M2 Pasang Kaca , tebal 5 mm
- Kaca M2 1.1000 111,000.00 122,100.00
- Pekerja Oh 0.0150 42,000.00 630.00
- Tukang kayu Oh 0.1500 65,000.00 9,750.00
- Kepala tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0008 80,000.00 64.00
Jumlah 133,669.00
Dibulatkan 133,669.00
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
M-01 1 Buah Closet jongkok Porselen Standar
Closet jongkok bh 1.00 188,200.00 188,200.00
P.C (50 gk) Kg 6.00 1,406.00 8,436.00
Pasir pasang m3 0.01 233,400.00 2,334.00
Pekerja org 1.0000 42,000.00 42,000.00
Tukang batu org 1.5000 65,000.00 97,500.00
Kepala Tukang org 1.5000 75,000.00 112,500.00
Mandor org 0.1600 80,000.00 12,800.00
Jumlah 463,770.00
Dibulatkan 463,770.00
M-02 1 Buah Urinoir
Urinoir bh 1.00 1,773,400.00 1,773,400.00
P.C (50 gk) Kg 6.00 1,406.00 8,436.00
Pasir pasang m3 0.01 233,400.00 2,334.00
Pekerja org 1.0000 42,000.00 42,000.00
Tukang batu org 1.0000 65,000.00 65,000.00
Kepala Tukang org 0.1000 75,000.00 7,500.00
Mandor org 0.0010 80,000.00 80.00
Perlengkapan 30 % harga urinoir lot 0.3000 1,773,400.00 532,020.00
Jumlah 2,430,770.00
Dibulatkan 2,430,770.00
M-03 1 Buah Wastafel
wastafel standar unit 1.00 1,012,700.00 1,012,700.00
P.C (50 gk) Kg 6.00 1,406.00 8,436.00
Pasir pasang m3 0.01 233,400.00 2,334.00
Pekerja org 1.2000 42,000.00 50,400.00
Tukang batu org 1.4500 65,000.00 94,250.00
Kepala Tukang org 0.1500 75,000.00 11,250.00
Mandor org 0.1000 80,000.00 8,000.00
Perlengkapan 12 % harga wastafel lot 0.1200 1,773,400.00 212,808.00
Jumlah 1,400,178.00
Dibulatkan 1,400,178.00
M-04 1 Buah bak Mandi Fibreglass Volume 0,30 m3
Bak fibreglass 0.60m x 0.60m bh 1.00 255,300.00 255,300.00
Pekerja org 1.8000 42,000.00 75,600.00
Tukang batu org 2.7000 65,000.00 175,500.00
Kepala Tukang org 0.5400 75,000.00 40,500.00
Mandor org 0.1100 80,000.00 8,800.00
Perlengkapan 18 % harga bak lot 0.1800 255,300.00 45,954.00
Jumlah 601,654.00
Dibulatkan 601,654.00
M-05 1 M' Saluran Air Limbah Buis beton d = 30 cm - 60 cm
Buis beton 30 cm bh 1.10 61,700.00 67,870.00
Bata merah bh 25.00 775.00 19,375.00
P.C (50 gk) Kg 10.300 1,406.00 14,481.80
Pasir pasang m3 0.061 233,400.00 14,237.40
Pasir urug m3 0.069 175,300.00 12,095.70
Pekerja org 0.3800 42,000.00 15,960.00
Tukang batu org 0.1900 65,000.00 12,350.00
Kepala Tukang org 0.0190 75,000.00 1,425.00
Mandor org 0.0190 80,000.00 1,520.00
Jumlah 159,314.90
Dibulatkan 159,315.00
M. PEKERJAAN SANITASI
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
M-06 1 Buah Bak Kontrol Pas Bata Merah Uk (60 x 60) cm
Bata merah bh 186.00 775.00 144,150.00
P.C (50 gk) Kg 114.000 1,406.00 160,284.00
Pasir pasang m3 0.184 233,400.00 42,945.60
Batu pecah 2/3 m3 0.033 211,100.00 6,966.30
Besi beton m3 4.850 16,500.00 80,025.00
Pasir beton m3 0.120 255,400.00 30,648.00
Pekerja org 2.1600 42,000.00 90,720.00
Tukang batu org 0.7200 65,000.00 46,800.00
Kepala Tukang org 0.0720 75,000.00 5,400.00
Mandor org 0.1080 80,000.00 8,640.00
Tukang gali org 0.1000 42,000.00 4,200.00
Jumlah 620,778.90
Dibulatkan 620,779.00
M-07 1 Buah Bak Kontrol Pas Bata Merah Uk (30 x 30) cm
Bata merah bh 53.00 775.00 41,075.00
P.C (50 gk) Kg 44.000 1,406.00 61,864.00
Pasir pasang m3 0.070 233,400.00 16,338.00
Batu pecah 2/3 m3 0.070 211,100.00 14,777.00
Besi beton m3 1.600 16,500.00 26,400.00
Pasir beton m3 0.060 255,400.00 15,324.00
Pekerja org 3.2000 42,000.00 134,400.00
Tukang batu org 1.0150 65,000.00 65,975.00
Kepala Tukang org 0.0015 75,000.00 112.50
Mandor org 0.0160 80,000.00 1,280.00
Jumlah 377,545.50
Dibulatkan 377,546.00
M-08 1 M' Pipa PVC 1/2" (AW)
Pipa pvc 1/2" m' 1.2000 10,025.00 12,030.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukang batu org 0.0600 65,000.00 3,900.00
Kepala Tukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan 35 % harga pipa lot 0.3500 12,030.00 4,210.50
Jumlah 22,246.50
Dibulatkan 22,247.00
M-09 1 M' Pipa PVC 1" (AW)
Pipa pvc 1" m' 1.2000 15,800.00 18,960.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukang batu org 0.0600 65,000.00 3,900.00
Kepala Tukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan 35 % harga pipa lot 0.3500 18,960.00 6,636.00
Jumlah 31,602.00
Dibulatkan 31,602.00
M-10 1 M' Pipa PVC 11/2" (AW)
Pipa pvc 11/2" m' 1.2000 26,475.00 31,770.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukang batu org 0.0600 65,000.00 3,900.00
Kepala Tukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan 35 % harga pipa lot 0.3500 31,770.00 11,119.50
Jumlah 48,895.50
Dibulatkan 48,896.00
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
M-11 1 M' Pipa PVC 2" (AW)
Pipa pvc 2" m' 1.2000 27,675.00 33,210.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukang batu org 0.0600 65,000.00 3,900.00
Kepala Tukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan 35 % harga pipa lot 0.3500 31,770.00 11,119.50
Jumlah 50,335.50
Dibulatkan 50,336.00
M-12 1 M' Pipa PVC 4" (AW)
Pipa pvc 4" m' 1.2000 86,975.00 104,370.00
Pekerja org 0.0810 42,000.00 3,402.00
Tukang batu org 0.1350 65,000.00 8,775.00
Kepala Tukang org 0.0135 75,000.00 1,012.50
Mandor org 0.0041 80,000.00 328.00
Perlengkapan 35 % harga pipa lot 0.3500 104,370.00 36,529.50
Jumlah 154,417.00
Dibulatkan 154,417.00
M-13 1 M' Pipa PVC 3/4" (AW)
Pipa pvc 3/4" m' 1.2000 13,050.00 15,660.00
Pekerja org 0.0810 42,000.00 3,402.00
Tukang batu org 0.1350 65,000.00 8,775.00
Kepala Tukang org 0.0135 75,000.00 1,012.50
Mandor org 0.0041 80,000.00 328.00
Perlengkapan 35 % harga pipa lot 0.3500 15,660.00 5,481.00
Jumlah 34,658.50
Dibulatkan 34,659.00
M-14 1 Buah Bak Cuci piring Stainless steel
Bak cuci stainless steel + asesoris lengkap bh 1.0000 397,800.00 397,800.00
Pekerja org 0.0300 42,000.00 1,260.00
Tukang batu org 0.3000 65,000.00 19,500.00
Kepala Tukang org 0.0300 75,000.00 2,250.00
Mandor org 0.0015 80,000.00 120.00
Jumlah 420,930.00
Dibulatkan 420,930.00
M-15 1 Buah Kran 1/2" - 3/4"
Kran air bh 1.0000 40,900.00 40,900.00
Seal tape bh 0.0250 4,200.00 105.00
Pekerja org 0.0100 42,000.00 420.00
Tukang batu org 0.1000 65,000.00 6,500.00
Kepala Tukang org 0.0100 75,000.00 750.00
Mandor org 0.0050 80,000.00 400.00
Jumlah 49,075.00
Dibulatkan 49,075.00
M-16 1 Buah Floor Drain
Floor drain bh 1.0000 66,600.00 66,600.00
Pekerja org 0.0100 42,000.00 420.00
Tukang batu org 0.1000 65,000.00 6,500.00
Kepala Tukang org 0.0100 75,000.00 750.00
Mandor org 0.0050 80,000.00 400.00
Jumlah 74,670.00
Dibulatkan 74,670.00
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
M-17 1 M' Grafel beton U 20 cm -60 cm
Pipa beton U bh 1.1000 44,300.00 48,730.00
Bata merah bh 12.0000 775.00 9,300.00
P.C (50 gk) zak 0.1030 1,406.00 144.82
Pasir pasang m3 0.0305 233,400.00 7,118.70
Pasir urug m3 0.0345 175,300.00 6,047.85
Pekerja org 0.0100 42,000.00 420.00
Tukang batu org 0.1000 65,000.00 6,500.00
Kepala Tukang org 0.0100 75,000.00 750.00
Mandor org 0.0050 80,000.00 400.00
Jumlah 79,411.37
Dibulatkan 79,411.00
M-18 1 M' Pasang Talang Plastik PVC U 15 cm (AW)
Talang plastik PVC m' 1.05000 60,000.00 63,000.00
Perlengkapan 35 % harga talang lot 0.3500 63,000.00 22,050.00
Pekerja org 0.1500 42,000.00 6,300.00
Tukang batu org 0.4000 65,000.00 26,000.00
Kepala Tukang org 0.0250 75,000.00 1,875.00
Mandor org 0.0013 80,000.00 100.00
Jumlah 119,325.00
Dibulatkan 119,325.00
M-19 1 M' Saluran Air Limbah Buis Beton 60 cm
Buis beton 60 cm bh 1.10 130,900.00 143,990.00
Bata merah bh 25.00 775.00 19,375.00
P.C (50 gk) zak 0.206 1,406.00 289.64
Pasir pasang m3 0.061 233,400.00 14,237.40
Pasir urug m3 0.069 175,300.00 12,095.70
Pekerja org 0.3800 42,000.00 15,960.00
Tukang batu org 0.1900 65,000.00 12,350.00
Kepala Tukang org 0.0190 75,000.00 1,425.00
Mandor org 0.0190 80,000.00 1,520.00
Jumlah 221,242.74
Dibulatkan 221,243.00
M-20 1 M' Pasang Talang Seng Datar
Seng pelat 3" x 6" lbr 0.50000 20,801.00 10,400.50
Paku kg 0.01500 23,400.00 351.00
Kayu kelas II m3 0.00960 2,850,000.00 27,360.00
Meni besi kg 0.2500 30,400.00 7,600.00
Pekerja org 0.1500 42,000.00 6,300.00
Tukang batu org 0.4000 65,000.00 26,000.00
Kepala Tukang org 0.0250 75,000.00 1,875.00
Mandor org 0.0013 80,000.00 100.00
Jumlah 79,986.50
Dibulatkan 79,987.00
M-21 1 Buah Closet Duduk
Closet duduk bh 1.00 1,724,700.00 1,724,700.00
Pekerja org 3.3000 42,000.00 138,600.00
Tukang batu org 1.1000 65,000.00 71,500.00
Kepala Tukang org 0.0010 75,000.00 75.00
Mandor org 0.1600 80,000.00 12,800.00
Perlengkapan 6 % harga closet lot 0.0600 1,724,700.00 103,482.00
Jumlah 2,051,157.00
Dibulatkan 2,051,157.00
No. URAIAN SAT VOLUME HARGA SAT HARGA
(Rp) (Rp)
M-22 1 Buah Tangki Air fibreglass Volume 1 m3
Bak fibreglass kapasitas 1 m3 bh 1.00 1,316,400.00 1,316,400.00
Pekerja org 3.3000 42,000.00 138,600.00
Tukang batu org 1.1000 65,000.00 71,500.00
Kepala Tukang org 0.0010 75,000.00 75.00
Mandor org 0.1600 80,000.00 12,800.00
Perlengkapan 6 % harga bak lot 0.0600 1,316,400.00 78,984.00
Jumlah 1,618,359.00
Dibulatkan 1,618,359.00
M-23 1 Unit Septictank 2x1,50x1,50 m + Rembesan
Galian tanah m3 4.500 26,252.00 118,134.00
Pasir urug m3 0.214 175,300.00 37,514.20
lantai kerja m3 2.250 716,798.00 1,612,795.50
Pas bata adk 1pc : 3ps m2 15.000 220,267.10 3,304,006.50
Pelat beton K-225 m3 0.300 6,438,864.00 1,931,659.20
Plesteran adk 1pc : 3ps m2 15.000 41,301.82 619,527.30
Pipa PVC 4" jenis AW m' 5.400 256,800.00 1,386,720.00
Pipa GIP 1 1/2" m' 5.000 46,750.00 233,750.00
Galian tanah untuk rembesan m3 3.375 20,000.00 67,500.00
Pas ijuk kg 5.400 23,400.00 126,360.00
Urugan kerikil 3/5 m3 1.050 205,000.00 215,250.00
Pipa PVC 4" berlubang jenis AW m' 9.000 36,700.00 330,300.00
