PUENTE BAHA DE CADIZ (Periodo de retorno 25 aos)

INICIO
Pila mas prxima PK
C. antes P-13
1+410
P-14
1+850
P-17
2+120
P-20
2+340
P-27
2+720
P-31
2+880
P-34
3+000

Pila mas prxima


P-14
P-17
P-20
P-27
P-31
P-34
E-2

FIN
PK
1+850
2+120
2+340
2+720
2+880
3+000
3+160

Longitud

PUENTE BAHA DE CADIZ (Periodo de retorno 10 aos)

Anchura
450
270
220
380
160
120
160

30.5
30.5
30.5
30.5
30.5
30.5
30.5

Caudal (0,051 l/s/m2)


699.98
419.99
342.21
591.09
248.88
186.66
248.88
2,737.68

INICIO
Pila mas prxima PK
C. antes P-13
1+410
P-14
1+850
P-17
2+120
P-20
2+340
P-27
2+720
P-31
2+880
P-34
3+000

Pila mas prxima


P-14
P-17
P-20
P-27
P-31
P-34
E-2

FIN
PK
1+850
2+120
2+340
2+720
2+880
3+000
3+160

Longitud

Anchura
450
270
220
380
160
120
160

30.5
30.5
30.5
30.5
30.5
30.5
30.5

Caudal (0,040 l/s/m2)


549.00
329.40
268.40
463.60
195.20
146.40
195.20
2,147.20

22.8
22.8
22.8

Caudal (0,040 l/s/m2)


401.28
27.36
91.20
519.84

22.8
22.8
22.8
22.8

Caudal (0,040 l/s/m2)


328.32
72.96
27.36
91.20
519.84

22.8
22.8
22.8
22.8
22.8

Caudal (0,040 l/s/m2)


291.84
36.48
72.96
27.36
91.20
519.84

22.8
22.8
22.8
22.8
22.8
22.8

Caudal (0,040 l/s/m2)


291.84
36.48
72.96
27.36
45.60
45.60
519.84

22.8
22.8
22.8
22.8
22.8
22.8
22.8

Caudal (0,040 l/s/m2)


136.80
155.04
36.48
72.96
27.36
45.60
45.60
519.84

ANULADO
VIADUCTO DE SAN PEDRO (Periodo de retorno 25 aos)

VIADUCTO DE SAN PEDRO (Periodo de retorno 10 aos)

Solucin 1
INICIO
Pila mas prxima PK
P-3
3+520
P-13
3+960
P-16
4+090

Solucin 1
FIN
Pila mas prxima PK
P-13
3+960
P-14
3+990
P-14
3+990

Longitud

Anchura
440
30
100

Caudal (0,051 l/s/m2)


22.8
511.63
22.8
34.88
22.8
116.28
662.80

Solucin 2
INICIO
Pila mas prxima PK
P-3
3+520
P-11
3+880
P-14
3+990
P-16
4+090

Longitud

Anchura
360
80
30
100

22.8
22.8
22.8
22.8

Caudal (0,051 l/s/m2)


418.61
93.02
34.88
116.28
662.80

Longitud

Anchura
320
40
80
30
100

22.8
22.8
22.8
22.8
22.8

Caudal (0,051 l/s/m2)


372.10
46.51
93.02
34.88
116.28
662.80

Pila mas prxima


P-11
P-13
P-13
P-14

FIN
PK
3+880
3+960
3+960
3+990

Pila mas prxima


P-10
P-11
P-13
P-13
P-14

FIN
PK
3+840
3+880
3+960
3+960
3+990

Pila mas prxima


P-10
P-11
P-13
P-14
P-15
P-14

FIN
PK
3+840
3+880
3+960
3+990
4+040
3+990

Pila mas prxima


P-6
P-10
P-11
P-13
P-14
P-15
P-14

FIN
PK
3+670
3+840
3+880
3+960
3+990
4+040
3+990

Longitud

Anchura
440
30
100

INICIO
Pila mas prxima PK
P-3
3+520
P-11
3+880
P-14
3+990
P-16
4+090

Longitud

Anchura
360
80
30
100

INICIO
Pila mas prxima PK
P-3
3+520
P-10
3+840
P-11
3+880
P-14
3+990
P-16
4+090

Longitud

Anchura
320
40
80
30
100

Solucin 4
FIN
Pila mas prxima PK
P-10
3+840
P-11
3+880
P-13
3+960
P-14
3+990
P-15
4+040
P-14
3+990

