Estimate :Stone Masonry

I.EARTHWORKS
1.)Excavation

a.)@ section A
Volume of excavation=1.5(12)(3.5)+4.85(12)(2.9)+3.9(12)(2.3)+3(1.8)(12)
=404.22cum
b.)@ section B
Volume of excavation=6.2(3.5)(24)+12(5.7)(3.4)+12(5.2)(3.10)
12(5.2)(3.10)+12(4.7)(2.8)+12(4.2)(2.5)+12(3.7)(2.2)+12(3.2)(1.9)+12(2.7)(1.6)+12(2.2)(1.3)+12(1.7)(1)+1
2(1.2)(0.70)+12(0.7)(0.40)
=1706.4cum
c.)@ section C
Volume of Excavation=27(6.2)(3.5)+12(5.7)(3.4)+12(4.7)(2.8)+12(3.7)(2.2)+
12(3.7)(2.2)+12(1.7)(1.6)+12(1.7)(1)
=1224.78 cum
d.)@ section D
Volume of Excavation=6(6.2)(3.5)+6(4.8)(2.9)+6(3.4)(1.3)
=240.24

Total Volume of Excavation=404.22cum+1706.4cum+1224.78 cum+240.24


=3575.64cum
B.Backfill
a.) @ section A
Volume of backfill=404.2212(.5)(.25+3.5)(6.2)+12(0.25+2.9)(.5)(4.85)+12(3.9)(0.25+2.30)(0.5)+12(0.25+1.8)(0.5)(3)
=76.49cum
%Volume of Backfill=76.49/404.22
=19 % say 20%
b.)@ section B
Volume of Backfill=20%(1706.4cum)
=341.28cum
c.)@ section C
Volume of Backfill=20%(1224.78 cum)
=244.96cum
d.)@ section D

Volume of Backfill=20%(240.24cum)
=48.04 cum
Total Volume Backfill=76.49cum+341.28cum+244.96cum+48.04 cum
=710.77 cum
II.MASONRY WORKS
1.)@ section A
Total
Volume=12(.5)(.25+3.5)(6.2)+12(0.25+2.9)(.5)(4.85)+12(3.9)(0.25+2.30)(0.5)+12(0.25+1.8)(0.5)(3)
=327.73cum
2. @Section B
Total
Volume={24(6.2)(0.25+3.5)+12(5.7)(3.4+0.25)+24(5.2)(3.10+.25)+12(4.7)(2.8+0.25)+12(4.2)(2.5+0.25)+1
2(3.7)(2.2+0.25)+12(3.2)(1.9+0.25)+12(2.7)(1.6+0.25)+12(2.2)(1.3+0.25)+12(1.7)(1+0.25)+12(1.2)(0.7+0.
25)+12(0.70)(0.40+0.25)}{0.50}
=936.6cum
3. @Section C
Total
Volume={27(6.5)(3.5+0.25)+12(5.7)(3.4+0.25)+12(4.7)(2.8+0.25)+12(3.7)(2.2+0.25)+12(3.7)(2.2+0.25)+1
2(2.7)(1.6+0.25)+12(1.7)(1+0.25)}{0.50}
=691.40 cum
4. @Section D
Total Volume=0.5(6){6.2(3.5+0.25)+4.8(0.25+2.9)+3.4(1.3+0.25)}
=130.92cum

Total Volume of Stone Masonry=327.73cum+936.6cum+691.40 cum+130.92cum


=2086.65 cum
Using Class C Rock with Class B Grout Mixture:
No. of bags cement=2086.65x1.5
=3129.98 say 3130 bags cement
No. of cum sand=2086.65x 0.124
=258.75 say 258 cum sand
For Base Coarse:
1.@ Section A
Volume={12}{0.15}(3.5+2.9+2.3+1.8)
=18.9 cum
2.@ section B