Urugan dan perataan tanah m3 1.125 34,584.00 38,907.00
Jumlah 10,022,423.70
Dibulatkan 10,022,424.00
M-24 1 Unit Septictank 1x1,50x1,50 m + Rembesan
Galian tanah m3 2.250 20,000.00 45,000.00
Pasir urug m3 0.107 175,300.00 18,757.10
lantai kerja m3 1.125 716,798.00 806,397.75
Pas bata adk 1pc : 3ps m2 7.500 220,267.10 1,652,003.25
Pelat beton K-225 m3 0.150 6,438,864.00 965,829.60
Plesteran adk 1pc : 3ps m2 7.500 41,301.82 309,763.65
Pipa PVC 4" jenis AW m' 9.000 256,800.00 2,311,200.00
Pipa GIP 1 1/2" m' 2.500 46,750.00 116,875.00
Galian tanah untuk rembesan m3 1.688 20,000.00 33,760.00
Pas ijuk kg 2.700 23,400.00 63,180.00
Urugan kerikil 3/5 m3 0.525 205,000.00 107,625.00
Pipa PVC 4" berlubang jenis AW m' 9.000 36,700.00 330,300.00
Urugan dan perataan tanah m3 0.563 34,584.00 19,470.79
Jumlah 6,780,162.14
Dibulatkan 6,780,162.00
N. ANALISA HARGA SATUAN PEKERJAAN PENGECATAN
No. URAIAN SAT VOLUME HARGA SAT HARGA
N-01 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama
- Soda api Kg 0.0500 35,600.00 1,780.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 8,280.00
Dibulatkan 8,280.00
N-02 1 M2 Mendempul Dan Menggosok Kayu
- Dempul Kg 0.0800 35,800.00 2,864.00
- Minyak cat Kg 0.0200 38,400.00 768.00
- Batu apung Kg 0.0100 29,600.00 296.00
- Pekerja Oh 0.0400 42,000.00 1,680.00
- Tukang cat Oh 0.0400 65,000.00 2,600.00
- Kepala tukang Oh 0.0040 75,000.00 300.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 8,708.00
Dibulatkan 8,708.00
N-03 1 M2 Pengecatan Bidang Kayu Lama Setara Sieve
- Plamir Kg 0.1500 25,000.00 3,750.00
- Cat dasar Kg 0.1700 30,000.00 5,100.00
- Cat penutup setara sieve 2x Kg 0.1700 41,700.00 7,089.00
- Pekerja Oh 0.0700 42,000.00 2,940.00
- Tukang cat Oh 0.0750 65,000.00 4,875.00
- Kepala tukang Oh 0.0075 75,000.00 562.50
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 24,516.50
Dibulatkan 24,517.00
N-04 1 M2 Pengecatan Bidang Kayu Baru Setara Sieve
- Cat meni Kg 0.2000 30,400.00 6,080.00
- Plamir Kg 0.1500 25,000.00 3,750.00
- Cat dasar Kg 0.1700 30,000.00 5,100.00
- Cat penutup 3x setara sieve Kg 0.3500 41,700.00 14,595.00
- Pekerja Oh 0.0700 42,000.00 2,940.00
- Tukang cat Oh 0.1050 65,000.00 6,825.00
- Kepala tukang Oh 0.0040 75,000.00 300.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 39,790.00
Dibulatkan 39,790.00
N-05 1 M2 Pelaburan Bidang Kayu dengan Politur
- Politur Ltr 0.1500 48,000.00 7,200.00
- Politur jadi Ltr 0.3720 112,700.00 41,924.40
- Ampelas Lbr 2.0000 5,000.00 10,000.00
- Tukang cat Oh 0.0600 65,000.00 3,900.00
- Kepala tukang Oh 0.0160 75,000.00 1,200.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 64,424.40
Dibulatkan 64,424.00
N-06 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter
- Residu atau ter Ltr 0.3500 8,100.00 2,835.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 7,515.00
Dibulatkan 7,515.00
No. URAIAN SAT VOLUME HARGA SAT HARGA
N-07 1 M2 Pengecatan Tembok Baru Setara ICI
- Plamir tembok Kg 0.1000 25,000.00 2,500.00
- Cat dasar Kg 0.1000 30,000.00 3,000.00
- Cat penutup 2x setara ICI Kg 0.2600 75,000.00 19,500.00
- Pekerja Oh 0.0200 42,000.00 840.00
- Tukang cat Oh 0.0630 65,000.00 4,095.00
- Kepala tukang Oh 0.0063 75,000.00 472.50
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 30,607.50
Dibulatkan 30,608.00
N-08 1 M2 Pengecatan Tembok Lama Setara ICI
- Cat dasar Kg 0.1200 30,000.00 3,600.00
- Cat penutup 2 x Kg 0.1800 75,000.00 13,500.00
- Pekerja Oh 0.0280 42,000.00 1,176.00
- Tukang cat Oh 0.0420 65,000.00 2,730.00
- Kepala tukang Oh 0.0042 75,000.00 315.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 21,521.00
Dibulatkan 21,521.00
N-09 1 M2 Pengecatan Plafond ( 3x ) Setara ICI
- Cat tembok setara ICI Kg 0.2000 75,000.00 15,000.00
- Plamir tembok Kg 0.1600 25,000.00 4,000.00
- Rol cat Bh 0.0100 32,500.00 325.00
- Steger werk Ls 1.0000 1,000.00 1,000.00
- Ampelas Lbr 0.5000 5,000.00 2,500.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang cat Oh 0.3000 65,000.00 19,500.00
- Kepala tukang Oh 0.0300 75,000.00 2,250.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 53,775.00
Dibulatkan 53,775.00
N-10 1 M2 Pengecatan Plafond ( 3x ) Setara Vinilex
- Cat tembok setara Vinilex Kg 0.2000 25,000.00 5,000.00
- Plamir tembok Kg 0.1600 25,000.00 4,000.00
- Rol cat Bh 0.0100 32,500.00 325.00
- Steger werk Ls 1.0000 1,000.00 1,000.00
- Ampelas Lbr 0.5000 5,000.00 2,500.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang cat Oh 0.3000 65,000.00 19,500.00
- Kepala tukang Oh 0.0300 75,000.00 2,250.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 43,775.00
Dibulatkan 43,775.00
N-10-r' 1 M2 Pengecatan Plafond ( 2x ) Setara Vinilex
- Cat tembok setara Vinilex Kg 0.1300 25,000.00 3,250.00
- Plamir tembok Kg 0.1100 25,000.00 2,750.00
- Rol cat Bh 0.1000 32,500.00 3,250.00
- Steger werk Ls 0.6700 1,000.00 670.00
- Ampelas Lbr 0.3300 5,000.00 1,650.00
- Pekerja Oh 0.1300 42,000.00 5,460.00
- Tukang cat Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 32,330.00
Dibulatkan 32,330.00
N-11 1 M2 Memasang Wallpaper
- Wallpaper m2 1.2000 55,700.00 66,840.00
- Lem Perekat Kg 0.2500 35,700.00 8,925.00
- Pekerja Oh 0.3500 42,000.00 14,700.00
- Tukang cat Oh 0.1750 65,000.00 11,375.00
- Kepala tukang Oh 0.0170 75,000.00 1,275.00
- Mandor Oh 0.0017 80,000.00 136.00
Jumlah 103,251.00
Dibulatkan 103,251.00
No. URAIAN SAT VOLUME HARGA SAT HARGA
N-12 1 M2 Pengecatan Permukaan Baja dengan Meni Besi
- Meni besi Kg 0.1000 30,400.00 3,040.00
- Kuas 3" Bh 0.0100 16,000.00 160.00
- Pekerja Oh 0.0200 42,000.00 840.00
- Tukang cat Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 19,340.00
Dibulatkan 19,340.00
N-13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah
- Meni besi Kg 0.1000 30,400.00 3,040.00
- Kuas 3" Bh 0.0100 16,000.00 160.00
- Kayu perancah m3 0.0020 2,069,800.00 4,139.60
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang cat Oh 0.2250 65,000.00 14,625.00
- Kepala tukang Oh 0.0225 75,000.00 1,687.50
- Mandor Oh 0.0075 80,000.00 600.00
Jumlah 34,752.10
Dibulatkan 34,752.00
N-14 1 M2 Pengecatan Permukaan Baja Lapis seng (galbani) secara manual 1 lps cat 2 um
- Cat besi setara ICI Kg 0.3000 67,700.00 20,310.00
- Pekerja Oh 0.0060 42,000.00 252.00
- Tukang cat Oh 0.0600 65,000.00 3,900.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 25,842.00
Dibulatkan 25,842.00
N-15 1 M2 Pengecatan Tembok Baru Setara Vinilex (2 x laburan)
- Plamir tembok Kg 0.1000 25,000.00 2,500.00
- Cat dasar Kg 0.1000 30,000.00 3,000.00
- Cat penutup 2x setara vinilex Kg 0.2600 25,000.00 6,500.00
- Pekerja Oh 0.0200 42,000.00 840.00
- Tukang cat Oh 0.0630 65,000.00 4,095.00
- Kepala tukang Oh 0.0063 75,000.00 472.50
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 17,607.50
Dibulatkan 17,608.00
N-15r' 1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan)
- Plamir tembok Kg 0.1000 25,000.00 2,500.00
- Cat dasar Kg 0.1000 30,000.00 3,000.00
- Cat penutup 3x setara vinilex Kg 0.3900 25,000.00 9,750.00
- Pekerja Oh 0.0300 42,000.00 1,260.00
- Tukang cat Oh 0.0945 65,000.00 6,142.50
- Kepala tukang Oh 0.0095 75,000.00 712.50
- Mandor Oh 0.0038 80,000.00 304.00
Jumlah 23,669.00
Dibulatkan 23,669.00
N-16 1 M2 Pengecatan Tembok Lama Setara Vinilex
- Cat dasar Kg 0.1200 30,000.00 3,600.00
- Cat penutup 2 x Kg 0.1800 25,000.00 4,500.00
- Pekerja Oh 0.0280 42,000.00 1,176.00
- Tukang cat Oh 0.0420 65,000.00 2,730.00
- Kepala tukang Oh 0.0042 75,000.00 315.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 12,521.00
Dibulatkan 12,521.00
O. PEKERJAAN PENANAMAN POHON
NO. URAIAN KOEF SAT. HARGA SAT. (Rp) HARGA (Rp)
O-01 1 Lubang (70x70x70) cm, tanam pohon pelindung tinggi 2m
Pupuk kandang 0.0800 krg 25,000.00 2,000.00
Furadan 0.0010 kg 24,000.00 24.00
Pohon pelindung 1.0000 btng 25,000.00 25,000.00
Pekerja 0.0250 org 42,000.00 1,050.00
Mandor 0.0025 org 80,000.00 200.00
Jumlah 28,274.00
Dibulatkan 28,274.00
O-02 1 Lubang (70x70x70) cm, tanam bambu krisik/jepang
Pupuk kandang 0.0800 krg 25,000.00 2,000.00
Furadan 0.0010 kg 24,000.00 24.00
Bambu krisik/jepang 1.0000 btng 50,000.00 50,000.00
Pekerja 0.0250 org 42,000.00 1,050.00
Mandor 0.0025 org 80,000.00 200.00
Jumlah 53,274.00
Dibulatkan 53,274.00
O-03 1 Lubang (40x40x40) cm, tanam pohon perdu (polibag)
Pupuk kandang 0.0400 krg 25,000.00 1,000.00
Furadan 0.0010 kg 24,000.00 24.00
Pohon perdu 1.0000 btng 10,000.00 10,000.00
Pekerja 0.0200 org 42,000.00 840.00
Mandor 0.0020 org 80,000.00 160.00
Jumlah 12,024.00
Dibulatkan 12,024.00
O-04 1 M2 Tanam rumput gajah (silang papan catur)
Pupuk kandang 0.0400 krg 25,000.00 1,000.00
Rumput gajah mini 0.5000 m2 15,000.00 7,500.00
Pekerja 0.0400 org 42,000.00 1,680.00
Mandor 0.0040 org 80,000.00 320.00
Jumlah 10,500.00
Dibulatkan 10,500.00
NO URAIAN SATUAN UPAH (Rp.) KETERANGAN
1 Mandor Org/hr 80,000.00 Rp
2 Kepala Tukang Batu Org/hr 75,000.00 Rp
3 Kepala Tukang Kayu Org/hr 75,000.00 Rp
4 Kepala Tukang Besi Org/hr 75,000.00 Rp
5 Kepala Tukang Cat Org/hr 75,000.00 Rp
6 Kepala Tukang Listrik Org/hr 75,000.00 Rp
7 Kepala Tukang Org/hr 75,000.00 Rp
8 Tukang Batu Org/hr 65,000.00 Rp
9 Tukang Kayu Org/hr 65,000.00 Rp
10 Tukang Besi/Baja Org/hr 65,000.00 Rp
11 Tukang Cat Org/hr 65,000.00 Rp
12 Tukang Listrik Org/hr 65,000.00 Rp
13 Tukang Pipa Org/hr 65,000.00 Rp
14 Tukang Plitur Org/hr 65,000.00 Rp
15 Tukang Taman Org/hr 65,000.00 Rp
16 Tukang Org/hr 65,000.00 Rp
17 Pembantu Tukang Org/hr 42,000.00 Rp
18 Pekerja Biasa Org/hr 42,000.00 Rp
19 Penjaga Malam Org/hr 42,000.00 Rp
20 Sopir Org/hr 65,000.00 Rp
21 Operator Org/hr 75,000.00 Rp
22 Mekanik Org/hr 65,000.00 Rp
