PROYECTO

UBICACION : Dpto: Hunuco Prov.: Pachitea Dist.:Umari


LUGAR : Tambillo
FECHA : J UNIO - 2012
UNID CANTIDAD PESO UNIT. PESO TOTAL
ALAMBRE NEGRO RECOCIDO # 8 kg 664.91 1.00 664.91
CLAVOS PARA MADERA C/C 3" kg 199.47 1.00 199.47
PERNOS HEXAGONALES DE 3/4" X 6" INC.TUER und 6.00 0.10 0.60
PIEDRA SELECCIONADA Y HABILITADA m3 40.77 875.00 35,672.00
CEMENTO PORTLAND TIPO I (42.5KG) BOL 377.85 42.50 16,058.80
CINTA SEALADORA AMARILLA pza 375.06 2.50 937.65
YESO kg 18.75 1.00 18.75
LIJA PARA MADERA und 2.00 0.10 0.20
MADERA TORNILLO p2 47.25 2.45 115.76
ESTACA DE MADERA TORNILLO TRATADA p2 15.00 2.40 36.01
MADERA TORNILLO INC.CORTE P/ENCOFRADO p2 7,925.73 2.40 19,021.75
TEKNOPOR DE 1" x 4' x 8' pln 852.60 1.32 1,125.43
PESO TOTAL 73,851.33
FLETE TERRESTRE (MATERIALES) DE HUANUCO A TAMBILLO= 39 KM.
UNIDAD DE TRANSPORTE CAMION VOLQUETE
CAPACIDAD DE CAMION EN PESO Kg 14,000.00
CAPACIDAD DE CAMION EN VOLUMEN M3 1,000.00
COSTO POR VIAJE S/. 800.00
COSTO POR PESO 0.06
FLETE POR PESO 4,220.08
IMPREVISTO 0.00
COSTO TOTAL DE FLETE TERRESTRE S/. 4,220.08
CALCULO DE FLETE
MATERIALES
CALCULO DE FLETE TERRESTRE