1 Order Form 1 25.7
2 TNA 1 25.7
3 Pattern 3 28.7
4 Fabric For Fit Sample 3 28.7
5 CAD 5 30.7
6 Budget Sheet 6 31.7
7 Fit Sample 8 3.8
8 Lab Dips 10 4.8
9 Fabric PO 6 31.7
10 Print, Embro Approval 15 10.8
11 Knitting 10 20
12 Dyed Delivery 20 30
13 Stitching Accs. PO 7 15
14 Stitching Accs. Inhouse 10 20
15 PP Sample 25
16 Size Set Patterns 35
17 Fabric Testing 22 32
18 Garment Testing 25 35
19 Cut 36 50
20 Rec. from Print/Embro 41 54
21 Input 43 55
22 Output 44 56
23 Press 45 59
24 Pack 46 60
25 Inspection 60