23 Pembantu Sopir Org/hr 42,000.00 Rp
24 Pembantu Operator Org/hr 50,000.00 Rp
25 Pembantu Mekanik Org/hr 42,000.00 Rp
harga sudah termasuk PPN dan keuntungan
DAFTAR HARGA SATUAN UPAH
NO MATERIAL SAT HARGA (Rp)
A. AGREGAT KASAR,BAHAN PEREKAT & BAHAN JADINYA
1 Pasir Urug m3 175,300.00
2 Tanah Urug Pilihan m3 89,200.00
3 Sirtu m3 203,500.00
4 Pasir Teras m3 174,200.00
5 Pasir Pasang Kali m3 233,400.00
6 Pasir Beton m3 255,400.00
7 Abu Batu m3 259,000.00
8 Batu Gosok ( Apung ) kg 29,600.00
9 Batu Pecah Mesin 1/2 m3 223,600.00
10 Batu Pecah Mesin 2/3 m3 211,100.00
11 Batu Pecah Mesin 3/5 m3 205,000.00
12 Batu Pecah Mesin 5/7 m3 196,000.00
13 Batu Belah Pondasi m3 205,500.00
14 Batu Bronjol ( Untuk Bronjong ) m3 180,800.00
15 Batu Koral Beton Kali m3 172,600.00
16 Batu Tempel Hitam m3 96,600.00
17 Batu Pinggir Beton 10 x 20 x 35 bh 14,100.00
18 Batu Pinggir Beton 15 x 35 x 50 ( K-225 ) bh 73,700.00
19 Batu Telor m3 97,800.00
20 Batako Kecil 8 x 10 x 20 bh 2,000.00
21 Batako Besar 8 x 20 x 30 bh 2,400.00
22 Con Blok 8 x 20 x 40 bh 5,400.00
23 Bata Merah Bakar kelas I bh 775.00
24 Bata Merah Bakar kelas II bh 675.00
25 Bata Merah Oven ( Klingker ) bh 1,800.00
26 Roster Beton 20 x 20 bh 14,800.00
27 Roster Beton 30 x 30 bh 15,500.00
28 Grass Blok 20 x 20 bh 9,700.00
29 Grass Blok 30 x 30 bh 22,500.00
30 Paving Blok Natural 8 cm m2 81,100.00
31 Paving Blok Warna 8 cm m2 108,600.00
32 Paving Blok Natural 6 cm m2 76,000.00
33 Paving Blok Warna 6 cm m2 86,000.00
34 Canstin Paving Blok m1 34,900.00
35 Semen PC /50 kg zak 70,300.00
1,406.00
36 Semen Putih zak 92,700.00
37 Kanstin Jalan Ukuran Besar ( Bina Marga ) 1bh =60cm bh 58,900.00
38 Readymix Beton K500, Tanpa Pompa ( Selang ) m3 1,105,000.00
39 Readymix Beton K400, Tanpa Pompa ( Selang ) m3 903,500.00
40 Readymix Beton K350, Tanpa Pompa ( Selang ) m3 877,500.00
41 Readymix Beton K300, Tanpa Pompa ( Selang ) m3 925,000.00
42 Readymix Beton K225, Tanpa Pompa ( Selang ) m3 850,000.00
43 Readymix Beton K175, Tanpa Pompa ( Selang ) m3 825,000.00
44 Kapur Pasang / Kapur Tembok m3 353,300.00
45 Kapur Sirih kg 18,300.00
46 Semen Warna kg 15,700.00
47 Tanah liat m3 31,300.00
48 Air ltr 3.00
DAFTAR HARGA SATUAN BAHAN BANGUNAN
Page 81 BHN
NO MATERIAL SAT HARGA (Rp)
49 Formite/spacer bh 2,500.00
50 Hollow/Con Blok 8 x 20 x 40 bh 5,000.00
51 Hollow/Con Blok 8 x 15 x 40 bh 4,000.00
52 Hollow/Con Blok 8 x 10 x 40 bh 3,000.00
B LABURAN,PENGISI DAN ALATNYA
1 Plamir Tembok kg 25,000.00
2 Cat Tembok ICI Eksterior ( Beton ) lt 120,000.00
3 Cat Tembok ICI Interior ( Plafon Dan Dinding ) lt 75,000.00
4 Cat Tembok Vinilex kg 25,000.00
5 Cat Dasar ICI untuk Interior ( 2 Pelapis ) lt 75,000.00
6 Cat Tembok Sanlek kg 20,000.00
7 Cat Dasar kg 30,000.00
8 Cat Tahan Asam lt 40,000.00
9 Pelapis Alkali ICI ( Cat Dasar Beton Ekterior ) kg 90,000.00
10 Cat Marka / Spotlight kg 185,000.00
11 Water Profing Emulsion ml 70,000.00
12 Water Profing Membrance bh 62,500.00
13 Rool Cat Tembok bh 32,500.00
14 Kape Tembok bh 8,500.00
15 Kape Kayu 5 lt 10,000.00
16 Soligneum 1 Blek kg 25,000.00
17 Plincote m3 29,000.00
18 Penawetan Kayu m3 382,600.00
19 Pegopenan Kayu bh 370,000.00
20 Kwas 3" bh 16,000.00
21 Oker bks 22,000.00
22 Oyan bks 5,200.00
23 Oten ( Pewarna Plitur ) lt 5,500.00
24 Spirtus kg 15,000.00
25 Bahan Pelitur Kripik ( Sirlak India ) kg 110,000.00
26 Dempul Lilin kg 34,200.00
27 Dempul Plitur kg 37,700.00
28 Dempul Halus / Imfra ( Wood Filler ) lt 37,700.00
29 Dempul Jadi kg 35,800.00
30 Politur lt 48,000.00
31 Politur Jadi lt 112,700.00
32 Terpentin kg 19,500.00
33 Tiner A kg 23,900.00
34 Tiner B kg 21,400.00
35 Kumpon lbr 30,800.00
36 Melamik kg 52,500.00
37 Dempul Plastik kg 39,200.00
38 Dempul Duco kg 35,800.00
39 Ampelas lbr 5,000.00
40 Dempul Kayu Cap Kucing kg 24,400.00
41 Meni Kayu / Besi kg 30,400.00
42 Sincromat kg 40,900.00
43 Cat Kayu Sieve lt 41,700.00
44 Cat Besi lt 44,000.00
45 Cat Besi Duco Danaglos / ICI bh 76,300.00
Page 82 BHN
NO MATERIAL SAT HARGA (Rp)
46 Cat Bron kg 67,700.00
47 Karet lis bh 3,300.00
48 Minyak cat kg 38,400.00
49 Glass beet kg 50,100.00
50 Residu lt 8,100.00
C BAHAN KAYU BERIKUT BAHAN JADINYA
1 Bambu 5 s.d 7 bt 17,700.00
2 Bambu 7 s.d 10 bt 25,000.00
3 Bambu Gombong bt 37,200.00
4 Kayu Kamper Singkil / Kapur ( Kayu Samarinda kls II ) m3 7,094,450.00
5 Kayu Balok Borneo Super m3 5,280,000.00
6 Kayu Papan Borneo Super m3 5,595,800.00
7 Kayu Balok Kamper Medan (Kruing ) m3 5,692,600.00
8 Kayu Papan Kamper Medan (Kruing ) m3 5,823,400.00
9 Kayu Balok Kamper Banjar m3 6,363,600.00
10 Kayu Papan Kamper Banjar m3 6,645,300.00
11 Kayu Balok Kamper Samarinda m3 8,633,700.00
12 Kayu Papan Kamper Samarinda m3 8,724,300.00
13 Kayu Balok Rasamala m3 2,658,000.00
14 Kayu Jati Jatim Tua dia. 40 cm m3 20,772,000.00
15 Kayu Jati Jateng Tua dia. 40 cm m3 22,188,400.00
16 Kayu Jati Jabar Tua dia. 40 cm m3 13,625,400.00
17 Kayu Jati Jabar Tua dia. 40 cm kebawah m3 12,736,100.00
18 Kayu Hutan Kelas I ( Segeng,Mahoni, Laban ) m3 2,069,800.00
19 Kayu Balok Albasia m3 1,870,500.00
20 Kayu Papan Albasia m3 2,071,700.00
21 Dolken 5 s/d 7 bt 22,600.00
22 Dolken 7 s/d 10 bt 28,000.00
23 List Profil Kamper 1 cm m1 8,900.00
24 List Profil Kamper 2 cm m1 10,000.00
25 List Profil Kamper 4 cm m1 14,300.00
26 List Profil Kamper 5 cm m1 17,200.00
27 List Profil Kamper 10 cm m1 29,400.00
28 Pegangan Tangga Profil Jati m1 160,100.00
29 Pegangan Tangga Profil Kamper m1 122,500.00
30 Kayu Kaso 4/6 m3 2,772,000.00
31 Kayu Kaso 5/7 Kamper Medan m3 3,356,800.00
32 Kayu Reng 2/3 Borneo Super m1 2,500.00
33 Kayu Reng 2/3 Kamper Banjar m1 3,300.00
34 Kayu Reng 3/4 Kamper Medan m3 4,000.00
35 Kayu Papan Terentang m3 2,850,000.00
36 Kayu Balok Terentang m3 2,640,000.00
37 Batang Kelapa bt 139,500.00
38 Tali Ijuk kg 23,400.00
39 lapisan Ijuk tebal 10 cm m2 22,000.00
40 Venetion Blind m2 537,300.00
41 Vertikal Blind m2 351,200.00
D BAHAN PENUTUP RANGKA PLAFOND
1 Plafond Enternit 4 mm m2 17,400.00
2 Plafond hardpleks 5 mm 120 x 240 lbr 62,400.00
Page 83 BHN
NO MATERIAL SAT HARGA (Rp)
3 Plafond Asbes Semen 5 mm m2 22,500.00
4 Plafond Asbes Semen 3,5 mm m2 19,500.00
5 Gypsum 120 x 240 t= 9 mm ex DN lbr 79,800.00
6 Gypsum 120 x 240 t= 9 mm ex Luar lbr 83,800.00
7 Tepung gypsum kg 12,500.00
8 Acustik Amstrong 60 x 120 lbr 132,800.00
9 Cotton Plester bh 15,000.00
10 GRC (120 x 240) cm, t = 4 mm lbr 67,500.00
11 Cornice Coumpound zak 75,000.00
12 List gypsum m' 8,500.00
E BAHAN KAYU LAPIS
1 Triplek 3 mm 120 x 240 lbr 61,700.00
2 Triplek 4 mm 120 x 240 lbr 64,400.00
3 Triplek 4 mm ukuran Pintu lbr 56,200.00
4 Triplek 6 mm 120 x 240 lbr 92,000.00
5 Triplek 9 mm 120 x 240 lbr 166,600.00
6 Jabar Wood 4 mm lbr 119,000.00
7 Bilik Bambu ( tanpa kulit ) m2 19,800.00
8 Bilik Bambu ( dengan kulit ) m2 22,700.00
9 Bilik Bambu Hitam Variasi m2 34,200.00
10 Wall paper m2 55,700.00
11 MultiPlek 9 mm 120 x 240 lbr 151,100.00
12 MultiPlek 12 mm 120 x 240 lbr 195,000.00
13 MultiPlek 18 mm 120 x 240 lbr 255,400.00
14 Ply Wood 18 mm 120 x 240 lbr 323,900.00
15 Ply Wood 9 mm 120 x 240 lbr 235,000.00
16 Ply Wood 4 mm 120 x 240 lbr 140,000.00
17 Teak Wood 3 mm 120 x 240 lbr 129,100.00
18 Teak Wood 4 mm 120 x 240 lbr 131,700.00
19 Teak Wood 3 mm 120 x 240 ukuran Pintu lbr 127,200.00
20 Teak Wood ukuran Pintu 4 mm lbr 114,700.00
21 Tacon ( Tahan Bakar ) m2 128,200.00
22 Supercon m2 57,900.00
23 Melamin 4 mm 120 x 240 lbr 89,200.00
24 Melamin TOK 4 mm lbr 133,400.00
25 Formika 120 x 240 lbr 170,000.00
26 Formika ukuran Pintu lbr 132,900.00
27 Formika Warna 4" x 8" lbr 238,100.00
F BAHAN LANTAI DAN PELAPIS DINDING
1 Tegel PC 20 x 20 bh 3,400.00
2 Plin Tegel PC 10 x 20 bh 2,400.00
3 Tegel PC 30 x 30 bh 3,400.00
4 Plin Tegel PC 15 x 30 bh 2,800.00
5 Tegel Warna 20 x 20 bh 3,600.00
6 Plin Tegel Warna 10 x 20 bh 3,400.00
7 Tegel Warna 30 x 30 bh 5,700.00
8 Plin Tegel Warna 15 x 30 bh 6,300.00
9 Tegel Wafel PC 20 x 20 bh 3,200.00
10 Tegel Wafel Warna 20 x 20 bh 2,500.00
Page 84 BHN
NO MATERIAL SAT HARGA (Rp)
11 Tegel Badak PC 30 x 30 bh 4,100.00
12 Poslin 11 x 11 Warna Standar DN m2 63,300.00
13 Poslin 11 x 11 Warna khusus DN m2 67,300.00
14 Keramik 10 x 20 dan 20 x 20 KW I DN Putih / Polos Mulia m2 54,500.00
15 Keramik 10 x 20 KW I DN Corak/Warna/Anti Slip Mulia m2 56,000.00
16 Keramik 20 x 20 (KM) KW I DN Corak/Warna /Anti Slip Mulia m2 62,500.00
17 Keramik 20 x 20 (KM) KW I DN Putih Polos Mulia m2 54,500.00
18 Keramik 20 x 25 Dinding KM KW I DN Corak Mulia m2 62,500.00
19 Keramik 30 x 30 KWI DN Putih Polos Mulia m2 53,000.00
20 Keramik 30 x 30 KWI DN Warna/Corak (ANTI SLIP) Mulia m2 58,000.00
21 Keramik 40 x 40 KWI DN Putih Polos Mulia m2 56,800.00
22 Keramik 40 x 40 KWI DN Warna/Corak (ANTI SLIP) Mulia m2 65,500.00
23 Keramik 10 x 20 dan 20 x 20 KW I DN Putih / Polos Roman m2 64,400.00
24 Keramik 10 x 20 KW I DN Corak/Warna/Anti Slip Roman m2 72,200.00
25 Keramik 20 x 20 (KM) KW I DN Corak/Warna/Anti Slip Roman m2 75,200.00
26 Keramik 20 x 20 (KM) KW I DN Putih Polos Roman m2 72,900.00
27 Keramik 20 x 25 Dinding KM KW I DN Corak Roman m2 75,200.00
28 Keramik 20 x 25 KW I DN Putih Polos Roman m2 72,900.00
29 Keramik 30 x 30 KW I DN Polos Roman m2 68,900.00
30 Keramik 30 x 30 KW I DN Warna/Corak (ANTI SLIP) Roman m2 76,600.00
31 Keramik 40 x 40 KW I DN Polos Roman m2 72,500.00
32 Keramik 40 x 40 KW I DN Warna/Corak (ANTI SLIP) Roman m2 77,000.00
33 Vinyl Lantai Standar m2 56,000.00
34 Karpet Kelas Baik LN m2 1,025,500.00
35 Karpet Kelas Sedang LN m2 353,500.00
36 Parquet Jati m2 375,400.00
37 Stairnosing Keramik 10/20 bh 13,700.00