Longitud

Anchura
320
40
80
30
50
50

22.8
22.8
22.8
22.8
22.8
22.8

Caudal (0,051 l/s/m2)


372.10
46.51
93.02
34.88
58.14
58.14
662.80

Solucin 5
INICIO
Pila mas prxima PK
P-3
3+520
P-6
3+670
P-10
3+840
P-11
3+880
P-13
3+960
P-16
4+090
P-15
4+040

FIN
PK
3+960
3+990
3+990

Solucin 3
FIN
Pila mas prxima PK
P-10
3+840
P-11
3+880
P-13
3+960
P-13
3+960
P-14
3+990

Solucin 4
INICIO
Pila mas prxima PK
P-3
3+520
P-10
3+840
P-11
3+880
P-13
3+960
P-16
4+090
P-15
4+040

Pila mas prxima


P-13
P-14
P-14

Solucin 2
FIN
Pila mas prxima PK
P-11
3+880
P-13
3+960
P-13
3+960
P-14
3+990

Solucin 3
INICIO
Pila mas prxima PK
P-3
3+520
P-10
3+840
P-11
3+880
P-14
3+990
P-16
4+090

INICIO
Pila mas prxima PK
P-3
3+520
P-13
3+960
P-16
4+090

INICIO
Pila mas prxima PK
P-3
3+520
P-10
3+840
P-11
3+880
P-13
3+960
P-16
4+090
P-15
4+040

Longitud

Anchura
320
40
80
30
50
50

Solucin 5
FIN
Pila mas prxima PK
P-6
3+670
P-10
3+840
P-11
3+880
P-13
3+960
P-14
3+990
P-15
4+040
P-14
3+990

Longitud

Anchura
150
170
40
80
30
50
50

22.8
22.8
22.8
22.8
22.8
22.8
22.8

Caudal (0,051 l/s/m2)


174.42
197.68
46.51
93.02
34.88
58.14
58.14
662.80

INICIO
Pila mas prxima PK
P-3
3+520
P-6
3+670
P-10
3+840
P-11
3+880
P-13
3+960
P-16
4+090
P-15
4+040

Longitud

Anchura
150
170
40
80
30
50
50

PUENTE BAHA DE CADIZ (Periodo de retorno 25 aos)


INICIO
Pila mas prxima PK
C. antes P-13
1+410
P-14
1+850
P-17
2+120
P-20
2+340
P-27
2+720
P-31
2+880
P-34
3+000

FIN
Pila mas prxima PK
P-14
1+850
P-17
2+120
P-20
2+340
P-27
2+720
P-31
2+880
P-34
3+000
E-2
3+160

Longitud

PUENTE BAHA DE CADIZ (Periodo de retorno 10 aos)

Anchura
450
270
220
380
160
120
160

30.5
30.5
30.5
30.5
30.5
30.5
30.5

Caudal (0,051 l/s/m2)


699.98
419.99
342.21
591.09
248.88
186.66
248.88
2,737.68

INICIO
Pila mas prxima PK
C. antes P-13
1+410
P-14
1+850
P-17
2+120
P-20
2+340
P-27
2+720
P-31
2+880
P-34
3+000

Pila mas prxima


P-14
P-17
P-20
P-27
P-31
P-34
E-2

FIN
PK
1+850
2+120
2+340
2+720
2+880
3+000
3+160

Longitud

Anchura
30.5
30.5
30.5
30.5
30.5
30.5
30.5

Caudal (0,040 l/s/m2)


549.00
329.40
268.40
463.60
195.20
146.40
195.20
2,147.20

95.829
431.767
132.552
136.118

22.8
22.8
22.8
22.8

Caudal (0,040 l/s/m2)


87.40
393.77
120.89
124.14
726.19

450
270
220
380
160
120
160

ANULADO
VIADUCTO DE SAN PEDRO (Periodo de retorno 25 aos)
INICIO
Pila mas prxima PK
E-1
P-3 (-10 m)
P-13 (-16 m)
P-16 (-14 m)

FIN
Pila mas prxima PK
P-3 (-10 m)
P-13 (-16 m)
P-16 (-14 m)
E-2

E-1
P-3 (-10 m)
P-6
P-13 (-16 m)
P-16 (-14 m)

Longitud

VIADUCTO DE SAN PEDRO (Periodo de retorno 10 aos)

Anchura

Caudal (0,051 l/s/m2)


