S10
Presupuesto
Presupuesto
0201002
Lugar
ESTUDIO DE PREINVERSION A NIVEL DE PERFIL PARA EL MEJORAMIENTO DE LA CARRETERA ANDAHUAYLAS PAMPACHIRI - NEGROMAYO, TRAMO : HUANCABAMBA - PAMPACHIRI - NEGROMAYO ALTERNATIVA A
TRAMO: PAMPACHIRI - NEGROMAYO 67.20
003
Costo al
MINISTERIO DE TRANSPORTES Y COMUNICACIONES
APURIMAC - ANDAHUAYLAS - ANDAHUAYLAS
Item
Descripcin
01
OBRAS PRELIMINARES
01.01
02
MOVIMIENTO DE TIERRAS
02.01
Subpresupuesto
Cliente
Und.
Metrado
Precio S/.
22/05/2014
Parcial S/.
473,794.54
glb
0.50
947,589.08
473,794.54
m2
20,160.00
5.84
117,734.40
02.02
m3
51,408.00
63.75
3,277,260.00
02.03
m3
2,900.00
59.12
03
PAVIMENTOS
03.01
SLURRY SEAL
m2
403,200.00
21.09
8,503,488.00
03.02
m2
403,200.00
21.22
8,555,904.00
04
04.01
75.00
1,872.81
140,460.75
04.02
und
7.00
20,576.09
144,032.63
05
TRANSPORTE
05.01
m3k
1,316.60
6.28
05.02
m3k
5,254.82
1.09
06
06.01
SEAL IMFORMATIVA
und
11.00
1,130.06
12,430.66
06.02
SEAL PREVENTIVA
und
8.00
775.69
6,205.52
06.03
SEAL REGLAMENTARIA
und
3.00
819.81
2,459.43
06.04
MARCAS EN EL PAVIMENTO
m2
24,475.00
12.90
315,727.50
06.05
und
300.00
163.40
49,020.00
06.06
und
68.00
131.89
8,968.52
06.07
COLOCACION DE GUARDAVIAS
200.00
391.39
78,278.00
07
PROTECCION AMBIENTAL
07.01
glb
1.00
10,687.56
10,687.56
07.02
und
1.00
22,500.00
22,500.00
07.03
REVEGETACION
ha
0.75
19,055.98
14,291.99
07.04
ha
0.75
10,973.91
8,230.43
07.05
ha
2.00
42,469.90
84,939.80
07.06
ha
1.00
17,401.41
17,401.41
07.07
glb
1.00
80,000.00
80,000.00
07.08
glb
1.00
55,600.00
55,600.00
07.09
glb
1.00
48,814.27
3,566,442.40
171,448.00
17,059,392.00
284,493.38
13,996.00
8,268.25
5,727.75
473,089.63
342,465.46
48,814.27
22,213,673.41
Costo Directo
2,221,367.34
Utilidades ( 10% )
-------------------24,435,040.75
SUB TOTAL
IGV
4,398,307.34
( 18% )
------------------28,833,348.09
TOTAL_PRESUPUESTO
67.20
LONGITUD Km
429,067.68
VEINTIOCHO MILLONES OCHOCIENTOS TRENTITRES MIL TRESCIENTOS CUARENTIOCHO Y 09/100 NUEVOS SOLES
Fecha :
27/05/2014 01:46:04p.m.