38 Stairnosing Fiber m 25,000.00
39 Taraso Kerang 30 x 30 m2 31,800.00
40 Plin Taraso 10 x 30 bh 13,500.00
41 Granit Alam LN Ukuran Besar m2 1,848,400.00
42 Granit Alam LN Ukuran Kecil m2 1,612,900.00
43 Granit Alam DN Ukuran Besar m2 1,331,100.00
44 Granit Alam DN Ukuran Kecil m2 1,299,400.00
45 Granito Tile Essenza Ukuran 40 x 40 Polis m2 345,000.00
46 Granito Tile Essenza Ukuran 30 x 30 m2 322,800.00
47 Granito Tile Essenza Ukuran 40 x 40 UnPolis m2 204,900.00
48 Marmer m2 550,000.00
49 Marmer Alam Lampung Ukuran Besar m2 550,200.00
50 Marmer Alam Lampung Ukuran kecil m2 345,700.00
51 Marmer Alam Citatah Ukuran Besar m2 340,800.00
52 Marmer Alam Citatah Ukuran Kecil m2 237,600.00
53 Marmer Sintetis m2 157,900.00
54 Granito Tile Essenza 60 x 60 Polis m2 358,100.00
55 Granito Tile Essenza 60 x 60 UnPolis m2 231,800.00
56 Batu Tempel Hitam m2 96,500.00
57 Bata Karawang bh 600.00
58 Campuran untuk Kedap Air ( AM ) ltr 37,600.00
59 Plint keramik 10 x 20 bh 3,000.00
60 Plint keramik 10 x 25 bh 3,250.00
Page 85 BHN
NO MATERIAL SAT HARGA (Rp)
61 Plint keramik 10 x 30 bh 3,500.00
62 Plint keramik 10 x 40 bh 4,000.00
63 Plint keramik 15 x 30 bh 4,500.00
64 Plint keramik 15 x 40 bh 5,250.00
65 Plint granito 10 x 30 bh 25,900.00
66 Plint granito 10 x 40 bh 27,600.00
67 Plint granito 15 x 30 bh 31,100.00
68 Plint granito 15 x 40 bh 41,300.00
G BAHAN SALURAN AIR KOTOR / BERSIH
1 Grafel U 20 cm' m1 44,300.00
2 Grafel U 30 cm' m1 56,400.00
3 Grafel U 40 cm' m1 74,200.00
4 Buis Beton 20 cm ( 1 M' ) m1 49,200.00
5 Buis Beton 30 cm ( 1 M' ) m1 61,700.00
6 Buis Beton 40 cm ( 1 M' ) m1 80,900.00
7 Buis Beton 50 cm ( 1 M' ) stk 94,300.00
8 Buis Beton 60 cm ( 1 M' ) stk 130,900.00
9 Buis Beton 100 cm ( 0.50 M' ) stk 299,800.00
10 Buis Beton 80 cm ( 0.50 M' ) stk 298,500.00
11 BuisTanah 10 cm ( 0.50 M' ) stk 9,600.00
12 BuisTanah 15 cm ( 0.50 M' ) stk 12,700.00
13 BuisTanah 20 cm ( 0.50 M' ) stk 16,800.00
14 BuisTanah 25 cm ( 0.50 M' ) stk 22,800.00
15 Injuk kg 17,400.00
H BAHAN LOGAM DAN BAHAN JADINYA
1 Besi Beton U-24 Rata-rata kg 16,500.00
2 Besi Beton U-39 / U-32 Rata-rata kg 20,700.00
3 Pagar BRC lengkap tiang ( Tanpa Pondasi ) m2 171,300.00
4 Bondek m2 185,000.00
5 Besi WF Ex DN SII kg 24,000.00
6 Besi WF Ex Jepang kg 23,900.00
7 Besi Profil DN SII kg 18,300.00
8 Besi Profil Ex LN kg 21,600.00
9 Besi C Lip Chanel kg 19,200.00
10 Ongkos Galfanis Besi kg 10,600.00
11 Kawat Beton kg 27,700.00
12 Kawat Duri kg 63,500.00
13 Kawat Pengikat m1 1,000.00
14 Kawat Bronjong 4 mm kg 28,200.00
15 Kawat Tembaga kg 41,400.00
16 Ram Nyamuk Hijau m2 13,400.00
17 Ram Kawat 1 x 1 cm m2 15,300.00
18 Ram Ayam m2 14,900.00
19 Kawat Kasa 1 x 1 ( Putih ) m2 32,100.00
20 Kawat Harmonika 4 cm m2 35,900.00
21 Kawat Harmonika 2 cm m2 28,600.00
22 Kawat Las Listrik kg 23,600.00
23 Wiremesh M8 m2 51,900.00
24 Wiremesh M6 m2 38,700.00
Page 86 BHN
NO MATERIAL SAT HARGA (Rp)
25 Timah kg 46,300.00
26 Timah Hitam kg 43,300.00
27 Ram nyamuk Alumunium m2 32,400.00
28 Plat Srip 2 x 30 mm ( 6 m1 ) bt 33,000.00
29 Plat Srip 3 x 30 mm ( 6 m1 ) bt 33,100.00
30 Plat Strip bt 18,200.00
31 Besi Strip kg 26,800.00
32 Plat Alumunium 0.2 mm m2 89,800.00
33 Plat Alumunium 0.3 mm m2 110,500.00
34 Plat Alumunium 0.4 mm m2 141,400.00
35 Plat Alumunium 0.5 mm m2 143,100.00
36 Plat Alumunium 0.6 mm m2 171,800.00
37 Plat Alumunium 0.1 mm m2 56,300.00
38 Kusen Alumunium Natural 1.3 mm t= 1,3 mm ( 4 " ) m1 151,100.00
39 Kusen Alumunium Warna 1.3 mm t= 1,3 mm ( 4 " ) m1 163,000.00
40 Kusen Alumunium Natural 1.3 mm t= 1,3 mm ( 3 " ) m1 81,000.00
41 Kusen Alumunium Warna 1.3 mm t= 1,3 mm ( 3 " ) m1 102,000.00
42 Daun Jendela Alumunium Natural ( tanpa kaca dan accessories ) m2 98,800.00
43 Daun Jendela Alumunium Warna ( tanpa kaca dan accessories ) m2 148,800.00
44 Daun Pintu Alumunium Natural ( tanpa kaca dan accessories ) m2 211,800.00
45 Daun Pintu Alumunium Warna ( tanpa kaca dan accessories ) m2 207,500.00
46 Handle Alumunium ( Tarikan Pintu Alumunium ) bh 345,200.00
47 Kait Angin Alumunium ps 104,500.00
48 Karet Asisoris Kusen / Pintu Alumunium m1 7,500.00
49 Jalusi Alluminium m' 35,000.00
50 Sunscreen Almunium m2 380,200.00
51 Seng Plat BJLS 30 60 cm ( 100 m1 ) roll 1,581,500.00
52 Seng Plat BJLS 30 90 cm ( 100 m1 ) roll 2,080,100.00
53 Plat Besi Tipis 1 mm kg 16,800.00
54 Plat Besi Tipis 0.5 mm kg 17,700.00
55 Plat Besi 2 mm s/d 5 mm kg 14,100.00
56 Plat Besi 6 mms/d 10 mm kg 14,100.00
57 Plat Besi 10 mm keatas kg 14,700.00
58 Kabel presstressed polos kg 26,700.00
59 Jaring Kawat Baja kg 28,900.00
60 Lem Kuning ( Aibond ) kg 35,700.00
61 Lem Fox kg 23,900.00
62 Lem Vinyl kg 44,000.00
63 Besi Strip Kaca Nako kg 11,000.00
64 Profil alumunium "T" m1 12,200.00
65 Besi Hallow ( 2 x 4 x 4) cm (400cm) btg 22,600.00
66 Besi Hallow ( 4 x 4) cm (400 cm) btg 29,200.00
67 Besi Rail Pengamanan kg 459,300.00
68 Jendela Besi m2 390,200.00
69 Jendela Besi tahan api m2 501,700.00
70 Pintu gulung besi m2 501,700.00
71 Pintu Roliing Door m2 306,600.00
72 Jendela nako kaca ryben + tralis 6 klips set 170,000.00
73 Jendela nako kaca ryben + tralis 7 klips set 200,000.00
74 Jendela nako kaca ryben + tralis 8 klips set 230,000.00
75 Jendela nako kaca ryben + tralis 10 klips set 290,000.00
Page 87 BHN
NO MATERIAL SAT HARGA (Rp)
76 Jendela nako kaca bening + tralis 4 klips set 120,000.00
77 Jendela nako kaca bening + tralis 5 klips set 140,000.00
78 Jendela nako kaca bening + tralis 6 klips set 170,000.00
79 Jendela nako kaca bening + tralis 7 klips set 210,000.00
80 Jendela nako kaca bening + tralis 8 klips set 230,000.00
81 Jendela nako kaca bening + tralis 10 klips set 300,000.00
I BAHAN KACA
1 Kaca Polos 2 mm ( ASAHI ) m2 69,000.00
2 Kaca Polos 3 mm ( ASAHI ) m2 87,400.00
3 Kaca Polos 5 mm ( ASAHI ) m2 111,000.00
4 Kaca Polos 8 mm ( ASAHI ) m2 183,100.00
5 Kaca Rayband 5 mm ( ASAHI ) m2 148,700.00
6 Kaca Rayband 8 mm ( ASAHI ) m2 323,400.00
7 Kaca Rayband 12 mm ( ASAHI ) m2 627,000.00
8 Kaca cermin 5 mm m2 150,500.00
9 Kaca cermin 6 mm m2 186,400.00
10 Kaca cermin 8 mm m2 234,300.00
11 Kaca Patri Lokal Terpasang ( ASAHI ) m2 1,621,100.00
12 Kaca Patri Ex Luar Negeri Terpasang m2 3,425,700.00
13 Kaca 6 mm Gravver m2 1,263,900.00
14 Glass Block DN 20 x 20 ( Kedawung ) bh 22,000.00
15 Glass Block DN 20 x 20 Ex LN bh 125,700.00
16 Sealant kg 211,800.00
17 Jendela Nako bh 109,200.00
J BAHAN PAKU DAN MUR BAUT
1 Paku 1/2" s/d 2" kg 23,800.00
2 Paku 2" s/d 5" kg 23,400.00
3 Paku 8 cm s/d 15 cm kg 20,000.00
4 Paku Beton 2 cm s/d 5 cm bh 1,600.00
5 Paku Kait Lengkap bh 900.00
6 Paku Cacing kg 57,100.00
7 Besi Beugel Kuda - Kuda kg 21,700.00
8 Duk Angker bh 7,500.00
9 Angker Mur Baut dia. 19 / Panjang 60 cm bh 71,800.00
10 Mur Baut HTB dia. 19 s/d 16 ( 5 cm ) bh 15,900.00
11 Mur Baut Biasa dia. 19 s/d 16 ( 5 cm ) bh 9,300.00
12 Piser dia.12 s/d 20 cm bh 5,300.00
13 Paku skrup 3" bh 800.00
14 Ramset / Dinabolt bh 7,200.00
15 Baut Besar bh 600.00
16 Baut Kecil bh 300.00
17 Paku GRC kg 35,000.00
18 Paku gypsum kg 17,500.00
19 Sekrup fixer bh 250.00
K BAHAN PERPIPAAN
1 Besi Pipa Untuk Hydrant BSP 1" bt 166,700.00
2 Besi Pipa Untuk Hydrant BSP 1.25" bt 210,200.00
3 Besi Pipa Untuk Hydrant BSP 1.5" bt 298,000.00
Page 88 BHN
NO MATERIAL SAT HARGA (Rp)
4 Besi Pipa Untuk Hydrant BSP 2" bt 351,800.00
5 Besi Pipa Untuk Hydrant BSP 2.5" bt 439,300.00
6 Besi Pipa Untuk Hydrant BSP 3" bt 595,000.00
7 Besi Pipa Untuk Hydrant BSP 4" bt 869,600.00
8 Besi Pipa Untuk Hydrant BSP 6" bt 1,423,400.00
9 Besi Pipa Hitam 1" t = 2 mm bt 172,300.00
10 Besi Pipa Hitam 2" t = 2 mm bt 227,900.00
11 Besi Pipa Hitam 3" t = 2mm bt 365,800.00
12 Besi Pipa Hitam 4" t = 2 mm bt 573,100.00
13 Besi Pipa Hitam 6" t = 2 mm bt 772,400.00
14 Pipa GIP Medium A 1/2" ( 6 m1 ) bt 109,100.00
15 Pipa GIP Medium A 3/4" ( 6 m1 ) bt 159,400.00
16 Pipa GIP Medium A 1" ( 6 m1 ) bt 181,500.00
17 Pipa GIP Medium A 1 1/4" ( 6 m1 ) bt 259,300.00
18 Pipa GIP Medium A 1 1/2" ( 6 m1 ) bt 280,500.00
19 Pipa GIP Medium A 1 3/4" ( 6 m1 ) bt 326,400.00
20 Pipa GIP Medium A 2" ( 6 m1 ) bt 467,400.00
21 Pipa GIP Medium A 2 1/2" ( 6 m1 ) bt 672,100.00
22 Pipa GIP Medium A 3" ( 6 m1 ) bt 849,900.00
23 Pipa GIP Medium A 4" ( 6 m1 ) bt 920,300.00
24 Macam2 Sambungan GIP 1/2" bh 6,300.00
25 Macam2 Sambungan GIP 3/4" bh 8,600.00
26 Macam2 Sambungan GIP 1" bh 16,700.00
27 Macam2 Sambungan GIP 1 1/4" bh 19,800.00
28 Macam2 Sambungan GIP 1 1/2" bh 20,700.00
29 Macam2 Sambungan GIP 1 3/4" bh 22,700.00
30 Macam2 Sambungan GIP 2" bh 51,200.00
31 Macam2 Sambungan GIP 2 1/2" bh 60,400.00
32 Macam2 Sambungan GIP 3" bh 75,900.00
33 Macam2 Sambungan GIP 4" bh 118,600.00
34 Pipa PVC RUCIKA type AW 1/2" bt 40,100.00
35 Pipa PVC RUCIKA type AW 3/4" bt 52,200.00
36 Pipa PVC RUCIKA type AW 1" bt 63,200.00
37 Pipa PVC RUCIKA type AW 1 1/4" bt 79,900.00
38 Pipa PVC RUCIKA type AW 1 1/2" bt 105,900.00
39 Pipa PVC RUCIKA type AW 2" bt 110,700.00
40 Pipa PVC RUCIKA type AW 2 1/2" bt 167,100.00
41 Pipa PVC RUCIKA type AW 3" bt 205,100.00
42 Pipa PVC RUCIKA type AW 4" bt 347,900.00
43 Pipa PVC RUCIKA type AW 6" bt 640,000.00
44 Pipa PVC RUCIKA type AW 8" bt 818,300.00
45 Pipa PVC MASPION ABU ( AW ) 1/2" bt 22,500.00
46 Pipa PVC MASPION ABU ( AW ) 3/4" bt 27,800.00
47 Pipa PVC MASPION ABU ( AW ) 1" bt 40,500.00
48 Pipa PVC MASPION ABU ( AW ) 1 1/4" bt 58,500.00
49 Pipa PVC MASPION ABU ( AW ) 1 1/2" bt 60,200.00
50 Pipa PVC MASPION ABU ( AW ) 2" bt 75,800.00
51 Pipa PVC MASPION ABU ( AW ) 2 1/2" bt 126,300.00
52 Pipa PVC MASPION ABU ( AW ) 3" bt 145,700.00
53 Pipa PVC MASPION ABU ( AW ) 4" bt 256,800.00
Page 89 BHN