Volume={12}{0.15}(3.4+2.8+2.5+2.2+1.9+1.6+1.3+1+0.70+0.30)+24(0.15)(3.5+3.10)
=55.62 cum
3. .@ section C
Volume=12(0.15)(3.4+2.8+2.2+2.2+1.6+1)+27(0.15)(3.5)
=37.94 cum
4.)@ section D
Volume=6(0.15)(3.5+2.9+1.3)
=6.93 cum
Total Volume of Base Coarse=18.9 cum+55.62 cum+37.94 cum+6.93 cum
=119.39 cum
For Gravel Bedding
1.@ Section A
Volume={12}{0.10}(3.5+2.9+2.3+1.8)
=12.6cum
2.@ section B
Volume={12}{0.10}(3.4+2.8+2.5+2.2+1.9+1.6+1.3+1+0.70+0.30)+24(0.10)(3.5+3.10)
=37.08 cum
3. .@ section C
Volume=12(0.10)(3.4+2.8+2.2+2.2+1.6+1)+27(0.10)(3.5)
=25.29 cum
4.)@ section D
Volume=6(0.10)(3.5+2.9+1.3)
=4.62cum
Total Volume of gravel bedding=12.6cum+37.08 cum+25.29 cum+4.62 cum
=79.59 cum

For Beam
Total Length=345 m
Using 12mmx 6 mm,
345/5.5
=63 pcsx4
=252 pcs 12 mm x 6 m bars
For stirrups,
Spacing=0.20m

Total no of Stirrups=345/0.20
=1725 stirrups
Length=4(.30)-4(.05)+.2
=1.2m
Total no of pcs per commercial length=6/1.2
=5 pcs
Total no of bars=1725/5
=use 350 pcs 10 mm x 6 m bars

Volume of beam=.30(.30)(345)
=31.05cum

No of bags=31.05x 9=288 bags cement


No of cum sand=16 cum
No of cum gravel=32 cum gravel
FOR FENCING
Total area=1.3(345)
=448.5 sqm
No of CHB=448.5*12.5
=5606.25 say 5620 pcs for breakage

Total Volume of Mortar=3(5620)(0.003)


=50.58 say 51 cum
No of bags=51x9=459 bags PC cement
No of cum sand=26 cum sand
No of cum Gravel=51 cum gravel

For plaster
No of cement=448.5(0.11)
=50 bags P.Cx 2 ==100 bags
NO of cum sand=0.006 x 448.5
=2.69 say 3x2==6 cum
For reinforcements;

Total length=345
Spacing=0.6 m
Total no of Bars=345/0.6
=575 pcs
No of pcs per commercial length=6/1.3
=4 pcs
No of 12 mm x 6 m bars=575/4
=144 pcs 12 mm x 6 bars(Vertical Bars)

For Horizontal Bars


Total area=448.5 sqm
Total Length=448.5x2.7(Spaced every 2 layers)
=1210.95 m
Total no of pcs 10 mm x 6 m bars
=1210.95/6
=201.83 say 202 pcs bars
For Weep holes:
Average length of weep hole=1.5 m
No of pcs per length=2 pcs
Total no of pc =345/2
=173 pcs 3 diam pipe PVc
Volume of Gravel Filter=345(.20)(.20)
=14 cum gravel filter
For Formworks
Total area of beam=.30(4)(345)
=414sqm

Total no of plywood=414/2.88
=144 pcs plywood
NO of studs and wales=345/4.85
=70 pcsx 4
280 pcs 2x2x16
Computation for no of days in concreting and masonry works

No of hours=5620/100
=56.2 days/4
=14 days for laying chb
Finishing of chb joints=5620/420
=13.38 days/4
=3.35 days say 5 days
Concreting of beam
No of days=31.05/0.50
=62.1days/4
=15.53 say 16 days
Reinforcement
Total no of kgs=396(5.33)+552(3.7)
=4154 kgs
Total no of hours=9 man hours/kl(4154)/100
=373.86 hours/8
=47/8
=6 days
For plastering
Total area=448.5x2
=897sqm
No of days=897/8
=113/4
=29 days