BUILT-UP RATE FOR BRICKWALLS

TENDER FILE NO :

PROJECT :

LOCATION :

SUPPLIER :

SUB-CONTRACTOR :

QUOTATION DATE :

Material Cost

Common bricks 0.23 per pc


Cement mortar ( 1:3 ) 100.00 per yrd3
Labour cost 0.13 per pc
Exmet 0.13 per ft ( 12 sheets 2" x 8' ) @ 12.00 per roll

Note : 1 yrd3 = 0.76m3 or 1m3 = 1.315 yrd3

Common Brickwall - Half Bricks Cost / 100 ft2

Common bricks 525 pcs @ 0.23 120.75


Mortar ( 1:3 ) @ 0.016m3 / m2 0.21 yrd3 @ 100.00 21.00
Exmet @ 3.00m / m2 91 ft @ 0.13 11.38
153.13
Wastage @ 5% 7.66
160.78
Labour Cost 500 pcs @ 0.13 65.00
Tender Price / 100ft2 225.78

Tender Cost / ft2 2.26

Tender Cost / m2 24.30

Material Cost

Cement & sand bricks 0.18 per pc


Cement mortar ( 1:3 ) 107.00 per yrd3
Labour cost 0.13 per pc
Exmet 0.13 ( 12 sheets 2" x 8' ) @ 12.00 per roll

Note : 1 yrd3 = 0.76m3 or 1m3 = 1.315 yrd3

Cement and Sand Brickwall - Half Bricks Cost / 100 ft2


Cement & sand bricks 525 pcs @ 0.18 94.50
Mortar ( 1:3 ) 0.21 yrd3 @ 100.00 21.00
Exmet 91 ft @ 0.13 11.38
126.88
Wastage @ 5% 6.34
133.22
Labour Cost 500 pcs @ 0.13 65.00
Tender Price / 100ft2 198.22

Tender Price / ft2 1.98

Tender Price / m2 21.30