NO MATERIAL SAT HARGA (Rp)
54 Macam2 Sambungan Paralon 1/2" bh 4,400.00
55 Macam2 Sambungan Paralon 3/4" bh 4,700.00
56 Macam2 Sambungan Paralon 1" bh 4,900.00
57 Macam2 Sambungan Paralon 1 1/4" bh 7,200.00
58 Macam2 Sambungan Paralon 1 1/2" bh 9,500.00
59 Macam2 Sambungan Paralon 1 3/4" bh 13,500.00
60 Macam2 Sambungan Paralon 2" bh 15,800.00
61 Macam2 Sambungan Paralon 2 1/2" bh 26,400.00
62 Macam2 Sambungan Paralon 3" bh 29,700.00
63 Macam2 Sambungan Paralon 4" bh 34,000.00
64 Sambungan Pipa PVC Jenis AW 4" TY bh 89,900.00
65 Lem Paralon tb 10,100.00
66 Solatip Ledeng gl 4,200.00
67 Pipa PVC 4" Berlobang Jenis AW m1 36,700.00
68 PVC Waterstop lebar 150 m1 53,500.00
69 PVC Waterstop lebar 200 m1 57,900.00
70 PVC Waterstop lebar 230 m1 65,700.00
71 PVC Waterstop lebar 250 m1 74,700.00
72 PVC Waterstop lebar 300 m1 83,600.00
73 PVC Waterstop lebar 320 m1 92,500.00
L BAHAN SANITAIR
1 Stop Kran 3/4" KIT bh 103,900.00
2 Stop Kran 1" KIT bh 124,200.00
3 Stop Kran 1 1/2" KIT bh 208,000.00
4 Stop Kran 2" KIT bh 267,900.00
5 Stop Kran 2 1/2" KIT bh 713,200.00
6 Stop Kran 3" KIT bh 830,300.00
7 Check Valve 1/2" bh 86,400.00
8 Double Neple 1/2" bh 32,400.00
9 Water Mur 1/2" bh 40,200.00
10 Gate walve 1/2" bh 55,500.00
11 Saringan Air Lt. KM Stainless Steel bh 66,600.00
12 Apooer Bath Tube bh 267,800.00
13 Kran Stainless Lokal Kait bh 46,100.00
14 Shower Dengan Tiang bh 221,000.00
15 Shower Tanpa Tiang bh 134,800.00
16 Kran Tembok Sun Eui dia. 1/2" bh 86,900.00
17 Kran Tembok ITAP dia. 1/2" bh 40,900.00
18 Kran Bebek Sun Eui 1/2" bh 144,600.00
19 Kran Bebek ITAP 1/2" bh 51,500.00
20 Kran Panas Dingin San Eui Standard bh 228,400.00
21 Bath Cape Washteren unit 2,098,700.00
22 Tempat Sabun Poslin bh 46,300.00
23 Wastafel Lengkap TOTO LW 230 unit 1,012,700.00
24 Wastafel Lengkap INA unit 699,900.00
25 Closet Jongkok Poslin Warna TOTO unit 205,600.00
26 Closet Jongkok Standard Putih Poslin TOTO unit 188,200.00
27 Closet Jongkok Lengkap Sistem Jet TOTO unit 2,032,900.00
Page 90 BHN
NO MATERIAL SAT HARGA (Rp)
28 Closet Duduk Warna Standard TOTO C 240 Lengkap unit 1,724,700.00
29 Wastafel Bulat Warna Standard Lengkap unit 910,800.00
30 Closet Duduk Warna Standard INA Lengkap bh 1,272,100.00
31 Urinoir Lengkap TOTO Warna Standard Lengkap unit 1,773,400.00
32 Penyekat Poslin Urinoar TOTO lbr 495,900.00
33 Kitchen Zink Stainless Standard Lokal ( 1 Lubang ) bh 397,800.00
34 Kitchen Zink Stainless Non Standard Franke ( 1 Lubang ) bh 1,272,300.00
35 Kitchen Zink Stainless Non Standard Franke ( 2 Lubang ) bh 1,650,200.00
36 Talang PVC U - 15 cm btng 60,000.00
M BAHAN PENUTUP ATAP
1 Atap Plastik Gelombang 80 x 180 lbr 33,100.00
2 Atap Fiber Glass Tipis 80 x 180 ( Gelombang ) lbr 47,100.00
3 Atap Fiber Glass Tebal 80 x 180 ( Gelombang ) lbr 100,000.00
4 Atap Alumunium Natural USR 26 ( JAINDO ) m2 140,600.00
5 Atap Alumunium Warna USR 26 ( JAINDO ) m2 164,700.00
6 Atap Asbes Gel. Kecil 80 x 180 x 4 mm lbr 77,200.00
7 Atap Asbes Gel. Besar 80 x 180 x 5 mm lbr 111,100.00
8 Atap Seng Gelombang 80 cm x 180 cm x 3 mm lbr 62,900.00
9 Atap Seng Gelombang 80 cm x 180 cm x 5 mm lbr 83,100.00
10 Atap Seng Gelombang 270 cm x 105 cm x 4mm lbr 73,300.00
11 Atap Seng Gelombang 240 cm x 105 cm x 4mm lbr 65,900.00
12 Atap Seng Gelombang 210 cm x 105 cm x 4mm lbr 58,500.00
13 Atap Seng Gelombang 150 cm x 105 cm x 4mm lbr 42,300.00
14 Atap Seng Gelombang 150 cm x 102 cm x 5mm lbr 78,500.00
15 Atap Seng Gelombang 180 cm x 102 cm x 5mm lbr 97,200.00
16 Atap Asbes Gelombang 300 cm x 105 cm x 4 mm lbr 80,000.00
17 Atap Tegola Kubota, lengkap m2 487,100.00
18 Atap Tegola Kwalitas Sedang m2 283,600.00
19 Alumunium Foile m2 19,600.00
20 Atap Genteng Plentong pres Bakar KW I bh 1,900.00
21 Atap Genteng Plentong pres Molen Oven KW I bh 2,700.00
22 Atap Genteng Flam pres Molen Oven Jatiwangi bh 2,300.00
23 Bubung Genteng pres Bulat Ex Jatiwangi bh 7,500.00
24 Genteng Bubungan Ex Jatiwangi Segi Tiga bh 4,800.00
25 Genteng Bubungan Beton bh 10,500.00
26 Genteng Metal ( Rainbow Roof ) m2 203,100.00
27 Genteng Metal Hana m2 172,700.00
28 Nok Atas Metal ( Rainbow Roof ) lbr 138,500.00
29 Nok Atas Metal Hana lbr 80,900.00
30 Nok Pingir Metal ( Rainbow Roof ) lbr 105,300.00
31 Nok Pingir Metal Hana lbr 100,800.00
32 Wall Flasing ( Rainbow Roof ) lbr 83,900.00
33 Wall Flasing Hana lbr 88,700.00
34 Atap Genteng Beton Warna 14.5/m2 m2 96,700.00
35 Genteng Beton Natural bh 8,500.00
36 Sirap Kelas I ( 80 / m2 ) m2 26,400.00
37 Genteng Keramik Natural Intan 14.5 / m2 m2 112,400.00
38 Genteng Keramik Glasur Standard 14.5 /m2 m2 142,200.00
39 Genteng Keramik Glasur Special 14.5 /m2 m2 139,300.00
40 Genteng Keramik Glasur Premium 14.5 /m2 m2 145,100.00
Page 91 BHN
NO MATERIAL SAT HARGA (Rp)
41 Genteng Murando Natural 1m2 = 18 bh bh 2,700.00
42 Genteng Murando Glasur 1m2 = 18 bh bh 4,000.00
43 Bubung Murando Natural bh 7,500.00
44 Bubung Murando Glasur bh 10,700.00
45 Bubungan Genteng Keramik bh 10,000.00
46 Atap Genteng Kodok bh 3,000.00
47 Bubungan Genteng Kodok bh 4,500.00
48 Bubungan Genteng Plentong bh 6,000.00
49 Bubungan Stel Gelombang bh 7,500.00
50 Nok Stel Gelombang lbr 38,100.00
51 Nok Atap Seng lbr 37,500.00
52 Nok standar 40 cm 18, SWG 22 m2 75,000.00
53 Pelat Asbes tebal 4 mm lbr 21,000.00
54 Pelat Asbes tebal 3.5 mm lbr 16,400.00
55 Trusses ZAM-75 t=0.8 Rangka Utama m1 34,500.00
56 Trusses ZAM-75 t=0.5 Rangka Utama m1 22,000.00
57 Reng 16-DB Roof Battens t=0.48 mm m1 11,000.00
58 Foot Plate t= 1.22 mm m1 7,200.00
59 PLD - Diafragma Plate bh 2,200.00
60 WIND Bracing m1 1,700.00
61 Tensioner ( Pengaku Tali angin ) bh 7,200.00
N BAHAN MEKANIKAL
1 Jockey Pump kap. 80 gln/menit 100 m1 ( 18.6 kW ) unit 71,396,400.00
2 Electrical Pump kap. 750 gln/menit 120 m1 ( 90 kW ) unit 216,358,900.00
3 Diesel Pump kap. 750 gln/menit 120 m1 ( 105 kW ) unit 591,647,100.00
4 Presure Tank kap. 500 liter lengkap unit 36,997,300.00
5 Hydran Box dlm Gedung ( Lengkap ) unit 6,854,400.00
6 Fire House 1.5 x 30 m + nose unit 4,866,100.00
7 Exhose Fan H 360 W 60 x 60 cm unit 6,862,900.00
8 Exhose Fan H 380 W CFM 55 x 55 cm unit 5,491,100.00
9 Exhose Fan H 100 W 40 x 40 cm unit 1,092,600.00
10 AC Split 3 PK Setara TOSHIBA unit 30,791,800.00
11 AC Split 2 PK Setara TOSHIBA unit 21,926,500.00
12 AC Split 1 PK Setara TOSHIBA unit 5,174,100.00
13 Mesin AC Split DAIKIN ( Indoor / Outdoor Unit ) 1 BTU 4,200,000.00
O BAHAN ELEKTRIKAL
1 Kabel NYA 1 x 1.5 Prima ( 1 rol = 50 m' ) ROLL 102,700.00
2 Kabel NYA 1 x 2.5 Prima ( 1 rol = 50 m' ) ROLL 151,700.00
3 Kabel NYM 2 x 1.5 Prima ( 1 rol = 50 m' ) m' 6,600.00
4 Kabel NYM 3 x 1.5 Prima ( 1 rol = 50 m' ) m' 7,600.00
5 Kabel NYM 2 x 2.5 Prima ( 1 rol = 50 m' ) m' 4,900.00
6 Kabel NYM 3 x 2.5 Prima ( 1 rol = 50 m' ) m' 10,900.00
7 Kabel NYM 4 x 2.5 Prima ( 1 rol = 50 m' ) m' 7,600.00
8 Kabel NYM 2 x 4 Prima ( 1 rol = 50 m' ) m' 6,300.00
9 Kabel NYM 3 x 4 Prima ( 1 rol = 50 m' ) m' 15,400.00
10 Kabel NYM 4 x 4 Prima ( 1 rol = 50 m' ) m' 20,700.00
11 Kabel NYM 2 x 6 Supreme ( 1 rol = 50 m' ) m' 11,800.00
12 Kabel NYM 3 x 6 Supreme ( 1 rol = 50 m' ) m' 13,700.00
Page 92 BHN
NO MATERIAL SAT HARGA (Rp)
13 Kabel NYM 4 x 6 Supreme ( 1 rol = 50 m' ) m' 18,600.00
14 Kabel NYM 2 x 10 Supreme ( 1 rol = 50 m' ) m' 17,600.00
15 Kabel NYM 3 x 10 Supreme ( 1 rol = 50 m' ) m' 119,700.00
16 Kabel NYM 4 x 10 Supreme ( 1 rol = 50 m' ) m' 26,500.00
17 Kabel NYM 4 x 16 Supreme ( 1 rol = 50 m' ) m' 29,700.00
18 Kabel NYY 2 x 4 Supreme ( 1 rol = 50 m' ) m' 12,000.00
19 Kabel NYY 3 x 4 Supreme ( 1 rol = 50 m' ) m' 19,300.00
20 Kabel NYY 4 x 4 Supreme ( 1 rol = 50 m' ) m' 23,800.00
21 Kabel NYY 2 x 6 Supreme ( 1 rol = 50 m' ) m' 14,500.00
22 Kabel NYY 3 x 6 Supreme ( 1 rol = 50 m' ) m' 19,200.00
23 Kabel NYY 4 x 6 Supreme ( 1 rol = 50 m' ) m' 18,500.00
24 Kabel NYY 2 x 10 Supreme ( 1 rol = 50 m' ) m' 20,400.00
25 Kabel NYY 3 x 10 Supreme ( 1 rol = 50 m' ) m' 25,800.00
26 Kabel NYY 4 x 10 Supreme ( 1 rol = 50 m' ) m' 35,500.00
27 Kabel NYY 4 x 16 Supreme ( 1 rol = 50 m' ) m' 41,900.00
28 NSFB FUJI EA - 100 A bh 841,900.00
29 NSFB FUJI EA - 150 A bh 2,182,600.00
30 Rumah Panel 30 x 60 cm ( Kosong ) unt 153,500.00
31 Skring Kas 2 grop Biasa unt 204,800.00
32 Skring Kas 3 grop Biasa unt 222,600.00
33 Skring Kas 5 grop Biasa unt 468,800.00
34 MCB 1 PAS bh 55,100.00
35 MCB 3 PAS bh 106,000.00
36 Tahanan 50 A Merk Fuji bh 521,100.00
37 Saklar Broko Tunggal Standard ( 1 Phase ) bh 23,800.00
38 Saklar Broko Seri Standard ( 1 Phase ) bh 26,300.00
39 Stop Kontak Broko Standard ( 1 Phase ) bh 23,800.00
40 Stop Kontak Broko 3 Phase (Out Bow) bh 87,700.00
41 Stop Kontak Broko 3 Phase ( In Bow) bh 144,900.00
42 Stop Kontak Handle 3 Phase bh 87,800.00
43 Instalas Titik Lampu / Stop Kontak (Upah dan Alat) ttk 179,600.00
44 Lampu pijar 25 Watt s/d 100 Watt bh 61,200.00
45 Lampu Neon Phillips 20 Watt bh 29,700.00
46 Lampu Neon Phillips 40 Watt bh 35,200.00
47 Trapo TL 20 W (Phillips) bh 41,800.00
48 Trapo TL 40 W (Phillips) bh 37,900.00
49 Trapo TL 20 W (Sinar) bh 40,600.00
50 Trapo TL 40 W (sinar) bh 41,300.00
51 Stater Neon Phillips bh 8,300.00
52 Stater Neon Biasa bh 6,500.00
53 Rumah TL In Bow / Out Bow 2 x 20 W (kosongan) bh 144,000.00
54 Down Light + SL 25 W bh 306,900.00
55 Lampu SL Philip 25 W bh 306,900.00
56 Lampu Sirkel TL 20 W Lengkap bh 67,900.00
57 Lampu Mercuri 80 W bh 147,400.00
58 Lampu Taman + Tiang + Lampu 1 Buah bh 307,600.00
59 Lampu Baret 30 cm + Neon bh 221,700.00
60 Lampu Neon Arcrilik 2 x 40 W Lengkap bh 738,000.00
61 Jarum Penangkal Petir 16 bh 101,500.00
62 Kawat BC ( Tembaga ) kg 65,100.00
