BUILT-UP RATE FOR PAVING

TENDER FILE NO : GS 2040

PROJECT : CADANGAN PEMBANGUNAN KOLEJ KOMUNITI PARLIAMENT ROMPIN,


PAHANG UNTUK KEMENTERIAN PENDIDIKAN MALAYSIA

LOCATION : ROMPIN, PAHANG

SUPPLIER : CMCM Sdn. Bhd. (cement)


Cao (white lime)
Kerisek Ind. Sdn. Bhd. (sand)
SUB-CONTRACTOR :

QUOTATION DATE :

Material Cost

Cement 10.35 per bags 50kg ( Including Rm 0.25 for unloading )


Sand (ex-mining) 150.00 per loads ( 14 cu. yard ) or 14.09 per m3

Cement & Sand ( 1:3 ) Mixed Material Cost

Cement ( 1440kg/50 ) @ 1 m3 29 bags @ 10.35 300.15


White Lime ( 1 bag / 100 ft2 ) - bags @ 0.00 -
Sand 3 m3 @ 14.09 42.27
Total cost For 4 m3 342.42

Net volume after shrinkage @ 33 1/3% 2.67 m3

Material cost per m3 128.34


Plant cost ( Concrete mixer @ 3.00/m3 ) 3.00
Total Cost : 131.34

Labour Cost
Paving 6.50 per m2 ( 0.60 per ft2 )
50mm Drop 3.28 per m ( 1.00 per ft )
100mm Drop 3.28 per m ( 1.00 per ft )
170mm Riser 3.28 per m ( 1.00 per ft )
250mm Tread 3.28 per m ( 1.00 per ft )
100mm x 100mm
Scupper Drain 6.56 per m ( 2.00 per ft )

Paving Cost / m2
Cement & Sand (1:3) 20mm thk 25mm thk
Material cost 2.63 3.28
Wastage @ 5% 0.13 0.16
Total material cost / m2 2.76 3.45
Labour Cost 6.50 6.50
Plant Cost ( Inclusived ) - -
Tender Cost / m2 9.26 9.95
Paving - 50mm/100mm Drop Cost / m
Cement & Sand (1:3) 25mm thk 25mm thk
50mm high 100mm high
Material cost 0.16 0.33
Wastage @ 5% 0.01 0.02
Total material cost / m 0.17 0.34
Labour Cost 3.28 3.28
Plant Cost ( Inclusived ) - -
Tender Cost / m 3.45 3.62

Paving - 170mm Riser /250mm Tread Cost / m


Cement & Sand (1:3) 25mm thk 25mm thk
170mm high 250mm wide
Material cost 0.56 0.82
Wastage @ 5% 0.03 0.04
Total material cost / m 0.59 0.86
Labour Cost 3.28 3.28
Plant Cost ( Inclusived ) - -
Tender Cost / m 3.87 4.14

Paving - 100mm x 100mm Scupper Drain Cost / m


Cement & Sand (1:3) 25mm thk 25mm thk
200mm girth 300mm girth
Material cost 0.66 0.99
Wastage @ 5% 0.03 0.05
Total material cost / m 0.69 1.03
Labour Cost 6.56 6.56
Plant Cost ( Inclusived ) - -
Tender Cost / m 7.25 7.59

Paving - Ramp with 15mm groovelive @ 50mm c/c Cost / m2


Cement & Sand (1:3) 20mm thk 25mm thk
Material cost 2.63 3.28
Forming 15mm groove @ say 0.20/ft2 2.15 2.15
4.78 5.43
Wastage @ 5% 0.24 0.27
Total material cost / m2 5.02 5.71
Labour Cost 6.50 6.50
Plant Cost ( Inclusived ) - -
Tender Cost / m 11.52 12.21
00mm high

50mm wide

00mm girth