111.43
502.06
154.13
158.28
925.90

INICIO
Pila mas prxima PK
E-1
P-3 (-10 m)
P-13 (-16 m)
P-16 (-14 m)

Pila mas prxima


P-3 (-10 m)
P-13 (-16 m)
P-16 (-14 m)
E-2

FIN
PK

Longitud

Anchura

95.829
431.767
132.552
136.118

22.8
22.8
22.8
22.8

P-3 (-10 m)
P-6
P-13 (-16 m)
P-16 (-14 m)
E-2

95.829
158.752
273.015
132.552
136.118

22.8
22.8
22.8
22.8
22.8

111.43
184.60
317.46
154.13
158.28
925.90

E-1
P-3 (-10 m)
P-6
P-13 (-16 m)
P-16 (-14 m)

P-3 (-10 m)
P-6
P-13 (-16 m)
P-16 (-14 m)
E-2

95.829
158.752
273.015
132.552
136.118

22.8
22.8
22.8
22.8
22.8

87.40
144.78
248.99
120.89
124.14
726.19

E-1
P-3 (-10 m)
P-6
P-10
P-13 (-16 m)
P-16 (-14 m)

P-3 (-10 m)
P-6
P-10
P-13 (-16 m)
P-16 (-14 m)
E-2

95.829
158.752
187.364
85.651
132.552
136.118

22.8
22.8
22.8
22.8
22.8
22.8

111.43
184.60
217.87
99.59
154.13
158.28
925.90

E-1
P-3 (-10 m)
P-6
P-10
P-13 (-16 m)
P-16 (-14 m)

P-3 (-10 m)
P-6
P-10
P-13 (-16 m)
P-16 (-14 m)
E-2

95.829
158.752
187.364
85.651
132.552
136.118

22.8
22.8
22.8
22.8
22.8
22.8

87.40
144.78
170.88
78.11
120.89
124.14
726.19

E-1
P-3 (-10 m)
P-6
P-10
P-12
P-13
P-16 (-14 m)

P-3 (-10 m)
P-6
P-10
P-12
P-13
P-16 (-14 m)
E-2

95.829
158.752
187.364
52.016
49.635
116.552
136.118

22.8
22.8
22.8
22.8
22.8
22.8
22.8

111.43
184.60
217.87
60.48
57.72
135.53
158.28
925.90

E-1
P-3 (-10 m)
P-6
P-10
P-12
P-13
P-16 (-14 m)

P-3 (-10 m)
P-6
P-10
P-12
P-13
P-16 (-14 m)
E-2

95.829
158.752
187.364
52.016
49.635
116.552
136.118

22.8
22.8
22.8
22.8
22.8
22.8
22.8

87.40
144.78
170.88
47.44
45.27
106.30
124.14
726.19

PUENTE BAHA DE CADIZ (Periodo de retorno 25 aos)


INICIO
Pila mas prxima
C. antes P-13
P-14
P-17
P-20
P-24
P-30
E-2

PK
1+410
1+850
2+120
2+340
2+590
2+840
3+160

FIN
Pila mas prxima
P-14
P-17
P-20
P-24
P-30
E-2
Terrapln

PK
1+850
2+120
2+340
2+590
2+840
3+160
3+300

Longitud
450
270
220
250
250
320
140

Anchura
30.5
30.5
30.5
30.5
30.5
30.5
26.65

Caudal (0,051 l/s/m2)


699.98
419.99
342.21
388.88
388.88
497.76
190.28
2,927.96

Caudal Acumulado
1,851.05
1,151.07
731.09
388.88
388.88

Caudal (0,040 l/s/m2)


549.00
329.40
268.40
305.00
305.00
390.40
190.28
2,337.48

Caudal Acumulado
1,451.80
902.80
573.40
305.00
305.00

1,076.92

A BALSA DE
RECOGIDA 1
A BALSA DE
RECOGIDA 2

PUENTE BAHA DE CADIZ (Periodo de retorno 10 aos)


INICIO
Pila mas prxima
C. antes P-13
P-14
P-17
P-20
P-24
P-30
E-2

PK
1+410
1+850
2+120
2+340
2+590
2+840
3+160

FIN
Pila mas prxima
P-14
P-17
P-20
P-24
P-30
E-2
Terrapln

PK
1+850
2+120
2+340
2+590
2+840
3+160
3+300

Longitud
450
270
220
250
250
320
140

Anchura
30.5
30.5
30.5
30.5
30.5
30.5
26.65

885.68