63 Pentanahan Penangkal Petir ttk 423,700.00
64 Pentanahan Panel ttk 296,100.00
Page 93 BHN
NO MATERIAL SAT HARGA (Rp)
P BAHAN ALAT PENGANTUNG DAN KUNCI
1 Kunci Silinder ALFA untuk Pintu Alumunium bh 410,900.00
2 Tarikan Pintu Alumunium bh 408,600.00
3 Kunci 2 Slaag ROYAL bh 126,500.00
4 Rel Henderson Lengkap bh 864,300.00
5 Rel maraton I Pintu unt 193,100.00
6 Kunci 2 Slaag Silinder SEIS Asli type 210 s/d type 226 bh 335,900.00
7 Kunci 2 Slaag Ancor Asli bh 165,300.00
8 Kunci 2 Slaag ISO bh 207,300.00
9 Kunci KM Bulat Kualitas Biasa bh 54,400.00
10 Kunci kM Bulat ALFA bh 102,700.00
11 Kunci 2 Slaag Silinder Utama Standard bh 586,600.00
12 Kunci Gembok Besar bh 85,200.00
13 Kunci 2 Slaag Kuda Terbang bh 94,500.00
14 Kunci Lemari bh 46,800.00
15 Espangolet ps 51,600.00
16 Grendel 15 cm bh 49,800.00
17 Grendel 5 cm bh 5,500.00
18 Hak Angin Kait Jendela Biasa ps 7,100.00
19 Hak Angin Jendela Antik ps 29,000.00
20 Hak Angin Sendok Stainless / Kuningan bh 32,200.00
21 Sloot Pintu Berikut Rantai bh 31,500.00
22 Sloot Jendela Tunggal bh 33,000.00
23 Engsel Pintu Unilon Standard ps 21,000.00
24 Engsel Jendela Unilon ps 15,000.00
25 Engsel Patrun ps 13,700.00
26 Engsel Harmonika m1 9,100.00
27 Door Closer Kelas Standard ( Kelas Sedang ) unt 420,000.00
28 Door Closer Kelas Standard ( Kelas Baik ) unt 597,500.00
29 Door Closer Kelas Rendah unt 200,000.00
30 Door Holder unt 205,400.00
31 Door Stoper unt 255,500.00
32 Tarikan Almari Rata-rata bh 19,500.00
33 Seng BJLS 30 Lebar 60 cm ( 1 rol 50 m' ) m1 43,500.00
34 Seng BJLS 30 Lebar 90 cm ( 1 rol 50 m' ) m1 53,500.00
35 Seng BJLS 30 / 3 x 0.3 mm lbr 86,900.00
36 Seng Plat lbr 50,100.00
37 Waterstop Lebar 200 mm m1 57,900.00
Q BAHAN PENGIKAT UNTUK KONSTRUKSI JALAN
1 Aspal Bitumen kg 12,459.00
2 Aspal Emulsi kg 12,459.00
3 Aspal Curah kg 10,890.00
4 Aspal Concrete / Laston( AC -WC) ton 1,348,300.00
5 Aspal Threated Base ( ATB ) ton 1,200,200.00
6 Lataston /Hot Rolls Sheet ( HRS ) ton 1,666,900.00
R BAHAN PENGISAP AIR SUMUR DALAM
1 Pompa Kodok unit 172,600.00
2 Pompa Dragon Tegal unit 243,800.00
Page 94 BHN
NO MATERIAL SAT HARGA (Rp)
3 Pompa Dragon Asli unit 718,500.00
4 Mesin Pompa Air 100 W - Sanyo unit 1,100,200.00
5 Mesin Pompa Air 150 W - Sanyo unit 1,890,700.00
6 Pompa Zet Pump 250 W - Sanyo unit 4,961,500.00
7 Pompa Zet Pump 450 W - Sanyo unit 7,878,000.00
8 Pompa Submersible kap. 150 liter / menit 3 KW unit 27,151,200.00
9 Gear Pump Kap. 60 liter / menit unit 15,702,700.00
10 Deep Well dengan kelengkapannya kap. 150 liter / menit unit 172,052,500.00
11 Hand Oil Pump unit 5,195,300.00
S BAHAN PENAMPUNG AIR
1 Tangki Air Fiber Glass 0.5 m3 ( Excel ) bh 1,172,500.00
2 Tangki Air Fiber Glass 1 m3 ( Excel ) bh 1,316,400.00
3 Tangki Air Fiber Glass 2 m3 ( Excel ) bh 1,954,200.00
4 Bak KM Fiber 60 x 60 bh 255,300.00
5 Bak Taraso WC 40 x 40 bh 118,500.00
6 Bak KM Taraso 60 x 60 bh 161,100.00
T ALAT TUKANG
1 Palu 0.5 kg bh 39,300.00
2 Cangkul bh 24,500.00
3 Singkup bh 41,400.00
4 Sekrop bh 50,100.00
5 Pengki bh 12,300.00
6 Linggis bh 41,700.00
7 Rool Meter 30 meter ( Bahan Plastik ) bh 101,000.00
8 Rool Meter 5 meter ( Bahan Besi ) bh 37,800.00
9 Selang Plastik untuk Water Pas dia. 0.5 cm m 1,600.00
10 Water Pas Alumunium 60 cm bh 88,200.00
U BAHAN BAKAR DAN PELUMAS
1 Minyak Tanah lt 18,000.00
2 Kayu Bakar dari Kayu Karet m3 151,100.00
3 Bahan Bakar Residu lt 28,435.00
4 Minyak Solar lt 7,150.00
5 Bensin Premium lt 7,800.00
6 Plus Oil lt 3,300.00
7 Oil Mesran 40 SAE lt 55,000.00
8 Elpiji / botol 15 kg 104,600.00
9 Asitilin / Botol 15.1 kg btl 88,900.00
10 Angin ( O2 ) / botol btl 66,400.00
11 Karbit kg 19,400.00
12 Minyak Bekisting ltr 40,500.00
13 Rapidrant Gln 15,700.00
14 Soda Api kg 35,600.00
15 Sabun kg 2,400.00
16 Arang Kayu kg 11,100.00
17 Kawat Las bh 1,400.00
V BAHAN PAGAR
1 Panel Beton Pracetak lbr 199,200.00
2 Kolom Beton Pracetak btg 264,000.00
Page 95 BHN
NO MATERIAL SAT HARGA (Rp)
B. BIDANG PERTAMANAN
1 Aglonema batang 50,000.00
2 Bambu krisik/jepang batang 50,000.00
3 Furadan kg 24,000.00
4 Kompos/pupuk kandang karung 25,000.00
5 M atoa (2 m) batang 40,000.00
6 Palm (botol, ekor tupai, putri, dll) tinggi 2 m batang 100,000.00
7 Philo batang 75,000.00
8 Pohon pelindung (angsana, mahoni, kamboja dll) tinggi 2m batang 25,000.00
9 Pohon perdu (kaca piring, puring, mawar, melati, dll) batang 10,000.00
10 Rumput gajah mini m2 15,000.00
harga sudah termasuk PPN dan keuntungan
Page 96 BHN
NO
A. PEKERJAAN PERSIAPAN
1 1 M' Pagar Sementara Dari Kayu Tinggi 2 m
2 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m
3 1 M' Pagar SementaraKawat Duri Tinggi 1,80 m
4 1 M2 Pengukuran Dan Pasang Bouwplank
5 1 M2 Pembuatan Kantor Sementara dgn Lantai Diplester
6 1 M2 Pembuatan Gudang Semen dan Alat-alat
7 1 M2 Pembuatan Bedeng Buruh
8 1 M2 Membersihkan Lapangan dan Perataan
9 1M2 Pembuatan Jalan Sementara
10 1 M3 Bongkaran Beton Bertulang
11 1 M3 Bongkaran Dinding Tembok Bata Merah
12 1 M Pagar beton Pracetak ( 5 x 50 x 213 ) cm
13 1 M Pagar kawat ayam tiang besi L50.50.5, tinggi 1 m'
14 1 M2 Pagar BRC lengkap dengan tiang
15 1 M2 Steiger Werk / perancah dari Bambu
16 1 M' Cerucuk Bambu
B. PEKERJAAN TANAH
1 1 M3 Galian Tanah Biasa sedalam 1 m
2 1 M3 Galian Tanah Biasa Sedalam 2 m
3 1 M3 Galian Tanah Biasa Sedalam 3 m
4 1 M3 Galian Tanah Keras Sedalam 1 m
5 1 M3 Galian Tanah Lumpur Sedalam 1 m
6 1 M2 Pekerjaan Stripping Setinggi 10 cm
7 1 M3 Pembuangan Tanah sejauh 150 m
8 1 M3 Urugan Kembali
9 1 M3 Pemadatan Tanah
10 1 M3 Urugaan Pasir
11 1 M2 Pemasangan Lapisan Ijuk Tebal 10 cm
12 1 M3 Urugan Sirtu
13 1 M3 Urugan Tanah Pilihan
14 1 M2 Pembuatan jalan sementara, tebal 25 cm
C. PEKERJAAN PONDASI
1 1 M3 Pasanag Pondasi batu Kali adk 1pc : 3 ps
2 1 M3 Pasang Pondasi Batu kali adk 1pc : 4ps
3 1 M3 Pasang Pondasi Batu kali adk 1pc : 5ps
4 1 M3 Pasang Pondasi Batu Kosong (aanstamping)
5 1 M3 Beton siklop adk 1pc : 2ps : 3kr + 40 % Batu Belah dgn besi tulangan
6 1 M3 Pasang Pondasi Sumuran adk 1pc:2ps:3kr + 40 % Batu Belah (D= 1m)
7 1 M3 Pondasi siklop adk 1pc:2ps:3kr + 40 % Batu Belah
8 1 M' Pembuatan Tiang Pancang (40x40) cm, Beton Tulang
9 1 M' Pembuatan Tiang Pancang (35x35) cm, Beton Tulang
10 1 M' Pembuatan Tiang Pancang f 40 cm, Beton Tulang
11 1 M' Memancang Tiang Pancang Beton Tulang
12 1 Buah Memotong Tiang Pancang (40x40) cm Beton Tulang
13 1 M' Menyambung Tiang Pancang Beton Bertulang
D. PEKERJAAN BETON
1 1 M3 Membuat Beton Tumbuk adk 1pc:3ps:5kr
2 1 M3 Membuat Beton Tumbuk adk 1pc:3ps:6kr
3 1 M3 Membuat Beton Tumbuk 1pc:2ps:3kr
4 1 M3 Membuat Tiang Pancang Beton Prestressed
5 1 M3 Membuat Beton Tumbuk adk 1pc:2ps:4kr
URAIAN PEKERJAAN
DAFTAR HARGA SATUAN PEKERJAAN
Page 97 HRGST
NO URAIAN PEKERJAAN
6 1 M Memasang PVC Waterstop Lebar 200 mm
7 1 Kg Pembesian Dengan Besi Polos/ulir
8 1 M2 Pasang Bekesting Untuk Pondasi
9 1 M2 Pasang Bekisting Untuk Sloof
10 1 M2 Pasang Bekesting Untuk Kolom
11 1 M2 Pasang Bekesting Untuk Balok
12 1 M2 Pasang Bekesting Untuk Lantai
13 1 M2 Pasang Bekesting Untuk Tangga
14 1 M3 Membuat Beton Cor Mutu K-225
15 1 M3 Membuat Beton Cor Mutu K-275
16 1 M3 Pondasi Beton Tulang (150 kg besi + bekisting)
17 1 M3 Sloof Beton Tulang (200 kg besi + bekisting)
1 M3 Sloof Beton Tulang 15/20 (150 kg besi + bekisting)
1 M3 Sloof Beton Tulang 15/20 (180 kg besi + bekisting) 4dia. 12 ring 8-15
1 M3 Sloof Beton Tulang 20/30 (150 kg besi + bekisting) Struktur bertingkat 4dia.16 8-15
1 M3 Sloof Beton Tulang 20/30 (200 kg besi + bekisting) Struktur bertingkat 6dia.16 8-15
1 M3 Sloof Beton Tulang 20/40 (240 kg besi + bekisting) Struktur bertingkat
18 1 M3 Kolom Beton Tulang (120 kg besi + bekisting)
1 M3 Kolom Beton Tulang 20/20 (140 kg besi + bekisting) 4dia. 12 8-15
1 M3 Kolom Beton Tulang 15/20 (180 kg besi + bekisting) 4dia.12 8-15
1 M3 Kolom Beton Tulang Praktis 12/12 (175 kg besi + bekisting)
1 M3 Kolom Beton Tulang Praktis 12/12 (210 kg besi + bekisting)
1 M3 Kolom Beton Tulang 20/20 (210 kg besi + bekisting) Struktur bertingkat 4dia.16 8-15
1 M3 Kolom Beton Tulang 20/30 (230 kg besi + bekisting) Struktur bertingkat 6dia.16 +2dia.12, 8-15
1 M3 Kolom Beton Tulang 20/40 (250 kg besi + bekisting) Struktur bertingkat
1 M3 Kolom Beton Tulang 30/30 (175 kg besi + bekisting) Struktur bertingkat 8dia.16, 8-15
1 M3 Kolom Beton Tulang 30/40 (200 kg besi + bekisting) Struktur bertingkat
19 1 M3 Kolom Beton Tulang (140 kg besi + bekisting)
20 1 M3 Kolom Beton Tulang (150 kg besi + bekisting)
21 1 M3 Kolom Beton Tulang (180 kg besi + bekisting)
22 1 M3 Kolom Beton Tulang (200 kg besi + bekisting)
23 1 M3 Kolom Beton Tulang (250 kg besi + bekisting)
24 1 M3 Kolom Beton Tulang (300 kg besi + bekisting)
25 1 M3 Balok Beton Tulang (120 kg besi + bekisting)
26 1 M3 Balok Beton Tulang 15/20 (150 kg besi + bekisting)
1 M3 Balok Beton Lintel 11/11 (300 kg besi + bekisting) 4dia.10 8-15
1 M3 Balok Beton Lintel 11/15 (234 kg besi + bekisting) 4dia.10 8-15
1 M3 Balok Beton Tulang 15/20 (180 kg besi + bekisting) 4dia. 12, 8-15
1 M3 Balok Beton Tulang 15/30 (190 kg besi + bekisting) Struktur bertingkat 4dia. 16, 8-15
27 1 M3 Balok Beton Tulang 20/40 (200 kg besi + bekisting) Struktur bertingkat 7dia.16+2dia.12, 8-15
1 M3 Balok Beton Tulang 20/30 (200 kg besi + bekisting) Struktur bertingkat 6dia. 16, 8-15
1 M3 Balok Beton Tulang 20/30 (175 kg besi + bekisting) Struktur bertingkat 5dia. 16, 8-15
1 M3 Balok Beton Tulang 25/55 (140 kg besi + bekisting) Struktur bertingkat 8dia.16 +2dia.12, 8-15
28 1 M3 Balok Beton Tulang (230 kg besi + bekisting)
29 1 M3 Tangga Beton Tulang (200 kg besi + bekisting)
30 1 M3 Pelat Lantai Beton Tulang T= 10 cm (90 kg besi + bekisting)
1 M3 Lisplang Beton Tulang T= 8 cm (77,5 kg besi + bekisting)
31 1 M3 Pelat Lantai Beton Tulang T= 12 cm (110 kg besi + bekisting) dia.8-12,5
32 1 M3 Pelat Lantai Beton Tulang T= 12 cm (130 kg besi + bekisting)
33 1 M3 Pelat Lantai Beton Tulang T= 15 cm (90 kg besi + bekisting)
34 1 M3 Pelat Lantai Beton Tulang T= 15 cm (115 kg besi + bekisting)
35 1 M' Kolom Praktis Beton Tulang (11x11) cm
36 1 M' Ring Balok Beton Tulang (10x15) cm
37 1 M2 Pasang Bekesting Untuk Dinding
38 1 M3 Pelat Beton Tulang (150 kg besi + bekisting)
39 1 M3 Dinding Beton Tulang (150 kg besi + bekisting)
40 1 M3 Dinding Beton Tulang (200 kg besi + bekisting)
41 1 M3 Membuat Beton Cor Mutu K-300
42 1 M3 Membuat Beton Cor Mutu K-200
43 1 M3 Membuat Beton Cor Mutu K-250
Page 98 HRGST
NO URAIAN PEKERJAAN
E. PEKERJAAN PASANGAN DINDING
1 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 3ps
2 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 4ps
3 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 5ps
4 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 3ps
5 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 4ps
6 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 5ps
7 1 M2 Pasang Dinding Roster Beton 20 x 20 adk 1pc : 3ps
8 1 M2 Pasang Dinding Roster Beton 20 x 20 adk 1pc : 4ps
9 1 M2 Pasang Dinding Roster/terawng (12 x 11 x 24) cm
10 1 M2 Pasang Dinding Batako Besar Pres uk. 8x20x30 adk. 1pc:4ps
11 1 M2 Pasang Dinding hollowblock (HB-20)
12 1 M2 Pasang Dinding hollowblock (HB-15)
13 1 M2 Pasang Dinding hollowblock (HB-10)
14 1 M2 Pasang Dinding Conblock (CB-20)
15 1 M2 Pasang Dinding Conblock (CB-15)
16 1 M2 Pasang Dinding Conblock (CB-10)
17 1 M2 Dinding Keramik Corak 10 x 20 cm Setara Mulia
18 1 M2 Dinding Keramik polos 10 x 20 cm Setara Mulia
Page 99 HRGST
NO URAIAN PEKERJAAN
19 1 M2 Dinding Keramik corak 20 x 20 cm setara Mulia
20 1 M2 Dinding Keramik polos 20 x 20 cm Setara Mulia
21 1 M2 Dinding Keramik polos 20 x 25 cm Setara Mulia
22 1 M2 Dinding Keramik Corak 20 x 25 cm Setara Mulia
23 1 M2 Dinding Keramik Polos 30 x 30 cm Setara Mulia
24 1 M2 Dinding Keramik Corak 30 x 30 cm Setara Mulia
25 1 M2 Dinding Keramik Polos 40 x 40 cm Setara Mulia
26 1 M2 Dinding Keramik Corak 40 x 40 cm Setara Mulia
27 1 M2 Dinding Keramik Corak 10 x 20 cm Setara Roman
28 1 M2 Dinding Keramik polos 10 x 20 cm Setara Roman
29 1 M2 Dinding Keramik corak 20 x 20 cm setara Roman
30 1 M2 Dinding Keramik polos 20 x 20 cm Setara Roman
31 1 M2 Dinding Keramik polos 20 x 25 cm Setara Roman
32 1 M2 Dinding Keramik Corak 20 x 25 cm Setara Roman
33 1 M2 Dinding Keramik Polos 30 x 30 cm Setara Roman
34 1 M2 Dinding Keramik Corak 30 x 30 cm Setara Roman
35 1 M2 Dinding Keramik Polos 40 x 40 cm Setara Roman
36 1 M2 Dinding Keramik Corak 40 x 40 cm Setara Roman
37 1 M2 Dinding Marmer
38 1 M2 Dinding Batu Tempel Hitam
39 1 M2 Dinding Porselen (11 x 11) cm
40 1 M2 Wall paper
41 1 M2 Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kamper Medan
42 1 M2 Dinding Pemisah Plywood Rangkap, Rangka Kayu Kamper Medan
43 1 M2 Dinding Pemisah Triplek 4 mm Rangkap, Rangka Kayu Kamper Medan
44 1 M2 Dinding Pemisah GRC t = 4 mm + rangka besi hollow
45 1 M2 Dinding Pemisah Plywood t = 4 mm + rangka besi hollow
46 1 M2 Dinding Pemisah teakwood t = 4 mm + rangka besi hollow
47 1 M2 Pasang Dinding Glass Block 20 x 20 adk 1pc : 4ps
48 1 M2 Pasang Dinding anyaman bambu, rangka kayu
F. PEKERJAAN PLESTERAN DAN SIARAN
17 1 M2 Plesteran adk. 1pc : 2ps Tebal 15 mm
18 1 M2 Plesteran adk. 1pc : 3ps Tebal 15 mm
19 1 M2 Plesteran adk. 1pc : 4ps Tebal 15 mm
20 1 M2 Plesteran adk. 1pc : 3ps Tebal 20 mm
21 1 M2 Plesteran adk. 1pc : 4ps Tebal 20 mm
22 1 M2 Plesteran adk. 1pc:5ps tebal 20 mm
1 M2 Plesteran adk. 1pc:5ps tebal 15 mm + Acian
23 1 M2 Berapen adk. 1pc : 5ps Tebal 15 mm
24 1 M2 Plesteran Beton adk. 1pc : 2ps Tebal 15 mm
25 1 M2 Plesteran Beton adk. 1pc : 3ps Tebal 15 mm
26 1 M2 Plesteran Skoning adk. 1pc : 2ps, tebal 10mm
27 1 M2 Acian Plesteran
28 1 M2 Plesteran Siar adk. 1pc : 2ps batu belah
29 1 M2 Plesteran Siar adk. 1pc : 2ps dinding bata merah
G. PEKERJAAN ATAP
1 1 M2 Pasang Atap Genteng Palentong
2 1 M2 Pasang Genteng Bubung Palentong
3 1 M2 Pasang Roof Light Fibreglass ( 180 x 90 ) cm
4 1 M2 Pasang Atap Asbes Gelombang ( 3,00 x 1,05 m ) x 4 mm
5 1 M2 Pasang Atap Asbes Gelombang ( 2,70 x 1,05 m ) x 4 mm
6 1 M2 Pasang Atap Asbes Gelombang ( 2,40 x 1,05 m ) x 4 mm
7 1 M2 Pasang Atap Asbes Gelombang ( 2,10 x 1,05 m ) x 4 mm
8 1 M2 Pasang Atap Asbes Gelombang ( 1,50 x 1,05 m ) x 4 mm
9 1 M Pasang Nok Stel Gelombang 1,05 m
10 1 M2 Pasang Atap Genteng Beton
11 1 M2 Pasang Atap Genteng Murando Natural
Page 100 HRGST
NO URAIAN PEKERJAAN
12 1 M2 Pasang Atap Genteng Murando Glazur
13 1 M2 Pasang Atap Genteng Metal
14 1 M Pasang Nok Genteng Beton
15 1 M Pasang Nok Genteng Metal
16 1 M2 Pasang Atap Seng Gelombang
17 1 M2 Pasang Atap Nok Seng
18 1 M2 Pasang Alluminium Foil / Sisalation
19 1 M2 Pasang Atap Alluminium Natural
20 1 M2 Pasang Atap Alluminium warna
21 1 M2 Pasang Nok Alluminium
22 1 M' Pasang Lisplank GRC ukuran 30 cm
1 M' Pasang Nok Pinggir
H. PEKERJAAN LANGIT-LANGIT
1 1 M2 Langit-langit Asbes ( 1,00 x 1,00 ) m, tebal 5 mm
2 1 M2 Langit-langit Asbes ( 1,00 x 1,00 ) m, tebal 3,5 mm
3 1 M2 Langit-langit Akustik ( 60 x 120 ) cm
4 1 M2 Langit-langit Akustik ( 60 x 120 ) cm + Rangka Alluminium
5 1 M2 Langit-langit teakwood (60 x 120) cm, t = 4 mm + rangka kayu borneo super
6 1 M2 Langit-langit Teakwood 3 mm + Rangka Kayu Borneo Super
7 1 M2 Langit-langit Triplek 4 mm + Rangka Kayu Borneo Super
8 1 M2 Langit-langit Gypsum Board, tebal 9 mm + rangka besi hollow
9 1 M2 Langit-langit GRC t = 4 mm + rangka besi hollow
10 1 M2 Langit-langit gypsum t = 9 mm + Rangka Kayu Borneo Super
11 1 M2 Langit-langit GRC t = 4 mm + Rangka Kayu Borneo Super
12 1 M List Langit-langit Kayu Profil 10 cm
13 1 M List Langit-langit Gypsum 10 cm
1 M List Langit-langit Kayu 1/4 cm
I. PEKERJAAN LANTAI
1 1 M2 Lantai Ubin Granito ukuran 40 x 40 cm Setara Essenza
2 1 M2 Lantai Ubin Granito ukuran 30 x 30 cm Setara Essenza
3 1 M Plint Ubin Granito ukuran 10 x 40 cm Setara Essenza
4 1 M Plint Ubin Granito ukuran 10 x 30 cm Setara Essenza
5 1 M2 Lantai Keramik Corak 10 x 20 cm setara Mulia
6 1 M2 Lantai Keramik corak 20 x 20 cm setara Mulia
7 1 M2 Lantai Keramik polos 30 x 30 cm setara Mulia
8 1 M2 Lantai Keramik corak 30 x 30 cm Setara Mulia
9 1 M2 Lantai Keramik polos 40 x 40 cm Setara Mulia
10 1 M2 Lantai Keramik corak 40 x 40 cm Setara Mulia
11 1 M2 Lantai Keramik Corak 10 x 20 cm setara Roman
12 1 M2 Lantai Keramik corak 20 x 20 cm setara Roman
13 1 M2 Lantai Keramik polos 30 x 30 cm setara Roman
14 1 M2 Lantai Keramik corak 30 x 30 cm Setara Roman
15 1 M2 Lantai Keramik polos 40 x 40 cm setara Roman
16 1 M2 Lantai Keramik corak 40 x 40 cm Setara Roman
17 1 M2 Lantai Marmer
18 1 M2 Lantai Parquet Jati
19 1 M Plint Keramik ukuran (10 x 40) cm
20 1 M Plint Keramik ukuran (10 x 30) cm
21 1 M' Plint kayu kamper Samarinda (2 x 10) cm
22 1 M' Plint keramik ukuran (10 x 20) cm
23 1 M2 Lantai karpet
24 1 M2 Paving block natural 8 cm
25 1 M2 Paving block warna 8 cm
26 1 M2 Paving block natural 6 cm
27 1 M2 Paving block warna 6 cm
28 1 M2 Grass Block 20 x 20
29 1 M2 Grass Block 30 x 30
Page 101 HRGST
NO URAIAN PEKERJAAN
J. PEKERJAAN KAYU
1 1 M3 Kusen Pintu & jendela kayu Kamper Samarinda
2 1 M3 Kusen Pintu & jendela kayu Kamper Medan/Kruing
3 1 M3 Kusen Pintu & jendela kayu Borneo Super
4 1 M2 Pintu Panel Kayu Kamper Samarinda
5 1 M2 Pintu Panel Kayu Kamper Medan/Kruing
6 1 M2 Pintu & Jendela Kaca Kayu Kamper Medan
7 1 M2 Pintu & Jendela Kaca Kayu Borneo
8 1 M2 Pintu & Jendela Jalusi Kayu Kamper Medan
9 1 M2 Pintu Triplek Rangkap, Rangka Tertutup Kayu Kamper Medan
10 1 M2 Jalusi Mati Kusen Kayu kamper Medan
11 1 M2 Pintu Triplek Rangkap, Rangka Kayu Borneo Super
12 1 M2 Pintu Teakwood Rangkap, rangka Kayu Kamper Medan
13 1 M2 Pintu Triplek & Formika, Rangka Kayu Kamper Medan
14 1 M2 Pintu Teakwood & Formika, Rangka Kayu Kamper Medan (dipolitur)
15 1 M3 Kuda-kuda Kayu Kamper Medan
16 1 M3 Kuda-kuda Kayu Borneo Super
17 1 M2 Kaso + Reng Genteng Plentong Kayu Borneo Super
18 1 M2 Kaso + Reng Genteng Beton Kayu Borneo Super
19 1 M' Lisplang uk (3x20)cm, Kayu Kamper Medan
20 1 M' Lisplang uk (3x30)cm, Kayu Kamper Medan
21 1 M List Plafond + kayu Profil 10 cm
22 1 M2 Pekerjaan partisi
23 1 M2 Rangka Langit-langit (1,00 x 1,00) m, Kayu borneo super
24 1 M2 Rangka langit-langit ( 0,50 x 1,00 ) m, Kayu Borneo Super
25 1 M' Reuter Kayu kamper Medan
26 1 M3 Gording kayu kelas II
27 1 M2 Dinding bilik, rangka kayu borneo
K. PEKERJAAN BESI DAN ALLUMINIUM
1 1 Kg Besi profil
2 1 Kg Perakitan baja
3 1 Cm Pengelasan dengan las listrik
4 1 m2 Pintu Rolling Door
5 1 m2 Pintu Alluminium Natural
6 1 m2 Terali Besi
7 1 m2 Kawat Harmonika 4 cm
8 1 m' Talang Datar, Seng BJLS 28 lebar 90 cm
9 1 m' Talang Miring, Seng BJLS 28 lebar 90 cm
10 1 m' Talang 1/2 lingkaran D-15 cm, seng pelat BJLS 28 lebar 90 cm
11 1 m' Pasang kusen pintu/jendela alluminium natural 4"
12 1 m' Pasang kusen pintu/jendela alluminium warna 4"
13 1 m' Pasang kusen pintu/jendela alluminium natural 3"
14 1 m' Pasang kusen pintu/jendela alluminium warna 3"
15 1 m2 Pintu alluminium strip lebar 8 cm
16 1 m2 Pintu/jendela kaca rangka alluminium natural 4"
17 1 m2 Pintu/jendela kaca rangka alluminium warna 4"
18 1 m2 Jendela nako & teralis (10 klips)
19 1 m2 Pintu pelat baja tebal 2mm rangkap, rangka baja siku
20 1 m2 Rangka jendela besi square tube (5 x 5) cm
21 1 m2 Pintu lipat (folding door)bahan besi
22 1 m2 Tirai (venetions blinds and vertical blinds)
23 1 m2 Rangka atap baja ringan
24 1 UNIT Pasang partisi Alumunium, Daun partisi Multiplek rangka kayu Kamper
25 1 UNIT Pek. Kusen Jendela Alumunium uk. 2 X 1,50 M' ( 3 lubang ) dgn 2 Daun Jendela
26 1 UNIT Pek. Kusen Pintu Jendela Alumunium uk. 2,2 X 2,70 M' ( 2 lb. Jendela + 1 lb. Pintu )
27 1 UNIT Pekerjaan Kusen Pintu Alumunium uk. 0,8 X 2,70 M'
Page 102 HRGST
NO URAIAN PEKERJAAN
28 1 UNIT Pek. Kusen Jendela Alumunium uk. 2,65 X 1,50 M' ( 4 lubang ) dgn 2 Daun Jendela
29 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk. 2,85 X 2,70 M' ( 3 lb. Jendela + 1 lb. Pintu )
30 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,30 X 2,80 M' ( 2 Daun Pintu )
31 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,50 X 2,70 M' ( 2 Daun Pintu )
32 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk.1,55 X 2,70 M' ( 1 lb. Jendela + 1 lb. Pintu )
33 1 UNIT Pekerjaan Jalusi Alumunium Sofi-sofi
34 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 1 lubang ) uk. 0,70 x 0,60 m
35 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 2 lubang ) uk. 1,35 x 0,60 m
36 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 3 lubang ) uk. 2,00 x 0,60 m
37 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 4 lubang ) uk. 2,65 x 0,60 m
L. PEKERJAAN KACA DAN KUNCI
1 1 Buah Pasang Kunci Tanam 2 slaag
2 1 Buah Pasang Kunci Tanam Biasa
3 1 Buah Pasang Kunci Tanam Kamar Mandi
4 1 Buah Pasang Engsel Pintu
5 1 Buah Pasang Engsel Jendela Kupu-kupu
6 1 Buah Pasang Kait Angin
7 1 Buah Pasang Door Closer
8 1 Buah Pasang Pegangan Pintu / Door Holder
9 1 M2 Pasang Kaca , tebal 3 mm
10 1 M2 Pasang Kaca , tebal 5 mm
M. PEKERJAAN SANITASI
1 1 Buah Closet jongkok Porselen Standar
2 1 Buah Urinoir
3 1 Buah Wastafel
4 1 Buah bak Mandi Fibreglass Volume 0,30 m3
5 1 M' Saluran Air Limbah Buis beton d = 30 cm - 60 cm
6 1 Buah Bak Kontrol Pas Bata Merah Uk (60 x 60) cm
7 1 Buah Bak Kontrol Pas Bata Merah Uk (30 x 30) cm
8 1 M' Pipa PVC 1/2" (AW)
9 1 M' Pipa PVC 1" (AW)
10 1 M' Pipa PVC 11/2" (AW)
11 1 M' Pipa PVC 2" (AW)
12 1 M' Pipa PVC 4" (AW)
13 1 M' Pipa PVC 3/4" (AW)
14 1 Buah Bak Cuci piring Stainless steel
15 1 Buah Kran 1/2" - 3/4"
16 1 Buah Floor Drain
17 1 M' Grafel beton U 20 cm -60 cm
18 1 M' Pasang Talang Plastik PVC U 15 cm (AW)
19 1 M' Saluran Air Limbah Buis Beton 60 cm
20 1 M' Pasang Talang Seng Datar
21 1 Buah Closet Duduk
22 1 Buah Tangki Air fibreglass Volume 1 m3
23 1 Unit Septictank 2x1,50x1,50 m + Rembesan
24 1 Unit Septictank 1x1,50x1,50 m + Rembesan
Page 103 HRGST
NO URAIAN PEKERJAAN
N PEKERJAAN PENGECATAN
1 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama
2 1 M2 Mendempul Dan Menggosok Kayu
3 1 M2 Pengecatan Bidang Kayu Lama Setara Sieve
4 1 M2 Pengecatan Bidang Kayu Baru Setara Sieve
5 1 M2 Pelaburan Bidang Kayu dengan Politur
6 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter
7 1 M2 Pengecatan Tembok Baru Setara ICI
8 1 M2 Pengecatan Tembok Lama Setara ICI
9 1 M2 Pengecatan Plafond ( 3x ) Setara ICI
10 1 M2 Pengecatan Plafond ( 3x ) Setara Vinilex
1 M2 Pengecatan Plafond ( 2x ) Setara Vinilex
11 1 M2 Memasang Wallpaper
12 1 M2 Pengecatan Permukaan Baja dengan Meni Besi
13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah
14 1 M2 Pengecatan Permukaan Baja Lapis seng (galbani) secara manual 1 lps cat 2 um
15 1 M2 Pengecatan Tembok Baru Setara Vinilex (2 x laburan)
1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan)
16 1 M2 Pengecatan Tembok Lama Setara Vinilex
O. PEKERJAAN PERTAMANAN
1 1 Lubang (70x70x70) cm, tanam pohon pelindung tinggi 2m
2 1 Lubang (70x70x70) cm, tanam bambu krisik/jepang
3 1 Lubang (40x40x40) cm, tanam pohon perdu (polibag)
4 1 M2 Tanam rumput gajah (silang papan catur)
Page 104 HRGST
NO URAIAN PEKERJAAN
K(2) PEKERJAAN KUSEN SD
1 1 UNIT Pasang partisi Alumunium, Daun partisi Multiplek rangka kayu Kamper
2 1 UNIT Pek. Kusen Jendela Alumunium uk. 2 X 1,50 M' ( 3 lubang ) dgn 2 Daun Jendela
2 1 UNIT Pek. Kusen Pintu Jendela Alumunium uk. 2,2 X 2,70 M' ( 2 lb. Jendela + 1 lb. Pintu )
3 1 UNIT Pekerjaan Kusen Pintu Alumunium uk. 0,8 X 2,70 M'
3 1 UNIT Pek. Kusen Jendela Alumunium uk. 2,65 X 1,50 M' ( 4 lubang ) dgn 2 Daun Jendela
4 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk. 2,85 X 2,70 M' ( 3 lb. Jendela + 1 lb. Pintu )
4 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,30 X 2,80 M' ( 2 Daun Pintu )
5 1 UNIT Pek. Kusen Pintu Alumunium + Kaca uk. 1,50 X 2,70 M' ( 2 Daun Pintu )
5 1 UNIT Pek. Kusen Pintu & Jendela Alumunium uk.1,55 X 2,70 M' ( 1 lb. Jendela + 1 lb. Pintu )
6 1 UNIT Pekerjaan Jalusi Alumunium Sofi-sofi
6 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 1 lubang ) uk. 0,70 x 0,60 m
1 UNIT Pek. Kusen Bouvenlight Alumunium ( 2 lubang ) uk. 1,35 x 0,60 m
7 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 3 lubang ) uk. 2,00 x 0,60 m
7 1 UNIT Pek. Kusen Bouvenlight Alumunium ( 4 lubang ) uk. 2,65 x 0,60 m
Page 105 HRGST
HARGA
(Rp)
269,316.00
355,236.00
222,843.00
49,266.00
1,135,066.00
927,350.00
861,935.00
8,200.00
96,799.00
306,654.00
282,654.00
474,296.00
166,813.00
265,378.00
43,645.00
54,250.00
20,000.00
26,252.00
36,710.00
31,210.00
41,206.00
2,500.00
25,672.00
9,584.00
25,000.00
223,760.00
33,900.00
256,700.00
119,540.00
120,456.00
735,761.00
689,096.00
656,736.00
363,345.00
2,020,939.00
870,632.00
761,279.00
1,104,309.00
864,246.00
1,073,335.00
128,057.00
216,932.00
628,577.00
716,798.00
689,279.00
970,698.00
1,047,667.00
914,882.00
DAFTAR HARGA SATUAN PEKERJAAN
Page 106 HRGST
HARGA
(Rp)
65,593.00
18,566.00
152,870.00
167,120.00
308,850.00
316,770.00
431,850.00
289,440.00
1,197,898.00
1,186,807.00
4,248,004.00
5,441,279.00
4,616,279.00
5,078,279.00
4,583,279.00
5,408,279.00
6,101,279.00
6,646,664.00
6,573,014.00
7,233,014.00
6,225,664.00
6,803,164.00
7,728,014.00
8,058,014.00
8,498,014.00
7,150,514.00
7,673,014.00
6,691,324.00
6,864,634.00
7,367,944.00
7,706,254.00
8,552,029.00
9,397,804.00
5,693,859.00
6,201,324.00
8,288,164.00
7,199,164.00
6,608,324.00
6,773,324.00
6,959,099.00
6,959,099.00
6,628,499.00
5,969,099.00
7,554,564.00
6,575,339.00
6,904,322.00
6,672,247.00
6,554,453.00
6,925,773.00
5,466,262.00
5,930,412.00
72,847.00
94,786.00
315,287.00
6,438,864.00
6,196,529.00
6,574,999.00
928,986.00
852,609.00
892,501.00
Page 107 HRGST
HARGA
(Rp)
220,267.00
211,736.00
207,720.00
105,680.00
102,345.00
100,253.00
580,016.00
577,485.00
580,016.00
46,791.00
151,794.00
129,077.00
109,862.00
190,791.00
117,281.00
104,781.00
108,782.00
107,282.00
Page 108 HRGST
HARGA
(Rp)
115,282.00
107,282.00
107,282.00
115,282.00
105,782.00
110,782.00
109,582.00
118,282.00
124,982.00
117,182.00
127,982.00
117,182.00
125,682.00
127,982.00
121,682.00
129,382.00
125,282.00
129,782.00
689,841.00
179,935.00
116,082.00
94,920.00
329,174.00
431,147.00
284,431.00
92,049.00
140,691.00
103,090.00
836,685.00
105,137.00
36,022.00
33,620.00
32,054.00
47,253.00
44,739.00
42,318.00
31,284.00
25,355.00
43,737.00
41,302.00
36,417.00
20,213.00
36,390.00
21,823.00
59,915.00
80,177.00
72,510.00
42,371.00
45,157.00
43,172.00
44,011.00
48,016.00
97,758.00
110,652.00
61,015.00
Page 109 HRGST
HARGA
(Rp)
84,415.00
227,572.00
109,174.00
175,955.00
68,516.00
24,132.00
31,145.00
204,160.00
229,465.00
161,550.00
43,125.00
30,000.00
31,443.00
28,143.00
210,400.00
298,060.00
154,907.00
153,893.00
128,684.00
93,960.00
91,408.00
136,615.00
133,743.00
37,073.00
16,765.00
7,500.00
421,657.00
402,591.00
82,032.00
101,549.00
92,670.00
99,170.00
89,670.00
94,670.00
93,470.00
102,170.00
108,870.00
111,870.00
105,570.00
113,270.00
109,170.00
113,670.00
672,798.00
475,845.00
19,492.00
27,552.00
36,348.00
29,301.00
403,815.00
153,570.00
182,445.00
148,215.00
158,715.00
323,040.00
330,990.00
Page 110 HRGST
HARGA
(Rp)
11,956,440.00
8,427,120.00
7,932,000.00
573,768.00
456,124.00
381,041.00
377,653.00
663,826.00
356,459.00
513,126.00
354,562.00
430,185.00
486,735.00
606,635.00
7,736,900.00
7,283,040.00
78,780.00
89,340.00
62,218.00
84,779.00
33,347.00
172,437.00
64,485.00
79,466.00
29,660.00
7,367,660.00
70,471.00
32,216.00
974.00
2,464.00
456,491.00
332,441.00
192,598.00
62,063.00
117,797.00
174,013.00
172,631.00
179,302.00
192,392.00
102,192.00
125,292.00
855,299.00
731,898.00
784,258.00
393,980.00
1,171,360.00
269,541.00
622,341.00
577,519.00
196,000.00
2,215,571.88
3,278,022.70
4,037,418.82
2,168,119.18
Page 111 HRGST
HARGA
(Rp)
4,021,101.40
5,165,780.62
3,001,582.62
3,066,970.73
3,009,751.68
1,264,968.60
789,516.00
912,681.00
1,302,386.40
1,692,091.80
382,160.00
199,370.00
127,785.00
32,569.00
22,710.00
15,119.00
458,550.00
243,950.00
107,705.00
133,669.00
463,770.00
2,430,770.00
1,400,178.00
601,654.00
159,315.00
620,779.00
377,546.00
22,247.00
31,602.00
48,896.00
50,336.00
154,417.00
34,659.00
420,930.00
49,075.00
74,670.00
79,411.00
119,325.00
221,243.00
79,987.00
2,051,157.00
1,618,359.00
10,022,424.00
6,780,162.00
Page 112 HRGST
HARGA
(Rp)
8,280.00
8,708.00
24,517.00
39,790.00
64,424.00
7,515.00
30,608.00
21,521.00
53,775.00
43,775.00
32,330.00
103,251.00
19,340.00
34,752.00
25,842.00
17,608.00
23,669.00
12,521.00
28,274.00
53,274.00
12,024.00
10,500.00
Page 113 HRGST
HARGA
(Rp)
2,215,572
3,278,023
4,037,419
2,168,119
4,021,101
5,165,781
3,001,583
3,066,971
3,009,752
1,264,969
789,516
912,681
1,302,386
1,692,092
Page 114 HRGST


DAFTAR HARGA SATUAN PEKERJAAN
UPAH & BAHAN
KOTA BOGOR
TAHUN ANGGARAN 2011